1. The document discusses time elements in a production planned order in SAP, including queue time, move time, wait time, float times, release period, and opening period.
2. It provides an example of a planned order with a PIR requirement date of 01.12.2021 and analyzes the calculation of schedule dates based on operation times and inputs.
3. The key dates calculated for the production order are a schedule start date of 12.11.2021, basic start date of 09.11.2021, and a schedule finish date of 23.11.2021.