SCHEDULE OF MATERIALS
The Importance of Construction
Scheduling
Proper planning and scheduling are
needed to ensure that a construction
project is completed on time and within
budget. A well planned construction
schedule not only helps in outlining the
pace of work but also how the work will
get done.
The schedule helps in defining the
methods and sequence in which the
materials are going to be put in
place. Preparing a construction
schedule is not an easy job as the
scheduler needs to think of many
elements to design the right
schedule.
The scheduler needs to take into
account overall scope of work as well
as connections between different
components to create a construction
schedule that works for everyone. A
well-designed construction scheduling
helps in maximizing efficiency and
productivity. Here is a list of some of
the major benefits of making a
construction schedule before the work
begins.
One of the biggest advantages of
preparing a construction schedule
before beginning the construction work
is that you get fewer surprises down the
road as everything is outlined in great
detail in the schedule. Creating a
schedule allows you to have complete
control over all of your projects and it
will enable you to plan your business
operations down to the lowest level.
Another advantage of scheduling is
that it allows you to maximize quality
control measures as you can properly
sequence the work and make sure the
right quality and quantity of material
are used at each step. It also helps you
with the planning of various resources
including equipment and labor, among
other things.
A big construction project requires a lot
of building materials, which means you
can use a schedule to buy the right
materials at the right time allowing you
to complete the project on time. You
need to submit a variety of samples,
data sheets and other types of
drawings in time to complete the project
and a schedule allows you to do the
same with ease and efficiency.
Proper construction scheduling also allows
you to give time to various parties
including your clients, designers, vendors
as well as subcontractors so they can
better plan their activities. Safety is a big
concern in any construction project and
planning all the activities with the help of a
schedule allows you to improve safety
performance and ensure proper protection
for all the
workers at the construction site. Proper
scheduling also allows you to save
money as you will know the activities
that need to be done during cold
weather allowing you to put pricing
protection measures in place. A proper
scheduling system also helps you
achieve high efficiency and complete
the project in a reasonable time frame.
MATERIAL SCHEDULES
• To help in finishing a construction job
within the time limit of the contract,
the contractor sets up a schedule of
materials. This schedule is based on
the contractor’s idea of the best way
to men, money, machinery and
materials.
The contractor lists each part of the
work along with an estimate of time.
He/she then sets up the schedule.
The schedule is changed from time
to time because of events on the job
or because of change in order from
the owner, architect or the engineer.
Why You Need a Material
Schedule for Construction
While some clients are well aware and
may be in possession of materials
schedule as issued to them by a
professional, deliberately, they put
aside the materials schedule and go
ahead to do or use that which suits
them.
This can lead to a number of structural
defects including building collapse. While
making careful use of the material
schedule is of utmost importance in every
building construction, a sound supervision
of the construction project to ensure
adequate and quality usage of the
specified materials is a key to attaining the
desired result.
To achieve a good quality building
construction project, capable of standing
the test of time, some experts in
construction industry have this to say;
“Sometimes the use of direct labour in
conjunction with supervisory and quality
control inputs from one or two
professionals is seen as a more budget-
friendly approach to the delivery of a
project, especially small-scale projects.
“Other times, the project owner may
choose to be engaged directly in
purchasing and organizing the supply of
construction materials to their site, also in
a bid to save cost. Whatever the case may
be, whether it’s your personal project or as
a group, it is important to know what and
what you should expect on completion of
the project. You don’t plant grapes and
expect to reap blueberries.
“A building development project is essentially a
product of the use of materials and
workmanship. You don’t order for tiles and
expect to see epoxy flooring; neither would you
see a classic brick wall when you actually paid
for blocks.
“The usefulness of a material schedule is not in
contention. You may never know it until you
lose money buying the wrong or a substandard
material at the same price as the original or
even more”.
Specifically, “Material schedule is that piece of
document that shows you the types, sizes,
quantities, quality specifications and sometimes
current price of all the materials you would
need for a project from start to finish. It is not
the same as a Bill of Quantities (B.O.Q) or Priced
Bill of Quantities which gives brief details of all
the items of work in a construction project and
cost included respectively, it doesn’t give you
the work item or work processes, it only deals
with the materials aspect.
The material schedule is presented in
such a way that the user can easily
identify with what materials to be used
in the construction of his/her project
and it often reveals approximate
quantity estimates of all the materials
needed with minimal allowance for
wastage.
“Usually the material schedule is a
construction document prepared after all
the relevant designs/drawings have been
completed and a thorough market survey
has been done to check availability/current
prices of the required materials, so that at
no point is any material omitted due to
incomplete architectural and engineering
details. It is often done in conjunction with
the owner’s specifications.
“When engaging a contractor, it is
important to ask for a material schedule so
that you can follow up on the quality of
materials used for your work. If the
materials used are not those you have
agreed on as duly reflected on the material
schedule in the absence of a pro-work
variation, you can call for a replacement.
“But if there are no documents to show
material specifications, then you can
expect anything.
Sometimes regrets may follow; this is
particularly the case when a supplier is
engaged without a material schedule
to back up your claims on the
specifications of the materials ordered
for.
“Take for instance, you need a simple
timber (wood) to construct your roof
structure, if you don’t specify the product
type, size and condition (e.g. Mahogany
Hardwood, 50 x 75mm full lengths, new
and smooth) but just say supply me ‘wood
for roofing’. Who takes the blame when a
truckload of used fragile softwood is
brought to your site and workers begin
installing them? Although the material
schedule comes at a cost, it is worth it”.
Schedule of materials sample
Outlines for schedules of materials are
supplied by architects. In brief, a
schedule of materials includes: A
description of materials to be used.
This includes sizes, quantity, quality,
brand names , style and specification
numbers.
Item description quality quantity unit Unit price Total
12mm reinforcement rods
16mm reinforcement rods
Mild steel
High yield steel
20
30
Pc
Pc
18,000/=
22,000/=
360,000/=
660,000/=
Total 1,020,000/=
Schedule of materials 2

More Related Content

PPT
Rates Analysis For Calculating Material and Labour for building works
PPTX
civil engineering-Contracts
PDF
PLANNING AND ANALYSIS OF COMMERCIAL BUILDING PROJECT REPORT.pdf
PDF
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
PPTX
Rate analysis
PPTX
Building Construction
PPTX
Mechanized construction
Rates Analysis For Calculating Material and Labour for building works
civil engineering-Contracts
PLANNING AND ANALYSIS OF COMMERCIAL BUILDING PROJECT REPORT.pdf
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Rate analysis
Building Construction
Mechanized construction

What's hot (20)

PPTX
Approximate estimate
PPTX
Construction Project Management
PDF
CONSTRUCTION METHODS BASICS BTCE-503-18
PPTX
Construction Project Management
PPTX
Estimating, administrative approval, technical sanction, budget provision
PDF
Construction Project Management
PDF
Introduction-construction management_Construction Management (2180611) (Semes...
PDF
Construction Methods & Sequence
PDF
Reports on Precast System
PPT
footing
PPTX
Rcc jacketing
PPTX
Specifications of buildings
PPTX
Estimating & Costing - I
PDF
CPM-Updating
PPTX
Design and analasys of a g+2 residential building
PPTX
Approximate estimate
PPTX
9. introduction to site preparation
PPTX
ESTIMATING AND COSTING
PPT
Stages in Construction
PPT
Estimation (power point)
Approximate estimate
Construction Project Management
CONSTRUCTION METHODS BASICS BTCE-503-18
Construction Project Management
Estimating, administrative approval, technical sanction, budget provision
Construction Project Management
Introduction-construction management_Construction Management (2180611) (Semes...
Construction Methods & Sequence
Reports on Precast System
footing
Rcc jacketing
Specifications of buildings
Estimating & Costing - I
CPM-Updating
Design and analasys of a g+2 residential building
Approximate estimate
9. introduction to site preparation
ESTIMATING AND COSTING
Stages in Construction
Estimation (power point)
Ad

Similar to Schedule of materials 2 (20)

PDF
Creating a Cost-Effective Construction Project
PPT
Planning and scheduling Techniques.ppt
PPT
Suvarna consultancy services
PDF
Construction-project-management-2-pdf-free.pdf
PPT
Work scheduling(2)
PPTX
Construction project management
PPTX
Construction Compliance Consultants
PDF
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
PPTX
Reduction of cost in construction
PPTX
A Time and Material (T&M) Contract , project agreement
DOCX
Pp group assignment
PPTX
Critical Path Method Scheduling for DOT
PDF
construction project planing
PPTX
project management and planning the projects
DOCX
Pm project-control-compiled
PDF
Project Planning and Scheduling
PDF
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
PDF
J.S. Daniel paper for practical checklist of schedule
PDF
Project management
Creating a Cost-Effective Construction Project
Planning and scheduling Techniques.ppt
Suvarna consultancy services
Construction-project-management-2-pdf-free.pdf
Work scheduling(2)
Construction project management
Construction Compliance Consultants
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
Reduction of cost in construction
A Time and Material (T&M) Contract , project agreement
Pp group assignment
Critical Path Method Scheduling for DOT
construction project planing
project management and planning the projects
Pm project-control-compiled
Project Planning and Scheduling
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
J.S. Daniel paper for practical checklist of schedule
Project management
Ad

Recently uploaded (20)

PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PPTX
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PPTX
Information Storage and Retrieval Techniques Unit III
PDF
737-MAX_SRG.pdf student reference guides
PPTX
"Array and Linked List in Data Structures with Types, Operations, Implementat...
PPTX
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
PDF
distributed database system" (DDBS) is often used to refer to both the distri...
PPTX
Safety Seminar civil to be ensured for safe working.
PDF
22EC502-MICROCONTROLLER AND INTERFACING-8051 MICROCONTROLLER.pdf
PPTX
communication and presentation skills 01
PPTX
Artificial Intelligence
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PDF
Abrasive, erosive and cavitation wear.pdf
PPT
Occupational Health and Safety Management System
PDF
Design Guidelines and solutions for Plastics parts
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPT
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
PDF
August 2025 - Top 10 Read Articles in Network Security & Its Applications
PPTX
Current and future trends in Computer Vision.pptx
Fundamentals of safety and accident prevention -final (1).pptx
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
Information Storage and Retrieval Techniques Unit III
737-MAX_SRG.pdf student reference guides
"Array and Linked List in Data Structures with Types, Operations, Implementat...
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
distributed database system" (DDBS) is often used to refer to both the distri...
Safety Seminar civil to be ensured for safe working.
22EC502-MICROCONTROLLER AND INTERFACING-8051 MICROCONTROLLER.pdf
communication and presentation skills 01
Artificial Intelligence
III.4.1.2_The_Space_Environment.p pdffdf
Abrasive, erosive and cavitation wear.pdf
Occupational Health and Safety Management System
Design Guidelines and solutions for Plastics parts
Automation-in-Manufacturing-Chapter-Introduction.pdf
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
August 2025 - Top 10 Read Articles in Network Security & Its Applications
Current and future trends in Computer Vision.pptx

Schedule of materials 2

  • 1. SCHEDULE OF MATERIALS The Importance of Construction Scheduling Proper planning and scheduling are needed to ensure that a construction project is completed on time and within budget. A well planned construction schedule not only helps in outlining the pace of work but also how the work will get done.
  • 2. The schedule helps in defining the methods and sequence in which the materials are going to be put in place. Preparing a construction schedule is not an easy job as the scheduler needs to think of many elements to design the right schedule.
  • 3. The scheduler needs to take into account overall scope of work as well as connections between different components to create a construction schedule that works for everyone. A well-designed construction scheduling helps in maximizing efficiency and productivity. Here is a list of some of the major benefits of making a construction schedule before the work begins.
  • 4. One of the biggest advantages of preparing a construction schedule before beginning the construction work is that you get fewer surprises down the road as everything is outlined in great detail in the schedule. Creating a schedule allows you to have complete control over all of your projects and it will enable you to plan your business operations down to the lowest level.
  • 5. Another advantage of scheduling is that it allows you to maximize quality control measures as you can properly sequence the work and make sure the right quality and quantity of material are used at each step. It also helps you with the planning of various resources including equipment and labor, among other things.
  • 6. A big construction project requires a lot of building materials, which means you can use a schedule to buy the right materials at the right time allowing you to complete the project on time. You need to submit a variety of samples, data sheets and other types of drawings in time to complete the project and a schedule allows you to do the same with ease and efficiency.
  • 7. Proper construction scheduling also allows you to give time to various parties including your clients, designers, vendors as well as subcontractors so they can better plan their activities. Safety is a big concern in any construction project and planning all the activities with the help of a schedule allows you to improve safety performance and ensure proper protection for all the
  • 8. workers at the construction site. Proper scheduling also allows you to save money as you will know the activities that need to be done during cold weather allowing you to put pricing protection measures in place. A proper scheduling system also helps you achieve high efficiency and complete the project in a reasonable time frame.
  • 9. MATERIAL SCHEDULES • To help in finishing a construction job within the time limit of the contract, the contractor sets up a schedule of materials. This schedule is based on the contractor’s idea of the best way to men, money, machinery and materials.
  • 10. The contractor lists each part of the work along with an estimate of time. He/she then sets up the schedule. The schedule is changed from time to time because of events on the job or because of change in order from the owner, architect or the engineer.
  • 11. Why You Need a Material Schedule for Construction While some clients are well aware and may be in possession of materials schedule as issued to them by a professional, deliberately, they put aside the materials schedule and go ahead to do or use that which suits them.
  • 12. This can lead to a number of structural defects including building collapse. While making careful use of the material schedule is of utmost importance in every building construction, a sound supervision of the construction project to ensure adequate and quality usage of the specified materials is a key to attaining the desired result.
  • 13. To achieve a good quality building construction project, capable of standing the test of time, some experts in construction industry have this to say; “Sometimes the use of direct labour in conjunction with supervisory and quality control inputs from one or two professionals is seen as a more budget- friendly approach to the delivery of a project, especially small-scale projects.
  • 14. “Other times, the project owner may choose to be engaged directly in purchasing and organizing the supply of construction materials to their site, also in a bid to save cost. Whatever the case may be, whether it’s your personal project or as a group, it is important to know what and what you should expect on completion of the project. You don’t plant grapes and expect to reap blueberries.
  • 15. “A building development project is essentially a product of the use of materials and workmanship. You don’t order for tiles and expect to see epoxy flooring; neither would you see a classic brick wall when you actually paid for blocks. “The usefulness of a material schedule is not in contention. You may never know it until you lose money buying the wrong or a substandard material at the same price as the original or even more”.
  • 16. Specifically, “Material schedule is that piece of document that shows you the types, sizes, quantities, quality specifications and sometimes current price of all the materials you would need for a project from start to finish. It is not the same as a Bill of Quantities (B.O.Q) or Priced Bill of Quantities which gives brief details of all the items of work in a construction project and cost included respectively, it doesn’t give you the work item or work processes, it only deals with the materials aspect.
  • 17. The material schedule is presented in such a way that the user can easily identify with what materials to be used in the construction of his/her project and it often reveals approximate quantity estimates of all the materials needed with minimal allowance for wastage.
  • 18. “Usually the material schedule is a construction document prepared after all the relevant designs/drawings have been completed and a thorough market survey has been done to check availability/current prices of the required materials, so that at no point is any material omitted due to incomplete architectural and engineering details. It is often done in conjunction with the owner’s specifications.
  • 19. “When engaging a contractor, it is important to ask for a material schedule so that you can follow up on the quality of materials used for your work. If the materials used are not those you have agreed on as duly reflected on the material schedule in the absence of a pro-work variation, you can call for a replacement. “But if there are no documents to show material specifications, then you can expect anything.
  • 20. Sometimes regrets may follow; this is particularly the case when a supplier is engaged without a material schedule to back up your claims on the specifications of the materials ordered for.
  • 21. “Take for instance, you need a simple timber (wood) to construct your roof structure, if you don’t specify the product type, size and condition (e.g. Mahogany Hardwood, 50 x 75mm full lengths, new and smooth) but just say supply me ‘wood for roofing’. Who takes the blame when a truckload of used fragile softwood is brought to your site and workers begin installing them? Although the material schedule comes at a cost, it is worth it”.
  • 22. Schedule of materials sample Outlines for schedules of materials are supplied by architects. In brief, a schedule of materials includes: A description of materials to be used. This includes sizes, quantity, quality, brand names , style and specification numbers.
  • 23. Item description quality quantity unit Unit price Total 12mm reinforcement rods 16mm reinforcement rods Mild steel High yield steel 20 30 Pc Pc 18,000/= 22,000/= 360,000/= 660,000/= Total 1,020,000/=