Data Centres in Shared Buildings Barry Shambrook RCDD Tuckers Consultancy Ltd
Why locate in a shared building? Server hugging Virtualisation VoIP Thin client Space available Dark fibre 10 miles in London £250K per annum Cost of shared facility Energy efficiency
Space example
Monthly colocation costs per rack Source: www.mobilepricing.com
Monthly TCO per rack
Cost and emissions £300 per month 1 Tonne CO 2 /Balloon 2 Balloons  per month
Carbon Reduction Commitment
Lurking Vulnerabilities Latent deficiencies can surface at the worst possible moment
How Much Redundancy is Enough?
Uptime Institute tier resilience – car tyres Tier I - no spare wheel.  Stop and wait for AA Tier II -  Four wheels and a spare.  Stop, replace, drive on Tier III - “Run Flat” tyres.  Drive slower until opportunity to replace the tyre Tier IV – Two sets of wheels on each axle
Tier IV resilience Power Cooling Mains Generator Mains Generator Change Over Change Over UPS UPS Equipment Heat Rejection Heat Rejection (N+N) (N+N) Room Units Room Units (N+N)
Cost of resilience – plant efficiency 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%
Shared building challenges Space for data centre Space for plant Size and number of utility supplies Risk limitation Noise restrictions
Case study #1 Large (10,000m 2  plus) office building Bespoke design for single anchor Tenant Sub-tenancies envisaged Requirement for 1000m 2  Data Centre On site processing and storage Remote back-up
CS1 Landlord data centre
CS1 Tenant data centre
CS1 – power 2 fully autonomous grid supplies Generators on each supply, redundant shared Building UPS N+1 Redundant distribution
CS1 cooling N+N/N+1 chillers and cooling towers N+N secondary chilled water N+N CRAC units
Water cooling
Heat recovery
CS1 fire protection Pre-action sprinklers – building insurance VESDA – manual intervention Limited fire load in floor void
Pre-action sprinklers Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve
Pre-action sprinklers - stage 1 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve
Pre-action sprinklers – stage 2 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve Water
Pre-action sprinklers – stage 3 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve Water
Upgrade to water mist?
CS1 redundancy summary Power Cooling Mains Generator Mains Generator Change Over Change Over UPS (N+1) Equipment Heat Rejection (N+1) Room Units (N+1) (N+N) UPS (N+1)
Case study #2 Speculative 8000m 2  office building Multiple tenancies Requirement for 100m 2  Data Centre On site processing and storage option On site development option Remote parallel processing and storage
CS2 data centre plan
CS2 – power 2 transformers, same HV ring Single generator, redundant switching Redundant distribution N+N UPS to data centre N UPS to trading floor and TR’s Redundant distribution N+1 alternative for higher capacity
Bus bar power
CS2 cooling N+N chillers, “free” cooling N+N cooling distribution to data centre N+N secondary chilled water N+N in row cooling units N cooling to trading floor and TR’s N+1 alternative for higher capacity
“ Free” cooling Summer Spring/Autumn/Morning/Evening Winter/Night
CS2 fire protection Pre-action sprinklers – building insurance VESDA Oxy-reduct for asset protection
Oxy-reduct Not approved by UK building insurers or Building Regulations so other protection also required. H&S limits exposure to 6 hours per day, otherwise completely safe. Oxygen level equivalent to 2700m above sea level.
CS2 infrastructure network Redundant external links 2 autonomous PoP rooms, 1 shared with data centre DC bypass
CS1 infrastructure network
CS2 4.5 kVA/rack N+N Power Cooling Transformer Generator UPS MER Racks MER Room Units Changeover Heat Rejection Heat Rejection MER Room Units UPS (N+N) SER S SER N 50% traders 50% traders (N+N) Changeover Transformer Mains (N+N)
CS2 8kVA/rack N+1 Power Cooling Transformer Generator N+1 UPS MER Racks N+1 MER Room Units Changeover N+1 Heat Rejection SER S SER N 50% traders 50% traders Changeover Transformer Mains
Summary Resilience compromises Efficiency improvements Added flexibility?

More Related Content

PDF
Smart Grid Gotland - Wind Power Integration
PPTX
Resultat från Smart Grid Gotland
PDF
Demand-Response in the Smart Grid Gotland project
PDF
Soft Magnetic Nanocrystalline Materials for Inductors and Shielding Applicati...
PDF
Apc cooling solutions
PDF
Tier III Data Center for Lease
PPT
Energy management 101
PPTX
Basics of fire sprinkler design ascet meeting 2 5 (1)
Smart Grid Gotland - Wind Power Integration
Resultat från Smart Grid Gotland
Demand-Response in the Smart Grid Gotland project
Soft Magnetic Nanocrystalline Materials for Inductors and Shielding Applicati...
Apc cooling solutions
Tier III Data Center for Lease
Energy management 101
Basics of fire sprinkler design ascet meeting 2 5 (1)

What's hot (6)

PDF
Cost Save Example - Maintenance
PDF
Factsheet off grid generator
PDF
Portable spectrophotometer Mini Incus
PPTX
High Efficiency technologies for Data Centre Air Conditioning
PDF
Bacs and water per il condizionamento degli edifici
PDF
Data Center 2.1
Cost Save Example - Maintenance
Factsheet off grid generator
Portable spectrophotometer Mini Incus
High Efficiency technologies for Data Centre Air Conditioning
Bacs and water per il condizionamento degli edifici
Data Center 2.1
Ad

Viewers also liked (11)

PDF
PPTX
CATALAN AIRPORTS NETWORK
PPT
Airport IT Strategy
PPTX
Tematik wilayah jabar
PDF
Smarter Airport Systems Transform Travel - IBM
PDF
Integrated ip network for airport terminal
PDF
Transformed Airports: From Physical Touchpoints to Digital Services
PPTX
Database Project Airport management System
PPTX
POWER POINT PRESENTATION ON DATA CENTER
PPTX
Airport planning and Design
CATALAN AIRPORTS NETWORK
Airport IT Strategy
Tematik wilayah jabar
Smarter Airport Systems Transform Travel - IBM
Integrated ip network for airport terminal
Transformed Airports: From Physical Touchpoints to Digital Services
Database Project Airport management System
POWER POINT PRESENTATION ON DATA CENTER
Airport planning and Design
Ad

Similar to Small Data Centres (20)

PDF
D146248
PDF
6 - Oracle.pdf
PDF
Datwyler data center presentation info tech middle east
PDF
Chapter 6 : Smart District heating/cooling, Summer Course, AUST 2015
PPT
Estrategias para ahorro de energía en applicaciones de misión crítica de IT
PDF
Cable ampacity calculations iec
PDF
cable ampacity calculations- IEC
PDF
Deltalis Factsheet English
PDF
Broadcast day 2011_gilat
PDF
Data Center Cooling, Critical Facility and Infrastructure Optimization
PPT
District Cooling Jenny Dahlberg, Fortum
PPSX
Case Study Caso Thor
PDF
D wave 2 x tech
PPTX
Green Data Center
PPT
Pmdc Smdc Technical Overview 24 Mar2010
PDF
Cirrascale forest container march 2011
PPT
BACnet Forum London 2011
PDF
Solving Heat Management Issues with Thermally Conductive Plastics
PPTX
Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
PPTX
Star Emerson - District sized heatpumps, experiences from Drammen
D146248
6 - Oracle.pdf
Datwyler data center presentation info tech middle east
Chapter 6 : Smart District heating/cooling, Summer Course, AUST 2015
Estrategias para ahorro de energía en applicaciones de misión crítica de IT
Cable ampacity calculations iec
cable ampacity calculations- IEC
Deltalis Factsheet English
Broadcast day 2011_gilat
Data Center Cooling, Critical Facility and Infrastructure Optimization
District Cooling Jenny Dahlberg, Fortum
Case Study Caso Thor
D wave 2 x tech
Green Data Center
Pmdc Smdc Technical Overview 24 Mar2010
Cirrascale forest container march 2011
BACnet Forum London 2011
Solving Heat Management Issues with Thermally Conductive Plastics
Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
Star Emerson - District sized heatpumps, experiences from Drammen

More from Tuckers Consultancy Ltd (7)

PDF
Cap and exp sport facilities its
PDF
Cap and exp data centres
PPTX
10 dos and donts of data centre design
PPTX
Crc Presentation
PPTX
BERi Service Provider Presentation
PPT
The investment case for reduction in building energy consumption
PPT
Bicsi 2010 IP Consolidation
Cap and exp sport facilities its
Cap and exp data centres
10 dos and donts of data centre design
Crc Presentation
BERi Service Provider Presentation
The investment case for reduction in building energy consumption
Bicsi 2010 IP Consolidation

Small Data Centres

  • 1. Data Centres in Shared Buildings Barry Shambrook RCDD Tuckers Consultancy Ltd
  • 2. Why locate in a shared building? Server hugging Virtualisation VoIP Thin client Space available Dark fibre 10 miles in London £250K per annum Cost of shared facility Energy efficiency
  • 4. Monthly colocation costs per rack Source: www.mobilepricing.com
  • 6. Cost and emissions £300 per month 1 Tonne CO 2 /Balloon 2 Balloons per month
  • 8. Lurking Vulnerabilities Latent deficiencies can surface at the worst possible moment
  • 9. How Much Redundancy is Enough?
  • 10. Uptime Institute tier resilience – car tyres Tier I - no spare wheel. Stop and wait for AA Tier II - Four wheels and a spare. Stop, replace, drive on Tier III - “Run Flat” tyres. Drive slower until opportunity to replace the tyre Tier IV – Two sets of wheels on each axle
  • 11. Tier IV resilience Power Cooling Mains Generator Mains Generator Change Over Change Over UPS UPS Equipment Heat Rejection Heat Rejection (N+N) (N+N) Room Units Room Units (N+N)
  • 12. Cost of resilience – plant efficiency 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%
  • 13. Shared building challenges Space for data centre Space for plant Size and number of utility supplies Risk limitation Noise restrictions
  • 14. Case study #1 Large (10,000m 2 plus) office building Bespoke design for single anchor Tenant Sub-tenancies envisaged Requirement for 1000m 2 Data Centre On site processing and storage Remote back-up
  • 16. CS1 Tenant data centre
  • 17. CS1 – power 2 fully autonomous grid supplies Generators on each supply, redundant shared Building UPS N+1 Redundant distribution
  • 18. CS1 cooling N+N/N+1 chillers and cooling towers N+N secondary chilled water N+N CRAC units
  • 21. CS1 fire protection Pre-action sprinklers – building insurance VESDA – manual intervention Limited fire load in floor void
  • 22. Pre-action sprinklers Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve
  • 23. Pre-action sprinklers - stage 1 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve
  • 24. Pre-action sprinklers – stage 2 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve Water
  • 25. Pre-action sprinklers – stage 3 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve Water
  • 27. CS1 redundancy summary Power Cooling Mains Generator Mains Generator Change Over Change Over UPS (N+1) Equipment Heat Rejection (N+1) Room Units (N+1) (N+N) UPS (N+1)
  • 28. Case study #2 Speculative 8000m 2 office building Multiple tenancies Requirement for 100m 2 Data Centre On site processing and storage option On site development option Remote parallel processing and storage
  • 30. CS2 – power 2 transformers, same HV ring Single generator, redundant switching Redundant distribution N+N UPS to data centre N UPS to trading floor and TR’s Redundant distribution N+1 alternative for higher capacity
  • 32. CS2 cooling N+N chillers, “free” cooling N+N cooling distribution to data centre N+N secondary chilled water N+N in row cooling units N cooling to trading floor and TR’s N+1 alternative for higher capacity
  • 33. “ Free” cooling Summer Spring/Autumn/Morning/Evening Winter/Night
  • 34. CS2 fire protection Pre-action sprinklers – building insurance VESDA Oxy-reduct for asset protection
  • 35. Oxy-reduct Not approved by UK building insurers or Building Regulations so other protection also required. H&S limits exposure to 6 hours per day, otherwise completely safe. Oxygen level equivalent to 2700m above sea level.
  • 36. CS2 infrastructure network Redundant external links 2 autonomous PoP rooms, 1 shared with data centre DC bypass
  • 38. CS2 4.5 kVA/rack N+N Power Cooling Transformer Generator UPS MER Racks MER Room Units Changeover Heat Rejection Heat Rejection MER Room Units UPS (N+N) SER S SER N 50% traders 50% traders (N+N) Changeover Transformer Mains (N+N)
  • 39. CS2 8kVA/rack N+1 Power Cooling Transformer Generator N+1 UPS MER Racks N+1 MER Room Units Changeover N+1 Heat Rejection SER S SER N 50% traders 50% traders Changeover Transformer Mains
  • 40. Summary Resilience compromises Efficiency improvements Added flexibility?

Editor's Notes

  • #6: ENERGY COST IS LARGE PROPORTION BUILD COST – GET IT RIGHT!
  • #9: Future Proofing - Optimizing Tier-IV Data Centers You are most vulnerable to what you don’t see or didn’t anticipate. FUTURE PROOFING collaboration and cross-pollination Where will it fail vs will it work? Investing in strategic planning
  • #10: Future Proofing - Optimizing Tier-IV Data Centers Fault tolerance = Mean Time Between Failures MTBF MTTR = Mean time to restore Critical Infrastructure must be intuitively operable Simplicity = Reliability
  • #32: Allows additional supplies and enhanced capacity N+1 INSERT PICTURES
  • #36: INSERT VIDEO AND OXYGEN CHART
  • #39: INSERT SUMMARY DIAGRAM