LECTURE 5: SOFTWARE PROJECT
MANAGEMENT
Software Engineering
Mike Wooldridge
Lecture 5 Software Engineering
1 Introduction
• The “software crisis” of the 1960s and
1970s was so called because of a string of
high profile software project failures: over
budget, overdue, etc.
• The crisis arose in part because the greater
power available in computers meant that
larger software projects were tackled with
techniques developed on much smaller
projects.
• Techniques were needed for software
project management.
Good project management cannot
guarantee success, but poor management
on significant projects always leads to
failure.
Mike Wooldridge 1
Lecture 5 Software Engineering
• Software projects have several properties
that make them very different to other
kinds of engineering project.
– The product is intangible.
Its hard to claim a bridge is 90%
complete if there is not 90% of the
bridge there.
It is easy to claim that a software project
is 90% complete, even if there are no
visible outcomes.
– We don’t have much experience.
Software engineering is a new
discipline, and so we simply don’t have
much understanding of how to
engineer large scale software projects.
– Large software projects are often “bespoke”.
Most large software systems are
one-off, with experience gained in one
project being of little help in another.
– The technology changes very quickly.
Most large software projects employ
new technology; for many projects, this
is the raison d’etre.
Mike Wooldridge 2
Lecture 5 Software Engineering
• Activities in software project management:
– project planning;
– project scheduling;
– risk management;
– managing people.
Mike Wooldridge 3
Lecture 5 Software Engineering
2 Project Planning
• The biggest single problem that afflicts
software developing is that of
underestimating resources required for a
project.
• Developing a realistic project plan is
essential to gain an understanding of the
resources required, and how these should
be applied.
• Types of plan:
– Software development plan.
The central plan, which describes how
the system will be developed.
– Quality assurance plan.
Specifies the quality procedures &
standards to be used.
– Validation plan.
Defines how a client will validate the
system that has been developed.
Mike Wooldridge 4
Lecture 5 Software Engineering
– Configuration management plan.
Defines how the system will be
configured and installed.
– Maintenance plan.
Defines how the system will be
maintained.
– Staff development plan.
Describes how the skills of the
participants will be developed.
• We will focus on software development &
quality assurance plan.
Mike Wooldridge 5
Lecture 5 Software Engineering
2.1 The Software Development Plan
• This is usually what is meant by a project
plan.
• Specifies the order of work to be carried
out, resources, responsibilities, and so on.
• Varies from small and relatively informal
to large and very formal.
• Developing a project plan is as important
as properly designing code:
On the basis of a project plan, contracts will be
signed and careers made or broken...
• Important not to:
– overestimate your team’s ability;
– simply tell clients what they want to
hear;
– be pressured by developers (“we can do
that in an afternoon!”)
Mike Wooldridge 6
Lecture 5 Software Engineering
2.2 Structure of Development Plan
1. Introduction
brief intro to project — references to
requirements spec
2. Project organisation
intro to organisations, people, and their
roles
3. Risk Analysis
what are the key risks to the project?
4. Hardware and software resources
what h/ware and s/ware resources will
be required for the project and when?
5. Work breakdown
the project divided into activities,
milestones, deliverables; dependencies
between tasks etc
6. Project schedule
actual time required — allocation of dates
7. Reporting and progress measurement
mechanisms to monitor progress.
Mike Wooldridge 7
Lecture 5 Software Engineering
2.3 Work Breakdown
• There are many ways of breaking down
the activities in a project, but the most
usual is into:
– work packages;
– tasks;
– deliverables;
– milestones.
Mike Wooldridge 8
Lecture 5 Software Engineering
• A workpackage is a large, logically distinct
section of work:
– typically at least 12 months duration;
– may include multiple concurrent
activities;
– independent of other activities;
– but may depend on, or feed into other
activities;
– typically allocated to a single team.
• A task is typically a much smaller piece of
work:
A part of a workpackage.
– typically 3–6 person months effort;
– may be dependent on other concurrent
activities;
– typically allocated to a single person.
Mike Wooldridge 9
Lecture 5 Software Engineering
• A deliverable is an output of the project that
can meaningfully be assessed.
Examples:
– a report (e.g., requirements spec);
– code (e.g., alpha tested product).
Deliverables are indicators (but only
indicators) of progress.
• A milestone is a point at which progress on
the project may be assessed.
Typically a major turning point in the
project.
EXAMPLES:
– delivery of requirements spec;
– delivery of alpha tested code.
Mike Wooldridge 10
Lecture 5 Software Engineering
• Usually...
– work packages are numbered WP1,
WP2, ...;
– tasks are numbered T1.1, T1.2, etc,
the first number is the number of the
workpackage;
the second is a sequence number.
– deliverables are numbered D1.1, D1.2,
etc
– milestones are numbered M1, M2 etc.
Mike Wooldridge 11
Lecture 5 Software Engineering
• For each workpackage & task, it is usual to
document:
– brief description;
– earliest start date;
– earliest end date;
– total person months effort;
– pre-requisite WPs or tasks;
– dependent WPs or tasks;
– who is responsible.
Mike Wooldridge 12
Lecture 5 Software Engineering
2.4 Critical Paths
• The pre-requisites and dependencies of
WPs and tasks determine a critical path: the
sequence of dependencies in the project.
• The critical path is the sequence of
activities that takes the longest time to
complete.
• Any delay to an activity in the critical path
will cause delays to the overall project.
• Delays to activities not on the critical path
need not necessarily cause overall delays.
Mike Wooldridge 13
Lecture 5 Software Engineering
3 Gantt Charts & Activity Networks
• Gantt charts are a kind of bar chart:
– time plotted on x axis
– bars on y axis for each activity.
Mike Wooldridge 14
Lecture 5 Software Engineering
• An activity network is a labelled graph,
with:
– nodes corresponding to activities,
– arcs labelled with estimated times;
– activities are linked if there is a
dependency between them.
Mike Wooldridge 15
Lecture 5 Software Engineering
4 Risks
When planning a project, it is critically
important to know what the key risks are,
and is possible plan for them:
• staff turnover;
• management change;
• hardware unavailability;
• requirements change;
• specification delays;
• size underestimate;
• technology change;
• product competition.
Mike Wooldridge 16
Lecture 5 Software Engineering
5 Quality Assurance
• Many organisations make use of a quality
assurance plan, which sets out standards
to be maintained during project
development.
• – Documentation standards:
∗ what documents;
∗ format & content;
– Coding standards:
∗ class/method/variable naming
conventions;
∗ comment standards
(e.g., javadoc);
∗ testing conventions;
Mike Wooldridge 17

More Related Content

PPTX
Case tools
PPT
Case tools and modern process of system development
PDF
PPTX
Case tools(computer Aided software Engineering)
PPTX
Case tools
PPTX
Case tool introduction
PPTX
Computer aided software engineering
PPTX
Case tools
Case tools and modern process of system development
Case tools(computer Aided software Engineering)
Case tools
Case tool introduction
Computer aided software engineering

What's hot (20)

PDF
PPTX
Case tools
PPTX
Introduction to Software Engineering
PDF
Software engineering process
PPT
Software AND its Types & CASE toolS
PPT
Case tools
PDF
SWE-401 - 12. Software CASE Tools Overview
PPT
SE chapter 4
PDF
An introduction to software engineering
PPT
Case tools
PPTX
Software engineering
PPTX
Software engineering
PPT
Software System Engineering - Chapter 1
PPTX
Software engineering
PPT
Intoduction to software engineering part 1
PPT
System Analysis And Design Management Information System
PPTX
CSC426 - Software Engineering Lecture Note
PPT
Slides chapter 3
Case tools
Introduction to Software Engineering
Software engineering process
Software AND its Types & CASE toolS
Case tools
SWE-401 - 12. Software CASE Tools Overview
SE chapter 4
An introduction to software engineering
Case tools
Software engineering
Software engineering
Software System Engineering - Chapter 1
Software engineering
Intoduction to software engineering part 1
System Analysis And Design Management Information System
CSC426 - Software Engineering Lecture Note
Slides chapter 3
Ad

Similar to software project management (20)

PDF
Emergancy guide
PPTX
UNIT-I.pptx
PDF
SE_Chapterrrrrrrrrrrrrrrrrrrrrrrrrr3.pdf
PPT
01- Lecture 01 - Introduction to SPM.ppt
DOCX
Project scheduling
PPTX
The Waterfall Model
PPTX
Project Management in Information Technologies
PPTX
SPM_UNIT-1(1).pptx
PDF
Computer current applications
PDF
PDF
Cs414 lec1 f2014
PPTX
unit 1 introudction of the file and sepm
PDF
Spm tutorials
PPTX
Software Engineering And Project Management Basics
PPT
Planning in Software Projects
PDF
Project Planning in Software Engineering
PPT
223417 Diploma_Sem4_software_engg-chap-05.ppt
PPT
Introduction to Software Project Management
PDF
1_Introduction & Process & Development Life Cycle.pdf
PPTX
Project Management System Architecture for Today
Emergancy guide
UNIT-I.pptx
SE_Chapterrrrrrrrrrrrrrrrrrrrrrrrrr3.pdf
01- Lecture 01 - Introduction to SPM.ppt
Project scheduling
The Waterfall Model
Project Management in Information Technologies
SPM_UNIT-1(1).pptx
Computer current applications
Cs414 lec1 f2014
unit 1 introudction of the file and sepm
Spm tutorials
Software Engineering And Project Management Basics
Planning in Software Projects
Project Planning in Software Engineering
223417 Diploma_Sem4_software_engg-chap-05.ppt
Introduction to Software Project Management
1_Introduction & Process & Development Life Cycle.pdf
Project Management System Architecture for Today
Ad

More from Ankit Gupta (20)

PPT
Biometricstechnology in iot and machine learning
PDF
Week2 cloud computing week2
PDF
Week 8 lecture material
PDF
Week 4 lecture material cc (1)
PDF
Week 3 lecture material cc
PDF
Week 1 lecture material cc
PDF
Mod05lec25(resource mgmt ii)
PDF
Mod05lec24(resource mgmt i)
PDF
Mod05lec23(map reduce tutorial)
PDF
Mod05lec22(cloudonomics tutorial)
PDF
Mod05lec21(sla tutorial)
PDF
Lecture29 cc-security4
PDF
Lecture28 cc-security3
PDF
Lecture27 cc-security2
PDF
Lecture26 cc-security1
PDF
Lecture 30 cloud mktplace
PDF
Week 7 lecture material
PDF
Gurukul Cse cbcs-2015-16
PDF
Microprocessor full hand made notes
PPTX
Transfer Leaning Using Pytorch synopsis Minor project pptx
Biometricstechnology in iot and machine learning
Week2 cloud computing week2
Week 8 lecture material
Week 4 lecture material cc (1)
Week 3 lecture material cc
Week 1 lecture material cc
Mod05lec25(resource mgmt ii)
Mod05lec24(resource mgmt i)
Mod05lec23(map reduce tutorial)
Mod05lec22(cloudonomics tutorial)
Mod05lec21(sla tutorial)
Lecture29 cc-security4
Lecture28 cc-security3
Lecture27 cc-security2
Lecture26 cc-security1
Lecture 30 cloud mktplace
Week 7 lecture material
Gurukul Cse cbcs-2015-16
Microprocessor full hand made notes
Transfer Leaning Using Pytorch synopsis Minor project pptx

Recently uploaded (20)

PPTX
Sustainable Sites - Green Building Construction
PPTX
Geodesy 1.pptx...............................................
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
additive manufacturing of ss316l using mig welding
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PPTX
Welding lecture in detail for understanding
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PPT
Project quality management in manufacturing
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Sustainable Sites - Green Building Construction
Geodesy 1.pptx...............................................
Lesson 3_Tessellation.pptx finite Mathematics
UNIT-1 - COAL BASED THERMAL POWER PLANTS
additive manufacturing of ss316l using mig welding
CYBER-CRIMES AND SECURITY A guide to understanding
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Strings in CPP - Strings in C++ are sequences of characters used to store and...
Welding lecture in detail for understanding
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Mechanical Engineering MATERIALS Selection
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
Model Code of Practice - Construction Work - 21102022 .pdf
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
Project quality management in manufacturing
bas. eng. economics group 4 presentation 1.pptx
Foundation to blockchain - A guide to Blockchain Tech
Internet of Things (IOT) - A guide to understanding
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx

software project management

  • 1. LECTURE 5: SOFTWARE PROJECT MANAGEMENT Software Engineering Mike Wooldridge
  • 2. Lecture 5 Software Engineering 1 Introduction • The “software crisis” of the 1960s and 1970s was so called because of a string of high profile software project failures: over budget, overdue, etc. • The crisis arose in part because the greater power available in computers meant that larger software projects were tackled with techniques developed on much smaller projects. • Techniques were needed for software project management. Good project management cannot guarantee success, but poor management on significant projects always leads to failure. Mike Wooldridge 1
  • 3. Lecture 5 Software Engineering • Software projects have several properties that make them very different to other kinds of engineering project. – The product is intangible. Its hard to claim a bridge is 90% complete if there is not 90% of the bridge there. It is easy to claim that a software project is 90% complete, even if there are no visible outcomes. – We don’t have much experience. Software engineering is a new discipline, and so we simply don’t have much understanding of how to engineer large scale software projects. – Large software projects are often “bespoke”. Most large software systems are one-off, with experience gained in one project being of little help in another. – The technology changes very quickly. Most large software projects employ new technology; for many projects, this is the raison d’etre. Mike Wooldridge 2
  • 4. Lecture 5 Software Engineering • Activities in software project management: – project planning; – project scheduling; – risk management; – managing people. Mike Wooldridge 3
  • 5. Lecture 5 Software Engineering 2 Project Planning • The biggest single problem that afflicts software developing is that of underestimating resources required for a project. • Developing a realistic project plan is essential to gain an understanding of the resources required, and how these should be applied. • Types of plan: – Software development plan. The central plan, which describes how the system will be developed. – Quality assurance plan. Specifies the quality procedures & standards to be used. – Validation plan. Defines how a client will validate the system that has been developed. Mike Wooldridge 4
  • 6. Lecture 5 Software Engineering – Configuration management plan. Defines how the system will be configured and installed. – Maintenance plan. Defines how the system will be maintained. – Staff development plan. Describes how the skills of the participants will be developed. • We will focus on software development & quality assurance plan. Mike Wooldridge 5
  • 7. Lecture 5 Software Engineering 2.1 The Software Development Plan • This is usually what is meant by a project plan. • Specifies the order of work to be carried out, resources, responsibilities, and so on. • Varies from small and relatively informal to large and very formal. • Developing a project plan is as important as properly designing code: On the basis of a project plan, contracts will be signed and careers made or broken... • Important not to: – overestimate your team’s ability; – simply tell clients what they want to hear; – be pressured by developers (“we can do that in an afternoon!”) Mike Wooldridge 6
  • 8. Lecture 5 Software Engineering 2.2 Structure of Development Plan 1. Introduction brief intro to project — references to requirements spec 2. Project organisation intro to organisations, people, and their roles 3. Risk Analysis what are the key risks to the project? 4. Hardware and software resources what h/ware and s/ware resources will be required for the project and when? 5. Work breakdown the project divided into activities, milestones, deliverables; dependencies between tasks etc 6. Project schedule actual time required — allocation of dates 7. Reporting and progress measurement mechanisms to monitor progress. Mike Wooldridge 7
  • 9. Lecture 5 Software Engineering 2.3 Work Breakdown • There are many ways of breaking down the activities in a project, but the most usual is into: – work packages; – tasks; – deliverables; – milestones. Mike Wooldridge 8
  • 10. Lecture 5 Software Engineering • A workpackage is a large, logically distinct section of work: – typically at least 12 months duration; – may include multiple concurrent activities; – independent of other activities; – but may depend on, or feed into other activities; – typically allocated to a single team. • A task is typically a much smaller piece of work: A part of a workpackage. – typically 3–6 person months effort; – may be dependent on other concurrent activities; – typically allocated to a single person. Mike Wooldridge 9
  • 11. Lecture 5 Software Engineering • A deliverable is an output of the project that can meaningfully be assessed. Examples: – a report (e.g., requirements spec); – code (e.g., alpha tested product). Deliverables are indicators (but only indicators) of progress. • A milestone is a point at which progress on the project may be assessed. Typically a major turning point in the project. EXAMPLES: – delivery of requirements spec; – delivery of alpha tested code. Mike Wooldridge 10
  • 12. Lecture 5 Software Engineering • Usually... – work packages are numbered WP1, WP2, ...; – tasks are numbered T1.1, T1.2, etc, the first number is the number of the workpackage; the second is a sequence number. – deliverables are numbered D1.1, D1.2, etc – milestones are numbered M1, M2 etc. Mike Wooldridge 11
  • 13. Lecture 5 Software Engineering • For each workpackage & task, it is usual to document: – brief description; – earliest start date; – earliest end date; – total person months effort; – pre-requisite WPs or tasks; – dependent WPs or tasks; – who is responsible. Mike Wooldridge 12
  • 14. Lecture 5 Software Engineering 2.4 Critical Paths • The pre-requisites and dependencies of WPs and tasks determine a critical path: the sequence of dependencies in the project. • The critical path is the sequence of activities that takes the longest time to complete. • Any delay to an activity in the critical path will cause delays to the overall project. • Delays to activities not on the critical path need not necessarily cause overall delays. Mike Wooldridge 13
  • 15. Lecture 5 Software Engineering 3 Gantt Charts & Activity Networks • Gantt charts are a kind of bar chart: – time plotted on x axis – bars on y axis for each activity. Mike Wooldridge 14
  • 16. Lecture 5 Software Engineering • An activity network is a labelled graph, with: – nodes corresponding to activities, – arcs labelled with estimated times; – activities are linked if there is a dependency between them. Mike Wooldridge 15
  • 17. Lecture 5 Software Engineering 4 Risks When planning a project, it is critically important to know what the key risks are, and is possible plan for them: • staff turnover; • management change; • hardware unavailability; • requirements change; • specification delays; • size underestimate; • technology change; • product competition. Mike Wooldridge 16
  • 18. Lecture 5 Software Engineering 5 Quality Assurance • Many organisations make use of a quality assurance plan, which sets out standards to be maintained during project development. • – Documentation standards: ∗ what documents; ∗ format & content; – Coding standards: ∗ class/method/variable naming conventions; ∗ comment standards (e.g., javadoc); ∗ testing conventions; Mike Wooldridge 17