SlideShare a Scribd company logo
CLOSING MONITORING & CONTROLLING
PLANNING
EXECUTINGINITIATING
PMBOK® GUIDE 5TH
EDITION - 47 PROJECT MANAGEMENT PROCESSES
Based on the PMBOK® Guide 5th
Edition (English Version) - 2013
Copyright: Project Management Institute, A Guide to the Project Management
Body of Knowledge - Fifth Edition (PMBOK® Guide), Project Management Institute,
Inc., (2013). Copyright and all rights reserved. The material from this publication
has been reproduced with the permission of PMI.
Explanatory Note: The represented process flow is based on figures of the
PMBOK® Guide. Only a few connections are depicted in the flow. To see the detailed
relationships, please recall the process data flow diagrams in the PMBOK® Guide.
This flow does not replace the need for reading the PMBOK® Guide. The PMBOK®
Guide contains a deep explanation of all processes including Inputs, Tools &
Techniques and Outputs that are not listed in this flow.
Adaptation: Ricardo Viana Vargas, MSc, CSM, PRINCE2® Practitioner, PMI-RMP, PMI-
SP, PMP. Download this processes flow at www.ricardo-vargas.com
Review: Wagner Maxsen, Kaplan-Norton BSC Certified Graduate, PMP, PRINCE2
Practitioner, PMI-RMP
Graphic Design: Sérgio Alves Lima Jardim, PMP
Become a member of PMI and download the PMBOK®
Guide 5th
Edition and all other PMI Standards.
www.pmi.org
PMBOK® GUIDE 5TH
EDITION
47 PROJECT MANAGEMENT PROCESSES
INTEGRATION
4.1 Develop Project Charter
Inputs
1. Project statement of work
2. Business case
3. Agreements
4. Enterprise environmental factors
5. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Facilitation techniques
Outputs
1. Project charter
STAKEHOLDER
13.1 Identify Stakeholders
Inputs
1. Project charter
2. Procurement documents
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Stakeholder analysis
2. Expert judgment
3. Meetings
Outputs
1. Stakeholder register
SCOPE
5.2 Collect Requirements
Inputs
1. Scope management plan
2. Requirements management plan
3. Stakeholder management plan
4. Project charter
5. Stakeholder register
Tools & Techniques
1. Interviews
2. Focus groups
3. Facilitated workshops
4. Group creativity techniques
5. Group decision-making techniques
6. Questionnaires and surveys
7. Observations
8. Prototypes
9. Benchmarking
10. Context diagrams
11. Document analysis
Outputs
1. Requirements documentation
2. Requirements traceability matrix
SCOPE
5.1 Plan Scope Management
Inputs
1. Project management plan
2. Project charter
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Meetings
Outputs
1. Scope management plan
2. Requirements management plan
SCOPE
5.4 Create WBS
Inputs
1. Scope management plan
2. Project scope statement
3. Requirements documentation
4. Enterprise environmental factors
5. Organizational process assets
Tools & Techniques
1. Decomposition
2. Expert judgment
Outputs
1. Scope baseline
2. Project documents updates
SCOPE
5.3 Define Scope
Inputs
1. Scope management plan
2. Project charter
3. Requirements documentation
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Product analysis
3. Alternatives generation
4. Facilitated workshops
Outputs
1. Project scope statement
2. Project documents updates
PROCUREMENT
12.1 Plan Procurement Management
Inputs
1. Project management plan
2. Requirements documentation
3. Risk register
4. Activity resource requirements
5. Project schedule
6. Activity cost estimates
7. Stakeholder register
8. Enterprise environmental factors
9. Organizational process assets
Tools & Techniques
1. Make-or-buy analysis
2. Expert judgment
3. Market research
4. Meetings
Outputs
1. Procurement management plan
2. Procurement statement of work
3. Procurement documents
4. Source selection criteria
5. Make-or-buy decisions
6. Change requests
7. Project documents updates
COMMUNICATIONS
10.1 Plan Communications
Management
Inputs
1. Project management plan
2. Stakeholder register
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Communication requirements analysis
2. Communication technology
3. Communication models
4. Communication methods
5. Meetings
Outputs
1. Communications management plan
2. Project documents updates
QUALITY
8.1 Plan Quality Management
Inputs
1. Project management plan
2. Stakeholder register
3. Risk register
4. Requirements documentation
5. Enterprise environmental factors
6. Organizational process assets
Tools & Techniques
1. Cost-benefit analysis
2. Cost of quality
3. Seven basic quality tools
4. Benchmarking
5. Design of experiments
6. Statistical sampling
7. Additional quality planning tools
8. Meetings
Outputs
1. Quality management plan
2. Process improvement plan
3. Quality metrics
4. Quality checklists
5. Project documents updates
STAKEHOLDER
13.2 Plan Stakeholder Management
Inputs
1. Project management plan
2. Stakeholder register
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Meetings
3. Analytical techniques
Outputs
1. Stakeholder management plan
2. Project documents updates
INTEGRATION
4.2 Develop Project
Management Plan
Inputs
1. Project charter
2. Outputs from other processes
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Facilitation techniques
Outputs
1. Project management plan
PROCUREMENT
12.2 Conduct Procurements
Inputs
1. Procurement management plan
2. Procurement documents
3. Source selection criteria
4. Seller proposals
5. Project documents
6. Make-or-buy decisions
7. Procurement statement of work
8. Organizational process assets
Tools & Techniques
1. Bidder conference
2. Proposal evaluation techniques
3. Independent estimates
4. Expert judgment
5. Advertising
6. Analytical techniques
7. Procurement negotiations
Outputs
1. Selected sellers
2. Agreements
3. Resource calendars
4. Change requests
5. Project management plan updates
6. Project documents updates
STAKEHOLDER
13.3 Manage Stakeholder
Engagement
Inputs
1. Stakeholder management plan
2. Communications management plan
3. Change log
4. Organizational process assets
Tools & Techniques
1. Communication methods
2. Interpersonal skills
3. Management skills
Outputs
1. Issue log
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates
INTEGRATION
4.3 Direct and Manage Project Work
Inputs
1. Project management plan
2. Approved change requests
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Project management information system
3. Meetings
Outputs
1. Deliverables
2. Work performance data
3. Change requests
4. Project management plan updates
5. Project documents updates
HUMAN RESOURCE
9.2 Acquire Project Team
Inputs
1. Human resource management plan
2. Enterprise environmental factors
3. Organizational process assets
Tools & Techniques
1. Pre-assignment
2. Negotiation
3. Acquisition
4. Virtual teams
5. Multi-criteria decision analysis
Outputs
1. Project staff assignments
2. Resource calendars
3. Project management plan updates
HUMAN RESOURCE
9.3 Develop Project Team
Inputs
1. Human resource management plan
2. Project staff assignments
3. Resource calendars
Tools & Techniques
1. Interpersonal skills
2. Training
3. Team-building activities
4. Ground rules
5. Colocation
6. Recognition and rewards
7. Personnel assessment tools
Outputs
1. Team performance assessments
2. Enterprise environmental factors updates
HUMAN RESOURCE
9.4 Manage Project Team
Inputs
1. Human resource management plan
2. Project staff assignments
3. Team performance assessments
4. Issue log
5. Work performance reports
6. Organizational process assets
Tools & Techniques
1. Observation and conversation
2. Project performance appraisals
3. Conflict management
4. Interpersonal skills
Outputs
1. Change requests
2. Project management plan updates
3. Project documents updates
4. Enterprise environmental factors updates
5. Organizational process assets updates
QUALITY
8.2 Perform Quality Assurance
Inputs
1. Quality management plan
2. Process improvement plan
3. Quality metrics
4. Quality control measurements
5. Project documents
Tools & Techniques
1. Quality management and control tools
2. Quality audits
3. Process analysis
Outputs
1. Change requests
2. Project management plan updates
3. Project documents updates
4. Organizational process assets updates
COMMUNICATIONS
10.2 Manage Communications
Inputs
1. Communications management plan
2. Work performance reports
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Communication technology
2. Communication models
3. Communication methods
4. Information management systems
5. Performance reporting
Outputs
1. Project communications
2. Project management plan updates
3. Project documents updates
4. Organizational process assets updates
PROCUREMENT
12.4 Close Procurements
Inputs
1. Project management plan
2. Procurement documents
Tools & Techniques
1. Procurement audits
2. Procurement negotiations
3. Records management system
Outputs
1. Closed procurements
2. Organizational process assets updates
INTEGRATION
4.6 Close Project or Phase
Inputs
1. Project management plan
2. Accepted deliverables
3. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analytical techniques
3. Meetings
Outputs
1. Final product, service, or result transition
2. Organizational process assets updates
QUALITY
8.3 Control Quality
Inputs
1. Project management plan
2. Quality metrics
3. Quality checklists
4. Work performance data
5. Approved change requests
6. Deliverables
7. Project documents
8. Organizational process assets
Tools & Techniques
1. Seven basic quality tools
2. Statistical sampling
3. Inspection
4. Approved change requests review
Outputs
1. Quality control measurements
2. Validated changes
3. Verified deliverables
4. Work performance information
5. Change requests
6. Project management plan updates
7. Project documents updates
8. Organizational process assets updates
COST
7.4 Control Costs
Inputs
1. Project management plan
2. Project funding requirements
3. Work performance data
4. Organizational process assets
Tools & Techniques
1. Earned value management
2. Forecasting
3. To-complete performance index (TCPI)
4. Performance reviews
5. Project management software
6. Reserve analysis
Outputs
1. Work performance information
2. Cost forecasts
3. Change requests
4. Project management plan updates
5. Project documents updates
6. Organizational process assets updates
TIME
6.7 Control Schedule
Inputs
1. Project management plan
2. Project schedule
3. Work performance data
4. Project calendars
5. Schedule data
6. Organizational process assets
Tools & Techniques
1. Performance reviews
2. Project management software
3. Resource optimization techniques
4. Modeling techniques
5. Leads and lags
6. Schedule compression
7. Scheduling tool
Outputs
1. Work performance information
2. Schedule forecasts
3. Change requests
4. Project management plan updates
5. Project documents updates
6. Organizational process assets updates
RISK
11.6 Control Risks
Inputs
1. Project management plan
2. Risk register
3. Work performance data
4. Work performance reports
Tools & Techniques
1. Risk reassessment
2. Risk audits
3. Variance and trend analysis
4. Technical performance measurement
5. Reserve analysis
6. Meetings
Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates
COMMUNICATIONS
10.3 Control Communications
Inputs
1. Project management plan
2. Project communications
3. Issue log
4. Work performance data
5. Organizational process assets
Tools & Techniques
1. Information management systems
2. Expert judgment
3. Meetings
Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates
PROCUREMENT
12.3 Control Procurements
Inputs
1. Project management plan
2. Procurement documents
3. Agreements
4. Approved change requests
5. Work performance reports
6. Work performance data
Tools & Techniques
1. Contract change control system
2. Procurement performance reviews
3. Inspections and audits
4. Performance reporting
5. Payment systems
6. Claims administration
7. Records management system
Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates
STAKEHOLDER
13.4 Control Stakeholder
Engagement
Inputs
1. Project management plan
2. Issue log
3. Work performance data
4. Project documents
Tools & Techniques
1. Information management systems
2. Expert judgment
3. Meetings
Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates
HUMAN RESOURCE
9.1 Plan Human Resource
Management
Inputs
1. Project management plan
2. Activity resource requirements
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Organization charts and position
descriptions
2. Networking
3. Organizational theory
4. Expert judgment
5. Meetings
Outputs
1. Human resource management plan
COST
7.1 Plan Cost Management
Inputs
1. Project management plan
2. Project charter
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analytical techniques
3. Meetings
Outputs
1. Cost management plan
COST
7.2 Estimate Costs
Inputs
1. Cost management plan
2. Human resource management plan
3. Scope baseline
4. Project schedule
5. Risk register
6. Enterprise environmental factors
7. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Bottom-up estimating
5. Three-point estimating
6. Reserve analysis
7. Cost of quality
8. Project management software
9. Vendor bid analysis
10. Group decision-making techniques
Outputs
1. Activity cost estimates
2. Basis of estimates
3. Project documents updates
COST
7.3 Determine Budget
Inputs
1. Cost management plan
2. Scope baseline
3. Activity cost estimates
4. Basis of estimates
5. Project schedule
6. Resource calendars
7. Risk register
8. Agreements
9. Organizational process assets
Tools & Techniques
1. Cost aggregation
2. Reserve analysis
3. Expert judgment
4. Historical relationships
5. Funding limit reconciliation
Outputs
1. Cost baseline
2. Project funding requirements
3. Project documents updates
TIME
6.1 Plan Schedule Management
Inputs
1. Project management plan
2. Project charter
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analytical techniques
3. Meetings
Outputs
1. Schedule management plan
TIME
6.6 Develop Schedule
Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Project schedule network diagrams
5. Activity resource requirements
6. Resource calendars
7. Activity duration estimates
8. Project scope statement
9. Risk register
10. Project staff assignments
11. Resource breakdown structure
12. Enterprise environmental factors
13. Organizational process assets
Tools & Techniques
1. Schedule network analysis
2. Critical path method
3. Critical chain method
4. Resource optimization techniques
5. Modeling techniques
6. Leads and lags
7. Schedule compression
8. Scheduling tool
Outputs
1. Schedule baseline
2. Project schedule
3. Schedule data
4. Project calendars
5. Project management plan updates
6. Project documents updates
TIME
6.2 Define Activities
Inputs
1. Schedule management plan
2. Scope baseline
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Decomposition
2. Rolling wave planning
3. Expert judgment
Outputs
1. Activity list
2. Activity attributes
3. Milestone list
TIME
6.4 Estimate Activity Resources
Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Resource calendars
5. Risk register
6. Activity cost estimates
7. Enterprise environmental factors
8. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Alternative analysis
3. Published estimating data
4. Bottom-up estimating
5. Project management software
Outputs
1. Activity resource requirements
2. Resource breakdown structure
3. Project documents updates
TIME
6.3 Sequence Activities
Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Milestone list
5. Project scope statement
6. Enterprise environmental factors
7. Organizational process assets
Tools & Techniques
1. Precedence diagramming method (PDM)
2. Dependency determination
3. Leads and lags
Outputs
1. Project schedule network diagrams
2. Project documents updates
TIME
6.5 Estimate Activity Durations
Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Activity resource requirements
5. Resource calendars
6. Project scope statement
7. Risk register
8. Resource breakdown structure
9. Enterprise environmental factors
10. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Three-point estimating
5. Group decision-making techniques
6. Reserve analysis
Outputs
1. Activity duration estimates
2. Project documents updates
RISK
11.1 Plan Risk Management
Inputs
1. Project management plan
2. Project charter
3. Stakeholder register
4. Enterprise environmental factors
5. Organizational process assets
Tools & Techniques
1. Analytical techniques
2. Expert judgment
3. Meetings
Outputs
1. Risk management plan
RISK
11.4 Perform Quantitative
Risk Analysis
Inputs
1. Risk management plan
2. Cost management plan
3. Schedule management plan
4. Risk register
5. Enterprise environmental factors
6. Organizational process assets
Tools & Techniques
1. Data gathering and representation
techniques
2. Quantitative risk analysis and modeling
techniques
3. Expert judgment
Outputs
1. Project documents updates
RISK
11.2 Identify Risks
Inputs
1. Risk management plan
2. Cost management plan
3. Schedule management plan
4. Quality management plan
5. Human resource management plan
6. Scope baseline
7. Activity cost estimates
8. Activity duration estimates
9. Stakeholder register
10. Project documents
11. Procurement documents
12. Enterprise environmental factors
13. Organizational process assets
Tools & Techniques
1. Documentation reviews
2. Information gathering techniques
3. Checklist analysis
4. Assumptions analysis
5. Diagramming techniques
6. SWOT analysis
7. Expert judgment
Outputs
1. Risk register
RISK
11.3 Perform Qualitative
Risk Analysis
Inputs
1. Risk management plan
2. Scope baseline
3. Risk register
4. Enterprise environmental factors
5. Organizational process assets
Tools & Techniques
1. Risk probability and impact assessment
2. Probability and impact matrix
3. Risk data quality assessment
4. Risk categorization
5. Risk urgency assessment
6. Expert judgment
Outputs
1. Project documents updates
RISK
11.5 Plan Risk Responses
Inputs
1. Risk management plan
2. Risk register
Tools & Techniques
1. Strategies for negative risks or threats
2. Strategies for positive risks or
opportunities
3. Contingent response strategies
4. Expert judgment
Outputs
1. Project management plan updates
2. Project documents updates
INTEGRATION
4.5 Perform Integrated
Change Control
Inputs
1. Project management plan
2. Work performance reports
3. Change requests
4. Enterprise environmental factors
5. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Meetings
3. Change control tools
Outputs
1. Approved change requests
2. Change log
3. Project management plan updates
4. Project documents updates
INTEGRATION
4.4 Monitor and Control
Project Work
Inputs
1. Project management plan
2. Schedule forecasts
3. Cost forecasts
4. Validated changes
5. Work performance information
6. Enterprise environmental factors
7. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analytical techniques
3. Project management information system
4. Meetings
Outputs
1. Change requests
2. Work performance reports
3. Project management plan updates
4. Project documents updates
SCOPE
5.5 Validate Scope
Inputs
1. Project management plan
2. Requirements documentation
3. Requirements traceability matrix
4. Verified deliverables
5. Work performance data
Tools & Techniques
1. Inspection
2. Group decision-making techniques
Outputs
1. Accepted deliverables
2. Change requests
3. Work performance information
4. Project documents updates
SCOPE
5.6 Control Scope
Inputs
1. Project management plan
2. Requirements documentation
3. Requirements traceability matrix
4. Work performance data
5. Organizational process assets
Tools & Techniques
1. Variance analysis
Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates

More Related Content

PDF
PMBOK 5th Edition Schema
PPTX
PMBOK(R) sixth edition Data Flow diagram by english, A3 Printable.
PDF
PMBOK 6th Processes Flow Main Lines
PDF
PMBOK processes schema by Ricardo Vargas
PDF
Mapa procesos pmbok 5
PDF
Organizational project maturity model (opm3)
PDF
Itto pmbok guide 6th edition
PDF
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK 5th Edition Schema
PMBOK(R) sixth edition Data Flow diagram by english, A3 Printable.
PMBOK 6th Processes Flow Main Lines
PMBOK processes schema by Ricardo Vargas
Mapa procesos pmbok 5
Organizational project maturity model (opm3)
Itto pmbok guide 6th edition
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version

What's hot (20)

PDF
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PDF
PMBOK® Guide Processes Flow – 6th Edition
PDF
Pmbok Processes Flow, ALL!
PDF
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PDF
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
PDF
Develop Project Management Plan Data Flow Diagram
PDF
PMP ITTOs Quick Review
PDF
PMP PMBOK 6th
PPT
PMP Certification Presentation
PPTX
Pmp ITTO Complete
PDF
Establishing an Effective PMO
PDF
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
PPTX
PMO Kick-Off Presentation
PPTX
Scope Management ITTO
PPSX
PMO-Framework
PPTX
The PMO VALUE RING Workshop
PDF
Chap 4.0 Project integration management Overview
PDF
Free CBAP V3 questions
PDF
How to Setup a High-IMPACT PMO
PPTX
Project Management - PMI Approach
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition
Pmbok Processes Flow, ALL!
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
Develop Project Management Plan Data Flow Diagram
PMP ITTOs Quick Review
PMP PMBOK 6th
PMP Certification Presentation
Pmp ITTO Complete
Establishing an Effective PMO
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
PMO Kick-Off Presentation
Scope Management ITTO
PMO-Framework
The PMO VALUE RING Workshop
Chap 4.0 Project integration management Overview
Free CBAP V3 questions
How to Setup a High-IMPACT PMO
Project Management - PMI Approach
Ad

Viewers also liked (9)

PPTX
1.3 project management process groups & knowledge areas 1
PDF
PMBOK 2008 Map of Processes
PPTX
Project Management Framework
PDF
Pmbok 5 ed diagram
PPT
Pmp exam overview
PDF
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
PPS
Temps verbals
PPTX
PMI Project Management Principles
PDF
Verb tots els temps
1.3 project management process groups & knowledge areas 1
PMBOK 2008 Map of Processes
Project Management Framework
Pmbok 5 ed diagram
Pmp exam overview
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Temps verbals
PMI Project Management Principles
Verb tots els temps
Ad

Similar to PMBOK® Guide 5th edition Processes Flow in English (20)

PDF
Pmp itto factors_dfd
PDF
Pmp itto factors
PPTX
Project Integration Management - PMP Preparation
PDF
Project Management Process Groups 101
PDF
Introduction to pmp
PDF
PMI knowledge areas and processes
PPTX
Pm training 1 18
PDF
PM process groups and processes
PPT
Project Management for Technical Communication Professionals
PPTX
PMI Changes to PMP Exam Content 2015
PDF
Project Management.pdf
PDF
PMBOK's Tools techniques combination matrix
PDF
CompTIA Project Study Guide Exam PK0 003 1st Edition Kim Heldman
PDF
Topic 6 - Project Integration Management.pdf
PDF
CompTIA Project Study Guide Exam PK0 003 1st Edition Kim Heldman
PDF
Topic 7 - Project Scope Management.pdf
PDF
Immediate download CompTIA Project Study Guide Exam PK0 003 1st Edition Kim H...
PPTX
Mastering ITTO DataFlow PMP - PMBOK Version 5
PPTX
Project management unlock Based on PMBOK®
Pmp itto factors_dfd
Pmp itto factors
Project Integration Management - PMP Preparation
Project Management Process Groups 101
Introduction to pmp
PMI knowledge areas and processes
Pm training 1 18
PM process groups and processes
Project Management for Technical Communication Professionals
PMI Changes to PMP Exam Content 2015
Project Management.pdf
PMBOK's Tools techniques combination matrix
CompTIA Project Study Guide Exam PK0 003 1st Edition Kim Heldman
Topic 6 - Project Integration Management.pdf
CompTIA Project Study Guide Exam PK0 003 1st Edition Kim Heldman
Topic 7 - Project Scope Management.pdf
Immediate download CompTIA Project Study Guide Exam PK0 003 1st Edition Kim H...
Mastering ITTO DataFlow PMP - PMBOK Version 5
Project management unlock Based on PMBOK®

More from Ricardo Viana Vargas (20)

PDF
Fluxo de Processos do Guia PMBOK® – 6ª Edição
PDF
Fluxo de Processos do Guia PMBOK® – 6ª Edição (Versão simplificada)
PDF
Aplicando Redes Neurais e Estimativa Análoga para Determinar o Orçamento do P...
PDF
Applying Neural Networks and Analogous Estimating to Determine the Project Bu...
PDF
Modelando Linhas de Balanço com Relacionamentos “Início-Término”
PDF
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
PDF
Sustainability Marker to Support the Project Selection Process: the UNOPS Case
PDF
Milestones Trend Analysis (MTA) - Conceitos Básicos
PDF
Milestones Trend Analysis (MTA) - Fundamentals
PDF
Diagrammes de Flux Guide PMBOK® 5e Édition en Français
PDF
Diagrammes de Flux Guide PMBOK® 5e Édition en Français - Version simplifiée
PDF
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano
PDF
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano - Versione sem...
PDF
Ricardo vargas pmbok_flow_5ed_color_es
PDF
Flujo de Procesos de la Guía PMBOK® 5ª edición en Español - Versión simplificada
PDF
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch (vereinfachte Version)
PDF
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch
PDF
Lessons from 40 PPM Experts on Making the Transition from Project Management ...
PDF
Understanding Opportunities, Challenges and Strategies to Build Your Career i...
PDF
Fluxo de Processos do Guia PMBOK® 5ª Edição em Português
Fluxo de Processos do Guia PMBOK® – 6ª Edição
Fluxo de Processos do Guia PMBOK® – 6ª Edição (Versão simplificada)
Aplicando Redes Neurais e Estimativa Análoga para Determinar o Orçamento do P...
Applying Neural Networks and Analogous Estimating to Determine the Project Bu...
Modelando Linhas de Balanço com Relacionamentos “Início-Término”
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Sustainability Marker to Support the Project Selection Process: the UNOPS Case
Milestones Trend Analysis (MTA) - Conceitos Básicos
Milestones Trend Analysis (MTA) - Fundamentals
Diagrammes de Flux Guide PMBOK® 5e Édition en Français
Diagrammes de Flux Guide PMBOK® 5e Édition en Français - Version simplifiée
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano - Versione sem...
Ricardo vargas pmbok_flow_5ed_color_es
Flujo de Procesos de la Guía PMBOK® 5ª edición en Español - Versión simplificada
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch (vereinfachte Version)
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch
Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Understanding Opportunities, Challenges and Strategies to Build Your Career i...
Fluxo de Processos do Guia PMBOK® 5ª Edição em Português

Recently uploaded (20)

PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
DOCX
Business Management - unit 1 and 2
PPT
Chapter four Project-Preparation material
PDF
Roadmap Map-digital Banking feature MB,IB,AB
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PPT
Data mining for business intelligence ch04 sharda
PPTX
Amazon (Business Studies) management studies
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
WRN_Investor_Presentation_August 2025.pdf
PDF
MSPs in 10 Words - Created by US MSP Network
DOCX
Euro SEO Services 1st 3 General Updates.docx
PDF
IFRS Notes in your pocket for study all the time
PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PDF
Traveri Digital Marketing Seminar 2025 by Corey and Jessica Perlman
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PPTX
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
PDF
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
Ôn tập tiếng anh trong kinh doanh nâng cao
Business Management - unit 1 and 2
Chapter four Project-Preparation material
Roadmap Map-digital Banking feature MB,IB,AB
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
Data mining for business intelligence ch04 sharda
Amazon (Business Studies) management studies
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
WRN_Investor_Presentation_August 2025.pdf
MSPs in 10 Words - Created by US MSP Network
Euro SEO Services 1st 3 General Updates.docx
IFRS Notes in your pocket for study all the time
New Microsoft PowerPoint Presentation - Copy.pptx
DOC-20250806-WA0002._20250806_112011_0000.pdf
Traveri Digital Marketing Seminar 2025 by Corey and Jessica Perlman
Power and position in leadershipDOC-20250808-WA0011..pdf
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf

PMBOK® Guide 5th edition Processes Flow in English

  • 1. CLOSING MONITORING & CONTROLLING PLANNING EXECUTINGINITIATING PMBOK® GUIDE 5TH EDITION - 47 PROJECT MANAGEMENT PROCESSES Based on the PMBOK® Guide 5th Edition (English Version) - 2013 Copyright: Project Management Institute, A Guide to the Project Management Body of Knowledge - Fifth Edition (PMBOK® Guide), Project Management Institute, Inc., (2013). Copyright and all rights reserved. The material from this publication has been reproduced with the permission of PMI. Explanatory Note: The represented process flow is based on figures of the PMBOK® Guide. Only a few connections are depicted in the flow. To see the detailed relationships, please recall the process data flow diagrams in the PMBOK® Guide. This flow does not replace the need for reading the PMBOK® Guide. The PMBOK® Guide contains a deep explanation of all processes including Inputs, Tools & Techniques and Outputs that are not listed in this flow. Adaptation: Ricardo Viana Vargas, MSc, CSM, PRINCE2® Practitioner, PMI-RMP, PMI- SP, PMP. Download this processes flow at www.ricardo-vargas.com Review: Wagner Maxsen, Kaplan-Norton BSC Certified Graduate, PMP, PRINCE2 Practitioner, PMI-RMP Graphic Design: Sérgio Alves Lima Jardim, PMP Become a member of PMI and download the PMBOK® Guide 5th Edition and all other PMI Standards. www.pmi.org PMBOK® GUIDE 5TH EDITION 47 PROJECT MANAGEMENT PROCESSES INTEGRATION 4.1 Develop Project Charter Inputs 1. Project statement of work 2. Business case 3. Agreements 4. Enterprise environmental factors 5. Organizational process assets Tools & Techniques 1. Expert judgment 2. Facilitation techniques Outputs 1. Project charter STAKEHOLDER 13.1 Identify Stakeholders Inputs 1. Project charter 2. Procurement documents 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Stakeholder analysis 2. Expert judgment 3. Meetings Outputs 1. Stakeholder register SCOPE 5.2 Collect Requirements Inputs 1. Scope management plan 2. Requirements management plan 3. Stakeholder management plan 4. Project charter 5. Stakeholder register Tools & Techniques 1. Interviews 2. Focus groups 3. Facilitated workshops 4. Group creativity techniques 5. Group decision-making techniques 6. Questionnaires and surveys 7. Observations 8. Prototypes 9. Benchmarking 10. Context diagrams 11. Document analysis Outputs 1. Requirements documentation 2. Requirements traceability matrix SCOPE 5.1 Plan Scope Management Inputs 1. Project management plan 2. Project charter 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment 2. Meetings Outputs 1. Scope management plan 2. Requirements management plan SCOPE 5.4 Create WBS Inputs 1. Scope management plan 2. Project scope statement 3. Requirements documentation 4. Enterprise environmental factors 5. Organizational process assets Tools & Techniques 1. Decomposition 2. Expert judgment Outputs 1. Scope baseline 2. Project documents updates SCOPE 5.3 Define Scope Inputs 1. Scope management plan 2. Project charter 3. Requirements documentation 4. Organizational process assets Tools & Techniques 1. Expert judgment 2. Product analysis 3. Alternatives generation 4. Facilitated workshops Outputs 1. Project scope statement 2. Project documents updates PROCUREMENT 12.1 Plan Procurement Management Inputs 1. Project management plan 2. Requirements documentation 3. Risk register 4. Activity resource requirements 5. Project schedule 6. Activity cost estimates 7. Stakeholder register 8. Enterprise environmental factors 9. Organizational process assets Tools & Techniques 1. Make-or-buy analysis 2. Expert judgment 3. Market research 4. Meetings Outputs 1. Procurement management plan 2. Procurement statement of work 3. Procurement documents 4. Source selection criteria 5. Make-or-buy decisions 6. Change requests 7. Project documents updates COMMUNICATIONS 10.1 Plan Communications Management Inputs 1. Project management plan 2. Stakeholder register 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Communication requirements analysis 2. Communication technology 3. Communication models 4. Communication methods 5. Meetings Outputs 1. Communications management plan 2. Project documents updates QUALITY 8.1 Plan Quality Management Inputs 1. Project management plan 2. Stakeholder register 3. Risk register 4. Requirements documentation 5. Enterprise environmental factors 6. Organizational process assets Tools & Techniques 1. Cost-benefit analysis 2. Cost of quality 3. Seven basic quality tools 4. Benchmarking 5. Design of experiments 6. Statistical sampling 7. Additional quality planning tools 8. Meetings Outputs 1. Quality management plan 2. Process improvement plan 3. Quality metrics 4. Quality checklists 5. Project documents updates STAKEHOLDER 13.2 Plan Stakeholder Management Inputs 1. Project management plan 2. Stakeholder register 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment 2. Meetings 3. Analytical techniques Outputs 1. Stakeholder management plan 2. Project documents updates INTEGRATION 4.2 Develop Project Management Plan Inputs 1. Project charter 2. Outputs from other processes 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment 2. Facilitation techniques Outputs 1. Project management plan PROCUREMENT 12.2 Conduct Procurements Inputs 1. Procurement management plan 2. Procurement documents 3. Source selection criteria 4. Seller proposals 5. Project documents 6. Make-or-buy decisions 7. Procurement statement of work 8. Organizational process assets Tools & Techniques 1. Bidder conference 2. Proposal evaluation techniques 3. Independent estimates 4. Expert judgment 5. Advertising 6. Analytical techniques 7. Procurement negotiations Outputs 1. Selected sellers 2. Agreements 3. Resource calendars 4. Change requests 5. Project management plan updates 6. Project documents updates STAKEHOLDER 13.3 Manage Stakeholder Engagement Inputs 1. Stakeholder management plan 2. Communications management plan 3. Change log 4. Organizational process assets Tools & Techniques 1. Communication methods 2. Interpersonal skills 3. Management skills Outputs 1. Issue log 2. Change requests 3. Project management plan updates 4. Project documents updates 5. Organizational process assets updates INTEGRATION 4.3 Direct and Manage Project Work Inputs 1. Project management plan 2. Approved change requests 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment 2. Project management information system 3. Meetings Outputs 1. Deliverables 2. Work performance data 3. Change requests 4. Project management plan updates 5. Project documents updates HUMAN RESOURCE 9.2 Acquire Project Team Inputs 1. Human resource management plan 2. Enterprise environmental factors 3. Organizational process assets Tools & Techniques 1. Pre-assignment 2. Negotiation 3. Acquisition 4. Virtual teams 5. Multi-criteria decision analysis Outputs 1. Project staff assignments 2. Resource calendars 3. Project management plan updates HUMAN RESOURCE 9.3 Develop Project Team Inputs 1. Human resource management plan 2. Project staff assignments 3. Resource calendars Tools & Techniques 1. Interpersonal skills 2. Training 3. Team-building activities 4. Ground rules 5. Colocation 6. Recognition and rewards 7. Personnel assessment tools Outputs 1. Team performance assessments 2. Enterprise environmental factors updates HUMAN RESOURCE 9.4 Manage Project Team Inputs 1. Human resource management plan 2. Project staff assignments 3. Team performance assessments 4. Issue log 5. Work performance reports 6. Organizational process assets Tools & Techniques 1. Observation and conversation 2. Project performance appraisals 3. Conflict management 4. Interpersonal skills Outputs 1. Change requests 2. Project management plan updates 3. Project documents updates 4. Enterprise environmental factors updates 5. Organizational process assets updates QUALITY 8.2 Perform Quality Assurance Inputs 1. Quality management plan 2. Process improvement plan 3. Quality metrics 4. Quality control measurements 5. Project documents Tools & Techniques 1. Quality management and control tools 2. Quality audits 3. Process analysis Outputs 1. Change requests 2. Project management plan updates 3. Project documents updates 4. Organizational process assets updates COMMUNICATIONS 10.2 Manage Communications Inputs 1. Communications management plan 2. Work performance reports 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Communication technology 2. Communication models 3. Communication methods 4. Information management systems 5. Performance reporting Outputs 1. Project communications 2. Project management plan updates 3. Project documents updates 4. Organizational process assets updates PROCUREMENT 12.4 Close Procurements Inputs 1. Project management plan 2. Procurement documents Tools & Techniques 1. Procurement audits 2. Procurement negotiations 3. Records management system Outputs 1. Closed procurements 2. Organizational process assets updates INTEGRATION 4.6 Close Project or Phase Inputs 1. Project management plan 2. Accepted deliverables 3. Organizational process assets Tools & Techniques 1. Expert judgment 2. Analytical techniques 3. Meetings Outputs 1. Final product, service, or result transition 2. Organizational process assets updates QUALITY 8.3 Control Quality Inputs 1. Project management plan 2. Quality metrics 3. Quality checklists 4. Work performance data 5. Approved change requests 6. Deliverables 7. Project documents 8. Organizational process assets Tools & Techniques 1. Seven basic quality tools 2. Statistical sampling 3. Inspection 4. Approved change requests review Outputs 1. Quality control measurements 2. Validated changes 3. Verified deliverables 4. Work performance information 5. Change requests 6. Project management plan updates 7. Project documents updates 8. Organizational process assets updates COST 7.4 Control Costs Inputs 1. Project management plan 2. Project funding requirements 3. Work performance data 4. Organizational process assets Tools & Techniques 1. Earned value management 2. Forecasting 3. To-complete performance index (TCPI) 4. Performance reviews 5. Project management software 6. Reserve analysis Outputs 1. Work performance information 2. Cost forecasts 3. Change requests 4. Project management plan updates 5. Project documents updates 6. Organizational process assets updates TIME 6.7 Control Schedule Inputs 1. Project management plan 2. Project schedule 3. Work performance data 4. Project calendars 5. Schedule data 6. Organizational process assets Tools & Techniques 1. Performance reviews 2. Project management software 3. Resource optimization techniques 4. Modeling techniques 5. Leads and lags 6. Schedule compression 7. Scheduling tool Outputs 1. Work performance information 2. Schedule forecasts 3. Change requests 4. Project management plan updates 5. Project documents updates 6. Organizational process assets updates RISK 11.6 Control Risks Inputs 1. Project management plan 2. Risk register 3. Work performance data 4. Work performance reports Tools & Techniques 1. Risk reassessment 2. Risk audits 3. Variance and trend analysis 4. Technical performance measurement 5. Reserve analysis 6. Meetings Outputs 1. Work performance information 2. Change requests 3. Project management plan updates 4. Project documents updates 5. Organizational process assets updates COMMUNICATIONS 10.3 Control Communications Inputs 1. Project management plan 2. Project communications 3. Issue log 4. Work performance data 5. Organizational process assets Tools & Techniques 1. Information management systems 2. Expert judgment 3. Meetings Outputs 1. Work performance information 2. Change requests 3. Project management plan updates 4. Project documents updates 5. Organizational process assets updates PROCUREMENT 12.3 Control Procurements Inputs 1. Project management plan 2. Procurement documents 3. Agreements 4. Approved change requests 5. Work performance reports 6. Work performance data Tools & Techniques 1. Contract change control system 2. Procurement performance reviews 3. Inspections and audits 4. Performance reporting 5. Payment systems 6. Claims administration 7. Records management system Outputs 1. Work performance information 2. Change requests 3. Project management plan updates 4. Project documents updates 5. Organizational process assets updates STAKEHOLDER 13.4 Control Stakeholder Engagement Inputs 1. Project management plan 2. Issue log 3. Work performance data 4. Project documents Tools & Techniques 1. Information management systems 2. Expert judgment 3. Meetings Outputs 1. Work performance information 2. Change requests 3. Project management plan updates 4. Project documents updates 5. Organizational process assets updates HUMAN RESOURCE 9.1 Plan Human Resource Management Inputs 1. Project management plan 2. Activity resource requirements 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Organization charts and position descriptions 2. Networking 3. Organizational theory 4. Expert judgment 5. Meetings Outputs 1. Human resource management plan COST 7.1 Plan Cost Management Inputs 1. Project management plan 2. Project charter 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment 2. Analytical techniques 3. Meetings Outputs 1. Cost management plan COST 7.2 Estimate Costs Inputs 1. Cost management plan 2. Human resource management plan 3. Scope baseline 4. Project schedule 5. Risk register 6. Enterprise environmental factors 7. Organizational process assets Tools & Techniques 1. Expert judgment 2. Analogous estimating 3. Parametric estimating 4. Bottom-up estimating 5. Three-point estimating 6. Reserve analysis 7. Cost of quality 8. Project management software 9. Vendor bid analysis 10. Group decision-making techniques Outputs 1. Activity cost estimates 2. Basis of estimates 3. Project documents updates COST 7.3 Determine Budget Inputs 1. Cost management plan 2. Scope baseline 3. Activity cost estimates 4. Basis of estimates 5. Project schedule 6. Resource calendars 7. Risk register 8. Agreements 9. Organizational process assets Tools & Techniques 1. Cost aggregation 2. Reserve analysis 3. Expert judgment 4. Historical relationships 5. Funding limit reconciliation Outputs 1. Cost baseline 2. Project funding requirements 3. Project documents updates TIME 6.1 Plan Schedule Management Inputs 1. Project management plan 2. Project charter 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment 2. Analytical techniques 3. Meetings Outputs 1. Schedule management plan TIME 6.6 Develop Schedule Inputs 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Project schedule network diagrams 5. Activity resource requirements 6. Resource calendars 7. Activity duration estimates 8. Project scope statement 9. Risk register 10. Project staff assignments 11. Resource breakdown structure 12. Enterprise environmental factors 13. Organizational process assets Tools & Techniques 1. Schedule network analysis 2. Critical path method 3. Critical chain method 4. Resource optimization techniques 5. Modeling techniques 6. Leads and lags 7. Schedule compression 8. Scheduling tool Outputs 1. Schedule baseline 2. Project schedule 3. Schedule data 4. Project calendars 5. Project management plan updates 6. Project documents updates TIME 6.2 Define Activities Inputs 1. Schedule management plan 2. Scope baseline 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Decomposition 2. Rolling wave planning 3. Expert judgment Outputs 1. Activity list 2. Activity attributes 3. Milestone list TIME 6.4 Estimate Activity Resources Inputs 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Resource calendars 5. Risk register 6. Activity cost estimates 7. Enterprise environmental factors 8. Organizational process assets Tools & Techniques 1. Expert judgment 2. Alternative analysis 3. Published estimating data 4. Bottom-up estimating 5. Project management software Outputs 1. Activity resource requirements 2. Resource breakdown structure 3. Project documents updates TIME 6.3 Sequence Activities Inputs 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Milestone list 5. Project scope statement 6. Enterprise environmental factors 7. Organizational process assets Tools & Techniques 1. Precedence diagramming method (PDM) 2. Dependency determination 3. Leads and lags Outputs 1. Project schedule network diagrams 2. Project documents updates TIME 6.5 Estimate Activity Durations Inputs 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Activity resource requirements 5. Resource calendars 6. Project scope statement 7. Risk register 8. Resource breakdown structure 9. Enterprise environmental factors 10. Organizational process assets Tools & Techniques 1. Expert judgment 2. Analogous estimating 3. Parametric estimating 4. Three-point estimating 5. Group decision-making techniques 6. Reserve analysis Outputs 1. Activity duration estimates 2. Project documents updates RISK 11.1 Plan Risk Management Inputs 1. Project management plan 2. Project charter 3. Stakeholder register 4. Enterprise environmental factors 5. Organizational process assets Tools & Techniques 1. Analytical techniques 2. Expert judgment 3. Meetings Outputs 1. Risk management plan RISK 11.4 Perform Quantitative Risk Analysis Inputs 1. Risk management plan 2. Cost management plan 3. Schedule management plan 4. Risk register 5. Enterprise environmental factors 6. Organizational process assets Tools & Techniques 1. Data gathering and representation techniques 2. Quantitative risk analysis and modeling techniques 3. Expert judgment Outputs 1. Project documents updates RISK 11.2 Identify Risks Inputs 1. Risk management plan 2. Cost management plan 3. Schedule management plan 4. Quality management plan 5. Human resource management plan 6. Scope baseline 7. Activity cost estimates 8. Activity duration estimates 9. Stakeholder register 10. Project documents 11. Procurement documents 12. Enterprise environmental factors 13. Organizational process assets Tools & Techniques 1. Documentation reviews 2. Information gathering techniques 3. Checklist analysis 4. Assumptions analysis 5. Diagramming techniques 6. SWOT analysis 7. Expert judgment Outputs 1. Risk register RISK 11.3 Perform Qualitative Risk Analysis Inputs 1. Risk management plan 2. Scope baseline 3. Risk register 4. Enterprise environmental factors 5. Organizational process assets Tools & Techniques 1. Risk probability and impact assessment 2. Probability and impact matrix 3. Risk data quality assessment 4. Risk categorization 5. Risk urgency assessment 6. Expert judgment Outputs 1. Project documents updates RISK 11.5 Plan Risk Responses Inputs 1. Risk management plan 2. Risk register Tools & Techniques 1. Strategies for negative risks or threats 2. Strategies for positive risks or opportunities 3. Contingent response strategies 4. Expert judgment Outputs 1. Project management plan updates 2. Project documents updates INTEGRATION 4.5 Perform Integrated Change Control Inputs 1. Project management plan 2. Work performance reports 3. Change requests 4. Enterprise environmental factors 5. Organizational process assets Tools & Techniques 1. Expert judgment 2. Meetings 3. Change control tools Outputs 1. Approved change requests 2. Change log 3. Project management plan updates 4. Project documents updates INTEGRATION 4.4 Monitor and Control Project Work Inputs 1. Project management plan 2. Schedule forecasts 3. Cost forecasts 4. Validated changes 5. Work performance information 6. Enterprise environmental factors 7. Organizational process assets Tools & Techniques 1. Expert judgment 2. Analytical techniques 3. Project management information system 4. Meetings Outputs 1. Change requests 2. Work performance reports 3. Project management plan updates 4. Project documents updates SCOPE 5.5 Validate Scope Inputs 1. Project management plan 2. Requirements documentation 3. Requirements traceability matrix 4. Verified deliverables 5. Work performance data Tools & Techniques 1. Inspection 2. Group decision-making techniques Outputs 1. Accepted deliverables 2. Change requests 3. Work performance information 4. Project documents updates SCOPE 5.6 Control Scope Inputs 1. Project management plan 2. Requirements documentation 3. Requirements traceability matrix 4. Work performance data 5. Organizational process assets Tools & Techniques 1. Variance analysis Outputs 1. Work performance information 2. Change requests 3. Project management plan updates 4. Project documents updates 5. Organizational process assets updates