METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 1 | 6
METHOD STATEMENT
FOR
AHU INSTALLATION
METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 2 | 6
INTRODUCTION
This Method statement describes in details the onsite installation of AHU. AHU shall be
installed as per approved material submittal.
SCOPE OF WORKS
The Method Statement shall cover all works related to the installation of AHU as per
approved shop drawing and approved material submittal for the project.
REFERENCE DOCUMENTS
3.1. Specification – Section 15855
3.2. Recommendation of approved material submittal
.
ORGANIZATION & RESPONSIBILITIES
Project Manager:
It is the Project Manager duty to ensure that all necessary safety and protective equipment are
provided along with properly trained and qualified personnel. Moreover, to ensure that all
survey works are carried out in accordance with this method statement.
Quality Engineer’s:
It is the Quality Engineer’s responsibility to ensure that all surveying equipment is being
calibrated. Ensure that all inspections and tests are carried out as per Project requirements and
that all are recorded. Maintaining all quality records relevant to verification of records.
Site Engineer / Site Supervisor’s:
It is the Site Engineer / Site Supervisor’s duty to organize the work force in a safe manner and to
ensure that safety and protective equipment are being properly utilized. He must also ensure
that the method statement procedure is followed and notify the HAC Q.C / EHAF International
for inspection.
Surveyor’s:
It is the Surveyor’s duty to obtain all data and information required for surveys. Determine
methods to establish survey control. Use appropriate equipment to complete assigned task.
Keep accurate notes and records to describe and certify work performed. Abide by all Site Safety
and Quality Requirements.
Safety Engineer / Officer’s:
METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 3 | 6
 The Safety Engineer is responsible for devising and implementing programmers and plans
to safeguard, health and safety of all employees, and to prevent loss or damage to the
existing assets and projects, He is responsible for the implementing of the safety
programs. He is also responsible to:
 Provide support to site safety officers advising them on safe working methods and
assisting with training of personnel.
 Carryout regular site safety audits and reports and correct unsafe work practices and
potential hazards.
 Investigate and report all accidents near misses and recommend prevention measures.
Ensure maintenances of good hygienic standards and availability of safety equipment and
first aid treatment.
 Present monthly safety reports and required documents.
Safety Officers are responsible for:
 The day to day activities of maintaining safety on project site, they must: Understand and
comply with requirements of the safety manual.
 Cooperate with the safety engineer to create and maintain safe working conditions.
 Assist the site engineers and foremen to organize the work area so that the men can
perform their duties with maximum efficiency and minimize risk to themselves or to
equipment.
 Inspect equipment and tools before use to ensure correct storage and properly
utilization. Maintain record of all injuries and damages on site, submit reports as
required.
RESOURCES
Equipment & Machinery:
The following equipment will be used to carry out the installation of FANS.
 Mechanical hand tool
 Mobile Crane
 Fork Lift
METHODOLOGY
Storage
 AHU shall be stored in such a manner as to preserve its quality condition.
 AHU are to be as per manufacturer recommendations but at the same time it should be
accessible.
METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 4 | 6
 The quantity to be delivered at site for installation shall be consistent with the necessary
required quantity of the work to perform.
Setting Out
 Check the readiness of reference and coordinates.
 Check the other activates works related with the installations.
 Arrange all necessary work permit, check and verify the actual site condition.
Unloading and Shifting:
 AHU shall be transported by a delivery truck and mechanical crane / fork lift to the specific
work place.
 Safety Officer will be present during loading and unloading of.
 Two lifting point will be used during the loading and unloading of AHU to ensure safety
that no incident will occurs. Traffic Aide will be present during loading and unloading of
Unit for maintaining the traffic in the project site if needed.
 All lifting equipment will be inspected daily before operating. Any parts detected damages
must be replaced immediately before operating.
Installation for AHU at Concrete roof
 Mech. Installation: -
 Set and fix AHU steel frame at Unit location at roof.
 Connect Unit with duct through duct reducer.
 Installation manual attached.
 Electrical Installation: -
 Connect power cable from MCC Panel to disconnecting switch.
 Connect Power Cable from disconnecting switch to Unit motor.
QUALITY ASSURANCE
Material : Approved submittal.
Location : As per approved shop drawings
HEALTH, SAFETY AND ENVIRONMENT
METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 5 | 6
PPE Requirements
As a minimum the following PPE should be used by staff / Labors
 Hard hat.
 Safety shoes.
 Safety eye glasses.
 Hand gloves.
 High visibility vest.
Any additional PPE as required by local rules or mandatory requirement shall be used.
Safety Accessories
 Traffic Cones.
 Warning /barricade/barrier tape.
 Safety signs.
 Cooled water container for drinking.
 First Aid box.
 Workers rest area
 Portable toilet
 Fire extinguishers
 Sign boards of Emergency contact details/persons
Information to Personnel.
 Safety Induction will be done in accordance with HSE Policy prior to start work in site.
 Safety toolbox meetings to be carried out prior to work.
 Before job start checklist of protective & safety equipment to be use are in order.
 Personal protective & safety equipment as per requirement to be performed by
personnel to do the task.
 Toolbox talk to be convened & attended by all personnel assigned to do the task.
Work crew will be given instruction on site surveying procedure & all risk associated
with the works and registered attendance.
 Safety personnel & designated responsible person will ensure that all above is carried
out & any other statutory requirements are complied with before any work takes.
 Hazard analysis to be done.
METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 6 | 6
 Personnel who have been briefed in the correct equipment set up.
 Personnel will wear gloves, footwear, head & eye protection during work.
 Use the correct tools to do the task.
 Removal of any obstructive / protruding materials.
APPENDICES
1. Risk assessment.

More Related Content

PPT
Scaffolding safety training.ppt
PDF
Hot Works Safety Training
PDF
DOCX
Painting risk assessment template
PPTX
Confined space entry ppt slide
PDF
7) hydro test 3
PPTX
Presentation hazop introduction
PDF
Safety abbreviations
Scaffolding safety training.ppt
Hot Works Safety Training
Painting risk assessment template
Confined space entry ppt slide
7) hydro test 3
Presentation hazop introduction
Safety abbreviations

What's hot (20)

PDF
Introduction to oil & gas health safety environment
PDF
Piping Isometric drawing guide
PPTX
PDF
Tank design - powerpoint slides
PPT
Scaffold Safety Presentation.ppt
PDF
occupational health and safety training manual
PPTX
Hazop Hazard and Operability Study
PPT
psv and pvrvdesign calculation.ppt
PDF
Working at height slides
PPTX
Hazards and safety in confined spaces
PDF
Scaffold safe work method statement
PPT
HAZOP AND OPERABILITY STUDY
PPTX
osha 1926 confined space construction 2015
PDF
Wellhead control panels
PPTX
Proper installation GRE
PPTX
PPT
Pipe Clamp Design, Application & Installation - November
PPT
Industrial safetY of height works
PPTX
Lifting Operation Safety ppt.pptx
PPT
Anhydrous ammonia safety
Introduction to oil & gas health safety environment
Piping Isometric drawing guide
Tank design - powerpoint slides
Scaffold Safety Presentation.ppt
occupational health and safety training manual
Hazop Hazard and Operability Study
psv and pvrvdesign calculation.ppt
Working at height slides
Hazards and safety in confined spaces
Scaffold safe work method statement
HAZOP AND OPERABILITY STUDY
osha 1926 confined space construction 2015
Wellhead control panels
Proper installation GRE
Pipe Clamp Design, Application & Installation - November
Industrial safetY of height works
Lifting Operation Safety ppt.pptx
Anhydrous ammonia safety
Ad

Similar to AHU.pdf (20)

PDF
Srinivasa Rao - HSE
PPTX
HSE-Monthly-Report-for-BPCL -Project.pptx
DOC
SARAVANAN RESUME
DOCX
HSE O-CV
DOC
CV-HSE sayed abdallah
PPT
Star II Project - IFE Safety Training Rev 1.ppt
DOC
HSE ABDUL GULREZ AKHTAR CV
DOCX
JUSTICE HSE CV
DOC
Javed_cv
PPTX
Safety plan
PDF
Cv reguieg h last update
DOCX
ROGEL resume up date as of AUG.
PPSX
Turn Key Group Services - OHS Toolkit
PPTX
Commissioning Induction Slide - Share.pptx
PPTX
Commissioning Induction Slide - Share.pptx
PPT
Safe work procedure1
DOC
MARS NOLAN RESUME 2
DOCX
kenneth lester Pedroche (UPDATED)
DOCX
Touseef cv
PDF
Full H&S policy
Srinivasa Rao - HSE
HSE-Monthly-Report-for-BPCL -Project.pptx
SARAVANAN RESUME
HSE O-CV
CV-HSE sayed abdallah
Star II Project - IFE Safety Training Rev 1.ppt
HSE ABDUL GULREZ AKHTAR CV
JUSTICE HSE CV
Javed_cv
Safety plan
Cv reguieg h last update
ROGEL resume up date as of AUG.
Turn Key Group Services - OHS Toolkit
Commissioning Induction Slide - Share.pptx
Commissioning Induction Slide - Share.pptx
Safe work procedure1
MARS NOLAN RESUME 2
kenneth lester Pedroche (UPDATED)
Touseef cv
Full H&S policy
Ad

More from SyedMoazzamAliAli1 (16)

PPTX
Pump Types.pptxPump Types.pptxPump Types.pptx
PPTX
HVAC DUCT Shapes Good PPT.pptxDUCT Shapes Good PP
PDF
pptonsmartcity-160421014045.pdf
PDF
VALVE AND TESTING.pdf
PDF
Boiler Maintenance and Safety PPT.pdf
PDF
PDF
EXTINGUISHER Training.pdf
PDF
Piping Design ppt.pdf
PDF
Control Valve.pdf
PDF
SCADA PPT.pdf
PDF
Compressor PPT.pdf
PDF
Job websites.pdf
PDF
PDF
UP in Air with CO2.pdf
PDF
Organic Wate Converter .pdf
PDF
Plumbing Design Course.pdf
Pump Types.pptxPump Types.pptxPump Types.pptx
HVAC DUCT Shapes Good PPT.pptxDUCT Shapes Good PP
pptonsmartcity-160421014045.pdf
VALVE AND TESTING.pdf
Boiler Maintenance and Safety PPT.pdf
EXTINGUISHER Training.pdf
Piping Design ppt.pdf
Control Valve.pdf
SCADA PPT.pdf
Compressor PPT.pdf
Job websites.pdf
UP in Air with CO2.pdf
Organic Wate Converter .pdf
Plumbing Design Course.pdf

Recently uploaded (20)

PPTX
Management Information system : MIS-e-Business Systems.pptx
PDF
737-MAX_SRG.pdf student reference guides
PPTX
"Array and Linked List in Data Structures with Types, Operations, Implementat...
PDF
Exploratory_Data_Analysis_Fundamentals.pdf
PDF
Soil Improvement Techniques Note - Rabbi
PDF
August -2025_Top10 Read_Articles_ijait.pdf
PPT
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PDF
Visual Aids for Exploratory Data Analysis.pdf
PPTX
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
PDF
distributed database system" (DDBS) is often used to refer to both the distri...
PPTX
tack Data Structure with Array and Linked List Implementation, Push and Pop O...
PPTX
Fundamentals of Mechanical Engineering.pptx
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PPTX
introduction to high performance computing
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
PPTX
Amdahl’s law is explained in the above power point presentations
PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
Management Information system : MIS-e-Business Systems.pptx
737-MAX_SRG.pdf student reference guides
"Array and Linked List in Data Structures with Types, Operations, Implementat...
Exploratory_Data_Analysis_Fundamentals.pdf
Soil Improvement Techniques Note - Rabbi
August -2025_Top10 Read_Articles_ijait.pdf
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
III.4.1.2_The_Space_Environment.p pdffdf
Visual Aids for Exploratory Data Analysis.pdf
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
distributed database system" (DDBS) is often used to refer to both the distri...
tack Data Structure with Array and Linked List Implementation, Push and Pop O...
Fundamentals of Mechanical Engineering.pptx
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
Fundamentals of safety and accident prevention -final (1).pptx
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
introduction to high performance computing
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Amdahl’s law is explained in the above power point presentations
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF

AHU.pdf

  • 1. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 1 | 6 METHOD STATEMENT FOR AHU INSTALLATION
  • 2. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 2 | 6 INTRODUCTION This Method statement describes in details the onsite installation of AHU. AHU shall be installed as per approved material submittal. SCOPE OF WORKS The Method Statement shall cover all works related to the installation of AHU as per approved shop drawing and approved material submittal for the project. REFERENCE DOCUMENTS 3.1. Specification – Section 15855 3.2. Recommendation of approved material submittal . ORGANIZATION & RESPONSIBILITIES Project Manager: It is the Project Manager duty to ensure that all necessary safety and protective equipment are provided along with properly trained and qualified personnel. Moreover, to ensure that all survey works are carried out in accordance with this method statement. Quality Engineer’s: It is the Quality Engineer’s responsibility to ensure that all surveying equipment is being calibrated. Ensure that all inspections and tests are carried out as per Project requirements and that all are recorded. Maintaining all quality records relevant to verification of records. Site Engineer / Site Supervisor’s: It is the Site Engineer / Site Supervisor’s duty to organize the work force in a safe manner and to ensure that safety and protective equipment are being properly utilized. He must also ensure that the method statement procedure is followed and notify the HAC Q.C / EHAF International for inspection. Surveyor’s: It is the Surveyor’s duty to obtain all data and information required for surveys. Determine methods to establish survey control. Use appropriate equipment to complete assigned task. Keep accurate notes and records to describe and certify work performed. Abide by all Site Safety and Quality Requirements. Safety Engineer / Officer’s:
  • 3. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 3 | 6  The Safety Engineer is responsible for devising and implementing programmers and plans to safeguard, health and safety of all employees, and to prevent loss or damage to the existing assets and projects, He is responsible for the implementing of the safety programs. He is also responsible to:  Provide support to site safety officers advising them on safe working methods and assisting with training of personnel.  Carryout regular site safety audits and reports and correct unsafe work practices and potential hazards.  Investigate and report all accidents near misses and recommend prevention measures. Ensure maintenances of good hygienic standards and availability of safety equipment and first aid treatment.  Present monthly safety reports and required documents. Safety Officers are responsible for:  The day to day activities of maintaining safety on project site, they must: Understand and comply with requirements of the safety manual.  Cooperate with the safety engineer to create and maintain safe working conditions.  Assist the site engineers and foremen to organize the work area so that the men can perform their duties with maximum efficiency and minimize risk to themselves or to equipment.  Inspect equipment and tools before use to ensure correct storage and properly utilization. Maintain record of all injuries and damages on site, submit reports as required. RESOURCES Equipment & Machinery: The following equipment will be used to carry out the installation of FANS.  Mechanical hand tool  Mobile Crane  Fork Lift METHODOLOGY Storage  AHU shall be stored in such a manner as to preserve its quality condition.  AHU are to be as per manufacturer recommendations but at the same time it should be accessible.
  • 4. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 4 | 6  The quantity to be delivered at site for installation shall be consistent with the necessary required quantity of the work to perform. Setting Out  Check the readiness of reference and coordinates.  Check the other activates works related with the installations.  Arrange all necessary work permit, check and verify the actual site condition. Unloading and Shifting:  AHU shall be transported by a delivery truck and mechanical crane / fork lift to the specific work place.  Safety Officer will be present during loading and unloading of.  Two lifting point will be used during the loading and unloading of AHU to ensure safety that no incident will occurs. Traffic Aide will be present during loading and unloading of Unit for maintaining the traffic in the project site if needed.  All lifting equipment will be inspected daily before operating. Any parts detected damages must be replaced immediately before operating. Installation for AHU at Concrete roof  Mech. Installation: -  Set and fix AHU steel frame at Unit location at roof.  Connect Unit with duct through duct reducer.  Installation manual attached.  Electrical Installation: -  Connect power cable from MCC Panel to disconnecting switch.  Connect Power Cable from disconnecting switch to Unit motor. QUALITY ASSURANCE Material : Approved submittal. Location : As per approved shop drawings HEALTH, SAFETY AND ENVIRONMENT
  • 5. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 5 | 6 PPE Requirements As a minimum the following PPE should be used by staff / Labors  Hard hat.  Safety shoes.  Safety eye glasses.  Hand gloves.  High visibility vest. Any additional PPE as required by local rules or mandatory requirement shall be used. Safety Accessories  Traffic Cones.  Warning /barricade/barrier tape.  Safety signs.  Cooled water container for drinking.  First Aid box.  Workers rest area  Portable toilet  Fire extinguishers  Sign boards of Emergency contact details/persons Information to Personnel.  Safety Induction will be done in accordance with HSE Policy prior to start work in site.  Safety toolbox meetings to be carried out prior to work.  Before job start checklist of protective & safety equipment to be use are in order.  Personal protective & safety equipment as per requirement to be performed by personnel to do the task.  Toolbox talk to be convened & attended by all personnel assigned to do the task. Work crew will be given instruction on site surveying procedure & all risk associated with the works and registered attendance.  Safety personnel & designated responsible person will ensure that all above is carried out & any other statutory requirements are complied with before any work takes.  Hazard analysis to be done.
  • 6. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 6 | 6  Personnel who have been briefed in the correct equipment set up.  Personnel will wear gloves, footwear, head & eye protection during work.  Use the correct tools to do the task.  Removal of any obstructive / protruding materials. APPENDICES 1. Risk assessment.