SCHOOL OF ARCHITECTURE · BUILDING · DESIGN
Centre for Modern Architecture Studies in Southeast Asia
Bachelor of Quantity Surveying (Honours)
PROFESSIONAL PRACTICE [QSB 3614]
1. This assignment shall make up 15% weightage of the final marks.
2. This is a group assignment and shall be submitted in groups of 7 students.
3. Dateline for submission of this Coursework No. 2 is on or before 14th May 2018.
Coursework No. 2 – Preparation of Final Account.
You are appointed as the consulting Quantity Surveyor for a apartment project based on PAM
Form of Contract 2006 (With Quantities). The summary of the Contract Sum is as follows:
Bill No. 1 – Preliminaries RM 5,250,000.00
Bill No. 2 – Building Works RM 50,450,000.00
Bill No. 3 – Local Infrastructure Works RM 6,500,000.00
Bill No. 4 – P.C. and Provisional Sums RM 9,600,000.00
Contract Sum RM 71,800,000.00
Question 1.
You are required to prepare a report to your director, explaining briefly the adjustments of the
essential elements in your preparation of this project’s final account.
(15 marks)
Question 2.
The tender drawings shows that the apartment has an entrance porch on the layout but no
details were provided sufficiently for measurement of quantities. The Quantity Surveyor then
had suggested that these items be listed as Provisional Sum. However you have forgot about
this item and did not include it in your tender document. The contract was awarded without
it. Your director would also like to know the significance and contractual implications of this
omission.
(10 marks)
Question 3.
In accordance with clause 30.10 of the contract, the contractor duly submitted his Final Accounts
within 6 months after the issuance of the Certificate of Practical Completion. You are then
required to assess this application and prepare the Final Account for the apartment project
based of the following valuations and adjustments made to the Contract Sum:
(35 marks)
1
Information provided (For question 3) are as follows:
a. The Architect had granted the Contractor’s first application for extension of time and
approved additional insurance premium amounting to RM 10,000.00 in accordance with
clause 24 of the contract due to the delay in the completion of the works caused by the
Employer’s late decision on the toilet design. 



In his second application for extension of time, the Contractor submitted an an
application for extension of time due to exceptionally inclement weather and a loss and
expense claim for RM200,000.00 in his Final Accounts to you. The Architect approved
the extension of time as per Clause 23.8 but not the Contractor’s loss & expense claims.
b. There are four variation orders carried out by the Contractor:
Addition Omission
i. Variation Order No. 1: RM 500,000.00 RM 300,000.00
Changes of entrance lobby from
floor tiles to granite floor
ii. Variation Order No. 2: RM 300,000.00 -
New Guard house.
iii. Variation Order No. 3:
Changes from concrete block RM 400,000.00 RM 200,000.00
drains to precast concrete culverts
iv. Variation Order No. 4:
Omission of hand railings to yard. - RM 86,000.00
c. The following are the nominated sub-contractor’s accounts:
Original P.C. & NSC’s
Provisional Sums final account
i. Lift Services: RM 1,500,000.00 RM 1,700,000.00
Profit @ 2% RM 30,000.00
Attendance as item RM 30,000.00
ii. Air Conditioning Services: RM 2,200,000.00 RM 2,000,000.00
Profit @ 2% RM 44,000.00
Attendance as item RM 44,000.00
iii. Electrical Services: RM 2,600,000.00 RM 2,700,000.00
Profit @ 2% RM 52,000.00
Attendance as item RM 52,000.00
iv. Provisional Sums: Entrance Porch RM 1,000,000.00 RM 1,250,000.00
v. Contingency Sum RM RM 2,048,000.00
RM 9,600,000.00

2
Question 4.
On a different project, you were asked to explain the basis on how the following variations may
be finalised and priced during the Final Account stage:
a. The Contractor had priced RM 160,000.00 for the Contractor All Risk Insurance policy in
the Preliminaries Bills. The Contractor failed to purchase this insurance when the works
commence. The Employer, then, bought and paid for the said insurance for RM
180,000.00 on behalf of the Contractor.
(10 marks)
b. Contractor is required to provide a desktop computer in the Preliminaries section for the
Resident Engineer’s use but this item was left unpriced, i.e. BQ item was left blank in the
rate/amount column in the contract document. However the Architect instructed the
Contractor to provide a laptop computer costing RM10,000.00 for the Resident Engineer
instead of the desktop computer as specified in the Preliminaries.
(10 marks)
c. A wash trough as required and priced in the Preliminaries section was not constructed
due to site constraints imposed later by the Employer. However, the vehicles leaving the
site during construction were always kept clean including the public roads using water jet
washing and full-timed workers.
(10 marks)
d. Mistake was made in the price for excavation through rocks at RM 50 per m3. Item was
not rationalised during contract documentation. However, original quantity in BQ is 100
m3 but re-measured as-built quantity was 20,000 m3. The Contractor submitted a claim
for revised rates of RM 150 per m3 for the total quantity of 20,000 m3.
(10 marks)
3

More Related Content

PDF
Seminar - Question
PDF
Pp2 final report
PDF
Assignment - Final Account
PDF
Pp2 assignment-final
PDF
Pp2 coursework 2 201808
PDF
Pp2 coursework 2
PDF
Pp2 coursework 2 BRIEF 201708
PDF
Pp2 coursework 2 201808
Seminar - Question
Pp2 final report
Assignment - Final Account
Pp2 assignment-final
Pp2 coursework 2 201808
Pp2 coursework 2
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2 201808

What's hot (20)

PDF
Assignment - Financial Appraisal
PDF
Pp2 group assignment
PDF
PP2 final report
PDF
Assignment - S Hotel
PDF
Assignmenr for pp2 final account
PDF
Pp2 final account assignment excel
PDF
Assignment - S Hotel (Presentation Slide)
PPTX
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
PDF
Pp2 coursework 2 brief
PDF
PP2 - Assignment
PDF
Professional practice 2
PDF
pp2 Final account-1
DOCX
Professional Practice II
DOCX
PP2 - Assignment
PDF
PP1 Project 3 Cover letter
PDF
PP1 Project 1 Project implementation
PDF
PP1 Project 2 Project Report
PDF
Assignment - Management Contracting (Presentation Slide)
PDF
Standard bill of quantities
DOCX
Professional Practice 2: Group Assignment
Assignment - Financial Appraisal
Pp2 group assignment
PP2 final report
Assignment - S Hotel
Assignmenr for pp2 final account
Pp2 final account assignment excel
Assignment - S Hotel (Presentation Slide)
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
Pp2 coursework 2 brief
PP2 - Assignment
Professional practice 2
pp2 Final account-1
Professional Practice II
PP2 - Assignment
PP1 Project 3 Cover letter
PP1 Project 1 Project implementation
PP1 Project 2 Project Report
Assignment - Management Contracting (Presentation Slide)
Standard bill of quantities
Professional Practice 2: Group Assignment
Ad

More from Kai Yun Pang (20)

PDF
Assignment 2 - Resort Proposal at Pulau Langkawi
PDF
Assignment 2 - Report
PDF
Assignment 1 - Water Pump Station
PDF
Assignment 1 - Microsoft Project
PDF
Assignment - Financial Appraisal
PDF
Assignment - FIDIC Contract
PDF
Assignment - Report
PDF
Seminar - CIPAA 2012
PDF
Assignment - Case Study Report
PDF
Assignment - Journal
PPTX
Assignment - Community Service
PDF
Seminar - Partial Possession by Employer
PDF
Assignment - MK Land
DOCX
Assignment - Financial Analysis
PDF
Assignment - Preliminary Cost Appraisal (Presentation Slide)
PDF
Assignment - Preliminary Cost Appraisal
PDF
Assignment - Cost Plan
PDF
Assignment 2 - Buildsoft Software
PDF
Assignment 2 - Bill of Quantities
PDF
Assignment 1 - Software (Presentation Slide)
Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Report
Assignment 1 - Water Pump Station
Assignment 1 - Microsoft Project
Assignment - Financial Appraisal
Assignment - FIDIC Contract
Assignment - Report
Seminar - CIPAA 2012
Assignment - Case Study Report
Assignment - Journal
Assignment - Community Service
Seminar - Partial Possession by Employer
Assignment - MK Land
Assignment - Financial Analysis
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal
Assignment - Cost Plan
Assignment 2 - Buildsoft Software
Assignment 2 - Bill of Quantities
Assignment 1 - Software (Presentation Slide)
Ad

Recently uploaded (20)

PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PPTX
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
PDF
LEARNERS WITH ADDITIONAL NEEDS ProfEd Topic
PDF
MICROENCAPSULATION_NDDS_BPHARMACY__SEM VII_PCI .pdf
PDF
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
PDF
LIFE & LIVING TRILOGY- PART (1) WHO ARE WE.pdf
PDF
Mucosal Drug Delivery system_NDDS_BPHARMACY__SEM VII_PCI.pdf
PPTX
Introduction to pro and eukaryotes and differences.pptx
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PDF
LIFE & LIVING TRILOGY - PART (3) REALITY & MYSTERY.pdf
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PDF
Race Reva University – Shaping Future Leaders in Artificial Intelligence
PPTX
Core Concepts of Personalized Learning and Virtual Learning Environments
PDF
LIFE & LIVING TRILOGY - PART - (2) THE PURPOSE OF LIFE.pdf
DOCX
Cambridge-Practice-Tests-for-IELTS-12.docx
PDF
International_Financial_Reporting_Standa.pdf
PDF
Empowerment Technology for Senior High School Guide
PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
PPTX
Education and Perspectives of Education.pptx
PPTX
What’s under the hood: Parsing standardized learning content for AI
Paper A Mock Exam 9_ Attempt review.pdf.
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
LEARNERS WITH ADDITIONAL NEEDS ProfEd Topic
MICROENCAPSULATION_NDDS_BPHARMACY__SEM VII_PCI .pdf
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
LIFE & LIVING TRILOGY- PART (1) WHO ARE WE.pdf
Mucosal Drug Delivery system_NDDS_BPHARMACY__SEM VII_PCI.pdf
Introduction to pro and eukaryotes and differences.pptx
B.Sc. DS Unit 2 Software Engineering.pptx
LIFE & LIVING TRILOGY - PART (3) REALITY & MYSTERY.pdf
FORM 1 BIOLOGY MIND MAPS and their schemes
Race Reva University – Shaping Future Leaders in Artificial Intelligence
Core Concepts of Personalized Learning and Virtual Learning Environments
LIFE & LIVING TRILOGY - PART - (2) THE PURPOSE OF LIFE.pdf
Cambridge-Practice-Tests-for-IELTS-12.docx
International_Financial_Reporting_Standa.pdf
Empowerment Technology for Senior High School Guide
Share_Module_2_Power_conflict_and_negotiation.pptx
Education and Perspectives of Education.pptx
What’s under the hood: Parsing standardized learning content for AI

Assignment - Report

  • 1. SCHOOL OF ARCHITECTURE · BUILDING · DESIGN Centre for Modern Architecture Studies in Southeast Asia Bachelor of Quantity Surveying (Honours) PROFESSIONAL PRACTICE [QSB 3614] 1. This assignment shall make up 15% weightage of the final marks. 2. This is a group assignment and shall be submitted in groups of 7 students. 3. Dateline for submission of this Coursework No. 2 is on or before 14th May 2018. Coursework No. 2 – Preparation of Final Account. You are appointed as the consulting Quantity Surveyor for a apartment project based on PAM Form of Contract 2006 (With Quantities). The summary of the Contract Sum is as follows: Bill No. 1 – Preliminaries RM 5,250,000.00 Bill No. 2 – Building Works RM 50,450,000.00 Bill No. 3 – Local Infrastructure Works RM 6,500,000.00 Bill No. 4 – P.C. and Provisional Sums RM 9,600,000.00 Contract Sum RM 71,800,000.00 Question 1. You are required to prepare a report to your director, explaining briefly the adjustments of the essential elements in your preparation of this project’s final account. (15 marks) Question 2. The tender drawings shows that the apartment has an entrance porch on the layout but no details were provided sufficiently for measurement of quantities. The Quantity Surveyor then had suggested that these items be listed as Provisional Sum. However you have forgot about this item and did not include it in your tender document. The contract was awarded without it. Your director would also like to know the significance and contractual implications of this omission. (10 marks) Question 3. In accordance with clause 30.10 of the contract, the contractor duly submitted his Final Accounts within 6 months after the issuance of the Certificate of Practical Completion. You are then required to assess this application and prepare the Final Account for the apartment project based of the following valuations and adjustments made to the Contract Sum: (35 marks) 1
  • 2. Information provided (For question 3) are as follows: a. The Architect had granted the Contractor’s first application for extension of time and approved additional insurance premium amounting to RM 10,000.00 in accordance with clause 24 of the contract due to the delay in the completion of the works caused by the Employer’s late decision on the toilet design. 
 
 In his second application for extension of time, the Contractor submitted an an application for extension of time due to exceptionally inclement weather and a loss and expense claim for RM200,000.00 in his Final Accounts to you. The Architect approved the extension of time as per Clause 23.8 but not the Contractor’s loss & expense claims. b. There are four variation orders carried out by the Contractor: Addition Omission i. Variation Order No. 1: RM 500,000.00 RM 300,000.00 Changes of entrance lobby from floor tiles to granite floor ii. Variation Order No. 2: RM 300,000.00 - New Guard house. iii. Variation Order No. 3: Changes from concrete block RM 400,000.00 RM 200,000.00 drains to precast concrete culverts iv. Variation Order No. 4: Omission of hand railings to yard. - RM 86,000.00 c. The following are the nominated sub-contractor’s accounts: Original P.C. & NSC’s Provisional Sums final account i. Lift Services: RM 1,500,000.00 RM 1,700,000.00 Profit @ 2% RM 30,000.00 Attendance as item RM 30,000.00 ii. Air Conditioning Services: RM 2,200,000.00 RM 2,000,000.00 Profit @ 2% RM 44,000.00 Attendance as item RM 44,000.00 iii. Electrical Services: RM 2,600,000.00 RM 2,700,000.00 Profit @ 2% RM 52,000.00 Attendance as item RM 52,000.00 iv. Provisional Sums: Entrance Porch RM 1,000,000.00 RM 1,250,000.00 v. Contingency Sum RM RM 2,048,000.00 RM 9,600,000.00
 2
  • 3. Question 4. On a different project, you were asked to explain the basis on how the following variations may be finalised and priced during the Final Account stage: a. The Contractor had priced RM 160,000.00 for the Contractor All Risk Insurance policy in the Preliminaries Bills. The Contractor failed to purchase this insurance when the works commence. The Employer, then, bought and paid for the said insurance for RM 180,000.00 on behalf of the Contractor. (10 marks) b. Contractor is required to provide a desktop computer in the Preliminaries section for the Resident Engineer’s use but this item was left unpriced, i.e. BQ item was left blank in the rate/amount column in the contract document. However the Architect instructed the Contractor to provide a laptop computer costing RM10,000.00 for the Resident Engineer instead of the desktop computer as specified in the Preliminaries. (10 marks) c. A wash trough as required and priced in the Preliminaries section was not constructed due to site constraints imposed later by the Employer. However, the vehicles leaving the site during construction were always kept clean including the public roads using water jet washing and full-timed workers. (10 marks) d. Mistake was made in the price for excavation through rocks at RM 50 per m3. Item was not rationalised during contract documentation. However, original quantity in BQ is 100 m3 but re-measured as-built quantity was 20,000 m3. The Contractor submitted a claim for revised rates of RM 150 per m3 for the total quantity of 20,000 m3. (10 marks) 3