SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
BACHELOR OF QUANTITY SURVEYING (HONOURS)
PROJECT MANAGEMENT (QSB4424/MGT60704)
Project type: Individual Assignment
Deadline: 12pm, 27th
Nov 2018
Submission format: Report and softcopy for MS project (save file as your
student ID)
Mark: 20%
The	
  Water	
  Pump	
  Station	
  Deterministic	
  Schedule	
  
You boss was very impressed with the great job you did in estimating the pump station, and she
asked you to be in charge of her scheduling department also. She asked you to meet with Marcia
Kellog, the superintendent of the pump water station, to find out how she is planning to build the
job.
The meeting took place at your boss office in the PJ on March 10, 2019. Marcia informed you that:
All activity on the project should start on May 19, 2019 the latest. Before you start any work, you
have to secure 2 permits from the municipality: a city permit and a building permit. The city permit
takes 5 working days to obtain, and must be secured before May 23, 2019. Given your experience
in the PJ area you are confident that the building permit takes 21 working days to obtain, but can
only be requested after the city permit has been secured. Additionally, you can only apply for a
building permit after you have installed temporary electrical connections and plumbing facilities on
site. Each of these takes 5 days to install, and you do not need to have a city permit to start them.
The site where the pump will be located is characterized by a clayey soil that will need an adequate
support system to prevent any soil collapse. Furthermore, given the proximity of the site to the
waterbed, you are very concerned to do your job efficiently to prevent any water seepage. Once
the building permit has been obtained, you can start driving sheet piles (a task estimated to take 18
days). Naturally, before you begin driving sheet piles, you need to mobilize all the necessary
equipment and personnel, but you are not allowed to move anything on site before June 17, 2019.
Furthermore, before you begin driving sheet piles you need to conduct 4 days of subsurface
exploration.
After driving the sheet piles is complete, you can begin excavating. The nature of soil requires a
staged excavation & tieback sequence. That means excavating, securing the slopes with tiebacks
and then continuing excavation. The process is simple and sequential, so you decided to just lump
it as 90 days of excavation and tieback.
As soon as you reach the bottom of the excavation, you will start laying down the concrete of the
mat foundation and the inverse slab, which you can expect to take a total of 43 days. Scheduling at
this point becomes tricky: Once you are done with the foundation and the inverse slab, you can
start building the wet well floor and doing the FRP (Formwork and Reinforcing steel Placement) of
the heavy wall (EL72 to EL95). These tasks are expected to last 4 and 5 days respectively. When
you are finished with both, you can start pouring concrete for the heavy wall, which will take you 8
days. A PVC waterproofing membrane will be lying on the exterior of all the walls. Installing the
waterproofing and backfilling up to EL95 will only take 3 days each, but you have to remember to
let the heavy wall dry for 7 days before applying the membrane. Once the membrane is applied,
you can backfill up to EL95 with soil.
Questions	
  
1. For the initial tasks shown below, build a table of activity precedence and duration for all
activities.
Activity ID Activity Name Duration Predecessors
1000 Mobilization 5 days
1010 City Permit 5 days
1020 Electrical Connections 5 days
2. Solve the network corresponding to these activities using Microsoft Project.
a. List out all your assumption.
b. The critical path for these activities.
c. Gantt of these activities.

More Related Content

PPTX
Slope Protection works
PDF
Assignment 1 - Water Pump Station
PPTX
Manpower planning for a construction company
PPTX
Critical Path Ppt
PDF
Resource allocation and smoothing
DOCX
Activities used in road construction
PPTX
Construction accidents and safety management
PPT
Formwork failures and remedial measures
Slope Protection works
Assignment 1 - Water Pump Station
Manpower planning for a construction company
Critical Path Ppt
Resource allocation and smoothing
Activities used in road construction
Construction accidents and safety management
Formwork failures and remedial measures

What's hot (20)

PPT
Planning of materials in Construction Project management
PPTX
Construction Equipment Management
PPTX
Environmental Considerations in Construction
PPTX
Construction Project Management
PPTX
Chapter 6
PPTX
Construction Material Management
PDF
What is Manpower Planning Organizing Staffing Important objectives of staffin...
PPTX
#Public-Private Partnership (PPP) Contract Models# By SN Panigrahi
PPTX
5 principles of construction project management
DOCX
Group Assignment:IBS System
PPTX
6.5 Resource Leveling and Resource Smoothing
PDF
PPTX
Site Possession
PPTX
Construction equipments
PPTX
Types of contracts
PDF
Housing Policies in Malaysia
PDF
Controling productivity in construction projects
PPT
Wbs & Project Scheduling
PPT
Chapter 2 soil investigation
PPTX
Construction planning & management
Planning of materials in Construction Project management
Construction Equipment Management
Environmental Considerations in Construction
Construction Project Management
Chapter 6
Construction Material Management
What is Manpower Planning Organizing Staffing Important objectives of staffin...
#Public-Private Partnership (PPP) Contract Models# By SN Panigrahi
5 principles of construction project management
Group Assignment:IBS System
6.5 Resource Leveling and Resource Smoothing
Site Possession
Construction equipments
Types of contracts
Housing Policies in Malaysia
Controling productivity in construction projects
Wbs & Project Scheduling
Chapter 2 soil investigation
Construction planning & management
Ad

Similar to Assignment 1 - Microsoft Project (20)

PDF
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
PPTX
A valuable journey proposal
PDF
Monthly Progress Report - September 2014
DOC
PPTX
Mascot Manorath - Landlinker.in
PPTX
Mascot soho group_ppt
PPTX
Mascot soho group_ppt
DOCX
The Project Brief
PDF
DOCX
Updated CV MValenzuela (latest)
PDF
Mascot soho group_ppt (1)
DOCX
Final Report
PPT
11 lecture project scheduling 3
PDF
Muthukumar Civil engineer resume UPDATED (1).pdf
PPTX
Residential building in Bangalore, Mysore, Mangalore, Karnataka, Hosur, Coimb...
PPT
Construction practices aphb
DOCX
induarial trainin report
DOCX
CEM455 CONSTRUCTION Final Project
DOC
Muhammad Azeem -
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
A valuable journey proposal
Monthly Progress Report - September 2014
Mascot Manorath - Landlinker.in
Mascot soho group_ppt
Mascot soho group_ppt
The Project Brief
Updated CV MValenzuela (latest)
Mascot soho group_ppt (1)
Final Report
11 lecture project scheduling 3
Muthukumar Civil engineer resume UPDATED (1).pdf
Residential building in Bangalore, Mysore, Mangalore, Karnataka, Hosur, Coimb...
Construction practices aphb
induarial trainin report
CEM455 CONSTRUCTION Final Project
Muhammad Azeem -
Ad

More from Kai Yun Pang (20)

PDF
Assignment 2 - Resort Proposal at Pulau Langkawi
PDF
Assignment 2 - Report
PDF
Assignment - Financial Appraisal
PDF
Assignment - Financial Appraisal
PDF
Assignment - FIDIC Contract
PDF
Assignment - Report
PDF
Seminar - CIPAA 2012
PDF
Assignment - S Hotel (Presentation Slide)
PDF
Assignment - S Hotel
PDF
Assignment - Case Study Report
PDF
Assignment - Journal
PPTX
Assignment - Community Service
PDF
Assignment - Final Account
PDF
Assignment - Report
PDF
Seminar - Partial Possession by Employer
PDF
Seminar - Question
PDF
Assignment - MK Land
DOCX
Assignment - Financial Analysis
PDF
Assignment - Preliminary Cost Appraisal (Presentation Slide)
PDF
Assignment - Preliminary Cost Appraisal
Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Report
Assignment - Financial Appraisal
Assignment - Financial Appraisal
Assignment - FIDIC Contract
Assignment - Report
Seminar - CIPAA 2012
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel
Assignment - Case Study Report
Assignment - Journal
Assignment - Community Service
Assignment - Final Account
Assignment - Report
Seminar - Partial Possession by Employer
Seminar - Question
Assignment - MK Land
Assignment - Financial Analysis
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal

Recently uploaded (20)

PDF
TR - Agricultural Crops Production NC III.pdf
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PDF
01-Introduction-to-Information-Management.pdf
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PPTX
human mycosis Human fungal infections are called human mycosis..pptx
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
VCE English Exam - Section C Student Revision Booklet
PDF
Microbial disease of the cardiovascular and lymphatic systems
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PPTX
Institutional Correction lecture only . . .
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PDF
O7-L3 Supply Chain Operations - ICLT Program
PPTX
Lesson notes of climatology university.
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PPTX
Cell Structure & Organelles in detailed.
PPTX
Cell Types and Its function , kingdom of life
PPTX
master seminar digital applications in india
TR - Agricultural Crops Production NC III.pdf
Module 4: Burden of Disease Tutorial Slides S2 2025
01-Introduction-to-Information-Management.pdf
Microbial diseases, their pathogenesis and prophylaxis
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
human mycosis Human fungal infections are called human mycosis..pptx
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
VCE English Exam - Section C Student Revision Booklet
Microbial disease of the cardiovascular and lymphatic systems
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
Abdominal Access Techniques with Prof. Dr. R K Mishra
Institutional Correction lecture only . . .
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
O7-L3 Supply Chain Operations - ICLT Program
Lesson notes of climatology university.
Supply Chain Operations Speaking Notes -ICLT Program
Cell Structure & Organelles in detailed.
Cell Types and Its function , kingdom of life
master seminar digital applications in india

Assignment 1 - Microsoft Project

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) PROJECT MANAGEMENT (QSB4424/MGT60704) Project type: Individual Assignment Deadline: 12pm, 27th Nov 2018 Submission format: Report and softcopy for MS project (save file as your student ID) Mark: 20% The  Water  Pump  Station  Deterministic  Schedule   You boss was very impressed with the great job you did in estimating the pump station, and she asked you to be in charge of her scheduling department also. She asked you to meet with Marcia Kellog, the superintendent of the pump water station, to find out how she is planning to build the job. The meeting took place at your boss office in the PJ on March 10, 2019. Marcia informed you that: All activity on the project should start on May 19, 2019 the latest. Before you start any work, you have to secure 2 permits from the municipality: a city permit and a building permit. The city permit takes 5 working days to obtain, and must be secured before May 23, 2019. Given your experience in the PJ area you are confident that the building permit takes 21 working days to obtain, but can only be requested after the city permit has been secured. Additionally, you can only apply for a building permit after you have installed temporary electrical connections and plumbing facilities on site. Each of these takes 5 days to install, and you do not need to have a city permit to start them. The site where the pump will be located is characterized by a clayey soil that will need an adequate support system to prevent any soil collapse. Furthermore, given the proximity of the site to the waterbed, you are very concerned to do your job efficiently to prevent any water seepage. Once the building permit has been obtained, you can start driving sheet piles (a task estimated to take 18 days). Naturally, before you begin driving sheet piles, you need to mobilize all the necessary equipment and personnel, but you are not allowed to move anything on site before June 17, 2019. Furthermore, before you begin driving sheet piles you need to conduct 4 days of subsurface exploration.
  • 2. After driving the sheet piles is complete, you can begin excavating. The nature of soil requires a staged excavation & tieback sequence. That means excavating, securing the slopes with tiebacks and then continuing excavation. The process is simple and sequential, so you decided to just lump it as 90 days of excavation and tieback. As soon as you reach the bottom of the excavation, you will start laying down the concrete of the mat foundation and the inverse slab, which you can expect to take a total of 43 days. Scheduling at this point becomes tricky: Once you are done with the foundation and the inverse slab, you can start building the wet well floor and doing the FRP (Formwork and Reinforcing steel Placement) of the heavy wall (EL72 to EL95). These tasks are expected to last 4 and 5 days respectively. When you are finished with both, you can start pouring concrete for the heavy wall, which will take you 8 days. A PVC waterproofing membrane will be lying on the exterior of all the walls. Installing the waterproofing and backfilling up to EL95 will only take 3 days each, but you have to remember to let the heavy wall dry for 7 days before applying the membrane. Once the membrane is applied, you can backfill up to EL95 with soil. Questions   1. For the initial tasks shown below, build a table of activity precedence and duration for all activities. Activity ID Activity Name Duration Predecessors 1000 Mobilization 5 days 1010 City Permit 5 days 1020 Electrical Connections 5 days 2. Solve the network corresponding to these activities using Microsoft Project. a. List out all your assumption. b. The critical path for these activities. c. Gantt of these activities.