CA	Project	&	Portfolio	Management	
and	MS	Project	Integration:	Tips,	
Tricks	and	What's	New	for	You
Shannon	Thoke,	Director	– Technical	Sales,	CA	Technologies,	Inc.
Dan	Greer	– President	– Rego Consulting
AMX68E
AGILE	MANAGEMENT
2 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
For	Informational	Purposes	Only	
Terms	of	this	Presentation
©	2016	CA.	All	rights	reserved.	All	trademarks	referenced	herein	belong	to	their	respective	companies.
The	content	provided	in	this CA	World	2016	presentation	is	intended	for	informational	purposes	only	and	does	not	form	any	type	of	
warranty. The information	provided	by	a	CA	partner	and/or	CA	customer	has	not	been	reviewed	for	accuracy	by	CA.
3 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Abstract
Join	this	session	for	the	latest	on	MS	Project	
and	CA	PPM. This	session	will	highlight	the	
latest	MSP	connector.
Shannon	
Thoke
CA	Technologies,	Inc.
Director	– Technical	
Sales
Dan	Greer
Rego Consulting
President
4 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Agenda
WHAT’S	NEW	IN	THE	MSP	INTERFACE?
DEFAULT	PROJECT	SETTINGS
CASE	STUDIES	&	BEST	PRACTICES
PERFORMANCE
FIELD	MAPPINGS
SCHEDULING
1
2
3
4
5
6
5 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Why	was	there	a	New	MSP	Interface	Beginning	in	14.x?
§ Microsoft	has	not	supported	the	OLE	framework	(which	is	
what	the	old	driver	utilized)	in	many	years.	
§ The	new	driver	provides	the	following:
– Tighter	integration	with	MSP
– Ability	for	Microsoft	to	fix	reported	bugs	(over	17	bugs	reported	
and	many	fixed	already)
– Better	performance
6 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
What’s	New	with	the	MSP	Interface?
§ For	master	projects	there	is	no	longer	a	resource	pool!
– All	resources	will	be	displayed	on		the	master	resource	sheet.
§ We	no	longer	will	save	custom	views	in	the	MPP	file.		
– Recommend	using	Global	Views
§ Save-As	no	longer	supports	overwriting	an	existing	project.		
Save-As	still	works	to	create	a	NEW	project	with	support	for	
project	ID	auto-numbering
§ We	do	not	automatically	map	Pending	ETC,	Pending	Actuals,	
or	charge	code	to	MSP
7 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
What	Else	is	New	with	the	MSP	Interface?
§ Less	task	constraints
§ The	progress	dialog	can	now	be	seen	in	MSP	and	not	
as	a	popup
§ Improved	logging,	troubleshooting,	and	benchmarking
§ Mapping	support	of	lookups	(static)	– both	OOB	and	custom.		
Multi-valued	and	Dynamic	lookups	are	not	supported.
8 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Project	Default	Settings
§ Setting	your	project	defaults	for	each	MSP	user	will	reduce	
scheduling	inconsistencies	across	your	user	base.		This	is	a	
critical	step	in	normalizing	your	MSP	to	be	ready	for	
integration	with	PPM
§ When	you	are	setting	or	checking	your	project	default	make	
sure	you	have	all	projects	closed	(including	project1)
9 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Mandatory	Default	Settings
10 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
CA	PPM	is	the	Primary	Owner	of	the	Following	
Data	Elements
§ Project	Plans
§ Resources	who	work	on	these	projects
§ The	rate	matrix	used	to	generate	the	project	budget	and	costs
§ Resource	Calendars
§ Attribute	Defaults	(such	as	Open	for	Time	Entry,	
Loading	Pattern,	etc).
11 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Performance	Tips	and	Tricks
§ Open	the	project	in	.xml	and	note	the	time.	This	is	how	long	
Microsoft	takes	to	open	the	project!
§ You	can	have	a	deep	project	(with	many	tasks),	or	you	can	
have	a	wide	project	(with	tasks	with	a	longer	duration).	
But	stay	away	from	a	Deep	and	Wide	project!
§ In	general	the	longer	the	task	duration,	the	longer	it	will	take	
to	export	the	project.	Keep	these	type	of	tasks	at	a	minimum
§ Review	each	task	and	set	realistic	start	and	finish	dates.
12 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Performance	Tips	and	Tricks	(Continued)
§ Remove	any	unnecessary	assignments.
§ Do	not	use	bucket	tasks	(assign	all	team	members	to	a	
single	task)
§ Only	export	the	current	baseline	to	MSP,	as	the	baseline	is	
a	snapshot	of	the	project	plan.
§ Use		Uniform	Loading	Pattern
13 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
The	Project	Object
§ There	are	2	main	areas	where	PPM	Project	Information	is	
stored	in	Microsoft	Project
– The	Project	Properties
§ File>Info>Project	Information	>	Advanced	>	Properties	>	
Summary	Tab
– The	Project	Summary	task	(Task	0)
§ File	>	Options	>	Advanced
– Select	the	“Project	Summary	Task”	checkbox
14 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
The	Task	Object
§ The	Gantt	is	the	best	view	to	review	your	task	information.		
The	following	is	a	list	of	non-standard	mapped	fields:
PPM	Field MSP	Field
Key Task Flag	1
Task	ID Text	1
*PPM	Reserved Text 3
*	Text3	is	a	reserved	field	which	
contains	the	unique	ID,	track	
mode,	open	for	time	entry	and	
other	important	PPM	information.		
This	field	should	not	be	edited.
15 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
The	Resource	and	Team	Objects
§ The	resource	sheet	view	gives	you	the	best	view	to	review	
your	resource	information.		The	following	is	a	list	of	non-
standard	mapped	fields:
PPM	Field MSP	Field
Resource	ID Initials
Category Group
Resource Type Type	(work,	material, cost)
Rate (from	rate	matrix) Std Rate
IsRole Generic
Max	% Team Allocation	on	Today’s	Date
* Text	3
*	Text3	is	a	reserved	field	which	
contains	the	unique	ID,	track	
mode,	open	for	time	entry	and	
other	important	PPM	information.		
This	field	should	not	be	edited.
16 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
The	Assignment	Object
§ The	MSP	task	usage	View	is	the	best	view	to	find	
Assignment	information.
PPM	Field MSP	Field
ETC Remaining Work
Total	Effort Work	(actuals	+	ETC)
Loading	Pattern Work Contour
Max%	Load Units
* Text 3
*	Text3	is	a	reserved	field	which	
contains	the	unique	ID,	track	
mode,	open	for	time	entry	and	
other	important	PPM	information.		
This	field	should	not	be	edited.
17 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Field	Mapping
§ There	is	a	new	page	in	CA	PPM	that	will	allow	admins	to	
create	their	own	field	mappings	to	MSP.	Customers	will	no	
longer	need	to	have	their	DBA	do	this	work!
§ The	MSP	Field	Mapping	page	can	be	found	in	the	Project	
Management	section	in	the	Admin	tool.
18 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Field	Mapping
Using	the	MSP	Field	mapping	page,	customers	will	be	able	to	
map	attributes	from	the	following	objects:
§ Object
§ Resource
§ Team
§ Task
§ Assignment
§ MSP	view
§ Resource	Sheet
§ Resource	Sheet
§ Gantt
§ Resource	usage	view
(NOT	task	usage)
19 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Field	Mapping
You	can	map	both	existing	fields	and	custom	fields!
PPM	Data	Type
§ Date
§ Number
§ Boolean
§ String
§ Static	Lookups!
MSPField
§ Date1	– Date10
§ Number1	– 20
§ Flag1	– Flag20
§ Text1	– Text30
§ Text1	– Text30
20 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Field	Mapping
Field	mappings	are	even	easier	beginning	in	14.4.	All	mapped	
lookups	will	have	a	dropdown	picklist!
21 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Project	Scheduling
§ MSP	is	a	scheduling	tool.	Its	job	is	to	schedule	the	project	
EVERY time	the	project	is	opened	from	PPM.
§ Factors	that	will	affect	the	project	schedule	include:				
– Timesheet	posting
– Assignment	changes,	such	as	modifying	remaining	work	(ETC),	adding	
team	members	to	tasks,	and	changes	to	allocation
– Resource	Calendar	changes
– Assignment	Loading	pattern
22 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Loading	Patterns
§ Loading	Patterns	determine	how	to	distribute	the	remaining	
work	(ETC	)	on	the	assignment
§ Uniform	Loading	Pattern	is	recommended	for	the	most	
consistent	and	predictable	work	distribution
§ The	assignment	Work	Contour	field	in	MSP	maps	to	the	
Loading	Pattern	field	in	PPM
23 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Task	Types
§ We	support	the	3		MSP	task	types,	Fixed	Work,	Fixed	Unit	
and	Fixed	Duration.	Fixed	units	is	the	more	reliable	
(predictable)	task	type.	
§ You	can	set	a	task	to	be	fixed	duration	in	Clarity.	Add	the	
“Fixed	Duration”	field	to	the	task	properties.
§ You	must	set	“Fixed	Work”	task	types	in	MSP.
24 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Loading	Patterns	(Continued)
§ When	opening	from	PPM:
– Fixed	(PPM)	becomes	Contour	(MSP)
– Uniform	(PPM)	becomes	Flat	(MSP)
– Front	(PPM)	becomes	Front	(MSP)
– Back	(PPM)	will	becomes	back	(MSP)
– Contour	(PPM)	will	map	to	Contour	(MSP)
§ Note:	Fixed	loading	pattern	uses	ETC	in	a	“use	it	or	lose	it”	
method.	Any	ETC	not	used	that	week	after	posting	will	not	be	
redistributed,	but	removed.
25 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Team	Allocations
§ The	Team	member’s	allocation	will	calculate	the	resource’s	
ETC	on	their	assignment.		For	example,	if	the	resource’s	
calendar	is	8	hours	per	day,	and	they	are	allocated	100%	to	a	
project,	they	will	be	scheduled	8	hours	per	day	by	default	
when	they	are	added	as	an	assignment	to	a	task.
§ If	they	are	allocated	50%	to	the	project,	they	will	be	
scheduled	at	50%	of	their	availability,	so	in	this	case,	it	will	be	
4	hours	per	day.
26 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Team	Allocation	(Continued)
§ PPM	also	allows	you	to	create	allocation	segments	for	a	
resource,	which	means	you	can	allocate	a	team	member	for	
100%	for	a	month,	and	the	next	month	50%.	When	you	assign	
the	resource	to	a	task,	the	ETC	will	be	8	hours	per	day	for	the	
first	month,	then	decreased	based	upon	the	allocation	
segment	at	4	hours	per	day
§ NOTE:	Allocation	segments	are	recommended	only	when	
resource	&	project	managers	are	comfortable	understanding	
and	setting	the	default	allocation.
27 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Team	Allocation	(Continued)
Setting	an	allocation	for	a	team	member	in	PPM:
28 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Team	Allocation	(Continued)
29 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
NOTE:	The	default	allocation	in	PPM	does	not	map	down	to	the	Max%	field	on	the	
resource	sheet	in	MSP.	The	number	shown	is	always	based	upon	today’s	date.	
For	example	if	today	is	12/14/2015
Shows	as	25%	in	MSP.
Team	Allocation	(Continued)
30 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Assignment	Units
§ The	Assignment	Units	field	in	MSP,	shows	the	percentage	that	
represents	the	assigned	resources'	allocation	to	a	task.
§ For	example,	in	MSP	if	you	have	the	Max%	set	to	100%	(8	
hours	per	day),	when	you	change	the	units	on	an	assignment	
to	25%,	the	Remaining	Work		distribution	will	be	2	hours	per	
day	on	the	assignment.	
§ By	default,	when	a	resource	is	assigned	to	a	task,	the	units	will	
reflect	what	the	Max%	is	shown	on	the	resource	sheet.
31 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Max	%	Load
In	PPM,	instead	of	assignment	units,	we	have	a	assignment	field	
called	Max	%	Load.	This	field	can	be	added	to	the	assignment	
section	of	the	task	properties	page.	It	essentially	works	as	the	
assignment	unit	in	MSP	does.
With	me	so	far?	Now	it’s	time	to	throw	a	wrench	in	the	works!
32 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Allocations,	Units,	Max%	Continued
§ To	make	things	very	interesting,	we	have	a	new	option	in	the	
Project	Management	settings	in	the	admin	tool.
§ When	this	is	checked,	PPM’s	Max	%	Load	will	map	to	MSP’s	
Assignment	units	field.
§ When	this	is	unchecked,	the	MSP	Assignment	Units	field	will	be	
based	upon	the	Team	member’s	default	allocation.
§ Be	sure	to	understand	how	both	settings	work	before	
recommending	to	a	customer.
– With	the	Legacy	interface,	this	setting	only	applies	to	assignments	with	
uniform	loading	pattern.
33 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Work	=	Units	x	Duration
34 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Fixed	Duration	Task	Types
§ If	the	assignment	has	remaining	work,	yet	the	task	finish	date	
is	reached,	the	finish	date	will	move	to	accommodate	the	
remaining	work.
§ WARNING:	Even	with	fixed	duration	task	types,	Microsoft	will	
want	to	try	to	resolve	overallocations on	fixed	duration	task	
types,	and	if	your	assignment	is	overallocated,	Microsoft	will	
increase	the	duration	of	a	fixed	duration	task	type	with	a	
warning.
35 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Impact	of	Timesheet	Posting
§ When	you	open	your	project	in	MSP,	it	will	be	scheduled.	
Actual	hours	posted	against	a	timesheet	will	cause	task	dates	
to	shift,	which	will	affect	the	overall	project	plan.
§ This	can	be	challenging	for	new	users	to	PPM	who	have	used	
MSP	in	the	past	and	are	used	to	instant	feedback	to	updating	
actuals	in	MSP	manually.
36 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Impact	of	Timesheet	Posting	(Continued)
37 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Marking	a	Task	100%	Complete
§ It	is	important	to	know	the	correct	way	in	MSP	to	mark	
a	task	100%.	
§ If	you	mark	the	task	complete,	MSP	may	add	actual	hours	to	
your	task	automatically!	These	actual	hours	will	be	discarded	
upon	save	to	PPM	because	PPM	will	only	allow	actuals	to	be	
entered	from	timesheets.
38 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
What	to	Do	if	You	See	an	Unanticipated	
Scheduling	Change
§ When	you	encounter	a	scheduling	change	when	you	export	a	
plan	to	MSP,	try	to	recreate	the	issue	in	MSP	standalone	from	
scratch	before	reporting	the	issue	to	PPM	Support.
§ When	you	do	report	a	scheduling	anomaly	to	PPM	Support,	
please	send	in	screenshots	of	the	plan	in	PPM,	steps	to	
reproduce	the	problem,	the	.mpp	file,	and	what	you	expect	to	
see.	This	information	will	allow	PPM	Support	to	be	able	to	
diagnose	and	resolve	the	issue	faster.
39 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Case	Studies	&	Best	Practices
40 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Case	Study	#1
• Project	Managers	responsible	for	task	
classification,	but	they	did	not	fully	
understand	the	impact
• Poor	data	quality	on	capital/expense	
classification on	tasks
• Missed	opportunity	for	capitalization
• Created	standard	templates	with	
minimum	phases	and	tasks
• Created	a	process	to	automate	the	
population	of	cost	type	on	detailed	
tasks
• Held	one-day	training	for	Project	
Managers
• Project	Managers	improved	adoption	and	
understanding	(took	a	couple	months)
• Labor	capitalization	more	accurate
• Time-tracking	improved	and	senior	
leaders	began	to	use	the	timesheet	data	
for	more	predictive	planning
• A	little	bit	of	automation	goes	a	long	
way	in	perception
• Train	project	managers	on	the	
“why”	as	well	as	the	“what”	– they	
need	to	understand
• Increased data	quality	=	higher	
leadership	buy	in
DRIVERS
LESSONS
OUTCOMES
APPROACH
41 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Case	Study	#2
• Business	unit	was	moving from	
Microsoft	EPM	into	an	enterprise	
CA	PPM	instance
• A	critical	success	factor	was	to	
allow	Project	Managers	to	
continue	using	MSP	for	scheduling
• Trained	a	core	group	on	how	to	migrate	the	
plans	from	EPM
• Migrated	all	plans	1	week	prior
• Held	One-day	training	for	Project	Managers
• Included	high-touch	support	for	Project	
Managers	for	following	month
• Migration	was	successful	with	
strong	support	and	adoption	from	
project	managers
• Very	few issues	with	plans	being	
migrated,	resulting	in	no	work	
disruption
• Microsoft	EPM	connection	and	the	MSP	
Connector	don’t	play	well	with	each	other
• Leave	plenty	of	time	to	test	and	confirm	
the	migration	approach
• High-touch	support	was	critical	for	high
scheduling	maturity	managers
DRIVERS
LESSONS
OUTCOMES
APPROACH
42 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Case	Study	#3
• Complex schedules	with	enforced	
details	for	financial	controls,	time	
tracking,	and	health	– leading	to	
poor	adoption
• Wanted	to	find	a	way	to	increase	
adoption	without giving	up	some	of	
the	complexity
• Provided	a	few	options	with	pros	and	
cons	for	scheduling
• Conducted	“conference	room	pilot”	
with	internal	team	with	a	few	options
• Conducted	pilot	with	a	few	users	with	
chosen	option
• Implemented	a	“compromise”
schedule	with	some	complex	and	other	
simple	elements
• Increased	adoption	and	acceptance	by	
project	managers
• A	project	schedule	will	not	solve	non-
schedule-related	issues
• Project	Managers	must	have	the	ability	
to	control	their	schedule	– if	not,	they	
will	continue	to	use	MSP	offline
• Sometimes	its	best	to	use	a “try	before	
you	commit”	approach
DRIVERS
LESSONS
OUTCOMES
APPROACH
43 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Best	Practices
§ Automation	can	improve	data	quality	and	increase	leadership	buy-in
§ When	Project	Managers	understand	the	complete	picture—the	
“why”,	not	just	the	“what”—they	are	more	likely	to	adopt
§ Training	and	high-touch	support		should	be	planned	to	get	users	over	
the	learning	curve
§ Project	Managers	must	have	the	ability	to	control	their	schedule	–
adoption	depends	on	schedules	being	used	mainly	for	scheduling
§ Invest	in	migration	planning	– test	and	“try	before	you	commit”
44 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Recommended	Sessions
SESSION	# TITLE DATE/TIME
AMT02S CA	PPM	Vision	&	Roadmap 11/16/2016	at	12:45	pm
AMT03S Seven	elements	for	strategic	portfolio	management	
success:	How	and	why	Agile	plays	a	key	role	in	
investment	strategies	and	portfolio	management.
11/17/2016	at	12:45	pm
AMT07S
Pleasing	customers	with	portfolio	management	that	is	
both	strategic	and	agile
11/17/2016	at	4:30	pm
45 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Must	See	Demos
Management	
Insights	
CA	PPM	Theater	#6	
– Agile	Management
Connect	
Strategy	to	
Execution
CA	PPM	&	Agile	
Central	Theater	#6	–
Agile	Management
Adaptive	
Project	
Manager
CA	PPM	Theater	#6	
– Agile	Management
Align	Strategy	
&	Portfolios
CA	PPM	Theater	#6	
– Agile	Management
46 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Questions?
47 ©	2016	CA.	ALL	RIGHTS	RESERVED.@CAWORLD				#CAWORLD
Stay	connected	at	communities.ca.com
Thank	you.
@CAWORLD					#CAWORLD ©	2016	CA.	All	RIGHTS	RESERVED.48 @CAWORLD					#CAWORLD
Agile	Management
For	more	information	on	Agile	Management,	please	visit:	
http://cainc.to/9Zed5W

More Related Content

PDF
Learn How CA Services Can Help You Optimize Your PPM Journey
PDF
Portfolio Management Best Practices
PDF
Pre-Con Ed: CA Project & Portfolio Management: The Lost Art of User Adoption
PDF
Case Study: Learn how Standard Chartered Bank used training, advocacy and the...
PDF
Inspire Your Enterprise and Become a Digital Change Agent Through Agile Archi...
PDF
How Intel Improved Delivery
PDF
Cisco’s Agile Journey
PDF
Building Software Where the Music Died
Learn How CA Services Can Help You Optimize Your PPM Journey
Portfolio Management Best Practices
Pre-Con Ed: CA Project & Portfolio Management: The Lost Art of User Adoption
Case Study: Learn how Standard Chartered Bank used training, advocacy and the...
Inspire Your Enterprise and Become a Digital Change Agent Through Agile Archi...
How Intel Improved Delivery
Cisco’s Agile Journey
Building Software Where the Music Died

What's hot (20)

PPTX
Transforming your organization to be Value Focused
PDF
Agile Communities of Practice: Set Up, Sustain, Succeed
PDF
Case Study: Driving the Next Level of CA Project & Portfolio Management Matur...
PDF
Leading a Digital Business with Greater Agility: How to Plan a Modern Portfol...
PDF
The 30% Of Your Business You Are Not Optimizing: Outcome-Driven Meetings with...
PDF
Pre-Con Ed: CA Project & Portfolio Management: Getting the Most from the Appl...
PDF
Improving Delivery and Execution at Vantiv
PDF
Pre-Con Ed: Storage Bootcamp: It's Not Your Fathers Storage Anymore: Preparin...
PDF
Accelerating Application Development and Rollout for Business
PDF
SAFe Implementation Unicorns at McKesson
PDF
Case Study: From Excel to PPM – IDEXX’s Move to Better Manage Its Business
PDF
Pre-Con Ed: Covering Your "Assets" - Don't get Caught with Your [Software] Pa...
PDF
Pre-Con Ed: Five Easy Steps for Migrating to CA Directory
PDF
Pre-Con Ed: Taking the "Hard" out of Hardware Asset Management
PPTX
Hands-on Lab: Get a Jumpstart on CA Service Management's New Jaspersoft Repor...
PDF
Tech Talk: How to Create and Steer an Agile Business
PPTX
Pre-Con Ed: CA API Gateway: Managing and Migrating Policies with the Gateway ...
PDF
How Trek-Segafredo Powers its Racing With CA Flowdock
PDF
Pre-Con Ed: Workshop on Policy Creation, Management and Support for OAuth and...
PDF
Technology Primer: Learn the Basics—APM 101 and a Holistic View of the Applic...
Transforming your organization to be Value Focused
Agile Communities of Practice: Set Up, Sustain, Succeed
Case Study: Driving the Next Level of CA Project & Portfolio Management Matur...
Leading a Digital Business with Greater Agility: How to Plan a Modern Portfol...
The 30% Of Your Business You Are Not Optimizing: Outcome-Driven Meetings with...
Pre-Con Ed: CA Project & Portfolio Management: Getting the Most from the Appl...
Improving Delivery and Execution at Vantiv
Pre-Con Ed: Storage Bootcamp: It's Not Your Fathers Storage Anymore: Preparin...
Accelerating Application Development and Rollout for Business
SAFe Implementation Unicorns at McKesson
Case Study: From Excel to PPM – IDEXX’s Move to Better Manage Its Business
Pre-Con Ed: Covering Your "Assets" - Don't get Caught with Your [Software] Pa...
Pre-Con Ed: Five Easy Steps for Migrating to CA Directory
Pre-Con Ed: Taking the "Hard" out of Hardware Asset Management
Hands-on Lab: Get a Jumpstart on CA Service Management's New Jaspersoft Repor...
Tech Talk: How to Create and Steer an Agile Business
Pre-Con Ed: CA API Gateway: Managing and Migrating Policies with the Gateway ...
How Trek-Segafredo Powers its Racing With CA Flowdock
Pre-Con Ed: Workshop on Policy Creation, Management and Support for OAuth and...
Technology Primer: Learn the Basics—APM 101 and a Holistic View of the Applic...
Ad

Similar to CA Project & Portfolio Management and MS Project Integration: Tips, Tricks and Why's New for You (20)

PDF
Pre-Con Ed: CA Workload Automation DE: Tips and Tricks
PDF
Pre-Con Ed: CA Workload Automation AE: Tips and Tricks
PDF
Pre-Con Ed: CA Workload Automation DE: Tips and Tricks
PDF
Tech Talk: Agile Product Management Playbook
PDF
Tech Talk: Federate to an SAML-Enabled App in Minutes
PDF
Critical Path Forecasting with CA Workload Automation iDash
PDF
Pre-Con Ed: Bridge the Gap From Alert Suppression to MTTR Through Enterprise ...
PDF
Tech Talk: Running Successful Betas in a DevOps World
PDF
Pre-Con Ed: Where's the Data? How CA's DevTest Solutions Work Together to Lev...
PDF
CA Project & Portfolio Management: Business Intelligence
PDF
Tech Talk: Customize Reporting Dashboards for New Business Insights
PDF
Tech Talk: Want to get in on the Secret? How fast is your Directory?
PDF
Tracking Message Flows in DataPower With CA APM
PDF
Hands-On Lab: Integrate CA Spectrum® and CA Unified Infrastructure Management
PDF
Strategies for DevOps in the API and Microservices World
PDF
CA Datacom®/AD Installation/Upgrade and Maintenance
PDF
Tech Talk: Coty Transforms from Event Management to Service Operations Manage...
PDF
Hands-On Lab: Tune CA Performance Management for an Optimal Network Performan...
PDF
What’s new in CA Datacom
PDF
Technology Primer: Attain Faster MTTR through CA Application Performance Mana...
Pre-Con Ed: CA Workload Automation DE: Tips and Tricks
Pre-Con Ed: CA Workload Automation AE: Tips and Tricks
Pre-Con Ed: CA Workload Automation DE: Tips and Tricks
Tech Talk: Agile Product Management Playbook
Tech Talk: Federate to an SAML-Enabled App in Minutes
Critical Path Forecasting with CA Workload Automation iDash
Pre-Con Ed: Bridge the Gap From Alert Suppression to MTTR Through Enterprise ...
Tech Talk: Running Successful Betas in a DevOps World
Pre-Con Ed: Where's the Data? How CA's DevTest Solutions Work Together to Lev...
CA Project & Portfolio Management: Business Intelligence
Tech Talk: Customize Reporting Dashboards for New Business Insights
Tech Talk: Want to get in on the Secret? How fast is your Directory?
Tracking Message Flows in DataPower With CA APM
Hands-On Lab: Integrate CA Spectrum® and CA Unified Infrastructure Management
Strategies for DevOps in the API and Microservices World
CA Datacom®/AD Installation/Upgrade and Maintenance
Tech Talk: Coty Transforms from Event Management to Service Operations Manage...
Hands-On Lab: Tune CA Performance Management for an Optimal Network Performan...
What’s new in CA Datacom
Technology Primer: Attain Faster MTTR through CA Application Performance Mana...
Ad

More from CA Technologies (20)

PPTX
CA Mainframe Resource Intelligence
PDF
Mainframe as a Service: Sample a Buffet of IBM z/OS® Platform Excellence
PDF
Case Study: How CA Went From 40 Days to Three Days Building Crystal-Clear Tes...
PDF
Case Study: How The Home Depot Built Quality Into Software Development
PDF
Pre-Con Ed: Privileged Identity Governance: Are You Certifying Privileged Use...
PDF
Case Study: Privileged Access in a World on Time
PDF
Case Study: How SGN Used Attack Path Mapping to Control Privileged Access in ...
PDF
Case Study: Putting Citizens at The Center of Digital Government
PDF
Making Security Work—Implementing a Transformational Security Program
PDF
Keynote: Making Security a Competitive Advantage
PDF
Emerging Managed Services Opportunities in Identity and Access Management
PDF
The Unmet Demand for Premium Cloud Monitoring Services—and How Service Provid...
PDF
Leveraging Monitoring Governance: How Service Providers Can Boost Operational...
PDF
The Next Big Service Provider Opportunity—Beyond Infrastructure: Architecting...
PDF
Application Experience Analytics Services: The Strategic Digital Transformati...
PDF
Application Experience Analytics Services: The Strategic Digital Transformati...
PDF
Strategic Direction Session: Deliver Next-Gen IT Ops with CA Mainframe Operat...
PDF
Strategic Direction Session: Enhancing Data Privacy with Data-Centric Securit...
PDF
Blockchain: Strategies for Moving From Hype to Realities of Deployment
PDF
Establish Digital Trust as the Currency of Digital Enterprise
CA Mainframe Resource Intelligence
Mainframe as a Service: Sample a Buffet of IBM z/OS® Platform Excellence
Case Study: How CA Went From 40 Days to Three Days Building Crystal-Clear Tes...
Case Study: How The Home Depot Built Quality Into Software Development
Pre-Con Ed: Privileged Identity Governance: Are You Certifying Privileged Use...
Case Study: Privileged Access in a World on Time
Case Study: How SGN Used Attack Path Mapping to Control Privileged Access in ...
Case Study: Putting Citizens at The Center of Digital Government
Making Security Work—Implementing a Transformational Security Program
Keynote: Making Security a Competitive Advantage
Emerging Managed Services Opportunities in Identity and Access Management
The Unmet Demand for Premium Cloud Monitoring Services—and How Service Provid...
Leveraging Monitoring Governance: How Service Providers Can Boost Operational...
The Next Big Service Provider Opportunity—Beyond Infrastructure: Architecting...
Application Experience Analytics Services: The Strategic Digital Transformati...
Application Experience Analytics Services: The Strategic Digital Transformati...
Strategic Direction Session: Deliver Next-Gen IT Ops with CA Mainframe Operat...
Strategic Direction Session: Enhancing Data Privacy with Data-Centric Securit...
Blockchain: Strategies for Moving From Hype to Realities of Deployment
Establish Digital Trust as the Currency of Digital Enterprise

Recently uploaded (20)

PDF
Getting started with AI Agents and Multi-Agent Systems
PDF
Zenith AI: Advanced Artificial Intelligence
PDF
Consumable AI The What, Why & How for Small Teams.pdf
PDF
A contest of sentiment analysis: k-nearest neighbor versus neural network
PDF
Produktkatalog für HOBO Datenlogger, Wetterstationen, Sensoren, Software und ...
PDF
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
PDF
Enhancing emotion recognition model for a student engagement use case through...
PDF
CloudStack 4.21: First Look Webinar slides
PDF
STKI Israel Market Study 2025 version august
PDF
1 - Historical Antecedents, Social Consideration.pdf
PDF
A Late Bloomer's Guide to GenAI: Ethics, Bias, and Effective Prompting - Boha...
PDF
Hindi spoken digit analysis for native and non-native speakers
PPT
What is a Computer? Input Devices /output devices
PDF
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
PDF
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
PDF
Developing a website for English-speaking practice to English as a foreign la...
PDF
Flame analysis and combustion estimation using large language and vision assi...
DOCX
search engine optimization ppt fir known well about this
PDF
The influence of sentiment analysis in enhancing early warning system model f...
PPT
Geologic Time for studying geology for geologist
Getting started with AI Agents and Multi-Agent Systems
Zenith AI: Advanced Artificial Intelligence
Consumable AI The What, Why & How for Small Teams.pdf
A contest of sentiment analysis: k-nearest neighbor versus neural network
Produktkatalog für HOBO Datenlogger, Wetterstationen, Sensoren, Software und ...
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
Enhancing emotion recognition model for a student engagement use case through...
CloudStack 4.21: First Look Webinar slides
STKI Israel Market Study 2025 version august
1 - Historical Antecedents, Social Consideration.pdf
A Late Bloomer's Guide to GenAI: Ethics, Bias, and Effective Prompting - Boha...
Hindi spoken digit analysis for native and non-native speakers
What is a Computer? Input Devices /output devices
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
Developing a website for English-speaking practice to English as a foreign la...
Flame analysis and combustion estimation using large language and vision assi...
search engine optimization ppt fir known well about this
The influence of sentiment analysis in enhancing early warning system model f...
Geologic Time for studying geology for geologist

CA Project & Portfolio Management and MS Project Integration: Tips, Tricks and Why's New for You