INSPECTION /RECORD SHEET FOR FOUNDATION EXCAVATION DIMENTION

NAME OF LINE:
CONSULTANT :
CLIENT              :
CONTRACTOR :


DATE                                                   12-Dec-07

TOWER NO:                                   0                     TOWER TYPE                 0


                                                LEG#1               LEG#2                    LEG#3              LEG#4
LEG EXT:                                          +4                     +2                       +3                +4
CHEMNEY EXT:                                       0                      0                       0                  0


SOIL CLASS:                           3                   DRAWING NUMBER:                        A/SP/7660/P/040


EXCAVATION DETAILS

EXCAVATION DRAWING NO:                                     A/SP/7660/P/040


                                                       LEG#1                  LEG#2                   LEG#3              LEG#4
                                                AS DRNG ACTUEL      AS DRNG      ACTUEL      AS DRNG ACTUEL     AS DRNG      ACTUEL

AVERAGE DEPTH TO CP                              4250      4250          4250         4250       4250    4250      4250          4250
EXCAVATION WIDTH                                 6030      6950          6030         7200       6030    6650      6030          6700
                                 WIDTH            150       150          150          150        150      150      150           150
      UNDER CUT                  HEIGHT           200       200          200          200        200      200      200           200


            SOIL STRATA                           MIXED SOIL             MIXED SOIL              MIXED SOIL         MIXED SOIL
DEWATERING REQUIRED                                    YES/NO              YES/NO                  YES/NO            YES/NO
SHUTERING EMPLOYED                                     YES/NO              YES/NO                  YES/NO            YES/NO

CHANGE OF FOUNDATION CLASS : YES/NO                               IF YES ACCEPTED CLASS:

Remark : Excavation accepted for stub setting and concreting




---------------------------------------------


INSPECTION /RECORD SHEET FOR STUB SETTING DIMENTION




                                                                     1
NAME OF LINE:                 0
CONSULTANT :
CLIENT      :
CONTRACTOR :

DATE                                   12-Dec-07

TOWER NO:                     0                 TOWER TYPE              0

                                  LEG#1               LEG#2              LEG#3            LEG#4
LEG EXT:                            +4  M                +2         M      +3  M             +4         M
CHEMNEY EXT:                         0  M                 0         M       0  M              0         M

SOIL CLASS:               3                 DRAWING NUMBER:                 A/SP/7660/P/040

STUB DETAILS

STUB MARK NO:                     H5800-1                           STUB LENGTH               6021

STUB DIMENTIONS

LEVEL LEG#2                                                                               LEVEL LEG#3
T=              0.616                     T=           14015.2                            T=          1.616
A=              0.614                     A=             8053.0                           A=          1.613



                                  T=        20108.0
                                  A=        11344.0
                                                                                  T=          14353.4
                                                                                  A=           7900.0

          T=            14292.7
          A=             8055.0

                                  T=        20272.7
                                  A=        11172.0




LEVEL LEG#1                               T=              14487.0                         LEVEL LEG#4
T=              1.616                     A=               7902.0                         T=          1.616
A=              1.616                                                                     A=          1.615

NOTE: SETTING LEG FOR LEVELL :LEG NO:……………………………….
                                                 1




INSPECTION /RECORD SHEET FOR REINFORCEMENT AND CONCRETING

NAME OF LINE:                 0
CONSULTANT :




                                                      2
CLIENT    :
CONTRACTOR :

DATE                                       12-Dec-07

TOWER NO:                           0                  TOWER TYPE             0

                                    LEG#1                 LEG#2                LEG#3                 LEG#4
LEG EXT:                              +4  M                  +2       M          +3  M                  +4          M
CHEMNEY EXT:                           0  M                   0       M           0  M                   0          M

SOIL CLASS:                   3               DRAWING NUMBER:                     A/SP/7660/P/040

CONCRETE MATERIALS (if as per drawing Y(es):


              ITEM                           OBSERVATION                                 COMMENTS
CEMENT                                              OK                                         N/A
GRAVEL SIZE                                         OK                                         N/A
SAND PROPERTY                                       OK                                         N/A
CONCRETE SUPPLIER
LOADING TIME                                11:43                 7:13                 10:52                 8:45
CONCRETING TIME                             13:10                 9:15                 12:00                 10:40

REINFORCEMENT MATERIALS (if as per drawing Yes):

REINFORCEMENT WEIGHT

                                  LEG#1                LEG#2                LEG#3                LEG#4
        PER LEG                1768.31                 1768.31              1768.31             1768.31
  TOTAL WEIGHT                                                    7073.24

CONCRETING

                 DATE OF                  DATE OF                CONCRETING VOLUME                        SLUMP
               CONCRETING               CONCRETING
   LEG           PYRAMID                 CHIMNEY          AS PER DRAWING              ACTUEL                 MM
    1             11/1/2007               11/1/2007               33.23                 46                    85
    2             28/2/2007               28/2/2007               33.23                 50                    90
    3             19/1/2007               25/1/2007               33.23                42.5                   90
    4             11/12/2006              11/12/2006              33.23                 42                   100
            TOTAL CONCRETING VOLUME                              132.91                180.5




INSPECTION /RECORD SHEET FOR REINFORCEMENT AND CONCRETING

NAME OF LINE:
CONSULTANT :
CLIENT      :
CONTRACTOR :




                                                          3
DATE                                  12-Dec-07

TOWER NO:                       0                 TOWER TYPE         0

                                LEG#1               LEG#2            LEG#3              LEG#4
LEG EXT:                          +4  M                +2      M       +3  M               +4   M
CHEMNEY EXT:                       0  M                 0      M        0  M                0   M

SOIL CLASS:                 3            DRAWING NUMBER:                  A/SP/7660/P/040

CUBES CYLINDRES TAKEN (ID=Mark identification )S for slab,C for chimney

    ID            DATE          LEG             DATE           LEG
     S          11/1/2007         1           19/1/2007          3
     C          28/2/2007         2          11/12/2006          4

FORM WORK REMOVED


   LEG            DATE                     OBSERVATION
     1          13/1/2007                          OK
     2           2/3/2007                          OK
     3          27/1/2007                          OK
     4          13/12/2006                         OK

REMARK: ACCEPTED FOR BACK FILLING
         FOUNDATION ACCEPTED FOR PAYMENT:




INSPECTION /RECORD SHEET FOR STUB SETTING DIMENTION

NAME OF LINE:
CONSULTANT :
CLIENT      :
CONTRACTOR :

DATE                                  12-Dec-07



                                                     4
TOWER NO:                 0                  TOWER TYPE             0

                          LEG#1                 LEG#2               LEG#3             LEG#4
LEG EXT:                    +4  M                  +2      M          +3  M              +4           M
CHEMNEY EXT:                 0  M                   0      M           0  M               0           M

SOIL CLASS:           3                 DRAWING NUMBER:                 A/SP/7660/P/040

STUB DETAILS

STUB MARK NO:                 H5800-1                      STUB LENGTH                    6021


CLEATS/STUB                     12                         CLEAT BOLTS/STUB                      24


STUB DIMENTIONS



                                                                LEG#1                LEG#2
                                           STUB SLOPE      WING1 WING2 WING1 WING2
                                          THEORETICAL          90       90      90         90
                                          ACTUAL AT SITE       90       90      89         90
1MTR

                  A                                             LEG#3                LEG#4
                                           STUB SLOPE      WING1 WING2 WING1 WING2
                                          THEORETICAL          90       90      90         90
                                          ACTUAL AT SITE       91       90      90         90




          STUB SETTING IS ACCEPTED FOR CONCRETING




INSPECTION /RECORD SHEET FOR STUB SETTING DIMENTION



NAME OF LINE:
CONSULTANT :
CLIENT      :
CONTRACTOR :




                                                 5
DATE                                12-Dec-07

TOWER NO:                    0                 TOWER TYPE            0


                    2                                                    3




                    1                                                    4

                          SLOPE IN 50CM    LEVEL
  LEG     LEG EXT CHI.EXT WING1 WING2 TOP OF STUB
   1         +4      0      45      45      1.616
   2         +2      0     44.5     45      0.614
   3         +3      0     45.5     45      1.613
   4         +4      0      45      45      1.615                        SIDE SLOPE IN 50CM=45

REFERENCE LEG FOR LEVEL                    1
                                                                                            -b


                                                                                            +b

                                           a



                         1-2      1-4     2-1          2-3       3-2       3-4      4-1          4-3
  DISTANCE"a"cm         1429.3   1448.7   1429.3       1401.5   1401.5    1435.3   1448.7         1435.3
    VALUE"b"cm            -4       6       0            0         0        2.5       -2           6
  (b/a)x100%value       -0.280    0.414    0.000        0.000    0.000     0.174   -0.138          0.418




INSPECTION /RECORD SHEET FOR EARTHING MEASURMENTS



NAME OF LINE:
CONSULTANT :
CLIENT      :
CONTRACTOR :


DATE                                12-Dec-07



                                                   6
TOWER NO:                   0             TOWER TYPE          0


                            LEG#1            LEG#2             LEG#3           LEG#4
LEG EXT:                      +4  M             +2      M        +3  M            +4      M
CHEMNEY EXT:                   0  M              0      M         0  M             0      M


BASIC EARTHING CONNECTED TO LEG NO:               1               3


DATE       EARTH RESISTANCE (OHM) WITH BASIC EARTHING
12/12/2007             1.8 OHM




NOTE: IF TOWER FOOTING RESISTANCE IS GREATER THAN 15 OHM ADDITIONAL EARTHING MAY BE REQUIRED
,SUBJECT TO THE APPROVAL OF ENGINEER



  AGREED FOR ADDITIONAL
 EARTHING TO BE INSTALLED       FOR EDF               FOR CONTRACTOR




DATE      EARTH RESISTANCE (OHM) WITH ADDITIONAL EARTHING
                         OHM


   EARTHING INSTALLATION
         ACCEPTED               FOR EDF               FOR CONTRACTOR




                                              7

More Related Content

PDF
Tes p-122.01-r0 (2)
PDF
TES-P-119-19-R1.pdf
PDF
Copy of prop setting calculations final
PDF
Tes p-122.10-r0 (1)
PPTX
Transmission line Project
PPTX
Transmisiion line design concept
PPTX
Overhead transmission lines_ Foundation.pptx
PDF
3-Drawings.pdf
Tes p-122.01-r0 (2)
TES-P-119-19-R1.pdf
Copy of prop setting calculations final
Tes p-122.10-r0 (1)
Transmission line Project
Transmisiion line design concept
Overhead transmission lines_ Foundation.pptx
3-Drawings.pdf

What's hot (20)

PDF
Copy of stub setting 1
DOCX
HV tower design 3
PDF
Copy of stub setting 3
PPT
Transmission Line Towers and details
PDF
Types of-tower
PDF
tower spotting
PDF
Construction EHV Transmission Line
PDF
Rt acceptance criteria by zas
PPT
Survey & ts for ehv lines
PPTX
Part 2 Self Supporting tower structures
PDF
Saudi Aramco Engineering Procedures (SAEP)1
PDF
Jacobs Recent changes to transmission line design standards and the impact on...
PDF
PDF
135613248 lifting-lug
PDF
Wind Actions According To EC1
PDF
Problems on lamis theorem.pdf
PDF
many projects shoring
DOCX
Design of Transmission Tower
PPTX
Singly R.C. beam
Copy of stub setting 1
HV tower design 3
Copy of stub setting 3
Transmission Line Towers and details
Types of-tower
tower spotting
Construction EHV Transmission Line
Rt acceptance criteria by zas
Survey & ts for ehv lines
Part 2 Self Supporting tower structures
Saudi Aramco Engineering Procedures (SAEP)1
Jacobs Recent changes to transmission line design standards and the impact on...
135613248 lifting-lug
Wind Actions According To EC1
Problems on lamis theorem.pdf
many projects shoring
Design of Transmission Tower
Singly R.C. beam
Ad

Viewers also liked (13)

PDF
Copy of stub setting 2
PDF
Tower smart tower_detailing_tips_series_4
PDF
Copy of prop setting calculations final
PDF
Use of bentonite
PDF
Techniquescontrolledblasting 091217003405-phpapp01
PDF
Tower smart tower_detailing_tips_series_3
PDF
Bab iii hitungan polygon
PDF
Concrete mix design
PDF
Concrete design mix (ss)
PPT
Foundation
PPT
TYPES OF FOUNDATION(PPT)
PPT
transmission line
Copy of stub setting 2
Tower smart tower_detailing_tips_series_4
Copy of prop setting calculations final
Use of bentonite
Techniquescontrolledblasting 091217003405-phpapp01
Tower smart tower_detailing_tips_series_3
Bab iii hitungan polygon
Concrete mix design
Concrete design mix (ss)
Foundation
TYPES OF FOUNDATION(PPT)
transmission line
Ad

Similar to Copy of stub setting (20)

PDF
Copy of stub setting 1
PDF
Copy of stub setting 1
PPT
1.5MT Longwall faces in SCCL-Few planning issues
PDF
Copy of prop setting calculations final
PDF
Copy of prop setting calculations final
PDF
Copy of prop setting calculations final
PDF
Bbs d2 deck segment ea06 496 r3
PDF
Project Development, Construction Documents
PDF
Building Conc. 100%
PDF
Rebar arrangement and construction carryout
PDF
Copy of stub setting 3
PDF
Copy of stub setting 3
PDF
Mixed Use Development
PDF
Porposal 2 sheet set sheet - a107 - east west elevations
PDF
Elevetor eng
PDF
Concrete ratio
PDF
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CAPITA
PDF
REVIT_MEP_ADT17_PAL Portfolio
PDF
Construction Documents Fall 2014
PDF
P.S.1 Field Guide / © William O'brien Jr
Copy of stub setting 1
Copy of stub setting 1
1.5MT Longwall faces in SCCL-Few planning issues
Copy of prop setting calculations final
Copy of prop setting calculations final
Copy of prop setting calculations final
Bbs d2 deck segment ea06 496 r3
Project Development, Construction Documents
Building Conc. 100%
Rebar arrangement and construction carryout
Copy of stub setting 3
Copy of stub setting 3
Mixed Use Development
Porposal 2 sheet set sheet - a107 - east west elevations
Elevetor eng
Concrete ratio
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CAPITA
REVIT_MEP_ADT17_PAL Portfolio
Construction Documents Fall 2014
P.S.1 Field Guide / © William O'brien Jr

More from Lahmeyer International, UAE (16)

PDF
AP88 & AP91 shifting proposal
PDF
Design of transmission lines in india a review of multiple swing angle
PDF
Guide to sampling concrete
PDF
Guide to sampling concrete
PDF
Ohl project risk register
PDF
Ohl project risk register
PDF
Counter mesaures aginst liquefaction induced settlemnt for ohl
PDF
Copy of stub setting
PDF
Copy of stub setting
PDF
Copy of stub setting
PDF
Copy of stub setting
PDF
Copy of stub setting 2
PDF
Copy of stub setting 2
PDF
Airbirne observation plate
AP88 & AP91 shifting proposal
Design of transmission lines in india a review of multiple swing angle
Guide to sampling concrete
Guide to sampling concrete
Ohl project risk register
Ohl project risk register
Counter mesaures aginst liquefaction induced settlemnt for ohl
Copy of stub setting
Copy of stub setting
Copy of stub setting
Copy of stub setting
Copy of stub setting 2
Copy of stub setting 2
Airbirne observation plate

Recently uploaded (20)

PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PPTX
TLE Review Electricity (Electricity).pptx
PDF
Transform Your ITIL® 4 & ITSM Strategy with AI in 2025.pdf
PPTX
Group 1 Presentation -Planning and Decision Making .pptx
PPTX
A Presentation on Touch Screen Technology
PDF
project resource management chapter-09.pdf
PPTX
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
PPTX
A Presentation on Artificial Intelligence
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PDF
Hindi spoken digit analysis for native and non-native speakers
PDF
Heart disease approach using modified random forest and particle swarm optimi...
PDF
Accuracy of neural networks in brain wave diagnosis of schizophrenia
PDF
Encapsulation_ Review paper, used for researhc scholars
PDF
NewMind AI Weekly Chronicles - August'25-Week II
PDF
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
PDF
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
PDF
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
PPTX
Tartificialntelligence_presentation.pptx
PDF
Assigned Numbers - 2025 - Bluetooth® Document
PDF
A novel scalable deep ensemble learning framework for big data classification...
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
TLE Review Electricity (Electricity).pptx
Transform Your ITIL® 4 & ITSM Strategy with AI in 2025.pdf
Group 1 Presentation -Planning and Decision Making .pptx
A Presentation on Touch Screen Technology
project resource management chapter-09.pdf
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
A Presentation on Artificial Intelligence
Agricultural_Statistics_at_a_Glance_2022_0.pdf
Hindi spoken digit analysis for native and non-native speakers
Heart disease approach using modified random forest and particle swarm optimi...
Accuracy of neural networks in brain wave diagnosis of schizophrenia
Encapsulation_ Review paper, used for researhc scholars
NewMind AI Weekly Chronicles - August'25-Week II
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
Tartificialntelligence_presentation.pptx
Assigned Numbers - 2025 - Bluetooth® Document
A novel scalable deep ensemble learning framework for big data classification...

Copy of stub setting

  • 1. INSPECTION /RECORD SHEET FOR FOUNDATION EXCAVATION DIMENTION NAME OF LINE: CONSULTANT : CLIENT : CONTRACTOR : DATE 12-Dec-07 TOWER NO: 0 TOWER TYPE 0 LEG#1 LEG#2 LEG#3 LEG#4 LEG EXT: +4 +2 +3 +4 CHEMNEY EXT: 0 0 0 0 SOIL CLASS: 3 DRAWING NUMBER: A/SP/7660/P/040 EXCAVATION DETAILS EXCAVATION DRAWING NO: A/SP/7660/P/040 LEG#1 LEG#2 LEG#3 LEG#4 AS DRNG ACTUEL AS DRNG ACTUEL AS DRNG ACTUEL AS DRNG ACTUEL AVERAGE DEPTH TO CP 4250 4250 4250 4250 4250 4250 4250 4250 EXCAVATION WIDTH 6030 6950 6030 7200 6030 6650 6030 6700 WIDTH 150 150 150 150 150 150 150 150 UNDER CUT HEIGHT 200 200 200 200 200 200 200 200 SOIL STRATA MIXED SOIL MIXED SOIL MIXED SOIL MIXED SOIL DEWATERING REQUIRED YES/NO YES/NO YES/NO YES/NO SHUTERING EMPLOYED YES/NO YES/NO YES/NO YES/NO CHANGE OF FOUNDATION CLASS : YES/NO IF YES ACCEPTED CLASS: Remark : Excavation accepted for stub setting and concreting --------------------------------------------- INSPECTION /RECORD SHEET FOR STUB SETTING DIMENTION 1
  • 2. NAME OF LINE: 0 CONSULTANT : CLIENT : CONTRACTOR : DATE 12-Dec-07 TOWER NO: 0 TOWER TYPE 0 LEG#1 LEG#2 LEG#3 LEG#4 LEG EXT: +4 M +2 M +3 M +4 M CHEMNEY EXT: 0 M 0 M 0 M 0 M SOIL CLASS: 3 DRAWING NUMBER: A/SP/7660/P/040 STUB DETAILS STUB MARK NO: H5800-1 STUB LENGTH 6021 STUB DIMENTIONS LEVEL LEG#2 LEVEL LEG#3 T= 0.616 T= 14015.2 T= 1.616 A= 0.614 A= 8053.0 A= 1.613 T= 20108.0 A= 11344.0 T= 14353.4 A= 7900.0 T= 14292.7 A= 8055.0 T= 20272.7 A= 11172.0 LEVEL LEG#1 T= 14487.0 LEVEL LEG#4 T= 1.616 A= 7902.0 T= 1.616 A= 1.616 A= 1.615 NOTE: SETTING LEG FOR LEVELL :LEG NO:………………………………. 1 INSPECTION /RECORD SHEET FOR REINFORCEMENT AND CONCRETING NAME OF LINE: 0 CONSULTANT : 2
  • 3. CLIENT : CONTRACTOR : DATE 12-Dec-07 TOWER NO: 0 TOWER TYPE 0 LEG#1 LEG#2 LEG#3 LEG#4 LEG EXT: +4 M +2 M +3 M +4 M CHEMNEY EXT: 0 M 0 M 0 M 0 M SOIL CLASS: 3 DRAWING NUMBER: A/SP/7660/P/040 CONCRETE MATERIALS (if as per drawing Y(es): ITEM OBSERVATION COMMENTS CEMENT OK N/A GRAVEL SIZE OK N/A SAND PROPERTY OK N/A CONCRETE SUPPLIER LOADING TIME 11:43 7:13 10:52 8:45 CONCRETING TIME 13:10 9:15 12:00 10:40 REINFORCEMENT MATERIALS (if as per drawing Yes): REINFORCEMENT WEIGHT LEG#1 LEG#2 LEG#3 LEG#4 PER LEG 1768.31 1768.31 1768.31 1768.31 TOTAL WEIGHT 7073.24 CONCRETING DATE OF DATE OF CONCRETING VOLUME SLUMP CONCRETING CONCRETING LEG PYRAMID CHIMNEY AS PER DRAWING ACTUEL MM 1 11/1/2007 11/1/2007 33.23 46 85 2 28/2/2007 28/2/2007 33.23 50 90 3 19/1/2007 25/1/2007 33.23 42.5 90 4 11/12/2006 11/12/2006 33.23 42 100 TOTAL CONCRETING VOLUME 132.91 180.5 INSPECTION /RECORD SHEET FOR REINFORCEMENT AND CONCRETING NAME OF LINE: CONSULTANT : CLIENT : CONTRACTOR : 3
  • 4. DATE 12-Dec-07 TOWER NO: 0 TOWER TYPE 0 LEG#1 LEG#2 LEG#3 LEG#4 LEG EXT: +4 M +2 M +3 M +4 M CHEMNEY EXT: 0 M 0 M 0 M 0 M SOIL CLASS: 3 DRAWING NUMBER: A/SP/7660/P/040 CUBES CYLINDRES TAKEN (ID=Mark identification )S for slab,C for chimney ID DATE LEG DATE LEG S 11/1/2007 1 19/1/2007 3 C 28/2/2007 2 11/12/2006 4 FORM WORK REMOVED LEG DATE OBSERVATION 1 13/1/2007 OK 2 2/3/2007 OK 3 27/1/2007 OK 4 13/12/2006 OK REMARK: ACCEPTED FOR BACK FILLING FOUNDATION ACCEPTED FOR PAYMENT: INSPECTION /RECORD SHEET FOR STUB SETTING DIMENTION NAME OF LINE: CONSULTANT : CLIENT : CONTRACTOR : DATE 12-Dec-07 4
  • 5. TOWER NO: 0 TOWER TYPE 0 LEG#1 LEG#2 LEG#3 LEG#4 LEG EXT: +4 M +2 M +3 M +4 M CHEMNEY EXT: 0 M 0 M 0 M 0 M SOIL CLASS: 3 DRAWING NUMBER: A/SP/7660/P/040 STUB DETAILS STUB MARK NO: H5800-1 STUB LENGTH 6021 CLEATS/STUB 12 CLEAT BOLTS/STUB 24 STUB DIMENTIONS LEG#1 LEG#2 STUB SLOPE WING1 WING2 WING1 WING2 THEORETICAL 90 90 90 90 ACTUAL AT SITE 90 90 89 90 1MTR A LEG#3 LEG#4 STUB SLOPE WING1 WING2 WING1 WING2 THEORETICAL 90 90 90 90 ACTUAL AT SITE 91 90 90 90 STUB SETTING IS ACCEPTED FOR CONCRETING INSPECTION /RECORD SHEET FOR STUB SETTING DIMENTION NAME OF LINE: CONSULTANT : CLIENT : CONTRACTOR : 5
  • 6. DATE 12-Dec-07 TOWER NO: 0 TOWER TYPE 0 2 3 1 4 SLOPE IN 50CM LEVEL LEG LEG EXT CHI.EXT WING1 WING2 TOP OF STUB 1 +4 0 45 45 1.616 2 +2 0 44.5 45 0.614 3 +3 0 45.5 45 1.613 4 +4 0 45 45 1.615 SIDE SLOPE IN 50CM=45 REFERENCE LEG FOR LEVEL 1 -b +b a 1-2 1-4 2-1 2-3 3-2 3-4 4-1 4-3 DISTANCE"a"cm 1429.3 1448.7 1429.3 1401.5 1401.5 1435.3 1448.7 1435.3 VALUE"b"cm -4 6 0 0 0 2.5 -2 6 (b/a)x100%value -0.280 0.414 0.000 0.000 0.000 0.174 -0.138 0.418 INSPECTION /RECORD SHEET FOR EARTHING MEASURMENTS NAME OF LINE: CONSULTANT : CLIENT : CONTRACTOR : DATE 12-Dec-07 6
  • 7. TOWER NO: 0 TOWER TYPE 0 LEG#1 LEG#2 LEG#3 LEG#4 LEG EXT: +4 M +2 M +3 M +4 M CHEMNEY EXT: 0 M 0 M 0 M 0 M BASIC EARTHING CONNECTED TO LEG NO: 1 3 DATE EARTH RESISTANCE (OHM) WITH BASIC EARTHING 12/12/2007 1.8 OHM NOTE: IF TOWER FOOTING RESISTANCE IS GREATER THAN 15 OHM ADDITIONAL EARTHING MAY BE REQUIRED ,SUBJECT TO THE APPROVAL OF ENGINEER AGREED FOR ADDITIONAL EARTHING TO BE INSTALLED FOR EDF FOR CONTRACTOR DATE EARTH RESISTANCE (OHM) WITH ADDITIONAL EARTHING OHM EARTHING INSTALLATION ACCEPTED FOR EDF FOR CONTRACTOR 7