Design-Build  Contract Award Processes in Washington State Mike Purdy Michael E. Purdy Associates (206) 295-1464 [email_address] www.mpurdy.com
Michael E. Purdy Associates - About Us Public Contracting Advice   for Public Agencies & Businesses Since 2005 Strategies Developing and implementing effective strategies Solutions   Creatively solving challenging contracting problems Training Providing clear, comprehensive, and focused training
Michael E. Purdy Associates - Subscribe by e-mail to the Blog - http://PublicContracting.blogspot.com
Outline Issue Request for Qualifications (RFQ) Evaluate Submittals to RFQ Issue RFP to finalists Evaluate Responses to RFP The material in this presentation is an outline of the requirements of Chapter 39.10 RCW.
Advertisement Publish notice of RFQ in legal newspaper.
Content of RFQ Describe project:   General description of project with sufficient information so proposers can submit qualifications. Why use design-build:   Reasons for using design-build. Qualifications needed:   Description of qualifications to be required of proposers. Contract to be used:   The form of the contract to be awarded.
Content of RFQ Honorarium:   The amount to be paid to finalists submitting responsive proposals and who are not awarded a design-build contract. Sufficient amount to generate meaningful competition among potential proposers. Public body to consider the level of effort required to meet the selection criteria. Schedule:   The schedule for the procurement process and the project.
Content of RFQ Other:   Other information relevant to the project. Evaluation and Selection Process:   Description of selection process to be used in evaluating qualifications and finalists’ proposals, including evaluation factors and weighting of factors.
RFQ Evaluation Factors - Must be in RFQ Technical qualifications, such as specialized experience and technical competence Capability to perform Past performance of the proposers’ team, including the A/E and construction members Other appropriate factors Cost or price-related factors may not be used in the RFQ phase.
RFP Evaluation Factors - Must be in RFQ All of the evaluation factors from the RFQ Technical approach design concept Alternative evaluation factor:   If public body determines that all finalists will be capable of producing a design that adequately meets project requirements, the public body may award the contract to the firm that submits the responsive proposal with the lowest price. Proposal price Ability of professional personnel Past performance on similar projects Ability to meet time and budget requirements Ability to provide a performance and payment bond Recent, current, and projected workloads of firm Location of firm
Evaluate RFQ Submittals Committee:   Establish evaluation committee Evaluate based on criteria:   Evaluate responses to the RFQ based on factors, weighting, and process in RFQ Maximum number of finalists:   Select no more than 5 finalists to submit proposals in response to an RFP
Issue RFP to Finalists - Content of RFP Describe project:   Description of the project including programmatic, performance, and technical requirements and specifications Describe functional issues:   Functional and operational elements Square Footage:   Minimum and maximum net and gross areas of any building Drawings:   Preliminary engineering and architectural drawings (at discretion of public body) Budget:   Target budget for design-build portion of the project
Evaluate Responses to RFP Committee:   Establish evaluation committee Evaluation procedure:   Select evaluation procedure from two options on the following slides. Identify Evaluation Procedure in RFQ
Option A for Evaluating Proposals Evaluation:  Evaluate proposals based on factors, weighting, and process identified in the RFQ Best and Final Proposals:   May request best and final proposals from finalists Negotiation:   Negotiate with firm with highest scored proposal If unable to successfully negotiate, may suspend or terminate negotiations and negotiate with next highest scored firm.
Option B for Evaluating Proposals Award based on lowest price:   If public body determines that all finalists will be capable of producing a design that adequately meets project requirements, the public body may award the contract to the firm that submits the responsive proposal with the lowest price.
Problems with Option B for Evaluating Proposals Owner doesn’t know at time of RFQ if all finalists can produce a sufficient design. Technical approach design concept appears to be the only thing that owner wouldn’t ask finalists to submit. Does not appear to enable owner to take into account non-design factors, weighting, and process identified in the RFQ relative to the RFP. Perhaps the RFQ should outline the two options and state that the decision will be made in the RFP as to whether all the finalists are capable of producing a good design.  This is really the only reasonable way to approach it, and is somewhat supported by RCW 39.10.330 (1)(d)(ii).
Michael E. Purdy Associates Mike Purdy  Principal (206) 295-1464 [email_address] www.mpurdy.com Mike Purdy’s Public Contracting Blog:   http://PublicContracting.blogspot.com The opinions and interpretations expressed in this presentation do not represent legal advice and the reader is encouraged to consult with an attorney to obtain legal advice.
Michael E. Purdy Associates:   Mike Purdy has almost 30 years of experience as a manager in public contracting and procurement.  He is the principal of Michael E. Purdy Associates ( www.mpurdy.com ), a consultant firm established in 2005 to help public agencies and businesses develop and implement effective contracting strategies, solve contracting problems, and learn more about contracting and procurement through tailored training. He maintains the popular Public Contracting Blog at  http://PublicContracting.blogspot.com .  Experience:   Mike is also the Contracts Manager for the University of Washington’s Capital Projects Office and is responsible for managing design and construction contracts for more than $1 billion worth of projects at the University.  Before joining the UW in 2005, he spent five years at the Seattle Housing Authority where he served as Contracting and Procurement Manager, overseeing all of the contracting and purchasing (construction, design consultants, other consultants, goods, supplies, and services) for the largest residential landlord in the state.  Prior to that he worked for the City of Seattle for more than 21 years, where he administered the City’s construction and consultant contracts as the City’s Contracting Manager.   Education:   He has a bachelor’s degree in business and public administration and an MBA, both from the University of Puget Sound, and a master of divinity degree from Fuller Theological Seminary.

More Related Content

PDF
Design-Build Procurement Approaches
PDF
Design build risks and rewards for public owner
PDF
20080704 innovative approach in contracts and tender procurement management
DOC
Single stage design and build method & construction project management
PPTX
Procurement system
DOCX
Resume _Vijay Zope
PDF
Chakradhar iyyunniandmonikas purohith
PPT
Net challenge training_material_vo eto_form_v002
Design-Build Procurement Approaches
Design build risks and rewards for public owner
20080704 innovative approach in contracts and tender procurement management
Single stage design and build method & construction project management
Procurement system
Resume _Vijay Zope
Chakradhar iyyunniandmonikas purohith
Net challenge training_material_vo eto_form_v002

What's hot (20)

DOCX
Procurement Methods
PDF
Curriculum Vitae-Indira Devi
PPT
Chapter 3- Contract Management
PDF
Site manager and site engineer (senior level)
PDF
Akinjiyan_Olufemi_DRP14-15 Submitted
PPTX
Project Delivery Method Selection Tool
PDF
Management projet international
PPT
Chapter 2- Contract Management
PPTX
The role of an Architect
PPTX
Project formulation slstl-iesl - 25th oct 2018 - to be published
PDF
DESIGN & BUILD
PPTX
Project evaluation for developers - India
PDF
Procurement system in the Indian construction industry issues and remedies
PDF
Professional practice 1 (QS)
PDF
Clark Dial RESUME 5-15-2015
PPT
Lecture 1 introduction to construction procurement process.
PDF
Tim Brewington revised format 2
DOCX
Smu mba sem 3 pm spring 2015 assignments
PDF
Procurement Strategies: A Seminar
PPTX
Professional practice-1-presentation
Procurement Methods
Curriculum Vitae-Indira Devi
Chapter 3- Contract Management
Site manager and site engineer (senior level)
Akinjiyan_Olufemi_DRP14-15 Submitted
Project Delivery Method Selection Tool
Management projet international
Chapter 2- Contract Management
The role of an Architect
Project formulation slstl-iesl - 25th oct 2018 - to be published
DESIGN & BUILD
Project evaluation for developers - India
Procurement system in the Indian construction industry issues and remedies
Professional practice 1 (QS)
Clark Dial RESUME 5-15-2015
Lecture 1 introduction to construction procurement process.
Tim Brewington revised format 2
Smu mba sem 3 pm spring 2015 assignments
Procurement Strategies: A Seminar
Professional practice-1-presentation
Ad

Viewers also liked (17)

PPT
FED GOV CON - Strategies For Partnering & Sub-Contracting
PPTX
Strategies for Reducing Risk on Design-Build Public Transit Projects
PDF
PRIMARY STRUCTURAL STEELWORKS MEMBERS - WATER TREATMENT PLANT
PPT
Envt 110 water treatment plant operator intro
PPT
Writing Effective Technical Specifications
PPTX
Water Treatment Plant
PDF
Integrated Project Delivery White Paper
PPTX
Automatic water treatment process
PDF
BLOCK (C.M.U.) EMBEDMENT PLATE PLACEMENT - WATER TREATMENT PLANT
PPT
Consensus Docs: Introduction to Integrated Project Delivery in Construction
PPS
Expansion of-water-treatment-plant
PPTX
Strategies in building procurement (summarized)
PDF
EIA - SEWAGE WATER TREATMENT PLANT FFC MIRPUR MATHELO
PPTX
Water Treatment Plant Presentation Final
PPT
Kelani River Water Treatment Plant in Colombo
PPTX
What is Procurement
PPT
Water Treatment Processes
FED GOV CON - Strategies For Partnering & Sub-Contracting
Strategies for Reducing Risk on Design-Build Public Transit Projects
PRIMARY STRUCTURAL STEELWORKS MEMBERS - WATER TREATMENT PLANT
Envt 110 water treatment plant operator intro
Writing Effective Technical Specifications
Water Treatment Plant
Integrated Project Delivery White Paper
Automatic water treatment process
BLOCK (C.M.U.) EMBEDMENT PLATE PLACEMENT - WATER TREATMENT PLANT
Consensus Docs: Introduction to Integrated Project Delivery in Construction
Expansion of-water-treatment-plant
Strategies in building procurement (summarized)
EIA - SEWAGE WATER TREATMENT PLANT FFC MIRPUR MATHELO
Water Treatment Plant Presentation Final
Kelani River Water Treatment Plant in Colombo
What is Procurement
Water Treatment Processes
Ad

Similar to Design Build Requirements In Washington State By Michael E Purdy (20)

PDF
CONSULTING SERVICES PROCUREMENT AND SELECTION AUGUST 2013 PRESENTATION
PPT
Construction contracts docuements_08092008
PPT
VoIP Project Request For Proposal Presentation
PDF
RFP Evaluation Training
PDF
Suggested Best Practices for Design-Build in Transportation Construction
PDF
Proforma Contract Bid Requirements
DOC
ENG 211 Week Three Assignment-Robyn Wolfe
PDF
Social Media Consulting Services RFP
PDF
SIA_Scope_of_Service_Matrix-20180814-for_website.pdf
PPT
Projectmanagement of any project chapter2.ppt
PDF
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
PDF
PMP Exam Q & A
PDF
Free PMP Exam Sample Question of the Week
PPTX
Proj management of site work and locations .pptx
PDF
Free PMP Exam Sample Question of the Week
DOCX
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
PPTX
How to Obtain the Best Consulting Support for your Radio System Upgrade or Re...
DOCX
Sample Project Charter in Project Management
PPTX
Uap Document
PPTX
CONSULTING SERVICES PROCUREMENT AND SELECTION AUGUST 2013 PRESENTATION
Construction contracts docuements_08092008
VoIP Project Request For Proposal Presentation
RFP Evaluation Training
Suggested Best Practices for Design-Build in Transportation Construction
Proforma Contract Bid Requirements
ENG 211 Week Three Assignment-Robyn Wolfe
Social Media Consulting Services RFP
SIA_Scope_of_Service_Matrix-20180814-for_website.pdf
Projectmanagement of any project chapter2.ppt
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
PMP Exam Q & A
Free PMP Exam Sample Question of the Week
Proj management of site work and locations .pptx
Free PMP Exam Sample Question of the Week
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
How to Obtain the Best Consulting Support for your Radio System Upgrade or Re...
Sample Project Charter in Project Management
Uap Document

More from Mike Purdy (8)

PDF
Presidential History News
PPT
Washington State Legislative Updates
PPT
ARRA Implementation
PDF
2009 Construction Industry Strategy Survey By Fmi
PDF
Integrated Project Delivery
PPTX
2009 Legislation Affecting Washington State Public Works Contracting
PPT
Retainage Law Changes In Washington State
PDF
Best Value Contracting for Public Works
Presidential History News
Washington State Legislative Updates
ARRA Implementation
2009 Construction Industry Strategy Survey By Fmi
Integrated Project Delivery
2009 Legislation Affecting Washington State Public Works Contracting
Retainage Law Changes In Washington State
Best Value Contracting for Public Works

Recently uploaded (20)

PDF
Module 3 - Functions of the Supervisor - Part 1 - Student Resource (1).pdf
PDF
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
PPTX
Slide gioi thieu VietinBank Quy 2 - 2025
PDF
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
PDF
Deliverable file - Regulatory guideline analysis.pdf
PDF
How to Get Funding for Your Trucking Business
PPTX
Principles of Marketing, Industrial, Consumers,
PPTX
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
PDF
Technical Architecture - Chainsys dataZap
PPTX
Slide gioi thieu VietinBank Quy 2 - 2025
PDF
How to Get Business Funding for Small Business Fast
PDF
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
PDF
Blood Collected straight from the donor into a blood bag and mixed with an an...
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PDF
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
PPTX
2025 Product Deck V1.0.pptxCATALOGTCLCIA
PDF
Booking.com The Global AI Sentiment Report 2025
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PDF
Building a Smart Pet Ecosystem: A Full Introduction to Zhejiang Beijing Techn...
Module 3 - Functions of the Supervisor - Part 1 - Student Resource (1).pdf
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
Slide gioi thieu VietinBank Quy 2 - 2025
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
Deliverable file - Regulatory guideline analysis.pdf
How to Get Funding for Your Trucking Business
Principles of Marketing, Industrial, Consumers,
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
Technical Architecture - Chainsys dataZap
Slide gioi thieu VietinBank Quy 2 - 2025
How to Get Business Funding for Small Business Fast
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
Blood Collected straight from the donor into a blood bag and mixed with an an...
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
2025 Product Deck V1.0.pptxCATALOGTCLCIA
Booking.com The Global AI Sentiment Report 2025
Lecture 3344;;,,(,(((((((((((((((((((((((
Building a Smart Pet Ecosystem: A Full Introduction to Zhejiang Beijing Techn...

Design Build Requirements In Washington State By Michael E Purdy

  • 1. Design-Build Contract Award Processes in Washington State Mike Purdy Michael E. Purdy Associates (206) 295-1464 [email_address] www.mpurdy.com
  • 2. Michael E. Purdy Associates - About Us Public Contracting Advice for Public Agencies & Businesses Since 2005 Strategies Developing and implementing effective strategies Solutions Creatively solving challenging contracting problems Training Providing clear, comprehensive, and focused training
  • 3. Michael E. Purdy Associates - Subscribe by e-mail to the Blog - http://PublicContracting.blogspot.com
  • 4. Outline Issue Request for Qualifications (RFQ) Evaluate Submittals to RFQ Issue RFP to finalists Evaluate Responses to RFP The material in this presentation is an outline of the requirements of Chapter 39.10 RCW.
  • 5. Advertisement Publish notice of RFQ in legal newspaper.
  • 6. Content of RFQ Describe project: General description of project with sufficient information so proposers can submit qualifications. Why use design-build: Reasons for using design-build. Qualifications needed: Description of qualifications to be required of proposers. Contract to be used: The form of the contract to be awarded.
  • 7. Content of RFQ Honorarium: The amount to be paid to finalists submitting responsive proposals and who are not awarded a design-build contract. Sufficient amount to generate meaningful competition among potential proposers. Public body to consider the level of effort required to meet the selection criteria. Schedule: The schedule for the procurement process and the project.
  • 8. Content of RFQ Other: Other information relevant to the project. Evaluation and Selection Process: Description of selection process to be used in evaluating qualifications and finalists’ proposals, including evaluation factors and weighting of factors.
  • 9. RFQ Evaluation Factors - Must be in RFQ Technical qualifications, such as specialized experience and technical competence Capability to perform Past performance of the proposers’ team, including the A/E and construction members Other appropriate factors Cost or price-related factors may not be used in the RFQ phase.
  • 10. RFP Evaluation Factors - Must be in RFQ All of the evaluation factors from the RFQ Technical approach design concept Alternative evaluation factor: If public body determines that all finalists will be capable of producing a design that adequately meets project requirements, the public body may award the contract to the firm that submits the responsive proposal with the lowest price. Proposal price Ability of professional personnel Past performance on similar projects Ability to meet time and budget requirements Ability to provide a performance and payment bond Recent, current, and projected workloads of firm Location of firm
  • 11. Evaluate RFQ Submittals Committee: Establish evaluation committee Evaluate based on criteria: Evaluate responses to the RFQ based on factors, weighting, and process in RFQ Maximum number of finalists: Select no more than 5 finalists to submit proposals in response to an RFP
  • 12. Issue RFP to Finalists - Content of RFP Describe project: Description of the project including programmatic, performance, and technical requirements and specifications Describe functional issues: Functional and operational elements Square Footage: Minimum and maximum net and gross areas of any building Drawings: Preliminary engineering and architectural drawings (at discretion of public body) Budget: Target budget for design-build portion of the project
  • 13. Evaluate Responses to RFP Committee: Establish evaluation committee Evaluation procedure: Select evaluation procedure from two options on the following slides. Identify Evaluation Procedure in RFQ
  • 14. Option A for Evaluating Proposals Evaluation: Evaluate proposals based on factors, weighting, and process identified in the RFQ Best and Final Proposals: May request best and final proposals from finalists Negotiation: Negotiate with firm with highest scored proposal If unable to successfully negotiate, may suspend or terminate negotiations and negotiate with next highest scored firm.
  • 15. Option B for Evaluating Proposals Award based on lowest price: If public body determines that all finalists will be capable of producing a design that adequately meets project requirements, the public body may award the contract to the firm that submits the responsive proposal with the lowest price.
  • 16. Problems with Option B for Evaluating Proposals Owner doesn’t know at time of RFQ if all finalists can produce a sufficient design. Technical approach design concept appears to be the only thing that owner wouldn’t ask finalists to submit. Does not appear to enable owner to take into account non-design factors, weighting, and process identified in the RFQ relative to the RFP. Perhaps the RFQ should outline the two options and state that the decision will be made in the RFP as to whether all the finalists are capable of producing a good design. This is really the only reasonable way to approach it, and is somewhat supported by RCW 39.10.330 (1)(d)(ii).
  • 17. Michael E. Purdy Associates Mike Purdy Principal (206) 295-1464 [email_address] www.mpurdy.com Mike Purdy’s Public Contracting Blog: http://PublicContracting.blogspot.com The opinions and interpretations expressed in this presentation do not represent legal advice and the reader is encouraged to consult with an attorney to obtain legal advice.
  • 18. Michael E. Purdy Associates: Mike Purdy has almost 30 years of experience as a manager in public contracting and procurement. He is the principal of Michael E. Purdy Associates ( www.mpurdy.com ), a consultant firm established in 2005 to help public agencies and businesses develop and implement effective contracting strategies, solve contracting problems, and learn more about contracting and procurement through tailored training. He maintains the popular Public Contracting Blog at http://PublicContracting.blogspot.com . Experience: Mike is also the Contracts Manager for the University of Washington’s Capital Projects Office and is responsible for managing design and construction contracts for more than $1 billion worth of projects at the University. Before joining the UW in 2005, he spent five years at the Seattle Housing Authority where he served as Contracting and Procurement Manager, overseeing all of the contracting and purchasing (construction, design consultants, other consultants, goods, supplies, and services) for the largest residential landlord in the state. Prior to that he worked for the City of Seattle for more than 21 years, where he administered the City’s construction and consultant contracts as the City’s Contracting Manager. Education: He has a bachelor’s degree in business and public administration and an MBA, both from the University of Puget Sound, and a master of divinity degree from Fuller Theological Seminary.

Editor's Notes

  • #2: Michael E. Purdy Michael E. Purdy May 8, 2008 Michael E. Purdy
  • #3: June 2007 Michael E. Purdy
  • #4: June 2007 Michael E. Purdy
  • #5: May 8, 2008 Michael E. Purdy
  • #6: May 8, 2008 Michael E. Purdy
  • #7: May 8, 2008 Michael E. Purdy
  • #8: May 8, 2008 Michael E. Purdy
  • #9: May 8, 2008 Michael E. Purdy
  • #10: May 8, 2008 Michael E. Purdy
  • #11: May 8, 2008 Michael E. Purdy
  • #12: May 8, 2008 Michael E. Purdy
  • #13: May 8, 2008 Michael E. Purdy
  • #14: May 8, 2008 Michael E. Purdy
  • #15: May 8, 2008 Michael E. Purdy
  • #16: May 8, 2008 Michael E. Purdy
  • #17: May 8, 2008 Michael E. Purdy
  • #18: June 2007 Michael E. Purdy
  • #19: June 2007 Michael E. Purdy