PRINCE2 Agile® Sample Papers
The Official PRINCE2 Agile Accreditor Sample Examination Papers
Terms of use
Please note that by downloading and/or using this document, you agree to comply with the terms of
use outlined below:
1. All sample papers (in electronic or paper format) are for personal use only.
2. The sample papers are intended for the following use only:
• As a study aid for candidates who wish to sit a PRINCE2 Agile examination, or
• For reference purposes.
3. By downloading a complimentary digital copy of any of the PRINCE2 Agile sample papers, you
agree not to:
• Print or reproduce it (unless it is for your own personal use);
• Forward or share it to/with any third party;
• Sell the document.
4. If you wish to use the whole, or part, of this sample paper for any purpose other than for your own
study or reference, please contact the AXELOS Accreditation Team (accreditation@axelos.com).
©AXELOS Limited 2018.
AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited.
Reproduction of this material requires the permission of AXELOS Limited.
All rights reserved.
Page 1 of 7
EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0
The PRINCE2 Agile®
Practitioner Examination
Sample Papers 1 & 2
Scenario Booklet
Multiple Choice
Examination Duration: 2 hours and 30 minutes
Instructions
1. Read the ‘Project Scenario’ carefully. You will need this information to answer
the questions in the Question Booklet.
2. For some questions you will also need the ‘Additional Information’. This is
indicated before the question in the Question Booklet.
3. The ‘Project Scenario’ and ‘Additional Information’ are not based on actual
organizations. Any similarities to known organizations are coincidental.
The PRINCE2 Agile®
Practitioner Examination
©AXELOS Limited 2018.
AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited.
Reproduction of this material requires the permission of AXELOS Limited.
All rights reserved.
Page 2 of 7
EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0
Project Scenario – Chesterton’s Cheese
(Note: The companies and people within the scenario are fictional)
Introduction
The Chesterton family started out as farmers, and four years ago they successfully moved in to the making
and selling of a wide range of cheeses. They now employ 80 people.
Chesterton’s sell most of their cheese to national supermarkets (referred to as ‘trade customers’).
However, two years ago they decided to sell cheese directly to the public by telephone or over the counter
at the farm shop. They did this in order to open up a new market in case their trade customers became
less profitable.
One of their cheeses, the Chesterton Blue, has been nominated for the International Cheese of the Year
Award. The winner of this award will be announced at the International Cheese Festival being held in
Amsterdam in three months’ time. Chesterton’s are expecting to see a significant increase in demand
resulting from the publicity.
In order to cope with the extra demand, Chesterton’s have decided to undertake a project which they have
called ‘The Golden Clog Project’.
Scope
The initial scope of the project includes:
• Rebranding of Chesterton’s Cheese;
• Creating a marketing campaign to highlight how successful Chesterton’s have been and to
publicize their new branding;
• Moving to new premises where the manufacturing of the cheese and the support office will be
in one place;
• Creating a new website.
The project has been set up with four work streams to deliver this work:
1. Rebranding;
2. Marketing campaign;
3. Website;
4. Move Premises.
Project Background
Most of the staff at Chesterton’s have been trained in PRINCE2 Agile. Last year a project office was
created to support best practice in the way Chesterton’s worked.
Due to the importance of this project, the Directors have decided to release the Board Room for use
throughout the project’s duration.
The PRINCE2 Agile®
Practitioner Examination
©AXELOS Limited 2018.
AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited.
Reproduction of this material requires the permission of AXELOS Limited.
All rights reserved.
Page 3 of 7
EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how
work streams are broken down into work packages and/or timeboxes.
The PRINCE2 Agile®
Practitioner Examination
©AXELOS Limited 2018.
AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited.
Reproduction of this material requires the permission of AXELOS Limited.
All rights reserved.
Page 4 of 7
EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0
Rebranding – Additional information for questions 7 to 18
Chesterton’s have used a company called Brand-u-Like for many years. They have a lot of respect for
Brand-u-Like as they are professional, easy to work with and produce high quality work.
Brand-u-Like are good at what they do. However, they require a very detailed ‘brief’ of the campaign and will
not commit to the work until it is documented and authorized. As they invest a lot of time in the creation of
the brief, any change will incur additional costs. They have recently invested in agile training in order to
become more agile and responsive in the way they work with customers.
There are three work packages within this work stream:
1. Corporate image:
• Scoping of objectives and key messages;
• Redesigning the corporate brand/image and all corporate brand standards to align to the new logo,
once it has been selected.
2. Logo:
• Redesigning the Chesterton’s corporate logo to prepare Chesterton’s for expansion into a wider
marketplace with more diverse customers.
3. Collateral:
• Corporate signage designs;
• Website look and feel;
• Letterheads;
• Fonts and tone of voice;
• Corporate clothing designs.
The PRINCE2 Agile®
Practitioner Examination
©AXELOS Limited 2018.
AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited.
Reproduction of this material requires the permission of AXELOS Limited.
All rights reserved.
Page 5 of 7
EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0
Marketing Campaign – Additional information for questions 19 to 26
Chesterton’s have only recently invested in marketing as their reputation until now has been spread by ‘word
of mouth’. The Marketing Team has been together for over a year now and the members of the team enjoy
working with each other. They were very successful with a past campaign called ‘Chesterton’s Cheese? Yes
please!’
The work is being split across a number of timeboxes and the campaign will be delivered across a variety of
channels such as:
• Social media;
• Newspaper and trade magazines;
• Radio;
• Television.
They are also thinking of creating a series of videos about cheese and putting them on a video-sharing
website. One idea is to make an amusing video that they hope will ‘go viral’.
The Marketing Team has been trained in PRINCE2 Agile and has recently been using it on some of their
current work. They are keen to use it on this project.
The PRINCE2 Agile®
Practitioner Examination
©AXELOS Limited 2018.
AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited.
Reproduction of this material requires the permission of AXELOS Limited.
All rights reserved.
Page 6 of 7
EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0
Website – Additional information for questions 27 to 38
The current website is very old and only has pictures of the farm, basic details about their cheeses and
contact details. It will need to be completely replaced.
There are four work packages within this work stream being delivered across four timeboxes:
1. Ordering:
• Customer account/login;
• Subscribe to a newsletter;
• Change customer details;
• Incorporate new branding;
• Cheese search and filter function;
• Cheese catalogue download.
2. Payment:
• Secure payment;
• Allow payment by credit card/debit card;
• Allow payment by PayPal.
3. Stock control:
• Update stock levels;
• Notification of low stock;
• Expiry date alerts.
4. The Story of Cheese:
• Incorporating new branding;
• History of cheese;
• History of Chesterton’s.
Two teams are involved in delivering the website. The Story of Cheese work package is being delivered by
Chesterton’s own Information Technology (IT) department (the IT Team). They are reasonably good at agile
ways of working but have not gained much real life experience as they have been limited, to date, by
Chesterton’s basic website.
The remaining work packages are being delivered by an IT website development company that specializes
in online sales called Web&Go. They are very experienced with agile ways of working and, in particular, they
use Kanban for everything they do. Their office is across the narrow access road near Chesterton’s new
premises.
The PRINCE2 Agile®
Practitioner Examination
©AXELOS Limited 2018.
AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited.
Reproduction of this material requires the permission of AXELOS Limited.
All rights reserved.
Page 7 of 7
EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0
Move Premises – Additional information for questions 39 to 50
Chesterton’s is currently located across several sites and they want to move to one site as quickly as
possible, due to the expected increase in demand. The new premises are very large, and therefore
Chesterton’s believe that all of the cheese making can be brought together onto one site.
There is a concern about the new premises because the access road is quite narrow and it also has limited
space for parking, although alternative parking arrangements are available. The landlord who owns the
building lives abroad but has agreed that if Chesterton’s do not like the new premises they can move out,
without penalty, as long as they do so within three months of their arrival.
Chesterton’s make several types of cheese and their aim is to have all four production lines fully operational
as soon as possible.
There will be a number of work packages in this work stream:
1. Production line:
• Move four production lines to the new premises (shown as P1-P4 on the timeline).
2. Refrigeration Room:
• Cold storage facilities for both raw produce and manufactured cheese.
3. Administration offices:
• Prepare office space ready for all administration staff including those working in IT, Facilities,
Operations, Sales, Marketing and Finance.
The premises team are not quite sure how the agile ways of working apply to their work in the project but are
willing to be guided.

More Related Content

PDF
En p2 a_prac_2015_samplepaper1_rationale_v6.0
PDF
En p2 a_prac_2015_samplepaper1_questionbk_v6.0
PDF
Agile sdlc
PDF
La alternativa agil v5.7
PDF
Delay analysis ... wise after the event.
PDF
Agile Release & Iteration Planning
PDF
#T3SCRUM: 12 principles of agile
En p2 a_prac_2015_samplepaper1_rationale_v6.0
En p2 a_prac_2015_samplepaper1_questionbk_v6.0
Agile sdlc
La alternativa agil v5.7
Delay analysis ... wise after the event.
Agile Release & Iteration Planning
#T3SCRUM: 12 principles of agile

What's hot (20)

DOCX
Project charterexample (1) (1)
PDF
Hybrides Projektmanagement – Wie Sie agile und klassische Methoden verbinden
PPTX
Effective project management: Traditional, Agile, Extreme
PPT
Primer on Agile Project Management and SCRUM
PPT
Critical Chain Basics
PDF
12 principles for Agile Development
PPTX
Scrum - Requirements and User Stories
PPTX
Agile DC 2013 - Comparing Scaled Agile Framework (SAFe) with Disciplined Agil...
PDF
Desarrollo de software para Operadores de Comercio Exterior - Iniciación
PDF
Project charter and plan document for millennium upgrade
ODP
Agile Project management
PPTX
Construction Delay Analysis, Simplified
PPTX
Agile - Scrum Presentation
PPTX
Project control. Management
PPTX
Agile Requirements Gathering Techniques
PDF
PRINCE2 Agile™ Guidance Preview (published by Axelos)
PDF
Leading agile teams - Advanced Scrum Master
PPTX
PMP Exam Prep Module 1.pptx
PDF
Digital construction for DfMA
DOCX
Project Management Tools and Techniques
Project charterexample (1) (1)
Hybrides Projektmanagement – Wie Sie agile und klassische Methoden verbinden
Effective project management: Traditional, Agile, Extreme
Primer on Agile Project Management and SCRUM
Critical Chain Basics
12 principles for Agile Development
Scrum - Requirements and User Stories
Agile DC 2013 - Comparing Scaled Agile Framework (SAFe) with Disciplined Agil...
Desarrollo de software para Operadores de Comercio Exterior - Iniciación
Project charter and plan document for millennium upgrade
Agile Project management
Construction Delay Analysis, Simplified
Agile - Scrum Presentation
Project control. Management
Agile Requirements Gathering Techniques
PRINCE2 Agile™ Guidance Preview (published by Axelos)
Leading agile teams - Advanced Scrum Master
PMP Exam Prep Module 1.pptx
Digital construction for DfMA
Project Management Tools and Techniques
Ad

Similar to En p2 a_prac_2015_samplepaper1&2_scenariobk_v6.0 (20)

PDF
Prince2 agile samplepaper_1_v4.0
PPSX
20201111 Agile DevOps East 2020 Conf Now You See It: Observing Flow using Kan...
PDF
DigitalFolks Portfolio (March 2017)
PPTX
SplDevOps: Making Splunk Development a Breeze With a Deep Dive on DevOps' Con...
PDF
Development of a SharePoint Portal
PPSX
20191114 Agile Day NYC Conf Now You See It! Observing Flow Using Kanban Boards
PDF
I Bytes Manufacturing Industry
PDF
SFA2018 Project to Product - Carmen DeArdo
PPTX
Migrating thinking not just applications to the cloud
PDF
Oracle Cloud modernized Finance Process at CSL
 
PDF
final project execution vajv.pdf
PDF
Liferay Portal Development_Sigma Infosolutions
PDF
Webex Teams Customer Success Playbook Excerpts
PPTX
Blockchain in Retail :Omnichannel retailers can now compete and beat Amazon!
PDF
Iot & ar compressed
DOC
Satish kumar
PDF
Asug sap oct 2018
DOC
HemantSoni-Resume
PDF
Untangling the Cloud
Prince2 agile samplepaper_1_v4.0
20201111 Agile DevOps East 2020 Conf Now You See It: Observing Flow using Kan...
DigitalFolks Portfolio (March 2017)
SplDevOps: Making Splunk Development a Breeze With a Deep Dive on DevOps' Con...
Development of a SharePoint Portal
20191114 Agile Day NYC Conf Now You See It! Observing Flow Using Kanban Boards
I Bytes Manufacturing Industry
SFA2018 Project to Product - Carmen DeArdo
Migrating thinking not just applications to the cloud
Oracle Cloud modernized Finance Process at CSL
 
final project execution vajv.pdf
Liferay Portal Development_Sigma Infosolutions
Webex Teams Customer Success Playbook Excerpts
Blockchain in Retail :Omnichannel retailers can now compete and beat Amazon!
Iot & ar compressed
Satish kumar
Asug sap oct 2018
HemantSoni-Resume
Untangling the Cloud
Ad

More from Matt Trigg (9)

PDF
MoV syllabus
PDF
MoV foundation sample paper
PDF
Mov foundation sample paper rationales
PDF
MoV Foundation sample paper answer key
PDF
PRINCE2 Agile Practitioner exam spec_v5.0
PDF
Course factsheet - AXELOS RESILIA Practitioner
PDF
Course Factsheet - AXELOS RESILIA Foundation
PPT
PRINCE2 - Presentation
DOTX
Prince2 - Business Case
MoV syllabus
MoV foundation sample paper
Mov foundation sample paper rationales
MoV Foundation sample paper answer key
PRINCE2 Agile Practitioner exam spec_v5.0
Course factsheet - AXELOS RESILIA Practitioner
Course Factsheet - AXELOS RESILIA Foundation
PRINCE2 - Presentation
Prince2 - Business Case

Recently uploaded (20)

PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PDF
102 student loan defaulters named and shamed – Is someone you know on the list?
PPTX
Cell Types and Its function , kingdom of life
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PDF
Complications of Minimal Access Surgery at WLH
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
TR - Agricultural Crops Production NC III.pdf
PDF
Classroom Observation Tools for Teachers
PPTX
PPH.pptx obstetrics and gynecology in nursing
PPTX
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
PDF
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PPTX
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PDF
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PPTX
Introduction to Child Health Nursing – Unit I | Child Health Nursing I | B.Sc...
Microbial disease of the cardiovascular and lymphatic systems
STATICS OF THE RIGID BODIES Hibbelers.pdf
102 student loan defaulters named and shamed – Is someone you know on the list?
Cell Types and Its function , kingdom of life
Pharmacology of Heart Failure /Pharmacotherapy of CHF
Complications of Minimal Access Surgery at WLH
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
TR - Agricultural Crops Production NC III.pdf
Classroom Observation Tools for Teachers
PPH.pptx obstetrics and gynecology in nursing
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
Microbial diseases, their pathogenesis and prophylaxis
Renaissance Architecture: A Journey from Faith to Humanism
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
2.FourierTransform-ShortQuestionswithAnswers.pdf
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
Abdominal Access Techniques with Prof. Dr. R K Mishra
Introduction to Child Health Nursing – Unit I | Child Health Nursing I | B.Sc...

En p2 a_prac_2015_samplepaper1&2_scenariobk_v6.0

  • 1. PRINCE2 Agile® Sample Papers The Official PRINCE2 Agile Accreditor Sample Examination Papers Terms of use Please note that by downloading and/or using this document, you agree to comply with the terms of use outlined below: 1. All sample papers (in electronic or paper format) are for personal use only. 2. The sample papers are intended for the following use only: • As a study aid for candidates who wish to sit a PRINCE2 Agile examination, or • For reference purposes. 3. By downloading a complimentary digital copy of any of the PRINCE2 Agile sample papers, you agree not to: • Print or reproduce it (unless it is for your own personal use); • Forward or share it to/with any third party; • Sell the document. 4. If you wish to use the whole, or part, of this sample paper for any purpose other than for your own study or reference, please contact the AXELOS Accreditation Team (accreditation@axelos.com).
  • 2. ©AXELOS Limited 2018. AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited. Reproduction of this material requires the permission of AXELOS Limited. All rights reserved. Page 1 of 7 EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0 The PRINCE2 Agile® Practitioner Examination Sample Papers 1 & 2 Scenario Booklet Multiple Choice Examination Duration: 2 hours and 30 minutes Instructions 1. Read the ‘Project Scenario’ carefully. You will need this information to answer the questions in the Question Booklet. 2. For some questions you will also need the ‘Additional Information’. This is indicated before the question in the Question Booklet. 3. The ‘Project Scenario’ and ‘Additional Information’ are not based on actual organizations. Any similarities to known organizations are coincidental.
  • 3. The PRINCE2 Agile® Practitioner Examination ©AXELOS Limited 2018. AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited. Reproduction of this material requires the permission of AXELOS Limited. All rights reserved. Page 2 of 7 EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0 Project Scenario – Chesterton’s Cheese (Note: The companies and people within the scenario are fictional) Introduction The Chesterton family started out as farmers, and four years ago they successfully moved in to the making and selling of a wide range of cheeses. They now employ 80 people. Chesterton’s sell most of their cheese to national supermarkets (referred to as ‘trade customers’). However, two years ago they decided to sell cheese directly to the public by telephone or over the counter at the farm shop. They did this in order to open up a new market in case their trade customers became less profitable. One of their cheeses, the Chesterton Blue, has been nominated for the International Cheese of the Year Award. The winner of this award will be announced at the International Cheese Festival being held in Amsterdam in three months’ time. Chesterton’s are expecting to see a significant increase in demand resulting from the publicity. In order to cope with the extra demand, Chesterton’s have decided to undertake a project which they have called ‘The Golden Clog Project’. Scope The initial scope of the project includes: • Rebranding of Chesterton’s Cheese; • Creating a marketing campaign to highlight how successful Chesterton’s have been and to publicize their new branding; • Moving to new premises where the manufacturing of the cheese and the support office will be in one place; • Creating a new website. The project has been set up with four work streams to deliver this work: 1. Rebranding; 2. Marketing campaign; 3. Website; 4. Move Premises. Project Background Most of the staff at Chesterton’s have been trained in PRINCE2 Agile. Last year a project office was created to support best practice in the way Chesterton’s worked. Due to the importance of this project, the Directors have decided to release the Board Room for use throughout the project’s duration.
  • 4. The PRINCE2 Agile® Practitioner Examination ©AXELOS Limited 2018. AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited. Reproduction of this material requires the permission of AXELOS Limited. All rights reserved. Page 3 of 7 EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0 Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
  • 5. The PRINCE2 Agile® Practitioner Examination ©AXELOS Limited 2018. AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited. Reproduction of this material requires the permission of AXELOS Limited. All rights reserved. Page 4 of 7 EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0 Rebranding – Additional information for questions 7 to 18 Chesterton’s have used a company called Brand-u-Like for many years. They have a lot of respect for Brand-u-Like as they are professional, easy to work with and produce high quality work. Brand-u-Like are good at what they do. However, they require a very detailed ‘brief’ of the campaign and will not commit to the work until it is documented and authorized. As they invest a lot of time in the creation of the brief, any change will incur additional costs. They have recently invested in agile training in order to become more agile and responsive in the way they work with customers. There are three work packages within this work stream: 1. Corporate image: • Scoping of objectives and key messages; • Redesigning the corporate brand/image and all corporate brand standards to align to the new logo, once it has been selected. 2. Logo: • Redesigning the Chesterton’s corporate logo to prepare Chesterton’s for expansion into a wider marketplace with more diverse customers. 3. Collateral: • Corporate signage designs; • Website look and feel; • Letterheads; • Fonts and tone of voice; • Corporate clothing designs.
  • 6. The PRINCE2 Agile® Practitioner Examination ©AXELOS Limited 2018. AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited. Reproduction of this material requires the permission of AXELOS Limited. All rights reserved. Page 5 of 7 EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0 Marketing Campaign – Additional information for questions 19 to 26 Chesterton’s have only recently invested in marketing as their reputation until now has been spread by ‘word of mouth’. The Marketing Team has been together for over a year now and the members of the team enjoy working with each other. They were very successful with a past campaign called ‘Chesterton’s Cheese? Yes please!’ The work is being split across a number of timeboxes and the campaign will be delivered across a variety of channels such as: • Social media; • Newspaper and trade magazines; • Radio; • Television. They are also thinking of creating a series of videos about cheese and putting them on a video-sharing website. One idea is to make an amusing video that they hope will ‘go viral’. The Marketing Team has been trained in PRINCE2 Agile and has recently been using it on some of their current work. They are keen to use it on this project.
  • 7. The PRINCE2 Agile® Practitioner Examination ©AXELOS Limited 2018. AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited. Reproduction of this material requires the permission of AXELOS Limited. All rights reserved. Page 6 of 7 EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0 Website – Additional information for questions 27 to 38 The current website is very old and only has pictures of the farm, basic details about their cheeses and contact details. It will need to be completely replaced. There are four work packages within this work stream being delivered across four timeboxes: 1. Ordering: • Customer account/login; • Subscribe to a newsletter; • Change customer details; • Incorporate new branding; • Cheese search and filter function; • Cheese catalogue download. 2. Payment: • Secure payment; • Allow payment by credit card/debit card; • Allow payment by PayPal. 3. Stock control: • Update stock levels; • Notification of low stock; • Expiry date alerts. 4. The Story of Cheese: • Incorporating new branding; • History of cheese; • History of Chesterton’s. Two teams are involved in delivering the website. The Story of Cheese work package is being delivered by Chesterton’s own Information Technology (IT) department (the IT Team). They are reasonably good at agile ways of working but have not gained much real life experience as they have been limited, to date, by Chesterton’s basic website. The remaining work packages are being delivered by an IT website development company that specializes in online sales called Web&Go. They are very experienced with agile ways of working and, in particular, they use Kanban for everything they do. Their office is across the narrow access road near Chesterton’s new premises.
  • 8. The PRINCE2 Agile® Practitioner Examination ©AXELOS Limited 2018. AXELOS®, PRINCE2® and the swirl logo are registered trade marks of AXELOS Limited. Reproduction of this material requires the permission of AXELOS Limited. All rights reserved. Page 7 of 7 EN_P2A_PRAC_2015_Sample Papers 1&2_ScenarioBk_v6.0 Move Premises – Additional information for questions 39 to 50 Chesterton’s is currently located across several sites and they want to move to one site as quickly as possible, due to the expected increase in demand. The new premises are very large, and therefore Chesterton’s believe that all of the cheese making can be brought together onto one site. There is a concern about the new premises because the access road is quite narrow and it also has limited space for parking, although alternative parking arrangements are available. The landlord who owns the building lives abroad but has agreed that if Chesterton’s do not like the new premises they can move out, without penalty, as long as they do so within three months of their arrival. Chesterton’s make several types of cheese and their aim is to have all four production lines fully operational as soon as possible. There will be a number of work packages in this work stream: 1. Production line: • Move four production lines to the new premises (shown as P1-P4 on the timeline). 2. Refrigeration Room: • Cold storage facilities for both raw produce and manufactured cheese. 3. Administration offices: • Prepare office space ready for all administration staff including those working in IT, Facilities, Operations, Sales, Marketing and Finance. The premises team are not quite sure how the agile ways of working apply to their work in the project but are willing to be guided.