Enhancing Planning and Scheduling Program by Using Benefits
of BIM-Based Applications
Reza Barati1
*, Aref Charehzehi1,
Christopher Nigel Preece3
1. Faculty of Civil Engineering, Universiti Teknologi Malaysia, Jalan Iman Skudai, 81300 Johor Bahru,
Johor, Malaysia
2. Professor of International Construction Business at Razak School of Engineering and Advanced
Technology, Kuala Lumpur, Malaysia
* E-mail of the corresponding author: rasam1376@gmail.com
Abstract
2D drawings are commonly being used to present the work process of 3D objects in the construction industry.
The engineers require having sufficient knowledge to interpret these drawings for use in various areas of the
work especially for providing planning and scheduling programs. In the construction projects, construction
managers face many problems such as over budget projects, schedule errors, omission of some activities like
safety tasks that originate from poor planning methods. Therefore, the study is going to examine alternative tools
for better understanding of real project tasks sequences and procedures. One of the most reliable applications is
introduced by the Building Information Modeling approach (BIM) that develops four-dimension model based on
a combination of three dimension models with time. The benefits of BIM-based on 4D modeling not only
improving the perception of planners and construction teams but also facilitate the procedure of planning and
scheduling like automatically clash detection, introduce parallel activity and etc. .This study discusses the
development and implementation of this innovative approach in construction planning. The research was carried
out based on questionnaire survey within construction companies in Singapore. The data was analyzed using
descriptive statistical analysis and been ranked with Average Index method.
Keywords: Planning, scheduling, BIM-Based Application
1. Introduction
Allen, J. and Koomen, J. (1983) mentioned that the sequence of activities must be identified to demonstrate the
process of the work from the first that the particular of the project purpose will be attained. Sequence of tasks in
construction involves with space, resources, time, procurement, dimension constraints, and other issues in the
project process. In conventional planning and scheduling methods, Gantt chart was not able to portray the links
of relationships between the sequential activities. In recent, planner and project engineers use Critical Path
Method (CPM) scheduling applications, e.g. Primavera or Microsoft Project Software for monitoring, tracking
and controlling the project time and resources (Charles Eastman, 1999). All the above conventional methods
were based on 2D information and all data extract from two-dimensional (2D) drawings in the construction
industry. 2D drawings are commonly used for training of fresh graduate engineers and planners. Interpretation of
2D drawings by planners and schedulers are difficult to understand due to lack of Supplementary data, and
visualization capabilities. More challenges face in the way forward for planners and schedulers with little or no
practical experience to illustrate the complex construction projects (Junshan L. and Roger K. 2012).
Furthermore, some general problems such as fragmented nature, lack of collaboration and integration between
involved parties, the considerable amount of missing data and the lack of capability of applicable visualization
are among of major issues that can be arise by utilizing the conventional approach in complex construction
project to provide a planning and scheduling program. In order to obtain fewer conflicts and more collaboration
between planner’s team and with other participants in construction project and more realization, the BIM-based
method can be used as a new technology.
1.1 Literature review
The BIM approach has been established since 1970 when industry was commencing to utilize ingenious CAD
system as most useful method in different level of manufacturing and production (Eastman, 2008).Various
definition of BIM is introduced to exhibit the utility of this approach in industry. BIM is an approach that can be
able to manipulate parametric objects to produce particular model that are interpreted by the rules embedded in
them (Eastman, 2008). In addition, Smith and Edgar (2008) defined that BIM is a “digital representation of
physical and functional characteristics of a facility”.
The foundation of BIM scheduling linked to time and visual presentation that refer to 4D modeling or 4D CAD.
However, this approach is widely discussed in some research studies and literatures (e.g. McKinney and Fischer
1998, Koo and Fischer 2000, Kamat and Martinez 2002, Kähkönen and Leinonen 2003, Heesom and Mahdjoubi
Civil and Environmental Research www.iiste.org
ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online)
Vol.3, No.5, 2013
42
2004 and Chau et.al. 2005 among others). BIM-based applications provide scheduling animation in 3D model
and present the being built building from start to finish. It helps in communicating the completion dates to
owners, gives subcontractors and trades people a better understanding of the scope and timing of their work, and
helps field personnel verify the project is on track. 4D modeling in BIM is considered as a main connection tool
between 3D modeling in design level and planning scheduling in construction level. 4D modeling assist to
improve realizing of schedule consequence by giving a graphical presentation and preparation of an opportunity
to distinguish unexpected problems and incompatibility conflicts. Therefore, this approach facilitates the
scheduling process and help to distinguish of potential time-space conflicts (Koo and Fischer 2000).
Figure 1 shows the construction project life cycle that need continuous scheduling and update (Brad Hardin,
2011).By proper scheduling, project planners can compare various schedules easily, and they can quickly
recognize whether the project is on track or not (Hergunsel. 2011).
Figure 1: BIM schedule updating in a continuous task (Brad Hardin, 2009)
The BIM-based model components can also contain production rate information (for all the associated tasks) that
will permit a line of balance schedule analysis; this approach allows the fine-tuning of tasks based on their
location in the project and production rates, and helps to eliminate start and stop cycles within tasks (Willem
Kymmell, 2008).
Furthermore, 4D BIM-based which; advance with time plus BIM-based 3D model can be used as a visualization
application for identifying the safety issues that will be required at different times. The temporary safety related
structures such as rails, fences can be modeled in the BIM-based and monitoring and controlling of safety on site
by utilizing 4D model can improve overall safety of the personals related to the work. On the other hand,
integration 4D modeling with safety into the scheduling process and use planning as a tool to decrease the rate of
accident on the site can collaborate monitoring of safety program that is applied on the site and performed the
defect identification of the program on time before the accident and injury. In addition, 4D modeling is
multilateral model that can be helpful for engineers in different parts of the jobsite safety (Hergunsel, 2011).
According to study in [12], for every construction planner, the most important task is preparing the schedule.
The schedule is one of the deriving factors in the success of any project and is a critical component to all team
members. At the onset of a project (and often before that), a member of the construction management team
creates the schedule that is specialized engineer who play a major role in the construction process to identify the
sequences of the work process and investigate the priority of any task in each particular dates. Hence,
schedulers’ effort can lead to implement the work effectively and attain the purpose of the project on time and
within budget. This schedule typically reflects experiences with construction timing, material lead time, weather,
crew, and equipment concerns. Therefore, new engineer or planners needed to be trained with this new
technology and it applications. The new technology of BIM-based can inculcate the interest of planners to
resolve the construction project problems with better project planning and scheduling.
1.2 Problem Statement
Duncan (1996) argued about conventional construction planning techniques in terms of basic theory and
approved the inefficiencies of these methods in the construction industry. Inadequate knowledge of planners,
unavailability of data between different activities and also neglect of the physical correlation between activities
lead to affect conventional planning method and make them inoperative. According Whilst Sriprasert and
Dawood (2002),three main deficiencies of traditional planning methods are as following:
• Insubstantial pattern of planning and negligible or insignificant short term planning
Civil and Environmental Research www.iiste.org
ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online)
Vol.3, No.5, 2013
43
• Lack of a systematic approach to manage executive process
• Insufficient control measurement and utilizing corrective action rather than learning process
Santos, A et al. (1998), identified the barriers that planners face to clarify different stage in construction by using
traditional methods that are following:
• Extension of planning procedure on informal foundation
• Lack of practical implementation of schedule
• Creating of schedule base on the experience and not in the real data that are related to the project goal
• Systematic defect in the short term plan
• Insufficient resource for scheduling
In this circumstance of construction projects, researchers are required to introduce the new technique and
approach to modify the process of planning and scheduling. One of the most practical approaches is BIM that is
going to improve the information flow, manage knowledge and also control the planners’ concept to achieve
most appropriate and reliable planning program (Ballard, 1999).
The importance of a schedule in regard to BIM-based is to inform the team better and track progress from the
beginning to the end of the project. In addition, the refinement of the schedule relies on the accuracy of the
construction manager to review the new design documents each time and judge the projected availability of
additional equipment, material quantities, etc.
In construction projects, it is common for construction managers and clients face many problems such as over
budgets, schedules errors, omission of some activity, and safety tasks that the origin from inappropriate method
of planning and scheduling. This is due to the inadequate t tools for better understanding of real project
sequences and procedures. Therefore, this research paper interested to highlights what are the benefits of BIM-
based approach for planning and scheduling.
2. Research Methodology and Respondents Background
To achieve the aim of this research, the chosen methodology for this study is based on the questionnaire survey.
The survey respondents were chosen directly from the construction companies in Singapore. The construction
companies in Singapore have been implementing BIM-based approach in recently. The survey included
managers, architectures, engineers, planners.
All of these participants were selected through random sampling. The questionnaire was piloted with a group of
3 consultant companies to assess its validity before it was distributed. The 32 questionnaires were distributed
among the construction companies that 72% of total questionnaire were fulfilled. All questions were structured
to enable a logical quantitative analysis of the result. The data were analysed by using Statistical Packages for
Social Sciences (SPSS). The study used two methods in analysing the data gained from the respondent. Step one
presents the data in a descriptive form, where responses on each item were presented and described in percentage
and means index. Whilst for step 2, the evaluation was made by ranked analysis using Average Index method.
All result, with Average Index (AI) scores more than 3.5, were accepted as the beneficial factors. The following
formula was applied in Average Index methods. By referring to Majid and McCaffer (1997), the rating scales
used for the questionnaires in this study are mentioned in table 1.
Table 1. Classification of the Rating Scores
Rating Scale Average Index
Very low or extremely in effective 1.00 ≤ A1 < 1.50
Low or ineffective 1.50 ≤ A1 < 2.50
Medium or moderately in effective 2.50 ≤ A1 < 3.50
High or very effective 3.50 ≤ A1 < 4.50
Very high or extremely effective 4.50 ≤ A1 ≤ 5.00
3. Results and Findings
The results processed by applying Statistical Package for Social Science (SPSS) version 19 of software to
facilitate the understanding of data and information, which gained from the questionnaires.
Civil and Environmental Research www.iiste.org
ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online)
Vol.3, No.5, 2013
44
Figure 2. Years of experience of the respondents
Fig. 2 shows the years of experience of the respondents in the construction industry. Majority of the respondents
have more than 10 years of experience representing 43.47% of the total respondents that present the respondents
have adequate experience in the construction industry.
Figure 3. Area of expertise of the respondents
Fig.3 portrays the distribution of respondents in respect of their area of expertise. 56.52% that presents the
majority of the respondents are Planners, 30.44% are engineers while the lowest group are from Architects who
formed 13.04 % of the respondents.
Figure 4. Level of Benefits and Effectiveness of BIM-based Applications
Figure 4 shows the level of effectiveness on benefits of BIM-based applications that are useful for planners and
schedulers. The result has shown that the clash detection has the highest index of 4.8. This result indicating that
this element was the main benefits gained in using BIM-based approach. Similarly, the results have shown a
significance level of agreement that reducing missing data is another benefit of using BIM-based. Furthermore,
BIM-based provide usefulness in the use of 4D BIM-based that have the ability of integrating schedule
dimension.
Civil and Environmental Research www.iiste.org
ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online)
Vol.3, No.5, 2013
45
Table 2. Correlation between BIM-based Benefits and Planners Realization
No. BIM-based Benefits Factors influence planners realization Fig. No.
1. Improve clash detection • Identifying parallel activities
• Identifying potential conflicts
6,7
2. Reduce missing data • Diminish omission of activities Sample figure
is not supply
3. The use of 4D BIM-based
(integrating schedule dimension)
• Visualising and interpreting
construction sequence
• Facilitates information sharing
6
4. Earlier and more accurate design
visualisation
Formalising design and construction
information:
• Forces users to visualize in their
minds
• Obviates interpretation process
7
5. Improved document management
and integration
• Producing of event documentation
using for any claims like extension
of time
Sample figure
is not supply
6. Reduced safety risks in the design
phase
• Allows detection to hazards
• Definition of safety tasks
8
7. Greater predictability of project time • Allows the generation of
alternative scenarios
• Decision making
Sample figure
is not supply
In this study, Table 2 shows the correlation for planner visualization, in order to accommodate the project
realization.
The following flowchart (Fig.5) exhibits the process of promoting the planning and scheduling method by
integration of 3D model with the main project information such as time, cost, quality and safety that lead to
create BIM model in the construction industry. BIM model simulate the progress of the work and assist the user
to predict most reliable planning and scheduling.
Civil and Environmental Research www.iiste.org
ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online)
Vol.3, No.5, 2013
46
Figure 5. The Progress of BIM Application achievement
Figure 6. Sequence of Activities
Civil and Environmental Research www.iiste.org
ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online)
Vol.3, No.5, 2013
47
Figure 7. Clash Detection
In Fig. 6 and Fig. 7, parallel activities can be identified for clash detection. By using 4D BIM-based,
visualisation and interpreting construction sequence can be made to integrate schedule dimension. Furthermore,
formalising design and construction information also can be interpreted earlier whereby, by BIM-based it forced
user to detail visualise that lead to accurate design.
.
Figure 7. Hennesy Centre Safety and Site Logistics Planning (Collins, 2011)
Fig. 8 shows that BIM- based allow detection to hazard and define the safety task. BIM- based helps in reducing
safety risks at design phase. As presented in the Table 2, the planners are able to identify parallel activities,
construction sequence, claim documentation process, safety tasks, and various construction technologies as
decision making methods. In comparison to 2D model, BIM-based also offers faster and more accuracy
information visualization through it 4D model. On the other hand, the blunder or omission tasks can be
minimized whereby BIM-based have the function to reducing the numbers of missing data. The specialty of
BIM-based helps the junior planners’ to be more capable in developing project scheduling and thus indirectly
support their designation promotion
4. Conclusion
The highlighted factors in this research paper show the benefits of using BIM applications in the construction
industry to create planning and scheduling program. This paper has proposed that by using BIM-based
applications; it can be an effective to enhance planning and scheduling methods. Additionally, it helps to develop
the skill of planners and/or schedulers. The evaluation results indicated that the BIM-based approach helped
planners and schedulers to recognize construction sequence, parallel activities, diminish omission of activities,
hazard detection, producing of event documentation, definition of safety tasks, etc. The proposed BIM-based
approach is expected to help construction planners to overcome the difficulty of reading and interpreting 2D
schedules and Work Breakdown Structures (WBSs); which consist of only activities and relationships between
Civil and Environmental Research www.iiste.org
ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online)
Vol.3, No.5, 2013
48
them. Therefore, The BIM-based approach in planning and scheduling can be replicated effectively in other
industries.
References
Abd.Majid, M.Z. and McCaffer, R., (1997), Assessment of work performance of maintenance contractors in
Saudi Arabia, Journal of Management in Engineering, ASCE, 13, 91.
Allen, J. and Koomen, J. (1983), Planning using a temporal world models, Proc. 8th Int. Joint Conf. On AI, pp.
741-747.
Ballard, G. (1999)., Improving work flow reliability. Proceedings of IGLC-7. Berkeley, USA: IGLC. pp. 275-286.
Brad Hardin, (2011), BIM and construction management (proven tools, methods, and workflows) (Wiley. ISBN:
9781118059449,2011)
Charles Eastman, (1999), Building product model:computer environments supporting design and
construction( ISBN-10: 0849302595 | ISBN-13: 978-0849302596)
Chau, K.W., Anson, M. and De Saram, D.D. (2005) , 4D dynamic construction management and visualization
software: 2. Site trial, Automation in Construction, Vol. 14, Issue 4, pp. 2005,525-536
Collins, Ronan. (2011), “BIM for Safety, Virtual Design and Construction VDC Application." , Intelibuild, Web.
March 2011. <Intelibuild.com>.
Duncan, W. (1996), A guide to the project management body of knowledge (Sylva NC:PMI Publications, 1996).
Eastman, C., Teicholz, P., Sacks, R., Liston K (2008), BIM Handbook A guide to building Information Modeling
for owners, Managers, Designers engineers, and Contractors.( John Wily & Sons, Inc.)
Heesom, D. and Mahdjoubi, L. (2004) ,Trends of 4D CAD ap-plications for construction planning. Construction
Manage-ment and Economics, Volume 22, Number 2, February 2004, pp. 171-182(12).
Hergunsel, (2011), Benefits of building information modeling for construction managers and BIM based
scheduling, Master of Science, worcester polytechnic institute
Junshan L. and Roger K. (2012), A Study of Using BIM as an Innovated Teaching Tool in an Estimating Class –
A Preliminary Report,48th ASC Annual International Conference Proceedings
Kähkönen K. and Leinonen J. (2003), Visual product Chronology as a Solution for Accessing Building Product
Model Data. Proceedings of the CIB W78 conference, Auckland, New Zealand.
Kamat, V.R., and Martinez, J.C. (2002), Comparison of Simulation-driven Construction Operations
Visualization and 4D CAD. Proceedings of the 2002 Winter Simulation Conference E. Yücesan, C.-H. Chen, J. L.
Snowdon, and J. M. Charnes, eds.
Koo, B., Fischer, M. (2000), Feasibility Study of 4D CAD in Commercial Construction. Journal of Construction
Engineering and Management, Vol. 126, No. 4, July/August 2000, pp. 251-260
McKinney, K., and Fischer, M,Generating, (1998), evaluating and visualizing construction with 4D-CAD.
Automation in Construction, 7(1998), 433-447.
Santos, A.D., Powell, J., Sharp, J and Formoso, C.T. (1998). Principle of transparency applied in construction.
Proceedings IGLC-6. Guaruja, Brazil: IGLC.
Smith, D., and Edgar, (2008), A, Building Information Modeling (BIM)
Sriprasert, E. and Dawood, N. (2002) , Next generation of construction planning and control system: the LEWIS
approach. Proceedings of IGLC-10. Gramado, Brazil: IGLC. pp. 1-44.
Willem Kymmell, (2008), Building information modeling (planning and managing construction projects with
4D CAD and simulations) (McGrow Hill, 2008)
Reza Barati received B.Sc. degrees in civil engineering from Islamic Azad University (IAU), Mashhad branch
(Mashhad, Iran), M.Sc. in construction management from Universiti Teknologi Malaysia (UTM), Malaysia in
2012 and currently PhD candidate of civil engineering , Universiti Teknologi Malaysia (UTM), Johor, Malaysia
Aref Charehzehi received B.Sc. degrees in civil engineering from Islamic Azad University (IAU), Zahedan
branch (Zahedan, Iran) in 2008 and M.Sc. in construction management from Universiti Teknologi Malaysia.
Prof. Dr. Christopher Nigel Preece, Professor of International Construction Business at Razak School of
Engineering and Advanced Technology, Kuala Lumpur, Malaysia

More Related Content

PDF
IRJET- Application of 4D CAD BIM Technology in Construction Scheduling
PDF
Application of ict benefits for building project management using ism model
PDF
Construction Cost Prediction by Using Building Information Modeling
PDF
Application of BIM and Construction Process Simulation using 5D BIM for Resid...
PDF
IRJET- Digital Engineering & Project Management for AEC Industry using BIM
PDF
A Statistical Analysis of Building Information Modeling in Project Management
PDF
IRJET- Redevelopment of Structure with the Help of Building Information M...
DOCX
BIM research report
IRJET- Application of 4D CAD BIM Technology in Construction Scheduling
Application of ict benefits for building project management using ism model
Construction Cost Prediction by Using Building Information Modeling
Application of BIM and Construction Process Simulation using 5D BIM for Resid...
IRJET- Digital Engineering & Project Management for AEC Industry using BIM
A Statistical Analysis of Building Information Modeling in Project Management
IRJET- Redevelopment of Structure with the Help of Building Information M...
BIM research report

What's hot (19)

PDF
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
PDF
Extended Summary_Sofia Sideri_Final
PDF
Technical Drawing with Engineering Graphics and Design in Practice_Definition...
PDF
A Review on Challenges Involved in Implementing Building Information Modeling...
PDF
Report on Planning & scheduling of a Minor bridge
PDF
Project management tools and techniques- tutorsindia.com
PDF
Building Information Modeling Implementation in Iran Review
PDF
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
PDF
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
PDF
Activities Oriented Design Environments
PDF
1 s2.0-s1877705817316855-main
PDF
Reducing i.t. project management failures adib chehade
PDF
Ijciet 10 01_075
PDF
Collaborative 3D Modelling and Printing: What you See is not Directly What Yo...
PDF
ArchiInspection Project: Integrated Non Destructive Testing, A Building Infor...
PDF
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
PDF
Pci journal 2005
PDF
IRJET- Impact of Change of Construction Drawing on Project Works
PDF
Implementation of a Simulation Model Using the Systems Dynamics: Case Study f...
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
Extended Summary_Sofia Sideri_Final
Technical Drawing with Engineering Graphics and Design in Practice_Definition...
A Review on Challenges Involved in Implementing Building Information Modeling...
Report on Planning & scheduling of a Minor bridge
Project management tools and techniques- tutorsindia.com
Building Information Modeling Implementation in Iran Review
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
Activities Oriented Design Environments
1 s2.0-s1877705817316855-main
Reducing i.t. project management failures adib chehade
Ijciet 10 01_075
Collaborative 3D Modelling and Printing: What you See is not Directly What Yo...
ArchiInspection Project: Integrated Non Destructive Testing, A Building Infor...
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
Pci journal 2005
IRJET- Impact of Change of Construction Drawing on Project Works
Implementation of a Simulation Model Using the Systems Dynamics: Case Study f...
Ad

Viewers also liked (6)

PDF
PPTX
final bim
PPT
Publishing your research-workshop-2014-October
PDF
Bim White Paper 11 9 09
PDF
BIM Show Live 2015: The challenges and the wins of Information Management on...
PPT
Bim Presentation
final bim
Publishing your research-workshop-2014-October
Bim White Paper 11 9 09
BIM Show Live 2015: The challenges and the wins of Information Management on...
Bim Presentation
Ad

Similar to Enhancing planning and scheduling program by using benefits of bim based applications (20)

PDF
Application of BIM for Scheduling and Costing of Construction Project
PDF
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
PDF
4D_BIM_for_Construction_Planning_and_Environmental.pdf
DOCX
The editors bookshelf
PDF
A Synergistic Approach To Information Systems Project Management
PDF
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
PDF
Application of Building Information Modelling Software’s for Planning and Sch...
DOCX
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docx
DOCX
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docx
PDF
Towards Innovate Methods of Construction Cost Management and Control
PDF
Towards Innovate Methods of Construction Cost Management and Control
PDF
A Case Study On Applying Lean Construction To Concrete
PDF
Application Of Building Information Modeling (BIM) To Civil Engineering Projects
PDF
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
PDF
Efficient Planning Scheduling and Delay Analysis of Residential Project
PDF
Anane_W_et_al_CON_329_The_use_of_BIM.pdf
PDF
IRJET- Building Information Modeling in AEC Industry with its Implementation ...
PDF
F1302033340
PDF
A Review of _Urban Water Networks Management Using GIS
PDF
Bim kpi manzione
Application of BIM for Scheduling and Costing of Construction Project
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
4D_BIM_for_Construction_Planning_and_Environmental.pdf
The editors bookshelf
A Synergistic Approach To Information Systems Project Management
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Application of Building Information Modelling Software’s for Planning and Sch...
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docx
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docx
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
A Case Study On Applying Lean Construction To Concrete
Application Of Building Information Modeling (BIM) To Civil Engineering Projects
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
Efficient Planning Scheduling and Delay Analysis of Residential Project
Anane_W_et_al_CON_329_The_use_of_BIM.pdf
IRJET- Building Information Modeling in AEC Industry with its Implementation ...
F1302033340
A Review of _Urban Water Networks Management Using GIS
Bim kpi manzione

More from Alexander Decker (20)

PDF
Abnormalities of hormones and inflammatory cytokines in women affected with p...
PDF
A validation of the adverse childhood experiences scale in
PDF
A usability evaluation framework for b2 c e commerce websites
PDF
A universal model for managing the marketing executives in nigerian banks
PDF
A unique common fixed point theorems in generalized d
PDF
A trends of salmonella and antibiotic resistance
PDF
A transformational generative approach towards understanding al-istifham
PDF
A time series analysis of the determinants of savings in namibia
PDF
A therapy for physical and mental fitness of school children
PDF
A theory of efficiency for managing the marketing executives in nigerian banks
PDF
A systematic evaluation of link budget for
PDF
A synthetic review of contraceptive supplies in punjab
PDF
A synthesis of taylor’s and fayol’s management approaches for managing market...
PDF
A survey paper on sequence pattern mining with incremental
PDF
A survey on live virtual machine migrations and its techniques
PDF
A survey on data mining and analysis in hadoop and mongo db
PDF
A survey on challenges to the media cloud
PDF
A survey of provenance leveraged
PDF
A survey of private equity investments in kenya
PDF
A study to measures the financial health of
Abnormalities of hormones and inflammatory cytokines in women affected with p...
A validation of the adverse childhood experiences scale in
A usability evaluation framework for b2 c e commerce websites
A universal model for managing the marketing executives in nigerian banks
A unique common fixed point theorems in generalized d
A trends of salmonella and antibiotic resistance
A transformational generative approach towards understanding al-istifham
A time series analysis of the determinants of savings in namibia
A therapy for physical and mental fitness of school children
A theory of efficiency for managing the marketing executives in nigerian banks
A systematic evaluation of link budget for
A synthetic review of contraceptive supplies in punjab
A synthesis of taylor’s and fayol’s management approaches for managing market...
A survey paper on sequence pattern mining with incremental
A survey on live virtual machine migrations and its techniques
A survey on data mining and analysis in hadoop and mongo db
A survey on challenges to the media cloud
A survey of provenance leveraged
A survey of private equity investments in kenya
A study to measures the financial health of

Recently uploaded (20)

PPTX
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
PDF
Approach and Philosophy of On baking technology
PDF
NewMind AI Weekly Chronicles - August'25 Week I
PPTX
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
PDF
Dropbox Q2 2025 Financial Results & Investor Presentation
PDF
Chapter 3 Spatial Domain Image Processing.pdf
PDF
KodekX | Application Modernization Development
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PDF
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PPTX
sap open course for s4hana steps from ECC to s4
PPTX
Understanding_Digital_Forensics_Presentation.pptx
PDF
Encapsulation theory and applications.pdf
PDF
MIND Revenue Release Quarter 2 2025 Press Release
PPT
Teaching material agriculture food technology
PDF
Empathic Computing: Creating Shared Understanding
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
Approach and Philosophy of On baking technology
NewMind AI Weekly Chronicles - August'25 Week I
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
Dropbox Q2 2025 Financial Results & Investor Presentation
Chapter 3 Spatial Domain Image Processing.pdf
KodekX | Application Modernization Development
Mobile App Security Testing_ A Comprehensive Guide.pdf
Diabetes mellitus diagnosis method based random forest with bat algorithm
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
sap open course for s4hana steps from ECC to s4
Understanding_Digital_Forensics_Presentation.pptx
Encapsulation theory and applications.pdf
MIND Revenue Release Quarter 2 2025 Press Release
Teaching material agriculture food technology
Empathic Computing: Creating Shared Understanding
Per capita expenditure prediction using model stacking based on satellite ima...

Enhancing planning and scheduling program by using benefits of bim based applications

  • 1. Civil and Environmental Research www.iiste.org ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online) Vol.3, No.5, 2013 41 Enhancing Planning and Scheduling Program by Using Benefits of BIM-Based Applications Reza Barati1 *, Aref Charehzehi1, Christopher Nigel Preece3 1. Faculty of Civil Engineering, Universiti Teknologi Malaysia, Jalan Iman Skudai, 81300 Johor Bahru, Johor, Malaysia 2. Professor of International Construction Business at Razak School of Engineering and Advanced Technology, Kuala Lumpur, Malaysia * E-mail of the corresponding author: rasam1376@gmail.com Abstract 2D drawings are commonly being used to present the work process of 3D objects in the construction industry. The engineers require having sufficient knowledge to interpret these drawings for use in various areas of the work especially for providing planning and scheduling programs. In the construction projects, construction managers face many problems such as over budget projects, schedule errors, omission of some activities like safety tasks that originate from poor planning methods. Therefore, the study is going to examine alternative tools for better understanding of real project tasks sequences and procedures. One of the most reliable applications is introduced by the Building Information Modeling approach (BIM) that develops four-dimension model based on a combination of three dimension models with time. The benefits of BIM-based on 4D modeling not only improving the perception of planners and construction teams but also facilitate the procedure of planning and scheduling like automatically clash detection, introduce parallel activity and etc. .This study discusses the development and implementation of this innovative approach in construction planning. The research was carried out based on questionnaire survey within construction companies in Singapore. The data was analyzed using descriptive statistical analysis and been ranked with Average Index method. Keywords: Planning, scheduling, BIM-Based Application 1. Introduction Allen, J. and Koomen, J. (1983) mentioned that the sequence of activities must be identified to demonstrate the process of the work from the first that the particular of the project purpose will be attained. Sequence of tasks in construction involves with space, resources, time, procurement, dimension constraints, and other issues in the project process. In conventional planning and scheduling methods, Gantt chart was not able to portray the links of relationships between the sequential activities. In recent, planner and project engineers use Critical Path Method (CPM) scheduling applications, e.g. Primavera or Microsoft Project Software for monitoring, tracking and controlling the project time and resources (Charles Eastman, 1999). All the above conventional methods were based on 2D information and all data extract from two-dimensional (2D) drawings in the construction industry. 2D drawings are commonly used for training of fresh graduate engineers and planners. Interpretation of 2D drawings by planners and schedulers are difficult to understand due to lack of Supplementary data, and visualization capabilities. More challenges face in the way forward for planners and schedulers with little or no practical experience to illustrate the complex construction projects (Junshan L. and Roger K. 2012). Furthermore, some general problems such as fragmented nature, lack of collaboration and integration between involved parties, the considerable amount of missing data and the lack of capability of applicable visualization are among of major issues that can be arise by utilizing the conventional approach in complex construction project to provide a planning and scheduling program. In order to obtain fewer conflicts and more collaboration between planner’s team and with other participants in construction project and more realization, the BIM-based method can be used as a new technology. 1.1 Literature review The BIM approach has been established since 1970 when industry was commencing to utilize ingenious CAD system as most useful method in different level of manufacturing and production (Eastman, 2008).Various definition of BIM is introduced to exhibit the utility of this approach in industry. BIM is an approach that can be able to manipulate parametric objects to produce particular model that are interpreted by the rules embedded in them (Eastman, 2008). In addition, Smith and Edgar (2008) defined that BIM is a “digital representation of physical and functional characteristics of a facility”. The foundation of BIM scheduling linked to time and visual presentation that refer to 4D modeling or 4D CAD. However, this approach is widely discussed in some research studies and literatures (e.g. McKinney and Fischer 1998, Koo and Fischer 2000, Kamat and Martinez 2002, Kähkönen and Leinonen 2003, Heesom and Mahdjoubi
  • 2. Civil and Environmental Research www.iiste.org ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online) Vol.3, No.5, 2013 42 2004 and Chau et.al. 2005 among others). BIM-based applications provide scheduling animation in 3D model and present the being built building from start to finish. It helps in communicating the completion dates to owners, gives subcontractors and trades people a better understanding of the scope and timing of their work, and helps field personnel verify the project is on track. 4D modeling in BIM is considered as a main connection tool between 3D modeling in design level and planning scheduling in construction level. 4D modeling assist to improve realizing of schedule consequence by giving a graphical presentation and preparation of an opportunity to distinguish unexpected problems and incompatibility conflicts. Therefore, this approach facilitates the scheduling process and help to distinguish of potential time-space conflicts (Koo and Fischer 2000). Figure 1 shows the construction project life cycle that need continuous scheduling and update (Brad Hardin, 2011).By proper scheduling, project planners can compare various schedules easily, and they can quickly recognize whether the project is on track or not (Hergunsel. 2011). Figure 1: BIM schedule updating in a continuous task (Brad Hardin, 2009) The BIM-based model components can also contain production rate information (for all the associated tasks) that will permit a line of balance schedule analysis; this approach allows the fine-tuning of tasks based on their location in the project and production rates, and helps to eliminate start and stop cycles within tasks (Willem Kymmell, 2008). Furthermore, 4D BIM-based which; advance with time plus BIM-based 3D model can be used as a visualization application for identifying the safety issues that will be required at different times. The temporary safety related structures such as rails, fences can be modeled in the BIM-based and monitoring and controlling of safety on site by utilizing 4D model can improve overall safety of the personals related to the work. On the other hand, integration 4D modeling with safety into the scheduling process and use planning as a tool to decrease the rate of accident on the site can collaborate monitoring of safety program that is applied on the site and performed the defect identification of the program on time before the accident and injury. In addition, 4D modeling is multilateral model that can be helpful for engineers in different parts of the jobsite safety (Hergunsel, 2011). According to study in [12], for every construction planner, the most important task is preparing the schedule. The schedule is one of the deriving factors in the success of any project and is a critical component to all team members. At the onset of a project (and often before that), a member of the construction management team creates the schedule that is specialized engineer who play a major role in the construction process to identify the sequences of the work process and investigate the priority of any task in each particular dates. Hence, schedulers’ effort can lead to implement the work effectively and attain the purpose of the project on time and within budget. This schedule typically reflects experiences with construction timing, material lead time, weather, crew, and equipment concerns. Therefore, new engineer or planners needed to be trained with this new technology and it applications. The new technology of BIM-based can inculcate the interest of planners to resolve the construction project problems with better project planning and scheduling. 1.2 Problem Statement Duncan (1996) argued about conventional construction planning techniques in terms of basic theory and approved the inefficiencies of these methods in the construction industry. Inadequate knowledge of planners, unavailability of data between different activities and also neglect of the physical correlation between activities lead to affect conventional planning method and make them inoperative. According Whilst Sriprasert and Dawood (2002),three main deficiencies of traditional planning methods are as following: • Insubstantial pattern of planning and negligible or insignificant short term planning
  • 3. Civil and Environmental Research www.iiste.org ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online) Vol.3, No.5, 2013 43 • Lack of a systematic approach to manage executive process • Insufficient control measurement and utilizing corrective action rather than learning process Santos, A et al. (1998), identified the barriers that planners face to clarify different stage in construction by using traditional methods that are following: • Extension of planning procedure on informal foundation • Lack of practical implementation of schedule • Creating of schedule base on the experience and not in the real data that are related to the project goal • Systematic defect in the short term plan • Insufficient resource for scheduling In this circumstance of construction projects, researchers are required to introduce the new technique and approach to modify the process of planning and scheduling. One of the most practical approaches is BIM that is going to improve the information flow, manage knowledge and also control the planners’ concept to achieve most appropriate and reliable planning program (Ballard, 1999). The importance of a schedule in regard to BIM-based is to inform the team better and track progress from the beginning to the end of the project. In addition, the refinement of the schedule relies on the accuracy of the construction manager to review the new design documents each time and judge the projected availability of additional equipment, material quantities, etc. In construction projects, it is common for construction managers and clients face many problems such as over budgets, schedules errors, omission of some activity, and safety tasks that the origin from inappropriate method of planning and scheduling. This is due to the inadequate t tools for better understanding of real project sequences and procedures. Therefore, this research paper interested to highlights what are the benefits of BIM- based approach for planning and scheduling. 2. Research Methodology and Respondents Background To achieve the aim of this research, the chosen methodology for this study is based on the questionnaire survey. The survey respondents were chosen directly from the construction companies in Singapore. The construction companies in Singapore have been implementing BIM-based approach in recently. The survey included managers, architectures, engineers, planners. All of these participants were selected through random sampling. The questionnaire was piloted with a group of 3 consultant companies to assess its validity before it was distributed. The 32 questionnaires were distributed among the construction companies that 72% of total questionnaire were fulfilled. All questions were structured to enable a logical quantitative analysis of the result. The data were analysed by using Statistical Packages for Social Sciences (SPSS). The study used two methods in analysing the data gained from the respondent. Step one presents the data in a descriptive form, where responses on each item were presented and described in percentage and means index. Whilst for step 2, the evaluation was made by ranked analysis using Average Index method. All result, with Average Index (AI) scores more than 3.5, were accepted as the beneficial factors. The following formula was applied in Average Index methods. By referring to Majid and McCaffer (1997), the rating scales used for the questionnaires in this study are mentioned in table 1. Table 1. Classification of the Rating Scores Rating Scale Average Index Very low or extremely in effective 1.00 ≤ A1 < 1.50 Low or ineffective 1.50 ≤ A1 < 2.50 Medium or moderately in effective 2.50 ≤ A1 < 3.50 High or very effective 3.50 ≤ A1 < 4.50 Very high or extremely effective 4.50 ≤ A1 ≤ 5.00 3. Results and Findings The results processed by applying Statistical Package for Social Science (SPSS) version 19 of software to facilitate the understanding of data and information, which gained from the questionnaires.
  • 4. Civil and Environmental Research www.iiste.org ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online) Vol.3, No.5, 2013 44 Figure 2. Years of experience of the respondents Fig. 2 shows the years of experience of the respondents in the construction industry. Majority of the respondents have more than 10 years of experience representing 43.47% of the total respondents that present the respondents have adequate experience in the construction industry. Figure 3. Area of expertise of the respondents Fig.3 portrays the distribution of respondents in respect of their area of expertise. 56.52% that presents the majority of the respondents are Planners, 30.44% are engineers while the lowest group are from Architects who formed 13.04 % of the respondents. Figure 4. Level of Benefits and Effectiveness of BIM-based Applications Figure 4 shows the level of effectiveness on benefits of BIM-based applications that are useful for planners and schedulers. The result has shown that the clash detection has the highest index of 4.8. This result indicating that this element was the main benefits gained in using BIM-based approach. Similarly, the results have shown a significance level of agreement that reducing missing data is another benefit of using BIM-based. Furthermore, BIM-based provide usefulness in the use of 4D BIM-based that have the ability of integrating schedule dimension.
  • 5. Civil and Environmental Research www.iiste.org ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online) Vol.3, No.5, 2013 45 Table 2. Correlation between BIM-based Benefits and Planners Realization No. BIM-based Benefits Factors influence planners realization Fig. No. 1. Improve clash detection • Identifying parallel activities • Identifying potential conflicts 6,7 2. Reduce missing data • Diminish omission of activities Sample figure is not supply 3. The use of 4D BIM-based (integrating schedule dimension) • Visualising and interpreting construction sequence • Facilitates information sharing 6 4. Earlier and more accurate design visualisation Formalising design and construction information: • Forces users to visualize in their minds • Obviates interpretation process 7 5. Improved document management and integration • Producing of event documentation using for any claims like extension of time Sample figure is not supply 6. Reduced safety risks in the design phase • Allows detection to hazards • Definition of safety tasks 8 7. Greater predictability of project time • Allows the generation of alternative scenarios • Decision making Sample figure is not supply In this study, Table 2 shows the correlation for planner visualization, in order to accommodate the project realization. The following flowchart (Fig.5) exhibits the process of promoting the planning and scheduling method by integration of 3D model with the main project information such as time, cost, quality and safety that lead to create BIM model in the construction industry. BIM model simulate the progress of the work and assist the user to predict most reliable planning and scheduling.
  • 6. Civil and Environmental Research www.iiste.org ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online) Vol.3, No.5, 2013 46 Figure 5. The Progress of BIM Application achievement Figure 6. Sequence of Activities
  • 7. Civil and Environmental Research www.iiste.org ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online) Vol.3, No.5, 2013 47 Figure 7. Clash Detection In Fig. 6 and Fig. 7, parallel activities can be identified for clash detection. By using 4D BIM-based, visualisation and interpreting construction sequence can be made to integrate schedule dimension. Furthermore, formalising design and construction information also can be interpreted earlier whereby, by BIM-based it forced user to detail visualise that lead to accurate design. . Figure 7. Hennesy Centre Safety and Site Logistics Planning (Collins, 2011) Fig. 8 shows that BIM- based allow detection to hazard and define the safety task. BIM- based helps in reducing safety risks at design phase. As presented in the Table 2, the planners are able to identify parallel activities, construction sequence, claim documentation process, safety tasks, and various construction technologies as decision making methods. In comparison to 2D model, BIM-based also offers faster and more accuracy information visualization through it 4D model. On the other hand, the blunder or omission tasks can be minimized whereby BIM-based have the function to reducing the numbers of missing data. The specialty of BIM-based helps the junior planners’ to be more capable in developing project scheduling and thus indirectly support their designation promotion 4. Conclusion The highlighted factors in this research paper show the benefits of using BIM applications in the construction industry to create planning and scheduling program. This paper has proposed that by using BIM-based applications; it can be an effective to enhance planning and scheduling methods. Additionally, it helps to develop the skill of planners and/or schedulers. The evaluation results indicated that the BIM-based approach helped planners and schedulers to recognize construction sequence, parallel activities, diminish omission of activities, hazard detection, producing of event documentation, definition of safety tasks, etc. The proposed BIM-based approach is expected to help construction planners to overcome the difficulty of reading and interpreting 2D schedules and Work Breakdown Structures (WBSs); which consist of only activities and relationships between
  • 8. Civil and Environmental Research www.iiste.org ISSN 2224-5790 (Paper) ISSN 2225-0514 (Online) Vol.3, No.5, 2013 48 them. Therefore, The BIM-based approach in planning and scheduling can be replicated effectively in other industries. References Abd.Majid, M.Z. and McCaffer, R., (1997), Assessment of work performance of maintenance contractors in Saudi Arabia, Journal of Management in Engineering, ASCE, 13, 91. Allen, J. and Koomen, J. (1983), Planning using a temporal world models, Proc. 8th Int. Joint Conf. On AI, pp. 741-747. Ballard, G. (1999)., Improving work flow reliability. Proceedings of IGLC-7. Berkeley, USA: IGLC. pp. 275-286. Brad Hardin, (2011), BIM and construction management (proven tools, methods, and workflows) (Wiley. ISBN: 9781118059449,2011) Charles Eastman, (1999), Building product model:computer environments supporting design and construction( ISBN-10: 0849302595 | ISBN-13: 978-0849302596) Chau, K.W., Anson, M. and De Saram, D.D. (2005) , 4D dynamic construction management and visualization software: 2. Site trial, Automation in Construction, Vol. 14, Issue 4, pp. 2005,525-536 Collins, Ronan. (2011), “BIM for Safety, Virtual Design and Construction VDC Application." , Intelibuild, Web. March 2011. <Intelibuild.com>. Duncan, W. (1996), A guide to the project management body of knowledge (Sylva NC:PMI Publications, 1996). Eastman, C., Teicholz, P., Sacks, R., Liston K (2008), BIM Handbook A guide to building Information Modeling for owners, Managers, Designers engineers, and Contractors.( John Wily & Sons, Inc.) Heesom, D. and Mahdjoubi, L. (2004) ,Trends of 4D CAD ap-plications for construction planning. Construction Manage-ment and Economics, Volume 22, Number 2, February 2004, pp. 171-182(12). Hergunsel, (2011), Benefits of building information modeling for construction managers and BIM based scheduling, Master of Science, worcester polytechnic institute Junshan L. and Roger K. (2012), A Study of Using BIM as an Innovated Teaching Tool in an Estimating Class – A Preliminary Report,48th ASC Annual International Conference Proceedings Kähkönen K. and Leinonen J. (2003), Visual product Chronology as a Solution for Accessing Building Product Model Data. Proceedings of the CIB W78 conference, Auckland, New Zealand. Kamat, V.R., and Martinez, J.C. (2002), Comparison of Simulation-driven Construction Operations Visualization and 4D CAD. Proceedings of the 2002 Winter Simulation Conference E. Yücesan, C.-H. Chen, J. L. Snowdon, and J. M. Charnes, eds. Koo, B., Fischer, M. (2000), Feasibility Study of 4D CAD in Commercial Construction. Journal of Construction Engineering and Management, Vol. 126, No. 4, July/August 2000, pp. 251-260 McKinney, K., and Fischer, M,Generating, (1998), evaluating and visualizing construction with 4D-CAD. Automation in Construction, 7(1998), 433-447. Santos, A.D., Powell, J., Sharp, J and Formoso, C.T. (1998). Principle of transparency applied in construction. Proceedings IGLC-6. Guaruja, Brazil: IGLC. Smith, D., and Edgar, (2008), A, Building Information Modeling (BIM) Sriprasert, E. and Dawood, N. (2002) , Next generation of construction planning and control system: the LEWIS approach. Proceedings of IGLC-10. Gramado, Brazil: IGLC. pp. 1-44. Willem Kymmell, (2008), Building information modeling (planning and managing construction projects with 4D CAD and simulations) (McGrow Hill, 2008) Reza Barati received B.Sc. degrees in civil engineering from Islamic Azad University (IAU), Mashhad branch (Mashhad, Iran), M.Sc. in construction management from Universiti Teknologi Malaysia (UTM), Malaysia in 2012 and currently PhD candidate of civil engineering , Universiti Teknologi Malaysia (UTM), Johor, Malaysia Aref Charehzehi received B.Sc. degrees in civil engineering from Islamic Azad University (IAU), Zahedan branch (Zahedan, Iran) in 2008 and M.Sc. in construction management from Universiti Teknologi Malaysia. Prof. Dr. Christopher Nigel Preece, Professor of International Construction Business at Razak School of Engineering and Advanced Technology, Kuala Lumpur, Malaysia