Earned Value Management (EVM)
EVM is used to track the Progress and Status of a Project and Forecast its future performance. EVM integrates the; Scope Schedule Cost of a project and can be used to derive; past performance of the project current performance of the project predict the future performance of the project by use of statistical techniques.
Three basic elements of EVM ; Planned Value ( PV  - BCWS)  Actual Cost (AC - ACWP)  Earned Value (EV - BCWP)  … all captured on an as-of reporting date and derived from a WBS associating costs to tasks.
Planned Value (PV) ; (BCWS) or (PV) = total cost of the work Scheduled /Planned as-of a reporting date. Calculated: PV or BCWS = Hourly Rate * Total Hours Planned or Scheduled NOTE: Hourly Rate is the rate at which effort will be valued.
Actual Cost (AC) ; (AC) or (ACWP) is the total cost taken to complete the work as of a reporting date. Calculated:   AC or ACWP = Hourly Rate * Total Hours Spent
Earned Value (EV) ; (EV) or (BCWP) = total cost of work Completed/Performed as of a reporting date. Calculated: EV or BCWP = Baseline Cost * % Complete Actual
% Completed Planned ; = PV / BAC % Completed Actual ; Percentage of work actually completed by the Reporting Date.  % Completed Actual = AC / EAC
Project Schedule and Cost variance. Schedule Variance (SV);   Earned Value - Planned Value  BCWP – BCWS Cost Variance (CV); Earned Value - Actual Cost  BCWP - ACWP
Keys ; Work Breakdown Structures. Discreet Element “Tasks” verses Level of Effort “activity”. Valuation of Tasks and Concatenation to a whole (process). Measurement.
Earned Value Management (EVM)

More Related Content

PDF
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
PDF
Platinum card for agile ev mr4
PPTX
Project cost & control
PPTX
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PPTX
PMP COST FORMULAE
PDF
Evm.calculations.Summary sheet
PPTX
Earned Value Management
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Platinum card for agile ev mr4
Project cost & control
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PMP COST FORMULAE
Evm.calculations.Summary sheet
Earned Value Management

What's hot (19)

PPTX
Lesson16
PDF
E2E - ERP integrated planning for Pay costs
PPTX
Earned Value Management (EVM) Limitations
PPTX
Session 10 4th edition PMP
PPTX
PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPTX
Ppsi pertemuan-3
PPTX
Nasa+evm+reference+card nov+2015
PDF
PDF
CO Planning Overview
PPTX
Implementation plan 5.2 june
PDF
Earned value management
PPTX
Evaluating Earned Value Management
PDF
RPP-2 U-3,4 Prog Sum-Sep-13
PPTX
Oracle grants accounting 13
PPTX
Types of estimate
DOC
High Level Overview Of Using The Earned Value On A T24 Project
PPT
PPTX
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
PPTX
Williamson Sketch Validation
Lesson16
E2E - ERP integrated planning for Pay costs
Earned Value Management (EVM) Limitations
Session 10 4th edition PMP
PPP05 - Creating Preventive Maintenance Schedules (MCU)
Ppsi pertemuan-3
Nasa+evm+reference+card nov+2015
CO Planning Overview
Implementation plan 5.2 june
Earned value management
Evaluating Earned Value Management
RPP-2 U-3,4 Prog Sum-Sep-13
Oracle grants accounting 13
Types of estimate
High Level Overview Of Using The Earned Value On A T24 Project
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
Williamson Sketch Validation
Ad

Similar to Evm Basics (20)

PDF
Earned Value Management
PDF
Project monitoring and controlling with earned value management
PPT
Earned Value Analysis
PPT
Earned value Project Management (evpm)
PPTX
Projects Control Using Earned Value Techniques - Part One
PPTX
project control using earned value analysis - Part 01
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PDF
Basic Concepts of Earned Value Management.pdf
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
PDF
Earned value management in action - A Webinar by Vivek Prakash, pmwares
PDF
Basics of EVM.pdf
PDF
Webinar: Earned value management pure common sense
PPTX
Earned value management for Beginners
DOCX
Develop a network schedule for your project using either the arrow.docx
DOCX
What Is Earned Value Analysis
PPTX
Earned value analysis
PPT
Module 06 Adv PM Budget Mgmt.ppt
PPT
Module 06 Adv Project Manager Budget Mgmt.ppt
Earned Value Management
Project monitoring and controlling with earned value management
Earned Value Analysis
Earned value Project Management (evpm)
Projects Control Using Earned Value Techniques - Part One
project control using earned value analysis - Part 01
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
Basic Concepts of Earned Value Management.pdf
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Basics of EVM.pdf
Webinar: Earned value management pure common sense
Earned value management for Beginners
Develop a network schedule for your project using either the arrow.docx
What Is Earned Value Analysis
Earned value analysis
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
Ad

Evm Basics

  • 2. EVM is used to track the Progress and Status of a Project and Forecast its future performance. EVM integrates the; Scope Schedule Cost of a project and can be used to derive; past performance of the project current performance of the project predict the future performance of the project by use of statistical techniques.
  • 3. Three basic elements of EVM ; Planned Value ( PV - BCWS) Actual Cost (AC - ACWP) Earned Value (EV - BCWP) … all captured on an as-of reporting date and derived from a WBS associating costs to tasks.
  • 4. Planned Value (PV) ; (BCWS) or (PV) = total cost of the work Scheduled /Planned as-of a reporting date. Calculated: PV or BCWS = Hourly Rate * Total Hours Planned or Scheduled NOTE: Hourly Rate is the rate at which effort will be valued.
  • 5. Actual Cost (AC) ; (AC) or (ACWP) is the total cost taken to complete the work as of a reporting date. Calculated:   AC or ACWP = Hourly Rate * Total Hours Spent
  • 6. Earned Value (EV) ; (EV) or (BCWP) = total cost of work Completed/Performed as of a reporting date. Calculated: EV or BCWP = Baseline Cost * % Complete Actual
  • 7. % Completed Planned ; = PV / BAC % Completed Actual ; Percentage of work actually completed by the Reporting Date. % Completed Actual = AC / EAC
  • 8. Project Schedule and Cost variance. Schedule Variance (SV); Earned Value - Planned Value BCWP – BCWS Cost Variance (CV); Earned Value - Actual Cost BCWP - ACWP
  • 9. Keys ; Work Breakdown Structures. Discreet Element “Tasks” verses Level of Effort “activity”. Valuation of Tasks and Concatenation to a whole (process). Measurement.