Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
 Introduction
 Background
 Problem Statement
 Objectives
 Scope of project
 Methodology
 Pavement Design Approach
 Pavement Response Modeling
 Pavement Alternatives
 AASHTO 1993 Design
 AASHTO 2002 Evaluation
 Economic Evaluation
 Pavement Type Selection
 Pavement Structure
 Conclusion
 Recommendations
Purpose of Access Road:
1. Facilitate the movement of farmers to and from
the backlands
2. Access route to arable farm lands for cultivation
3. Low volume roadway
Geometric Configuration:
Length = 3 miles ( km)
Width = 22 ft ( m)
The Access Road in Vergenoegen
Look at this
road…I ain’t
going deh!
Location (6052’24.9’’N and 58021’51.30’’W)
Main Road
Access Road
Access Road
Condition (Wet Seasons)
Condition (Dry Seasons)
The statement of problem is to design a new
pavement structure for the access road in
Vergenoegen that could fulfill all the traffic and
environmental conditions while at the same
time being an economically viable structure.
 Quantify and characterize the loadings of the various
vehicles that uses the current facility
 Investigate and evaluate the potential of suitable pavement
alternatives for a cost effective alternative to
accommodate the present and future traffic loads on the
road
 Evaluate the potential advantages and disadvantages of
pavement alternatives
 Carry out life cycle cost analysis on the various pavement
alternatives to determine the most promising alternative
 Design proposal of a suitable access road based on the
most promising pavement alternative
Selection is limited to the most feasible
alternatives considered
Use of the AASHTO 1993 & AASHTO 2002
Guides for the Design of Pavement structures
Pavement distress is based on cracking and
rutting predictions as computed from the
pavement responses using the WinJULEA
software
1 Inputs
Materials
Traffic
loadings
Environmen
tal data
2 Design
Alternatives
Layer
thickness
design
3
Evaluation
Technical
Economical
4 Pavement
selection
Most
feasible
alternative
5 Design
Proposal
Site
specific
conditions
AASHTO 1993 Guide for the Design
of Pavement Structures
AASHTO 2002 Guide for the
Mechanistic-Empirical Design of
Pavement Structures
Final year project ppt - The Future of Pavement Design
Alternative 1 Flexible Pavement
Alternative 2 Semi Rigid Pavement
Alternative 3 Cement Treated Pavement
Design Traffic (Overall 18kips ESALs)
Graph Showing the Cumulative 18kips ESALs Over the 20 year Design Life
0
20000
40000
60000
80000
100000
120000
140000
160000
0 5 10 15 20
18kips ESAL
Time(years)
Cumulative 18kips ESAL
136, 584
Design Traffic for 20 Years
W18 = DDxDLxW18
DD = 50% (0.5) DL = 100% (1)
W18 = 136,584.6342 [18kips ESALs]
Therefore,
W18 = 0.5 x 1 x 136, 584.6342 18kips ESALs
W18 = 68, 293 [18kips ESAL]
Pavement Material Properties
Material Function CBR (%) Modulus (psi) Structural Layer
Coefficient
(Correlated from
AASHTO 93 )
Hot Mix Asphalt Surface Course 400,000 @ 68F 0.43
Crusher Run Base Course 60 0.12
Cement
Stabilized
Material
Base Course 830,000 @ 7days 0.22
White Sand Subbase Course 6 0.06
In-Situ Soil Subgrade 2 3000
Design Parameters
Reliability, R = 75%
Standard Deviation, So = 0.45
Initial Serviceability, pi = 4.5
Terminal Serviceability, pt = 2
Required Structural Number
Design Chart for Flexible Pavements used for Estimating the Structural
Number Required
Alternative 1 (Flexible Pavement)
Initial Structural Number 2.3
Layer Thickness Determination
Layer 1 Thickness, D1 (inch) 2
Layer 2 Thickness, D2 (inch) 6
Layer 3 Thickness, D3 (inch) 12
Final Structural Number 2.3
Asphalt Concrete
Ordinary White Sand
2in
6in
12in
Alternative 2 (Semi Rigid Pavement)
Initial Structural Number 2.3
Layer Thickness Determination
Layer 1 Thickness, D1 (inch) 2
Layer 2 Thickness, D2 (inch) 4
Layer 3 Thickness, D3 (inch) 12
Final Structural Number 2.5
Asphalt Concrete
Cement Treated
Base
Ordinary White
Sand
2in
4in
12in
Alternative 3 (Cement Treated Pavement)
Initial Structural Number 2.3
Layer Thickness Determination
Layer 1 Thickness, D1 (inch) 1
Layer 2 Thickness, D2 (inch) 7
Layer 3 Thickness, D3 (inch) 13
Final Structural Number 2.3
Chip Seal
Cement Treated
Base
Ordinary White
Sand
1in
7in
13in
Material Function Resilient Modulus
(psi)
Poisson’s Ratio
Hot Mix Asphalt Surface Course 400,000 0.25
Crusher Run Base Course 25,715 0.15
Cement Stabilized
Material
Base Course 830,000 0.35
White Sand Subbase Course 8,182 0.3
In-Situ Soil Subgrade 3000 0.2
Note:
All pavement layers were assumed to be fully bonded together at the
interfaces.
Traffic Loadings
9000 lbs9,000 lbs
18,000 lbs
Tire Radius = 6inches
Tire Pressure = 75psi
Fully Bonded Conditions
Bottom Up Cracking (HMA)
0
1
2
3
4
5
6
7
8
9
0 5 10 15 20
% of lane area cracked
Time (years)
Bottom Up Cracking Prediction vs Time
Chart Showing the % of Lane Area Cracked Over the Design Life for the
Flexible Pavement as a Result of Bottom Up Cracking
Top Down (Longitudinal) Cracking (HMA)
0
1000
2000
3000
4000
5000
6000
7000
8000
0 5 10 15 20
Feet/mile
Time (Years)
Longitudional Cracking Prediction vs Time
Chart Showing the Length of Longitudinal Cracking of the Flexible
Pavement Over the Design Life as a Result of Top Down Cracking
Rutting (Entire Pavement)
0.2
0.25
0.3
0.35
0.4
0.45
0.5
0.55
0.6
0 5 10 15 20
Rutting (in)
Time(years)
Rutting vs Time
Chart Indicating Total Rutting of the Flexible Pavement Over the Design
Life
Bottom Up Cracking (HMA)
0
0.00005
0.0001
0.00015
0.0002
0.00025
0 5 10 15 20
% of lane cracked
Time (years)
Bottom Up Cracking vs Time
Chart Indicating Predicated % of Lane Area Cracked for the HMA Layer of
the Semi Rigid Pavement Over the Design Life as a Result of Bottom Up
Cracking
Top Down (Longitudinal) Cracking (HMA)
0
0.005
0.01
0.015
0.02
0.025
0.03
0.035
0.04
0 5 10 15 20
Feet/mile
Time (Years)
Longitudinal Cracking Vs Time
Chart Indicating Predicted Longitudinal Cracking of the HMA Layer for the
Semi Rigid Pavement over the Design Life as a Result of Top Down
Cracking
Rutting (HMA)
0
0.005
0.01
0.015
0.02
0 5 10 15 20
Rutting (in)
Time (years)
Rutting Vs Time
Chart Indicating Total Rutting in HMA Layer of the Semi Rigid Pavement
Over the Design Life
Flexural Cracking (CTB)
0
200
400
600
800
1000
1200
0 5 10 15 20
feet/500ft
Time(Years)
Fatigue Cracking vs Time
Chart Indicating Length of Cracking at the Bottom of the Cement
Treated Layer for the Semi Rigid Pavement Over the Design Life as a
Result of Fatigue Cracking
Flexural Cracking (CTB)
250
300
350
400
450
500
0 5 10 15 20
feet/500ft
Time(years)
Fatigue Cracking vs Time
Chart Indicating Length of cracks at the Bottom of the Cement Treated
Layer for the Cement Treated Pavement over the Design Life as a Result
of Fatigue Cracking
Pavement Alternatives Construction Cost/100m (G$)
Flexible Pavement 4, 601, 600
Semi Rigid Pavement 3, 153, 600
Cement Treated
Pavement
1, 661, 400
Cost of Construction for Pavement
Alternatives
Evaluation
Criteria
Construction
Cost
Ease of
Maintenance
Life Cycle
Cost
Failure
potential
Load
Distribution
Moisture
Sensitivity
Total
Weight 25 5 30 10 20 10 100
Flexible
Pavement
10 2 16 2 8 4 42
Semi Rigid
Pavement
16 3 20 4 12 5 60
CTB
Pavement
22 3.5 28 5 15 8 81.5
Decision Matrix for the Selection of the Most Suitable Pavement Alternative
Final year project ppt - The Future of Pavement Design
Subgrade
Shoulder
Chip Seal
(1in) Cement
Treated
Layer (7in)
White
Sand
(13in)
The pavement alternatives evaluated ranged
from flexible, semi rigid to cement treated
pavements
Utilization of the AASHTO 2002 Guide for the
Design & Evaluation of Pavement Structures
The most viable pavement alternative is the
cement treated pavement since it is the most cost
effective pavement structure while optimizing the
level of service to the road users
Calibration of the empirical models to local
conditions to relate predicted distress to actual
distress occurrence
The use of the axle load spectra concept instead
of the 18kips ESAL concept
Modeling of the environmental conditions on the
performance of the pavement structures
(temperature & moisture)
Modeling of other distress modes such as
reflective cracking
Final year project ppt - The Future of Pavement Design

More Related Content

PDF
DESIGN PROJECT FOR PAVEMENT
PPT
Rigid pavement
PPTX
Flexible pavement design by aashto method
PPTX
Burmister 2 layer
PPT
ppt on pavement design
PPTX
Benkelman beam deflection studies
PPTX
Flexible pavement presentation
PPTX
Pile load test
DESIGN PROJECT FOR PAVEMENT
Rigid pavement
Flexible pavement design by aashto method
Burmister 2 layer
ppt on pavement design
Benkelman beam deflection studies
Flexible pavement presentation
Pile load test

What's hot (20)

PPTX
Highway Alignment
PPTX
Self compacting concrete (scc)
PDF
6. Pavement Engineering.pdf
PPTX
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
PDF
Flow test of concrete
PPTX
PPTX
Importance of highway maintenance
PPTX
Training report of road construction
PPTX
Cc road summer training ppt @akshay kumar
PPTX
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PDF
Project report file on construction of flexible pavement by Harshit Prakash Garg
PPT
Plastic as a soil stabilizer by yashwanth sagar
PPTX
Irc method of design of flexible pavement 1
PPTX
Road Construction
PPSX
Design and construction procedure of otta seal
PPTX
Bituminous road construction
PPTX
Bombay road plan
PPT
Flexible Pavement Design
PPT
Plastic as a soil stabilizer
PDF
CBR Test
Highway Alignment
Self compacting concrete (scc)
6. Pavement Engineering.pdf
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
Flow test of concrete
Importance of highway maintenance
Training report of road construction
Cc road summer training ppt @akshay kumar
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
Project report file on construction of flexible pavement by Harshit Prakash Garg
Plastic as a soil stabilizer by yashwanth sagar
Irc method of design of flexible pavement 1
Road Construction
Design and construction procedure of otta seal
Bituminous road construction
Bombay road plan
Flexible Pavement Design
Plastic as a soil stabilizer
CBR Test
Ad

Similar to Final year project ppt - The Future of Pavement Design (20)

PPT
Lect 6 pavement design
DOCX
Pavement eng re
PPT
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
PDF
Rutting resistance of filler modified bituminous concrete surfaces 2
PPTX
Village networking ppt
PPTX
Highway design presentation (Malyar Talash)
PDF
IRJET - Design of Improved Drainage System using Pervious Concrete
PPTX
Pavement-Design.pptx for designing of slabs
PPTX
462460293-Design-of-flexible-pavement-pptx.pptx
PPTX
stage construction.pptx
PDF
Influence of subgrade condition on rutting in flexible pavements
PDF
7._AASHTO_Flexible_Pavement_Design_Method (1).pdf
PDF
IRJET- Design and Comparision of Flexible and Rigid Pavements
PPT
Pavement thickness design
PDF
Amr7231044
PDF
Benefit analysis of subgrade and surface improvements in flexible pavements 2
PDF
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
PDF
COST OPTIMIZATION OF CONCRETE BY REPLACING FINE AGGREGATE WITH WALNUT SHELL P...
PDF
RoadstaB : Road Stabilization
Lect 6 pavement design
Pavement eng re
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
Rutting resistance of filler modified bituminous concrete surfaces 2
Village networking ppt
Highway design presentation (Malyar Talash)
IRJET - Design of Improved Drainage System using Pervious Concrete
Pavement-Design.pptx for designing of slabs
462460293-Design-of-flexible-pavement-pptx.pptx
stage construction.pptx
Influence of subgrade condition on rutting in flexible pavements
7._AASHTO_Flexible_Pavement_Design_Method (1).pdf
IRJET- Design and Comparision of Flexible and Rigid Pavements
Pavement thickness design
Amr7231044
Benefit analysis of subgrade and surface improvements in flexible pavements 2
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
COST OPTIMIZATION OF CONCRETE BY REPLACING FINE AGGREGATE WITH WALNUT SHELL P...
RoadstaB : Road Stabilization
Ad

Recently uploaded (20)

PDF
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PDF
My India Quiz Book_20210205121199924.pdf
PDF
International_Financial_Reporting_Standa.pdf
PDF
IGGE1 Understanding the Self1234567891011
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PDF
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PDF
HVAC Specification 2024 according to central public works department
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PDF
Trump Administration's workforce development strategy
PPTX
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PDF
advance database management system book.pdf
PDF
Hazard Identification & Risk Assessment .pdf
PDF
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
My India Quiz Book_20210205121199924.pdf
International_Financial_Reporting_Standa.pdf
IGGE1 Understanding the Self1234567891011
Paper A Mock Exam 9_ Attempt review.pdf.
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
LDMMIA Reiki Yoga Finals Review Spring Summer
HVAC Specification 2024 according to central public works department
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
B.Sc. DS Unit 2 Software Engineering.pptx
Trump Administration's workforce development strategy
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
Practical Manual AGRO-233 Principles and Practices of Natural Farming
Share_Module_2_Power_conflict_and_negotiation.pptx
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
advance database management system book.pdf
Hazard Identification & Risk Assessment .pdf
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf

Final year project ppt - The Future of Pavement Design

  • 3.  Introduction  Background  Problem Statement  Objectives  Scope of project  Methodology  Pavement Design Approach  Pavement Response Modeling  Pavement Alternatives  AASHTO 1993 Design  AASHTO 2002 Evaluation  Economic Evaluation  Pavement Type Selection  Pavement Structure  Conclusion  Recommendations
  • 4. Purpose of Access Road: 1. Facilitate the movement of farmers to and from the backlands 2. Access route to arable farm lands for cultivation 3. Low volume roadway Geometric Configuration: Length = 3 miles ( km) Width = 22 ft ( m)
  • 5. The Access Road in Vergenoegen Look at this road…I ain’t going deh!
  • 6. Location (6052’24.9’’N and 58021’51.30’’W) Main Road Access Road Access Road
  • 9. The statement of problem is to design a new pavement structure for the access road in Vergenoegen that could fulfill all the traffic and environmental conditions while at the same time being an economically viable structure.
  • 10.  Quantify and characterize the loadings of the various vehicles that uses the current facility  Investigate and evaluate the potential of suitable pavement alternatives for a cost effective alternative to accommodate the present and future traffic loads on the road  Evaluate the potential advantages and disadvantages of pavement alternatives  Carry out life cycle cost analysis on the various pavement alternatives to determine the most promising alternative  Design proposal of a suitable access road based on the most promising pavement alternative
  • 11. Selection is limited to the most feasible alternatives considered Use of the AASHTO 1993 & AASHTO 2002 Guides for the Design of Pavement structures Pavement distress is based on cracking and rutting predictions as computed from the pavement responses using the WinJULEA software
  • 12. 1 Inputs Materials Traffic loadings Environmen tal data 2 Design Alternatives Layer thickness design 3 Evaluation Technical Economical 4 Pavement selection Most feasible alternative 5 Design Proposal Site specific conditions
  • 13. AASHTO 1993 Guide for the Design of Pavement Structures AASHTO 2002 Guide for the Mechanistic-Empirical Design of Pavement Structures
  • 15. Alternative 1 Flexible Pavement Alternative 2 Semi Rigid Pavement Alternative 3 Cement Treated Pavement
  • 16. Design Traffic (Overall 18kips ESALs) Graph Showing the Cumulative 18kips ESALs Over the 20 year Design Life 0 20000 40000 60000 80000 100000 120000 140000 160000 0 5 10 15 20 18kips ESAL Time(years) Cumulative 18kips ESAL 136, 584
  • 17. Design Traffic for 20 Years W18 = DDxDLxW18 DD = 50% (0.5) DL = 100% (1) W18 = 136,584.6342 [18kips ESALs] Therefore, W18 = 0.5 x 1 x 136, 584.6342 18kips ESALs W18 = 68, 293 [18kips ESAL]
  • 18. Pavement Material Properties Material Function CBR (%) Modulus (psi) Structural Layer Coefficient (Correlated from AASHTO 93 ) Hot Mix Asphalt Surface Course 400,000 @ 68F 0.43 Crusher Run Base Course 60 0.12 Cement Stabilized Material Base Course 830,000 @ 7days 0.22 White Sand Subbase Course 6 0.06 In-Situ Soil Subgrade 2 3000
  • 19. Design Parameters Reliability, R = 75% Standard Deviation, So = 0.45 Initial Serviceability, pi = 4.5 Terminal Serviceability, pt = 2
  • 20. Required Structural Number Design Chart for Flexible Pavements used for Estimating the Structural Number Required
  • 21. Alternative 1 (Flexible Pavement) Initial Structural Number 2.3 Layer Thickness Determination Layer 1 Thickness, D1 (inch) 2 Layer 2 Thickness, D2 (inch) 6 Layer 3 Thickness, D3 (inch) 12 Final Structural Number 2.3 Asphalt Concrete Ordinary White Sand 2in 6in 12in
  • 22. Alternative 2 (Semi Rigid Pavement) Initial Structural Number 2.3 Layer Thickness Determination Layer 1 Thickness, D1 (inch) 2 Layer 2 Thickness, D2 (inch) 4 Layer 3 Thickness, D3 (inch) 12 Final Structural Number 2.5 Asphalt Concrete Cement Treated Base Ordinary White Sand 2in 4in 12in
  • 23. Alternative 3 (Cement Treated Pavement) Initial Structural Number 2.3 Layer Thickness Determination Layer 1 Thickness, D1 (inch) 1 Layer 2 Thickness, D2 (inch) 7 Layer 3 Thickness, D3 (inch) 13 Final Structural Number 2.3 Chip Seal Cement Treated Base Ordinary White Sand 1in 7in 13in
  • 24. Material Function Resilient Modulus (psi) Poisson’s Ratio Hot Mix Asphalt Surface Course 400,000 0.25 Crusher Run Base Course 25,715 0.15 Cement Stabilized Material Base Course 830,000 0.35 White Sand Subbase Course 8,182 0.3 In-Situ Soil Subgrade 3000 0.2 Note: All pavement layers were assumed to be fully bonded together at the interfaces.
  • 25. Traffic Loadings 9000 lbs9,000 lbs 18,000 lbs Tire Radius = 6inches Tire Pressure = 75psi Fully Bonded Conditions
  • 26. Bottom Up Cracking (HMA) 0 1 2 3 4 5 6 7 8 9 0 5 10 15 20 % of lane area cracked Time (years) Bottom Up Cracking Prediction vs Time Chart Showing the % of Lane Area Cracked Over the Design Life for the Flexible Pavement as a Result of Bottom Up Cracking
  • 27. Top Down (Longitudinal) Cracking (HMA) 0 1000 2000 3000 4000 5000 6000 7000 8000 0 5 10 15 20 Feet/mile Time (Years) Longitudional Cracking Prediction vs Time Chart Showing the Length of Longitudinal Cracking of the Flexible Pavement Over the Design Life as a Result of Top Down Cracking
  • 28. Rutting (Entire Pavement) 0.2 0.25 0.3 0.35 0.4 0.45 0.5 0.55 0.6 0 5 10 15 20 Rutting (in) Time(years) Rutting vs Time Chart Indicating Total Rutting of the Flexible Pavement Over the Design Life
  • 29. Bottom Up Cracking (HMA) 0 0.00005 0.0001 0.00015 0.0002 0.00025 0 5 10 15 20 % of lane cracked Time (years) Bottom Up Cracking vs Time Chart Indicating Predicated % of Lane Area Cracked for the HMA Layer of the Semi Rigid Pavement Over the Design Life as a Result of Bottom Up Cracking
  • 30. Top Down (Longitudinal) Cracking (HMA) 0 0.005 0.01 0.015 0.02 0.025 0.03 0.035 0.04 0 5 10 15 20 Feet/mile Time (Years) Longitudinal Cracking Vs Time Chart Indicating Predicted Longitudinal Cracking of the HMA Layer for the Semi Rigid Pavement over the Design Life as a Result of Top Down Cracking
  • 31. Rutting (HMA) 0 0.005 0.01 0.015 0.02 0 5 10 15 20 Rutting (in) Time (years) Rutting Vs Time Chart Indicating Total Rutting in HMA Layer of the Semi Rigid Pavement Over the Design Life
  • 32. Flexural Cracking (CTB) 0 200 400 600 800 1000 1200 0 5 10 15 20 feet/500ft Time(Years) Fatigue Cracking vs Time Chart Indicating Length of Cracking at the Bottom of the Cement Treated Layer for the Semi Rigid Pavement Over the Design Life as a Result of Fatigue Cracking
  • 33. Flexural Cracking (CTB) 250 300 350 400 450 500 0 5 10 15 20 feet/500ft Time(years) Fatigue Cracking vs Time Chart Indicating Length of cracks at the Bottom of the Cement Treated Layer for the Cement Treated Pavement over the Design Life as a Result of Fatigue Cracking
  • 34. Pavement Alternatives Construction Cost/100m (G$) Flexible Pavement 4, 601, 600 Semi Rigid Pavement 3, 153, 600 Cement Treated Pavement 1, 661, 400 Cost of Construction for Pavement Alternatives
  • 35. Evaluation Criteria Construction Cost Ease of Maintenance Life Cycle Cost Failure potential Load Distribution Moisture Sensitivity Total Weight 25 5 30 10 20 10 100 Flexible Pavement 10 2 16 2 8 4 42 Semi Rigid Pavement 16 3 20 4 12 5 60 CTB Pavement 22 3.5 28 5 15 8 81.5 Decision Matrix for the Selection of the Most Suitable Pavement Alternative
  • 38. The pavement alternatives evaluated ranged from flexible, semi rigid to cement treated pavements Utilization of the AASHTO 2002 Guide for the Design & Evaluation of Pavement Structures The most viable pavement alternative is the cement treated pavement since it is the most cost effective pavement structure while optimizing the level of service to the road users
  • 39. Calibration of the empirical models to local conditions to relate predicted distress to actual distress occurrence The use of the axle load spectra concept instead of the 18kips ESAL concept Modeling of the environmental conditions on the performance of the pavement structures (temperature & moisture) Modeling of other distress modes such as reflective cracking