Engineering Services
Raising the performance
Giovanni Ferrenan
© 2017 HFC/FO UNIT - Giovanni Ferrenan 2
Executive summary
 HFC Node: SI-064
 Segments in service: A, B, C.
 Analysis: 26-May-2017
 Initial MER Avg.: 30.05dB
 Initial NPI Avg.: 45/100
 High noise from 5.30pm to 7am.
KPIs after a week of monitoring
02-Jun-2017
 NPI improved from 57 to 89
 MER reached to 39.7dB
© 2017 HFC/FO UNIT - Giovanni Ferrenan 3
 Node SI-064 running in low-modulation (32QAM) due to B segment.
SSM dashboard - Glimpse of the three segments: A, B, C
---- MER
---- MER No Ec
---- NOISE
C SEGMENT:
A SEGMENT:
B SEGMENT: Severe impact on
daily performance
© 2017 HFC/FO UNIT - Giovanni Ferrenan 4
Affected segment: SI-064-B. Affected time span: 5pm – 07am
MACtrak
View
Additional
detail
High noise producing low MER
© 2017 HFC/FO UNIT - Giovanni Ferrenan 5
After analysis: the area to find issues was delimited
A03
Av. Pezet
Av.Romanet
P
2
P
4
1073
STB + CM
Lobby
ACI
TAP
0303
RG11 Cable
QAM Leak
Cochera
Piso 1
Piso 4
© 2017 HFC/FO UNIT - Giovanni Ferrenan 6
QAM Egress confirmation
QAM Egress
detected and
confirmed with
the instruments.
The leaking was
found under
garaje.
© 2017 HFC/FO UNIT - Giovanni Ferrenan 7
It was found different damages on one cable
Results from the same day after repairing
01/06/2017
© 2017 HFC/FO UNIT - Giovanni Ferrenan 9
Performance after cable replacement – Now the Node is running on
64QAM
SSM Timeline:
Performance at
glance
• Better node’s performance.
• Saving cost / CMTS.
• More bandwith with the Same Infrastructure.
Reached Goals
MACTRAK:
Technical DrillDown
© 2017 HFC/FO UNIT - Giovanni Ferrenan 10
Thanks!!!
PNM - Proactive Network Maintenance
SB-036
Giovanni Ferrenan
© 2017 HFC/FO UNIT - Giovanni Ferrenan 12
Nodo SBR036 – 399 CM
51 CM - two Groups: A (34 modems) y B (17 modems)
© 2017 HFC/FO UNIT - Giovanni Ferrenan 13
BSS shows alarmed Nodes –> Node SB036
BSSPNM
© 2017 HFC/FO UNIT - Giovanni Ferrenan 14
Localization of the possible issue
Common
pointFailed
Element
Affected CM
© 2017 HFC/FO UNIT - Giovanni Ferrenan 15
Findings and Fixing: broken pin acting as an antenna causing noise ingress
Pin removed to
fix subscriber
issues
© 2017 HFC/FO UNIT - Giovanni Ferrenan 16
No more groups => No more affected CM
© 2017 HFC/FO UNIT - Giovanni Ferrenan 17
PathTrak and BSS Verification
Indicadores de Afectación Lineal
Customer’s BSSPathtrak
© 2017 HFC/FO UNIT - Giovanni Ferrenan 18
Thanks!!!

More Related Content

PPTX
Spm vibration data integration to cmms
PDF
Operation and design hfc
DOC
Preventive Maintenance Report - Dubai
PPT
Mw training slide
PPT
Ome200301 gsm bts trouble shooting issue3.0
PPT
Ome200301 gsm bts trouble shooting issue3.0
PPTX
PROJECT 2016-2017
PDF
Huawei Capacity Upgrade
Spm vibration data integration to cmms
Operation and design hfc
Preventive Maintenance Report - Dubai
Mw training slide
Ome200301 gsm bts trouble shooting issue3.0
Ome200301 gsm bts trouble shooting issue3.0
PROJECT 2016-2017
Huawei Capacity Upgrade

Similar to HFC network optimization and PNM in the field - Proactive Service (7)

PDF
Frequency Response Analysis by Prof Satish IISc
PPT
fall00_boone.ppt
PPT
presentation on LCI Load Commutative Inverter nigeria.ppt
PDF
SICAM FCM – Feeder Condition Monitor
PPTX
Services Master
PDF
BRKDCT-3144 - Advanced - Troubleshooting Cisco Nexus 7000 Series Switches (20...
DOC
Mini-Fiber Node Technology
Frequency Response Analysis by Prof Satish IISc
fall00_boone.ppt
presentation on LCI Load Commutative Inverter nigeria.ppt
SICAM FCM – Feeder Condition Monitor
Services Master
BRKDCT-3144 - Advanced - Troubleshooting Cisco Nexus 7000 Series Switches (20...
Mini-Fiber Node Technology
Ad

Recently uploaded (20)

PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PDF
Univ-Connecticut-ChatGPT-Presentaion.pdf
PDF
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
PPTX
Group 1 Presentation -Planning and Decision Making .pptx
PDF
Zenith AI: Advanced Artificial Intelligence
PDF
Hindi spoken digit analysis for native and non-native speakers
PDF
August Patch Tuesday
PDF
Getting Started with Data Integration: FME Form 101
PPTX
A Presentation on Artificial Intelligence
PPTX
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
PDF
Assigned Numbers - 2025 - Bluetooth® Document
PDF
Mushroom cultivation and it's methods.pdf
PDF
Transform Your ITIL® 4 & ITSM Strategy with AI in 2025.pdf
PDF
gpt5_lecture_notes_comprehensive_20250812015547.pdf
PDF
Accuracy of neural networks in brain wave diagnosis of schizophrenia
PDF
project resource management chapter-09.pdf
PDF
WOOl fibre morphology and structure.pdf for textiles
PDF
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
PDF
A comparative study of natural language inference in Swahili using monolingua...
PPTX
1. Introduction to Computer Programming.pptx
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
Univ-Connecticut-ChatGPT-Presentaion.pdf
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
Group 1 Presentation -Planning and Decision Making .pptx
Zenith AI: Advanced Artificial Intelligence
Hindi spoken digit analysis for native and non-native speakers
August Patch Tuesday
Getting Started with Data Integration: FME Form 101
A Presentation on Artificial Intelligence
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
Assigned Numbers - 2025 - Bluetooth® Document
Mushroom cultivation and it's methods.pdf
Transform Your ITIL® 4 & ITSM Strategy with AI in 2025.pdf
gpt5_lecture_notes_comprehensive_20250812015547.pdf
Accuracy of neural networks in brain wave diagnosis of schizophrenia
project resource management chapter-09.pdf
WOOl fibre morphology and structure.pdf for textiles
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
A comparative study of natural language inference in Swahili using monolingua...
1. Introduction to Computer Programming.pptx
Ad

HFC network optimization and PNM in the field - Proactive Service

  • 1. Engineering Services Raising the performance Giovanni Ferrenan
  • 2. © 2017 HFC/FO UNIT - Giovanni Ferrenan 2 Executive summary  HFC Node: SI-064  Segments in service: A, B, C.  Analysis: 26-May-2017  Initial MER Avg.: 30.05dB  Initial NPI Avg.: 45/100  High noise from 5.30pm to 7am. KPIs after a week of monitoring 02-Jun-2017  NPI improved from 57 to 89  MER reached to 39.7dB
  • 3. © 2017 HFC/FO UNIT - Giovanni Ferrenan 3  Node SI-064 running in low-modulation (32QAM) due to B segment. SSM dashboard - Glimpse of the three segments: A, B, C ---- MER ---- MER No Ec ---- NOISE C SEGMENT: A SEGMENT: B SEGMENT: Severe impact on daily performance
  • 4. © 2017 HFC/FO UNIT - Giovanni Ferrenan 4 Affected segment: SI-064-B. Affected time span: 5pm – 07am MACtrak View Additional detail High noise producing low MER
  • 5. © 2017 HFC/FO UNIT - Giovanni Ferrenan 5 After analysis: the area to find issues was delimited A03 Av. Pezet Av.Romanet P 2 P 4 1073 STB + CM Lobby ACI TAP 0303 RG11 Cable QAM Leak Cochera Piso 1 Piso 4
  • 6. © 2017 HFC/FO UNIT - Giovanni Ferrenan 6 QAM Egress confirmation QAM Egress detected and confirmed with the instruments. The leaking was found under garaje.
  • 7. © 2017 HFC/FO UNIT - Giovanni Ferrenan 7 It was found different damages on one cable
  • 8. Results from the same day after repairing 01/06/2017
  • 9. © 2017 HFC/FO UNIT - Giovanni Ferrenan 9 Performance after cable replacement – Now the Node is running on 64QAM SSM Timeline: Performance at glance • Better node’s performance. • Saving cost / CMTS. • More bandwith with the Same Infrastructure. Reached Goals MACTRAK: Technical DrillDown
  • 10. © 2017 HFC/FO UNIT - Giovanni Ferrenan 10 Thanks!!!
  • 11. PNM - Proactive Network Maintenance SB-036 Giovanni Ferrenan
  • 12. © 2017 HFC/FO UNIT - Giovanni Ferrenan 12 Nodo SBR036 – 399 CM 51 CM - two Groups: A (34 modems) y B (17 modems)
  • 13. © 2017 HFC/FO UNIT - Giovanni Ferrenan 13 BSS shows alarmed Nodes –> Node SB036 BSSPNM
  • 14. © 2017 HFC/FO UNIT - Giovanni Ferrenan 14 Localization of the possible issue Common pointFailed Element Affected CM
  • 15. © 2017 HFC/FO UNIT - Giovanni Ferrenan 15 Findings and Fixing: broken pin acting as an antenna causing noise ingress Pin removed to fix subscriber issues
  • 16. © 2017 HFC/FO UNIT - Giovanni Ferrenan 16 No more groups => No more affected CM
  • 17. © 2017 HFC/FO UNIT - Giovanni Ferrenan 17 PathTrak and BSS Verification Indicadores de Afectación Lineal Customer’s BSSPathtrak
  • 18. © 2017 HFC/FO UNIT - Giovanni Ferrenan 18 Thanks!!!