SlideShare a Scribd company logo
REMINDER
Check in on the COLLABORATE
mobile app
Implementation Review: EPPM P6
8.x at a Major Utility
Prepared by:
Bill Hyde
Director
SUB3 Management, Inc.
Aligning OPPM and SAP Interface
Session ID#: 15473
This is a divider slide title that
can be two lines
Implementation Review: Pepco Holding, Inc.
Pepco Holding, Inc.
■  Service Area
▪  Delaware
▪  District of District of
Columbia
▪  Maryland and
▪  New Jersey
■  Provides regulated electric
service
▪  Atlantic City Electric
▪  Delmarva Power
▪  Pepco
■  Provides Natural Gas Service
■  Provides Energy Efficiency &
Renewable Solutions
Pepco Holding, Inc. Fun Facts
■  Incorporated: 2002
■  Service Territory:
▪  8,340 sq miles / 13,421.9 km
▪  Customers: 2M
▪  Substations: 530+
▪  Transmission Lines:
—  3,500 miles / 5,632.7 km
▪  Distribution Lines:
—  30,000 miles /48,280.3 km
■  Diverse geographic area
Project Vision
■  Departments within the organization working in concert with
one another utilizing centralized and linked databases to track
comprehensive aspects of the capital projects throughout
their lifecycle.
Future	
  State	
   Current	
  State	
  /	
  Challenges	
  
One	
  Project	
  data	
  repository	
  (Only	
  one	
  version	
  
of	
  the	
  truth)	
  
•  Department	
  &	
  Individual	
  repositories	
  
•  Excel	
  for	
  Everything!	
  	
  
Transparency	
  
What	
  is	
  the	
  true	
  resource	
  need?	
  Who	
  is	
  
accountable?	
  
•  SeEng	
  and	
  Enforcing	
  expectaFons	
  of	
  the	
  
responsible	
  engineer	
  
•  Using	
  the	
  tool	
  conFnuously	
  &	
  consistently	
  
Capital	
  Budget	
  Steering	
  CommiJee	
   •  Eliminate	
  best	
  ‘PowerPoint’	
  wins	
  
•  Ensure	
  proper	
  representaFon	
  	
  
•  Eliminates	
  5	
  year	
  Excel	
  spreadsheet	
  
Projects	
  entered	
  into	
  PPM	
  @	
  concepFon	
  with	
  
prioriFzaFon	
  criteria	
  
•  Provides	
  rich	
  data	
  on	
  upcoming	
  projects	
  	
  
•  CollaboraFon	
  between	
  planning	
  &	
  
engineering	
  
•  EliminaFng	
  individual	
  data	
  repositories	
  
Project	
  PorRolio	
  analyzed	
  monthly	
  (actual	
  &	
  
forecast	
  spend),	
  target	
  financials	
  from	
  10K	
  
report,	
  and	
  prioriFzaFon	
  cost/value	
  analysis	
  
•  Paradigm	
  Shirt	
  
•  Living	
  to	
  the	
  Target	
  Plan	
  
Future State vs. Current State
Future	
  State	
   Current	
  State	
  /	
  Challenges	
  
Fully	
  loaded	
  schedules	
  exist	
  for	
  all	
  project	
  the	
  
Project	
  PorRolio	
  
•  Implement	
  WBS	
  consistently	
  	
  	
  
•  Work	
  with	
  responsible	
  engineer	
  
throughout	
  organizaFon	
  
Update	
  schedules	
  consistently	
  and	
  regularly	
  
to	
  drive	
  monthly	
  forecast	
  	
  
•  SeEng	
  and	
  Enforcing	
  expectaFons	
  of	
  the	
  
responsible	
  engineer	
  
	
  
Scope	
  Changes:	
  Must	
  be	
  approved	
  by	
  sponsor	
  
&	
  routed	
  via	
  the	
  Capital	
  Budget	
  Steering	
  
CommiJee	
  prior	
  to	
  any	
  changes	
  
•  EliminaFng	
  individual/small	
  group	
  
decision	
  making	
  
•  Eliminate	
  Monday	
  Morning	
  
Quarterbacking	
  
Annual	
  budget	
  prepared	
  from	
  project	
  
porRolio	
  which	
  is	
  acFvely	
  managed	
  to	
  
financial	
  targets	
  
•  Shi_ing	
  the	
  paradigm	
  
•  AccepFng	
  there	
  is	
  a	
  beJer	
  way	
  
Future State vs. Current State (cont’d)
Previous State: Project Management
Lifecycle
Determine the Solution
■  Various Departments
▪  Identify areas of Improvements
▪  Work with ‘bundling’ individuals solutions for the ‘greater good’
■  Utilize Existing IT systems
■  Process Impacts
▪  Cross functional mapping
▪  Data collection
■  Analysis of possible solutions
▪  Vendor presentations
▪  Hands on exercises with vendors
▪  References
Data Repository Solution
Implementation State: Project Management
Lifecycle
Reasons for Implementation State Solutions
■  P6 was already being used for schedules (versus SAP, MSP)
■  P6 was already was integrated with SAP
■  OPPM configuration
▪  Build to business requirements
▪  Adjust & made improvements on the fly
▪  Future enhancements
■  OPPM parallel workflows
▪  Align workflow to requirements
▪  Minimize time projects spent within a process
■  PPM -> P6 Bridge exists and configurable
Integrated Solution
■  Four Phase Implementation Methodology
▪  Strategic Alignment
▪  Design
▪  Configure
▪  Implement
■  Strategic Alignment
▪  Align Proposal to true business need
▪  Received approval of modified approach
■  Design
▪  Project Definition to match SAP
▪  Enhanced Work Breakdown Structure
▪  Enhanced SAP->P6 Interface Design
Integrated Solution
■  Configure
▪  Phase 1
—  Initiate Project
—  Retrofitted In Flight Projects
—  Tested Revised SAP->P6 Interface
—  Configured flexible solution to allow for easy enhancements
▪  Phase 2
—  Populated System
—  Analytics / Reporting
■  Implement
▪  JIT Training Workshops
▪  Rolling wave of projects
▪  Lesson Learned
OPPM – Modules Implemented
■  Processes
■  Workflows
■  Investor Module
■  Scorecard Module
■  Forms Module
OPPM System Processes
■  Project Initiation*(5)
■  Scope Change (1)
■  PM Coordination (4)
■  Standard Reporting (1)
■  Instructions, shortcuts and
references provided within
each process
■  * Tied to P6 EPPM
11 Processes +
OPPM Workflows
■  Project Initiation (21)
■  Scope Change (13)
■  Instructions, shortcuts and
references provided within
each workflow
■  Provides individuals with their
‘to-do’ list
34 Workflows +
OPPM Investor Module
■  Multi-dimensional view of
project data
■  Investor Maps for financial
data (3)
■  Color Coding to distinguish
different aspects of the project
The Capital Program
OPPM Scorecard Module
■  40+ Scorecards
▪  Capital Program
—  5 Year Capital Plan
—  1 Year Capital Plan
▪  PJM Interconnection LLC (PJM) Reports
—  Regional Transmission Organization in the United States
▪  Reliability Enhancement Plan
▪  Manage Portfolio Data Dynamically
—  New Project Requests
—  Project Scope Change Status
—  Project Teams
OPPM Forms
■  25+ Forms
■  Forms has several tabs (1 to 7)
■  Forms include:
▪  Admin
▪  Scope changes
▪  Project Initiation
▪  Project Prioritization
▪  Project Review
▪  Work Coordination
P6 EPPM – Modules Implemented
■  Professional (Client)
■  EPPM - Web
■  Business Intelligence (BI) Reports
■  Primavera Analytics
P6 Professional (Client)
■  Input: 5 Year Plan Stage Schedule
P6 EPPM (Web)
■  Configurable on a global level
or by an individual
■  Select Dashboard and select
portlets will be on each
■  Role based profile to minimize
Graphical User Interface
(GUI) and keep job easy
Dashboards
P6 EPPM (Web)
■  Output: 5 Year Resource Plan Usage
P6 Primavera Analytics
■  Highly Configurable reporting
tool
■  Easy to use with minimal data
clicks
■  Data is published to system
twice a month
The BIG Picture
Lesson Learned – What went well
■  Admit a problem(s) needs to be addressed
■  Senior Management Support
■  Vision
■  Defined Scope
■  Stakeholder involvement
■  Dedicated, multi-disciplinary team
■  Current State / Future State Analysis
■  Embracing Change – the users
Lesson Learned – Opportunities for
Improvement
■  IT Resources, competing Projects
■  Some areas did not provide desired level of input during
design stage
■  IT security measures provided some limitations implementing
solutions full capabilities
■  Push back from process changes ‘be careful what you ask
for’
■  Changing strategies effected timeline
■  Keeping users happy - Rolling out additional features
Thank You!.......Questions
■  Contact Info
▪  Bill Hyde
▪  whyde@sub3mgmt.com
▪  SUB3 Management Inc.
—  www.sub3mgmt.com
—  @SUB3MGMT
■  Sources and Thanks to Pepco Holdings, Inc.
▪  Kim Deeley, kim.deeley@pepcoholdings.com
▪  Pamela Zucaro, pamela.zucaro@pepcoholdings.com
Please complete the session
evaluation
We appreciate your feedback and insight
You may complete the session evaluation either
on paper or online via the mobile app

More Related Content

PDF
Primavera gateway SAP provider - Oracle Primavera P6 Collaborate 14
PPTX
Why Project Management with Primavera?
PDF
Oracle primavera eppm presentation
PDF
Primavera Gateway overview - Oracle Primavera P6 Collaborate 14
PDF
Primavera P6 Tips and Tricks
PDF
Use of unifier with primavera
PDF
Implementing oracle primavera_analytics
PDF
The Primavera suite how the tools work together - Oracle Primavera Collabor...
Primavera gateway SAP provider - Oracle Primavera P6 Collaborate 14
Why Project Management with Primavera?
Oracle primavera eppm presentation
Primavera Gateway overview - Oracle Primavera P6 Collaborate 14
Primavera P6 Tips and Tricks
Use of unifier with primavera
Implementing oracle primavera_analytics
The Primavera suite how the tools work together - Oracle Primavera Collabor...

What's hot (19)

PDF
What's New in Primavera Prime 16.1
PDF
Primavera EPPM in Asset-Intensive Organizations
PDF
P6 analytics product roadmap and overview - Oracle Primavera P6 Collaborate 14
PDF
Leveraging P6 and Unifier combined strengths - Oracle Primavera P6 Collaborat...
PDF
206450 primavera gateway
PDF
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
PPT
Integrating primavera p6 with oracle erp which technology path is right for...
PDF
Primavera Unifier Roadmap 2015
PDF
P6 analytics producing meaningful results in P6 analytics - Oracle Primavera...
PPTX
Oracle Primavera P6 partner programs
PDF
Primavera Unifier Tips and Tricks
PPTX
Primavera P6 Online Training
PDF
Primavera P6 Team Member - For Primavera Users on the Go
PDF
What's New in Unifier 16.1
PDF
Oracle Primavera P6 R16.1
PDF
Oracle primavera p6 and ebs projects where do they meet ppt
PDF
What's New In Primavera Analytics 16.1
PDF
Oracle Primavera Roadmap 2015
What's New in Primavera Prime 16.1
Primavera EPPM in Asset-Intensive Organizations
P6 analytics product roadmap and overview - Oracle Primavera P6 Collaborate 14
Leveraging P6 and Unifier combined strengths - Oracle Primavera P6 Collaborat...
206450 primavera gateway
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
Integrating primavera p6 with oracle erp which technology path is right for...
Primavera Unifier Roadmap 2015
P6 analytics producing meaningful results in P6 analytics - Oracle Primavera...
Oracle Primavera P6 partner programs
Primavera Unifier Tips and Tricks
Primavera P6 Online Training
Primavera P6 Team Member - For Primavera Users on the Go
What's New in Unifier 16.1
Oracle Primavera P6 R16.1
Oracle primavera p6 and ebs projects where do they meet ppt
What's New In Primavera Analytics 16.1
Oracle Primavera Roadmap 2015
Ad

Viewers also liked (20)

PDF
Reentry Resource Center Design and Implementation Plan 2014
PDF
Project initiation in oppm to project execution in p6 eppm - Oracle Primavera...
PPTX
P6 analytics r1 vp public 001
PDF
205410 primavera and sap
PDF
Primavera integration possibilities technical overview ppt
PDF
206430 whats new in primavera p6 rel8 3
PDF
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
PDF
SE_Lec 12_ Project Planning
PPT
3 Project Cycle and Planning (4-6 hours)
PPT
Planning And Project Management
PPT
Project Planning Basics - Everything you need to start managing a project
PPT
Project Planning
PPT
Project Planning
PPTX
Introduction to Agile Project Planning and Project Management
PDF
Pdf primavera tutorial
PPT
Fundamentals of Project Management
PDF
Project Management Concepts (from PMBOK 5th Ed)
PPT
The Project Management Process - Week 1
PPTX
PMI Project Management Principles
PPTX
Project planning and project work plan
Reentry Resource Center Design and Implementation Plan 2014
Project initiation in oppm to project execution in p6 eppm - Oracle Primavera...
P6 analytics r1 vp public 001
205410 primavera and sap
Primavera integration possibilities technical overview ppt
206430 whats new in primavera p6 rel8 3
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
SE_Lec 12_ Project Planning
3 Project Cycle and Planning (4-6 hours)
Planning And Project Management
Project Planning Basics - Everything you need to start managing a project
Project Planning
Project Planning
Introduction to Agile Project Planning and Project Management
Pdf primavera tutorial
Fundamentals of Project Management
Project Management Concepts (from PMBOK 5th Ed)
The Project Management Process - Week 1
PMI Project Management Principles
Project planning and project work plan
Ad

Similar to Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Collaborate 14 (20)

PPTX
Managing IT Projects with Oracle Primavera
PPT
Project Management basic componentss.ppt
PPTX
Defining organizational project management 2012
PPTX
Epm presentation itvamp paragon_102111 (3)
PDF
Enterprise Project Management and the US Armed Forces - EPC Group
PPTX
Microsoft EPM and Team Foundation Server [TFS]
PDF
If you dont know where you are going any road will do visioning for impleme...
PDF
Flow Chart Junkie does the PMO: Unifier as it applies to different PMO profiles
PDF
PMP PMBOK 5TH Ch 6 time management
PDF
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
PDF
ePMO & Enterprise Implementations
PPTX
PPM Challenge #3: Providing Value to All Levels – 2012 PPM Challenge and Oppo...
PDF
Projectmanagement 141108102434-conversion-gate01
PPTX
Primavara
PPTX
Project Management Framework
PDF
Enterprise Project Management Solutions - Install and train, job done? by "Da...
PDF
EPPM Webcast
PPTX
Building a Project Management Information System for the State of Hawai'i
PPTX
How to get more from your project server deployment
PDF
Ppm Solutions For It Governance, The User Perspective
Managing IT Projects with Oracle Primavera
Project Management basic componentss.ppt
Defining organizational project management 2012
Epm presentation itvamp paragon_102111 (3)
Enterprise Project Management and the US Armed Forces - EPC Group
Microsoft EPM and Team Foundation Server [TFS]
If you dont know where you are going any road will do visioning for impleme...
Flow Chart Junkie does the PMO: Unifier as it applies to different PMO profiles
PMP PMBOK 5TH Ch 6 time management
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
ePMO & Enterprise Implementations
PPM Challenge #3: Providing Value to All Levels – 2012 PPM Challenge and Oppo...
Projectmanagement 141108102434-conversion-gate01
Primavara
Project Management Framework
Enterprise Project Management Solutions - Install and train, job done? by "Da...
EPPM Webcast
Building a Project Management Information System for the State of Hawai'i
How to get more from your project server deployment
Ppm Solutions For It Governance, The User Perspective

More from p6academy (20)

PDF
Oracle OpenWorld 2015
PDF
Plan and Execute the Right Projects— Easily and Affordably
PDF
What's New In Primavera P6 EPPM 17.1
PDF
Oracle Primavera Unifier What's New in Release 16.2
PDF
Oracle What's New In Primavera P6 16.2
PDF
What's New in Primavera Gateway 16.1
PDF
20160405 How to Install Primavera P6 16.1 Professional desktop
PDF
Oracle Primavera P6 16.1 Announced
PDF
Oracle Primavera Unifier 16.1
PDF
P6 Release 8 Application Considerations Overview
PDF
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
PDF
P6 Release 8 Installation Orientation
PDF
Oracle Primavera P6 R8 Release Value Proposition
PDF
Oracle Primavera P6 v7 Release Value Proposition
PDF
Oracle Primavera P6 Release Content Document (RCD)
PDF
Oracle Support Accreditation – Level 1 Study Guide
PDF
Oracle Primavera Support Accreditation Study Guide
PDF
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) ...
PDF
Primavera Oracle Cloud Market Place
PDF
P6 Services: How to install, configure, tips and troubleshooting
Oracle OpenWorld 2015
Plan and Execute the Right Projects— Easily and Affordably
What's New In Primavera P6 EPPM 17.1
Oracle Primavera Unifier What's New in Release 16.2
Oracle What's New In Primavera P6 16.2
What's New in Primavera Gateway 16.1
20160405 How to Install Primavera P6 16.1 Professional desktop
Oracle Primavera P6 16.1 Announced
Oracle Primavera Unifier 16.1
P6 Release 8 Application Considerations Overview
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
P6 Release 8 Installation Orientation
Oracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 Release Content Document (RCD)
Oracle Support Accreditation – Level 1 Study Guide
Oracle Primavera Support Accreditation Study Guide
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) ...
Primavera Oracle Cloud Market Place
P6 Services: How to install, configure, tips and troubleshooting

Recently uploaded (20)

PDF
Nidhal Samdaie CV - International Business Consultant
PDF
Laughter Yoga Basic Learning Workshop Manual
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PPTX
HR Introduction Slide (1).pptx on hr intro
PDF
Unit 1 Cost Accounting - Cost sheet
PDF
Deliverable file - Regulatory guideline analysis.pdf
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PPTX
Lecture (1)-Introduction.pptx business communication
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PDF
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PDF
MSPs in 10 Words - Created by US MSP Network
PPTX
5 Stages of group development guide.pptx
PPTX
Amazon (Business Studies) management studies
PDF
Types of control:Qualitative vs Quantitative
PDF
Dr. Enrique Segura Ense Group - A Self-Made Entrepreneur And Executive
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
Nidhal Samdaie CV - International Business Consultant
Laughter Yoga Basic Learning Workshop Manual
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
DOC-20250806-WA0002._20250806_112011_0000.pdf
HR Introduction Slide (1).pptx on hr intro
Unit 1 Cost Accounting - Cost sheet
Deliverable file - Regulatory guideline analysis.pdf
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
ICG2025_ICG 6th steering committee 30-8-24.pptx
Lecture (1)-Introduction.pptx business communication
Belch_12e_PPT_Ch18_Accessible_university.pptx
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
MSPs in 10 Words - Created by US MSP Network
5 Stages of group development guide.pptx
Amazon (Business Studies) management studies
Types of control:Qualitative vs Quantitative
Dr. Enrique Segura Ense Group - A Self-Made Entrepreneur And Executive
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry

Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Collaborate 14

  • 1. REMINDER Check in on the COLLABORATE mobile app Implementation Review: EPPM P6 8.x at a Major Utility Prepared by: Bill Hyde Director SUB3 Management, Inc. Aligning OPPM and SAP Interface Session ID#: 15473
  • 2. This is a divider slide title that can be two lines Implementation Review: Pepco Holding, Inc.
  • 3. Pepco Holding, Inc. ■  Service Area ▪  Delaware ▪  District of District of Columbia ▪  Maryland and ▪  New Jersey ■  Provides regulated electric service ▪  Atlantic City Electric ▪  Delmarva Power ▪  Pepco ■  Provides Natural Gas Service ■  Provides Energy Efficiency & Renewable Solutions
  • 4. Pepco Holding, Inc. Fun Facts ■  Incorporated: 2002 ■  Service Territory: ▪  8,340 sq miles / 13,421.9 km ▪  Customers: 2M ▪  Substations: 530+ ▪  Transmission Lines: —  3,500 miles / 5,632.7 km ▪  Distribution Lines: —  30,000 miles /48,280.3 km ■  Diverse geographic area
  • 5. Project Vision ■  Departments within the organization working in concert with one another utilizing centralized and linked databases to track comprehensive aspects of the capital projects throughout their lifecycle.
  • 6. Future  State   Current  State  /  Challenges   One  Project  data  repository  (Only  one  version   of  the  truth)   •  Department  &  Individual  repositories   •  Excel  for  Everything!     Transparency   What  is  the  true  resource  need?  Who  is   accountable?   •  SeEng  and  Enforcing  expectaFons  of  the   responsible  engineer   •  Using  the  tool  conFnuously  &  consistently   Capital  Budget  Steering  CommiJee   •  Eliminate  best  ‘PowerPoint’  wins   •  Ensure  proper  representaFon     •  Eliminates  5  year  Excel  spreadsheet   Projects  entered  into  PPM  @  concepFon  with   prioriFzaFon  criteria   •  Provides  rich  data  on  upcoming  projects     •  CollaboraFon  between  planning  &   engineering   •  EliminaFng  individual  data  repositories   Project  PorRolio  analyzed  monthly  (actual  &   forecast  spend),  target  financials  from  10K   report,  and  prioriFzaFon  cost/value  analysis   •  Paradigm  Shirt   •  Living  to  the  Target  Plan   Future State vs. Current State
  • 7. Future  State   Current  State  /  Challenges   Fully  loaded  schedules  exist  for  all  project  the   Project  PorRolio   •  Implement  WBS  consistently       •  Work  with  responsible  engineer   throughout  organizaFon   Update  schedules  consistently  and  regularly   to  drive  monthly  forecast     •  SeEng  and  Enforcing  expectaFons  of  the   responsible  engineer     Scope  Changes:  Must  be  approved  by  sponsor   &  routed  via  the  Capital  Budget  Steering   CommiJee  prior  to  any  changes   •  EliminaFng  individual/small  group   decision  making   •  Eliminate  Monday  Morning   Quarterbacking   Annual  budget  prepared  from  project   porRolio  which  is  acFvely  managed  to   financial  targets   •  Shi_ing  the  paradigm   •  AccepFng  there  is  a  beJer  way   Future State vs. Current State (cont’d)
  • 8. Previous State: Project Management Lifecycle
  • 9. Determine the Solution ■  Various Departments ▪  Identify areas of Improvements ▪  Work with ‘bundling’ individuals solutions for the ‘greater good’ ■  Utilize Existing IT systems ■  Process Impacts ▪  Cross functional mapping ▪  Data collection ■  Analysis of possible solutions ▪  Vendor presentations ▪  Hands on exercises with vendors ▪  References
  • 11. Implementation State: Project Management Lifecycle
  • 12. Reasons for Implementation State Solutions ■  P6 was already being used for schedules (versus SAP, MSP) ■  P6 was already was integrated with SAP ■  OPPM configuration ▪  Build to business requirements ▪  Adjust & made improvements on the fly ▪  Future enhancements ■  OPPM parallel workflows ▪  Align workflow to requirements ▪  Minimize time projects spent within a process ■  PPM -> P6 Bridge exists and configurable
  • 13. Integrated Solution ■  Four Phase Implementation Methodology ▪  Strategic Alignment ▪  Design ▪  Configure ▪  Implement ■  Strategic Alignment ▪  Align Proposal to true business need ▪  Received approval of modified approach ■  Design ▪  Project Definition to match SAP ▪  Enhanced Work Breakdown Structure ▪  Enhanced SAP->P6 Interface Design
  • 14. Integrated Solution ■  Configure ▪  Phase 1 —  Initiate Project —  Retrofitted In Flight Projects —  Tested Revised SAP->P6 Interface —  Configured flexible solution to allow for easy enhancements ▪  Phase 2 —  Populated System —  Analytics / Reporting ■  Implement ▪  JIT Training Workshops ▪  Rolling wave of projects ▪  Lesson Learned
  • 15. OPPM – Modules Implemented ■  Processes ■  Workflows ■  Investor Module ■  Scorecard Module ■  Forms Module
  • 16. OPPM System Processes ■  Project Initiation*(5) ■  Scope Change (1) ■  PM Coordination (4) ■  Standard Reporting (1) ■  Instructions, shortcuts and references provided within each process ■  * Tied to P6 EPPM 11 Processes +
  • 17. OPPM Workflows ■  Project Initiation (21) ■  Scope Change (13) ■  Instructions, shortcuts and references provided within each workflow ■  Provides individuals with their ‘to-do’ list 34 Workflows +
  • 18. OPPM Investor Module ■  Multi-dimensional view of project data ■  Investor Maps for financial data (3) ■  Color Coding to distinguish different aspects of the project The Capital Program
  • 19. OPPM Scorecard Module ■  40+ Scorecards ▪  Capital Program —  5 Year Capital Plan —  1 Year Capital Plan ▪  PJM Interconnection LLC (PJM) Reports —  Regional Transmission Organization in the United States ▪  Reliability Enhancement Plan ▪  Manage Portfolio Data Dynamically —  New Project Requests —  Project Scope Change Status —  Project Teams
  • 20. OPPM Forms ■  25+ Forms ■  Forms has several tabs (1 to 7) ■  Forms include: ▪  Admin ▪  Scope changes ▪  Project Initiation ▪  Project Prioritization ▪  Project Review ▪  Work Coordination
  • 21. P6 EPPM – Modules Implemented ■  Professional (Client) ■  EPPM - Web ■  Business Intelligence (BI) Reports ■  Primavera Analytics
  • 22. P6 Professional (Client) ■  Input: 5 Year Plan Stage Schedule
  • 23. P6 EPPM (Web) ■  Configurable on a global level or by an individual ■  Select Dashboard and select portlets will be on each ■  Role based profile to minimize Graphical User Interface (GUI) and keep job easy Dashboards
  • 24. P6 EPPM (Web) ■  Output: 5 Year Resource Plan Usage
  • 25. P6 Primavera Analytics ■  Highly Configurable reporting tool ■  Easy to use with minimal data clicks ■  Data is published to system twice a month The BIG Picture
  • 26. Lesson Learned – What went well ■  Admit a problem(s) needs to be addressed ■  Senior Management Support ■  Vision ■  Defined Scope ■  Stakeholder involvement ■  Dedicated, multi-disciplinary team ■  Current State / Future State Analysis ■  Embracing Change – the users
  • 27. Lesson Learned – Opportunities for Improvement ■  IT Resources, competing Projects ■  Some areas did not provide desired level of input during design stage ■  IT security measures provided some limitations implementing solutions full capabilities ■  Push back from process changes ‘be careful what you ask for’ ■  Changing strategies effected timeline ■  Keeping users happy - Rolling out additional features
  • 28. Thank You!.......Questions ■  Contact Info ▪  Bill Hyde ▪  whyde@sub3mgmt.com ▪  SUB3 Management Inc. —  www.sub3mgmt.com —  @SUB3MGMT ■  Sources and Thanks to Pepco Holdings, Inc. ▪  Kim Deeley, kim.deeley@pepcoholdings.com ▪  Pamela Zucaro, pamela.zucaro@pepcoholdings.com
  • 29. Please complete the session evaluation We appreciate your feedback and insight You may complete the session evaluation either on paper or online via the mobile app