Getting started with Microsoft Project 2010
Madou, 07th of March 2014
European
Commission
Contents
 Introduction
 The MS Project interface
 Basic steps to create a
project
 Let's practice!
 Recommendations
Getting started with Microsoft Project 2010
European
Commission
MS Project overview: Strengths
 Microsoft Project is a project management software program,
developed and sold by Microsoft, which is designed to assist a
project manager in developing a plan, assigning resources to tasks,
tracking progress, managing the budget, and analysing workloads.
 The first commercial version of Project was released for DOS in
1984
 The most widely used PM program because:
 It is fairly generic in its approach
 Highly automated once configured. Requires relatively low amount of user
manipulation
 Scalable – can be used for small to enormous projects
 Balances visual approach (charts, graphs, etc) with logical structured approach
(task and resources lists)
Getting started with Microsoft Project 2010
European
Commission
Initiating
• Set the project goal
• Identify the necessary start or finish date limitations
• Identify the project manager
• Identify budget and quality considerations
• Enter project tasks, duration and relationships
• Identify project milestones
• Define available resources and costs
• Assign resources to tasks
• Producing work results
• Requesting changes
• Recommending improvements
• Creating project records, reports, and presentations
• Updating project
• Managing resources and tasks
• Meet management timing, resource, and cost objectives
• Identify budget and quality considerations
• Review and analyze performance of the project
• Create a Closure Report
• Archive records
Planning
Executing
Controlling
Closing
Project
Management:
process of initiating,
planning, executing,
controlling, and
closing a project
MS Project overview: PM steps
Getting started with Microsoft Project 2010
European
Commission
Contents
 Introduction
 The MS Project interface
 Basic steps to create a
project
 Let's practice!
 Recommendations
Getting started with Microsoft Project 2010
European
Commission
The MS Project interface
The Quick Access Toolbar (File, Task, Resource,
Project, View, Developer, Format)
The Ribbon (tabs, buttons and drop-down list)
Main Screen components
 Indicators column with message icons
 Status bar with messages
 Screen divider, to separate spreadsheet from timescale
 View buttons
 Zoom slider
Getting started with Microsoft Project 2010
European
Commission
The MS Project interface
Getting started with Microsoft Project 2010
European
Commission
The MS Project interface
Getting started with Microsoft Project 2010
Single view versus combination view (example)
European
Commission
The MS Project interface
Getting started with Microsoft Project 2010
Change the timescale in a view 1. In the View
group select
Timescale
2. In the
Timescale
dialog box,
click the Top
Tier, Middle
Tier, or
Bottom Tier
tab.
3. In the Units box,
select the time unit that
you want to use. (e.g.
Years)
4. In the Label list, select
the label format that
you want to use to
display the time unit.
5. In the Count box,
type or select a
number to specify the
frequency of unit
labels on the
timescale tier.
To focus on a specific time period or group of tasks, use the zoom slider in the
status bar at the bottom of the screen.
European
Commission
Contents
 Introduction
 The MS Project interface
 Basic steps to create a
project
 Let's practice!
 Recommendations
Getting started with Microsoft Project 2010
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Find critical path
Close Project
Getting started with Microsoft Project 2010
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Start a new project: Start or Finish date
 By default, the new project file is scheduled from a
Project Start Date
 All tasks are scheduled to begin as soon as possible
 Project 2010 calculates the project’s Finish date based on Tasks,
Durations,Dependencies.
 When a project is scheduled from a Finish date, such as
a conference, all tasks are scheduled to begin as late as
possible
 To schedule from a Finish Date, apply this setting as soon as the
project is created
Getting started with Microsoft Project 2010
European
Commission
Start a new project: from a Start date
Getting started with Microsoft Project 2010
1. Click on Project
Information
button
2. Enter the start
date of your
project
This is a description
of the costraint on
this project
This allows you to
choose between
forward scheduling
(Project Start date)
and backward
scheduling (Project
Finish date)
European
Commission
Start a new project: from a Finish date
Getting started with Microsoft Project 2010
European
Commission
Create a project: Customize standard calendar
 By default, the entire project, each task, and each resource is
scheduled according to the Standard calendar.
 The Standard calendar specifies that Monday through Friday
are working days with 8 hours of work completed each
day. Saturday and Sunday are designated as nonworking
days.
 The Calendar can be modified to identify holidays or other
nonworking days or times in which work should not be
scheduled.
 You can also create unique calendars for tasks and resources
that do not follow the working and nonworking times specified
by the Standard calendar.
Getting started with Microsoft Project 2010
European
Commission
Create a project: Customize standard calendar
Getting started with Microsoft Project 2010
Select
Exceptions Tab
Add Holiday as
exceptions
Nonworking holiday
will be showed on
the Calendar
To customize the standard calendar click on Change
Working Time on the Ribbon Project.
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Create a project: Entering tasks and durations
 Entering tasks and durations is probably the single
most important effort in developing a useful project file.
 If tasks are omitted or durations underestimated, the
value of the project’s scheduling and cost information is
compromised.
 Often you will need to change an existing task or insert,
delete, split or move a task. Project 2010 offers a
variety of tools that you can use to accomplish these
common tasks.
Getting started with Microsoft Project 2010
European
Commission
Create a project: insert, delete, inactivate tasks
Getting started with Microsoft Project 2010
Right‐click
shortcut
menus task
European
Commission
Create a project: entering recurring tasks
 A recurring task is a task that repeats at a regular
interval (i.e. status meeting )
 In Project 2010, you can define a recurring task one
time using the Recurring Task Information dialog box
from the task menu.
 Project 2010 then handles the details of scheduling
the task at specified interval for the entire project or
for the time period you specify.
Getting started with Microsoft Project 2010
European
Commission
Create a project: entering recurring tasks
Getting started with Microsoft Project 2010
European
Commission
Create a project: entering milestones
 A milestone is a task that marks a significant point in
time or a progress checkpoint.
 It has a zero duration and is therefore a symbolic task
that is used mainly to communicate progress or to
mark the end of a significant phase of the project.
Examples include the signing of a contract or the
announcement of a new product.
 Milestones can also be used to motivate project
participants by recognizing accomplishments.
Getting started with Microsoft Project 2010
European
Commission
Create a project: entering milestones
Getting started with Microsoft Project 2010
European
Commission
Create a project: attaching documents to tasks
Getting started with Microsoft Project 2010
1. Double click on the
task name to open the
Task Information
Dialog Box
2. In the Notes tab, click
on Insert Object
button
3. Select Create from
File, then Browse and
locate your file and
Insert
4. Turn on Link check box, if you want
that the icon will be linked to the file. In
this way changes to the attached file
will be reflected in your project.
European
Commission
Create a project: display information about tasks
Getting started with Microsoft Project 2010
2. Select
Indicators
1. Click on Add
New Column
3. Drag the
column to a
new location
Useful information and alerts related to tasks and resources can be displayed
showing the Indicators Column.
European
Commission
Create a project: display information about tasks
Getting started with Microsoft Project 2010
4. Indicators column displays:
• Miscellaneous indicators
• Constraint indicators
• Task type indicators
• Dependency indicators
European
Commission
Create a project: add a deadline
Getting started with Microsoft Project 2010
1. Double click on the
task name to open the
Task Information
Dialog Box
2. In the Advanced tab,
click on Deadline
Menu and define date
If you know that your task has a deadline one common mistake is to put inflexible
constraint -> must finish on Why? Because you are telling MS PROJECT that this
task MUST finish on that date and NOT BEFORE!
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Create a project: WBS with Summary Tasks
 A very important strategy for managing projects well is
to organize the work that needs to be done in a logical
manner, a Work Breakdown Structure (WBS) can be
an example.
 In order to use a WBS in Project 2010, you must
organize tasks into Summary tasks (groups of tasks
that logically belong together).
Getting started with Microsoft Project 2010
European
Commission
Create a project: WBS with Summary Tasks
 When developing a new, large project, some project
managers prefer to start with broad groupings of summary
tasks and then break them down into smaller tasks. This is
called the top‐down method of creating a WBS.
 Other project managers prefer to list all of the individual
tasks, and then collect them into logical groupings using
the bottom‐up method.
 Once you have identified your summary tasks, you use
Outdenting and Indenting in Project 2010 to create the
summary tasks.
Getting started with Microsoft Project 2010
European
Commission
Create a project: WBS with Summary Tasks
Getting started with Microsoft Project 2010
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Create a project: entering tasks dependencies
 Create relationships between tasks: task dependencies.
Four task dependencies define the relationships
between tasks in MS Project.
Getting started with Microsoft Project 2010
European
Commission
Create a project: entering tasks dependencies
Getting started with Microsoft Project 2010
1. Double click on the
task name to open the
Task Information
Dialog Box
2. Click on the
Predecessors tab
3. Chose the
Predecessor and the
Constrain type
4. In the Lag field, type
the Lag time (positive
or negative)
Lag time is a delay between two tasks that are linked by a dependency.
European
Commission
Create a project: entering tasks dependencies
Getting started with Microsoft Project 2010
Create task dependencies using the predecessors column.
2. Select
Predecessors
1. Click on Add
New Column
3. Digit the ID of the
task you want to
link.
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Assign resources to tasks
 One of the most important but often overlooked parts of the
project management process is allocating resources properly.
 In 4 steps you can allocate resources in Microsoft Project and
keep you in control of your project from start to finish.
1. Consider resource availability when estimating task
duration.
2. Create and organize a resource pool for the project
3. Assign each work task to a resource
4. Check the resource allocation in the resource graph view
Getting started with Microsoft Project 2010
European
Commission
1. Consider resource availability when estimating
task duration
 This step is crucial but often overlooked. Resources
must be considered during the construction of the
schedule, not just afterwards.
 Pay special attention to concurrent tasks (those that
happen at the same time) that use the same
resources
 Focus on man-hours rather than total workdays, to
take into account how many resources will be needed
Getting started with Microsoft Project 2010
European
Commission
2. Create and organize a resource pool for the project
 On the View menu, click Resource
Sheet
 On the Resource menu, click Add
Resources
 Define which kind of resource you
need:
• "Work" resources are the most
useful, and should be used to
categorize
• "Material" resources should refer
to materials that get used up
during work,
• "Cost" resources are time
independent resources (like
Airplane tickets)
Getting started with Microsoft Project 2010
European
Commission
3. Assign a resource to each work task
 Find the task's line in the left panel, and click the cell in the
"Resource" column. A drop-down menu will appear listing all the
resources you have created. Select the appropriate resource.
Getting started with Microsoft Project 2010
European
Commission
4. Check the resource allocation in the resource
graph view
 After creating your schedule and assigning resources, you
can check for over-allocation (click on "View" and select
"Resource Graph")
 Any point at which a resource exceeds 100 percent usage
represents an over-allocation (meaning the resource can't
possibly perform all the tasks assigned to it in the given
time). Over-allocation is represented in red.
 To remedy this, increase the task durations, assign more
resources to the tasks, or shift concurrent tasks to create
less overlap.
Getting started with Microsoft Project 2010
European
Commission
4. Check the resource allocation in the resource
graph view
 On the contrary, any point at which the resource is being used
very little may point to inefficient under-allocation. Consider
decreasing the task durations or using fewer total resources.
 The Resource Graph shows
allocation over time, resource
by resource.
 When the vertical bar is higher
than the horizontal line and
part of the bar is bright red, the
resource is overallocated.
Getting started with Microsoft Project 2010
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Find critical path
 Critical path: the series of critical tasks that dictates the
calculated finish date of the project in Project path.
 Critical tasks: the tasks that cannot be delayed without
affecting the project finish date. A task becomes critical
when it meets any one of the following conditions:
 It has no slack.
 It has a Must Start On (MSO) or Must Finish On (MFO) date
constraint.
 It has an As Late As Possible (ALAP) constraint in a project
scheduled from a start date.
 It has an As Soon As Possible (ASAP) constraint in a project
scheduled from a finish date.
Getting started with Microsoft Project 2010
European
Commission
Find critical path: viewing the slack
 Inserting the columns Total Slack, Free Slack and Critical you'll be able to see the
reason why a task is considered critical or not.
 The critical path calculation is also being influenced by relationships, constraints,
deadlines, resource assignments, and task, resource and project calendars.
Only you can determine if the critical path is correct!!
Total Slack
The amount of time a task's finish
date can be delayed without
delaying the project's finish date.
Free Slack
The amount of time than a task
can be delayed without delaying
any successor tasks.
If the task has no successors Free
Slack is the amount of time a task
can be delayed without delaying
the entire project's finish date.
Critical
When you apply the Critical
filter this column shows tasks
on critical path.
Getting started with Microsoft Project 2010
European
Commission
Find critical path: crash your project
 If you want to bring in the project finish date, you need to bring in the
dates of your critical path tasks. This is also known as crashing a
project.
 Crash: To decrease a project's overall duration without changing
task relationships. Crashing a project typically requires assigning
additional resources to tasks.
To crash a project you can:
 Shorten the duration or work on a task on the critical path.
 Change a task constraint to allow for more scheduling flexibility.
 Break a critical task into smaller tasks that can be worked on simultaneously by different
resources.
 Revise task dependencies to allow more scheduling flexibility.
 Set lead time between dependent tasks where applicable.
 Schedule overtime.
 Assign additional resources to work on critical path tasks.
Getting started with Microsoft Project 2010
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Close a project: key elements
Identify
Lesson learnt
• The end of a project is a great time to sit back and reflect on achievements and identify and
prepare to share what’s been learnt. Adopting an aura of constructive feedback, this can be
done in a ‘lessons learnt session’ with resources, stakeholders and management involved.
Review the
project
• There are several elements of the project that can be reviewed, but at least a Project
Closure Report should be created. This report will provide confirmation that the project has
met success criteria and can be used to request a sign-off from the sponsor to close the
project.
Archive project
records
• At least the following records should be archived:
 Project Plan
 Management Control Documents (Correspondence, Relevant meeting notes, Status reports)
 Technical documents
 Project Closure Report
Getting started with Microsoft Project 2010
European
Commission
Close a project: Print a view
Getting started with Microsoft Project 2010
European
Commission
Contents
 Introduction
 The MS Project interface
 Basic steps to create a
project
 Let's practise!
 Recommendations
Getting started with Microsoft Project 2010
European
Commission
Excercise 1/2
1. DRAFTING NEW REGULATION
1. 1 Assess new regulation
1.1.1 Create questionnaires
1.1.2 Send questionnaires (task starts when 1.1.1 finish)
1.1.3 Receive feedbacks (task starts when 1.1.2 finish)
1.1.4 Analyse questionnaires (task starts when 1.1.3 finish)
1.2 Verify impacts of new regulation (task starts when 1.1 finish)
1.3 Analyse impacts (task starts when 1.2 finish)
1.4 Create Report (task starts when 1.3 finish)
1.5 Propose Report to Parliament and Council (Task starts when 1.4
finish, and finishes 1/04/2016. Set as a deadline!)
Getting started with Microsoft Project 2010
 Create a project starting the 1st of February 2014 and ending on
the 1st of April 2016
 Add "Commission Easter holidays" to the Calendar (17th and 18th
of April)
 Create the following tasks and subtasks. Add dependencies.
European
Commission
 Add a "Weekly Team meeting"
recurring every Wednesday
until the end of the project
 Attach a document to the first
meeting
 Create a resource pool with
your names
 Assign resources to tasks
 Set the timescale to view the
entire project in the Gantt
Chart
Excercise 2/2
Getting started with Microsoft Project 2010
European
Commission
Contents
 Introduction
 The MS Project interface
 Basic steps to create a
project
 Let's practice!
 Recommendations
Getting started with Microsoft Project 2010
European
Commission
Recommendations
 Know the project goal before beginning
 Know the required tasks before beginning
 Identify resources before beginning
 Identify task relationships before beginning
 Refer to the tutorial as often as needed
 Refer to help section as often as needed
 Keep the configuration as simple as possible
 Avoid losing touch with the project
Getting started with Microsoft Project 2010
European
Commission
Recommendations
 MS Project is only a tool – it does not create or
“own” the project – it reflects the data provided
 The simpler the configuration, the easier the
data will be to understand, for all involved
 If the plan doesn’t look right, it probably isn’t!
 Check resource and task assignments/relationships
 Check constraints and dependencies
 Look for what has changed in the plan and follow the clues -
a small unintentional change can compromise the entire
project
Getting started with Microsoft Project 2010
European
Commission
Useful links
 Getting started with Project 2010
(Microsoft Office online training
video)
 Support on Project 2010
(Microsoft Office Support page)
 Finding answers, sharing ideas
and solving problems related to
Project 2010 (Microsoft
Community)
 Microsoft Project 2010 – 1
(Course material from Georgia
Technology Authority)
Getting started with Microsoft Project 2010
Monica Di Bratto

More Related Content

PDF
Master MSProject 2010
DOCX
Project Management Quick Reference Guide for Microsoft Project 2007
PPT
Using Microsoft Project 2003
PDF
Microsoft project 2003
PPTX
Primavera vs Microsoft project
PPSX
MS Project 2010 Training
PDF
MS Project Integration: Tips, Tricks and What's New for You
PPSX
Project network scheduling and S-curve
Master MSProject 2010
Project Management Quick Reference Guide for Microsoft Project 2007
Using Microsoft Project 2003
Microsoft project 2003
Primavera vs Microsoft project
MS Project 2010 Training
MS Project Integration: Tips, Tricks and What's New for You
Project network scheduling and S-curve

What's hot (20)

PDF
Primavera - Tutorial
PDF
PPTX
MS Project Presentation
PPT
Project Planning Basics - Everything you need to start managing a project
PDF
Primavera P6 manual
PDF
Building Formulas And Dashboard In Ms Project
PPSX
How to Create S Curve by MS Project 2013
PPTX
Primavera Project Management P6 Course session 5
PDF
Project charter and plan document for millennium upgrade
PDF
Primavera P6 Notes for Beginners
DOCX
Project manager project-plan-template-cm
PDF
Cmgt 410 cmgt410
PDF
204460 create s curve reports
PPTX
Primavara
PDF
Project Plan template
PPT
PM Session 4
PPT
Is5540 course review
PPT
Chap 4 Defining A Project
PPTX
Project Management using MS Project 2010
PDF
Online primavera p6 advanced topics training
Primavera - Tutorial
MS Project Presentation
Project Planning Basics - Everything you need to start managing a project
Primavera P6 manual
Building Formulas And Dashboard In Ms Project
How to Create S Curve by MS Project 2013
Primavera Project Management P6 Course session 5
Project charter and plan document for millennium upgrade
Primavera P6 Notes for Beginners
Project manager project-plan-template-cm
Cmgt 410 cmgt410
204460 create s curve reports
Primavara
Project Plan template
PM Session 4
Is5540 course review
Chap 4 Defining A Project
Project Management using MS Project 2010
Online primavera p6 advanced topics training
Ad

Viewers also liked (20)

PDF
Microsoft project 2010 (final)
PPTX
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
PDF
Project management by MS Project 2010
PPTX
PPS
MS Project Svcs Productivity
PDF
Ms Project 2010
PPTX
MS Project
PDF
Ms project training ver 01
PDF
Ms project lectures
PPTX
PPTX
Ms project 2016 overview
PPT
Microsoft project 2010
PDF
Practical Use of Microsoft Project for Project Managers
PDF
PDF
Civil engineering objective 3
PDF
Microsoft Projects; a step by-step guide for beginner's
PDF
Introduction to content curation
PPTX
Duration - The Holy Grail of MS Project?
DOCX
نموذج للامتحان
PPTX
MS Project 2010 Getting Started
Microsoft project 2010 (final)
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project management by MS Project 2010
MS Project Svcs Productivity
Ms Project 2010
MS Project
Ms project training ver 01
Ms project lectures
Ms project 2016 overview
Microsoft project 2010
Practical Use of Microsoft Project for Project Managers
Civil engineering objective 3
Microsoft Projects; a step by-step guide for beginner's
Introduction to content curation
Duration - The Holy Grail of MS Project?
نموذج للامتحان
MS Project 2010 Getting Started
Ad

Similar to Getting started with MS Project 2010 (20)

PDF
Ms project 2000 tutorial
PPTX
Mastering Microsoft Project_ A Comprehensive Guide.pptx
DOCX
Before doing assignment read it.txtAssignment -1 - Read Micros.docx
PPTX
2eee22222w811-Microsoft-Project-2016.pptx
PPTX
44259126 ms-project-presentation
PPTX
Ms project presentation
DOCX
Franchise Agreement Analysis Paper Guidelines and Grading Guide.docx
PPTX
Sharing Knowledge Microsoft Project 2013.pptx
PDF
class-notes-5-tutorial-ms-project-28042025-101858am.pdf
PPTX
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
DOCX
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
PDF
Ms project 2010 tutorial 2
PPTX
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
PPT
Software Project Management lecture 9
PDF
ms-project-2016-overview-160216021349.pdf
PPTX
dokumen.tips_ms-project-presentation.pptx
PPTX
ms-project-presentation.pptx
PPTX
It's not a bug, it's a feature!
PPT
Project management teaching
PPT
MS Project is uese for engineering studnet which will be useful
Ms project 2000 tutorial
Mastering Microsoft Project_ A Comprehensive Guide.pptx
Before doing assignment read it.txtAssignment -1 - Read Micros.docx
2eee22222w811-Microsoft-Project-2016.pptx
44259126 ms-project-presentation
Ms project presentation
Franchise Agreement Analysis Paper Guidelines and Grading Guide.docx
Sharing Knowledge Microsoft Project 2013.pptx
class-notes-5-tutorial-ms-project-28042025-101858am.pdf
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
Ms project 2010 tutorial 2
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
Software Project Management lecture 9
ms-project-2016-overview-160216021349.pdf
dokumen.tips_ms-project-presentation.pptx
ms-project-presentation.pptx
It's not a bug, it's a feature!
Project management teaching
MS Project is uese for engineering studnet which will be useful

Recently uploaded (20)

PDF
medical staffing services at VALiNTRY
PDF
2025 Textile ERP Trends: SAP, Odoo & Oracle
PDF
Design an Analysis of Algorithms I-SECS-1021-03
PDF
How to Choose the Right IT Partner for Your Business in Malaysia
PDF
Digital Strategies for Manufacturing Companies
PPTX
CHAPTER 2 - PM Management and IT Context
PDF
Softaken Excel to vCard Converter Software.pdf
PDF
SAP S4 Hana Brochure 3 (PTS SYSTEMS AND SOLUTIONS)
PDF
PTS Company Brochure 2025 (1).pdf.......
PDF
Internet Downloader Manager (IDM) Crack 6.42 Build 41
PPTX
Lecture 3: Operating Systems Introduction to Computer Hardware Systems
PDF
How Creative Agencies Leverage Project Management Software.pdf
PDF
Which alternative to Crystal Reports is best for small or large businesses.pdf
PDF
Upgrade and Innovation Strategies for SAP ERP Customers
PDF
Claude Code: Everyone is a 10x Developer - A Comprehensive AI-Powered CLI Tool
PDF
Addressing The Cult of Project Management Tools-Why Disconnected Work is Hold...
PPTX
Agentic AI Use Case- Contract Lifecycle Management (CLM).pptx
PDF
top salesforce developer skills in 2025.pdf
PDF
Flood Susceptibility Mapping Using Image-Based 2D-CNN Deep Learnin. Overview ...
PDF
How to Migrate SBCGlobal Email to Yahoo Easily
medical staffing services at VALiNTRY
2025 Textile ERP Trends: SAP, Odoo & Oracle
Design an Analysis of Algorithms I-SECS-1021-03
How to Choose the Right IT Partner for Your Business in Malaysia
Digital Strategies for Manufacturing Companies
CHAPTER 2 - PM Management and IT Context
Softaken Excel to vCard Converter Software.pdf
SAP S4 Hana Brochure 3 (PTS SYSTEMS AND SOLUTIONS)
PTS Company Brochure 2025 (1).pdf.......
Internet Downloader Manager (IDM) Crack 6.42 Build 41
Lecture 3: Operating Systems Introduction to Computer Hardware Systems
How Creative Agencies Leverage Project Management Software.pdf
Which alternative to Crystal Reports is best for small or large businesses.pdf
Upgrade and Innovation Strategies for SAP ERP Customers
Claude Code: Everyone is a 10x Developer - A Comprehensive AI-Powered CLI Tool
Addressing The Cult of Project Management Tools-Why Disconnected Work is Hold...
Agentic AI Use Case- Contract Lifecycle Management (CLM).pptx
top salesforce developer skills in 2025.pdf
Flood Susceptibility Mapping Using Image-Based 2D-CNN Deep Learnin. Overview ...
How to Migrate SBCGlobal Email to Yahoo Easily

Getting started with MS Project 2010

  • 1. Getting started with Microsoft Project 2010 Madou, 07th of March 2014
  • 2. European Commission Contents  Introduction  The MS Project interface  Basic steps to create a project  Let's practice!  Recommendations Getting started with Microsoft Project 2010
  • 3. European Commission MS Project overview: Strengths  Microsoft Project is a project management software program, developed and sold by Microsoft, which is designed to assist a project manager in developing a plan, assigning resources to tasks, tracking progress, managing the budget, and analysing workloads.  The first commercial version of Project was released for DOS in 1984  The most widely used PM program because:  It is fairly generic in its approach  Highly automated once configured. Requires relatively low amount of user manipulation  Scalable – can be used for small to enormous projects  Balances visual approach (charts, graphs, etc) with logical structured approach (task and resources lists) Getting started with Microsoft Project 2010
  • 4. European Commission Initiating • Set the project goal • Identify the necessary start or finish date limitations • Identify the project manager • Identify budget and quality considerations • Enter project tasks, duration and relationships • Identify project milestones • Define available resources and costs • Assign resources to tasks • Producing work results • Requesting changes • Recommending improvements • Creating project records, reports, and presentations • Updating project • Managing resources and tasks • Meet management timing, resource, and cost objectives • Identify budget and quality considerations • Review and analyze performance of the project • Create a Closure Report • Archive records Planning Executing Controlling Closing Project Management: process of initiating, planning, executing, controlling, and closing a project MS Project overview: PM steps Getting started with Microsoft Project 2010
  • 5. European Commission Contents  Introduction  The MS Project interface  Basic steps to create a project  Let's practice!  Recommendations Getting started with Microsoft Project 2010
  • 6. European Commission The MS Project interface The Quick Access Toolbar (File, Task, Resource, Project, View, Developer, Format) The Ribbon (tabs, buttons and drop-down list) Main Screen components  Indicators column with message icons  Status bar with messages  Screen divider, to separate spreadsheet from timescale  View buttons  Zoom slider Getting started with Microsoft Project 2010
  • 7. European Commission The MS Project interface Getting started with Microsoft Project 2010
  • 8. European Commission The MS Project interface Getting started with Microsoft Project 2010 Single view versus combination view (example)
  • 9. European Commission The MS Project interface Getting started with Microsoft Project 2010 Change the timescale in a view 1. In the View group select Timescale 2. In the Timescale dialog box, click the Top Tier, Middle Tier, or Bottom Tier tab. 3. In the Units box, select the time unit that you want to use. (e.g. Years) 4. In the Label list, select the label format that you want to use to display the time unit. 5. In the Count box, type or select a number to specify the frequency of unit labels on the timescale tier. To focus on a specific time period or group of tasks, use the zoom slider in the status bar at the bottom of the screen.
  • 10. European Commission Contents  Introduction  The MS Project interface  Basic steps to create a project  Let's practice!  Recommendations Getting started with Microsoft Project 2010
  • 11. European Commission Create a project: basic steps Start a new project from a Start or Finish date Add tasks, recurring tasks and milestones Creating WBS with Summary Tasks Create dependencies Assign resources Find critical path Close Project Getting started with Microsoft Project 2010
  • 12. European Commission Create a project: basic steps Start a new project from a Start or Finish date Add tasks, recurring tasks and milestones Creating WBS with Summary Tasks Create dependencies Assign resources Close Project Find critical path Getting started with Microsoft Project 2010
  • 13. European Commission Start a new project: Start or Finish date  By default, the new project file is scheduled from a Project Start Date  All tasks are scheduled to begin as soon as possible  Project 2010 calculates the project’s Finish date based on Tasks, Durations,Dependencies.  When a project is scheduled from a Finish date, such as a conference, all tasks are scheduled to begin as late as possible  To schedule from a Finish Date, apply this setting as soon as the project is created Getting started with Microsoft Project 2010
  • 14. European Commission Start a new project: from a Start date Getting started with Microsoft Project 2010 1. Click on Project Information button 2. Enter the start date of your project This is a description of the costraint on this project This allows you to choose between forward scheduling (Project Start date) and backward scheduling (Project Finish date)
  • 15. European Commission Start a new project: from a Finish date Getting started with Microsoft Project 2010
  • 16. European Commission Create a project: Customize standard calendar  By default, the entire project, each task, and each resource is scheduled according to the Standard calendar.  The Standard calendar specifies that Monday through Friday are working days with 8 hours of work completed each day. Saturday and Sunday are designated as nonworking days.  The Calendar can be modified to identify holidays or other nonworking days or times in which work should not be scheduled.  You can also create unique calendars for tasks and resources that do not follow the working and nonworking times specified by the Standard calendar. Getting started with Microsoft Project 2010
  • 17. European Commission Create a project: Customize standard calendar Getting started with Microsoft Project 2010 Select Exceptions Tab Add Holiday as exceptions Nonworking holiday will be showed on the Calendar To customize the standard calendar click on Change Working Time on the Ribbon Project.
  • 18. European Commission Create a project: basic steps Start a new project from a Start or Finish date Add tasks, recurring tasks and milestones Creating WBS with Summary Tasks Create dependencies Assign resources Close Project Find critical path Getting started with Microsoft Project 2010
  • 19. European Commission Create a project: Entering tasks and durations  Entering tasks and durations is probably the single most important effort in developing a useful project file.  If tasks are omitted or durations underestimated, the value of the project’s scheduling and cost information is compromised.  Often you will need to change an existing task or insert, delete, split or move a task. Project 2010 offers a variety of tools that you can use to accomplish these common tasks. Getting started with Microsoft Project 2010
  • 20. European Commission Create a project: insert, delete, inactivate tasks Getting started with Microsoft Project 2010 Right‐click shortcut menus task
  • 21. European Commission Create a project: entering recurring tasks  A recurring task is a task that repeats at a regular interval (i.e. status meeting )  In Project 2010, you can define a recurring task one time using the Recurring Task Information dialog box from the task menu.  Project 2010 then handles the details of scheduling the task at specified interval for the entire project or for the time period you specify. Getting started with Microsoft Project 2010
  • 22. European Commission Create a project: entering recurring tasks Getting started with Microsoft Project 2010
  • 23. European Commission Create a project: entering milestones  A milestone is a task that marks a significant point in time or a progress checkpoint.  It has a zero duration and is therefore a symbolic task that is used mainly to communicate progress or to mark the end of a significant phase of the project. Examples include the signing of a contract or the announcement of a new product.  Milestones can also be used to motivate project participants by recognizing accomplishments. Getting started with Microsoft Project 2010
  • 24. European Commission Create a project: entering milestones Getting started with Microsoft Project 2010
  • 25. European Commission Create a project: attaching documents to tasks Getting started with Microsoft Project 2010 1. Double click on the task name to open the Task Information Dialog Box 2. In the Notes tab, click on Insert Object button 3. Select Create from File, then Browse and locate your file and Insert 4. Turn on Link check box, if you want that the icon will be linked to the file. In this way changes to the attached file will be reflected in your project.
  • 26. European Commission Create a project: display information about tasks Getting started with Microsoft Project 2010 2. Select Indicators 1. Click on Add New Column 3. Drag the column to a new location Useful information and alerts related to tasks and resources can be displayed showing the Indicators Column.
  • 27. European Commission Create a project: display information about tasks Getting started with Microsoft Project 2010 4. Indicators column displays: • Miscellaneous indicators • Constraint indicators • Task type indicators • Dependency indicators
  • 28. European Commission Create a project: add a deadline Getting started with Microsoft Project 2010 1. Double click on the task name to open the Task Information Dialog Box 2. In the Advanced tab, click on Deadline Menu and define date If you know that your task has a deadline one common mistake is to put inflexible constraint -> must finish on Why? Because you are telling MS PROJECT that this task MUST finish on that date and NOT BEFORE!
  • 29. European Commission Create a project: basic steps Start a new project from a Start or Finish date Add tasks, recurring tasks and milestones Creating WBS with Summary Tasks Create dependencies Assign resources Close Project Find critical path Getting started with Microsoft Project 2010
  • 30. European Commission Create a project: WBS with Summary Tasks  A very important strategy for managing projects well is to organize the work that needs to be done in a logical manner, a Work Breakdown Structure (WBS) can be an example.  In order to use a WBS in Project 2010, you must organize tasks into Summary tasks (groups of tasks that logically belong together). Getting started with Microsoft Project 2010
  • 31. European Commission Create a project: WBS with Summary Tasks  When developing a new, large project, some project managers prefer to start with broad groupings of summary tasks and then break them down into smaller tasks. This is called the top‐down method of creating a WBS.  Other project managers prefer to list all of the individual tasks, and then collect them into logical groupings using the bottom‐up method.  Once you have identified your summary tasks, you use Outdenting and Indenting in Project 2010 to create the summary tasks. Getting started with Microsoft Project 2010
  • 32. European Commission Create a project: WBS with Summary Tasks Getting started with Microsoft Project 2010
  • 33. European Commission Create a project: basic steps Start a new project from a Start or Finish date Add tasks, recurring tasks and milestones Creating WBS with Summary Tasks Create dependencies Assign resources Close Project Find critical path Getting started with Microsoft Project 2010
  • 34. European Commission Create a project: entering tasks dependencies  Create relationships between tasks: task dependencies. Four task dependencies define the relationships between tasks in MS Project. Getting started with Microsoft Project 2010
  • 35. European Commission Create a project: entering tasks dependencies Getting started with Microsoft Project 2010 1. Double click on the task name to open the Task Information Dialog Box 2. Click on the Predecessors tab 3. Chose the Predecessor and the Constrain type 4. In the Lag field, type the Lag time (positive or negative) Lag time is a delay between two tasks that are linked by a dependency.
  • 36. European Commission Create a project: entering tasks dependencies Getting started with Microsoft Project 2010 Create task dependencies using the predecessors column. 2. Select Predecessors 1. Click on Add New Column 3. Digit the ID of the task you want to link.
  • 37. European Commission Create a project: basic steps Start a new project from a Start or Finish date Add tasks, recurring tasks and milestones Creating WBS with Summary Tasks Create dependencies Assign resources Close Project Find critical path Getting started with Microsoft Project 2010
  • 38. European Commission Assign resources to tasks  One of the most important but often overlooked parts of the project management process is allocating resources properly.  In 4 steps you can allocate resources in Microsoft Project and keep you in control of your project from start to finish. 1. Consider resource availability when estimating task duration. 2. Create and organize a resource pool for the project 3. Assign each work task to a resource 4. Check the resource allocation in the resource graph view Getting started with Microsoft Project 2010
  • 39. European Commission 1. Consider resource availability when estimating task duration  This step is crucial but often overlooked. Resources must be considered during the construction of the schedule, not just afterwards.  Pay special attention to concurrent tasks (those that happen at the same time) that use the same resources  Focus on man-hours rather than total workdays, to take into account how many resources will be needed Getting started with Microsoft Project 2010
  • 40. European Commission 2. Create and organize a resource pool for the project  On the View menu, click Resource Sheet  On the Resource menu, click Add Resources  Define which kind of resource you need: • "Work" resources are the most useful, and should be used to categorize • "Material" resources should refer to materials that get used up during work, • "Cost" resources are time independent resources (like Airplane tickets) Getting started with Microsoft Project 2010
  • 41. European Commission 3. Assign a resource to each work task  Find the task's line in the left panel, and click the cell in the "Resource" column. A drop-down menu will appear listing all the resources you have created. Select the appropriate resource. Getting started with Microsoft Project 2010
  • 42. European Commission 4. Check the resource allocation in the resource graph view  After creating your schedule and assigning resources, you can check for over-allocation (click on "View" and select "Resource Graph")  Any point at which a resource exceeds 100 percent usage represents an over-allocation (meaning the resource can't possibly perform all the tasks assigned to it in the given time). Over-allocation is represented in red.  To remedy this, increase the task durations, assign more resources to the tasks, or shift concurrent tasks to create less overlap. Getting started with Microsoft Project 2010
  • 43. European Commission 4. Check the resource allocation in the resource graph view  On the contrary, any point at which the resource is being used very little may point to inefficient under-allocation. Consider decreasing the task durations or using fewer total resources.  The Resource Graph shows allocation over time, resource by resource.  When the vertical bar is higher than the horizontal line and part of the bar is bright red, the resource is overallocated. Getting started with Microsoft Project 2010
  • 44. European Commission Create a project: basic steps Start a new project from a Start or Finish date Add tasks, recurring tasks and milestones Creating WBS with Summary Tasks Create dependencies Assign resources Close Project Find critical path Getting started with Microsoft Project 2010
  • 45. European Commission Find critical path  Critical path: the series of critical tasks that dictates the calculated finish date of the project in Project path.  Critical tasks: the tasks that cannot be delayed without affecting the project finish date. A task becomes critical when it meets any one of the following conditions:  It has no slack.  It has a Must Start On (MSO) or Must Finish On (MFO) date constraint.  It has an As Late As Possible (ALAP) constraint in a project scheduled from a start date.  It has an As Soon As Possible (ASAP) constraint in a project scheduled from a finish date. Getting started with Microsoft Project 2010
  • 46. European Commission Find critical path: viewing the slack  Inserting the columns Total Slack, Free Slack and Critical you'll be able to see the reason why a task is considered critical or not.  The critical path calculation is also being influenced by relationships, constraints, deadlines, resource assignments, and task, resource and project calendars. Only you can determine if the critical path is correct!! Total Slack The amount of time a task's finish date can be delayed without delaying the project's finish date. Free Slack The amount of time than a task can be delayed without delaying any successor tasks. If the task has no successors Free Slack is the amount of time a task can be delayed without delaying the entire project's finish date. Critical When you apply the Critical filter this column shows tasks on critical path. Getting started with Microsoft Project 2010
  • 47. European Commission Find critical path: crash your project  If you want to bring in the project finish date, you need to bring in the dates of your critical path tasks. This is also known as crashing a project.  Crash: To decrease a project's overall duration without changing task relationships. Crashing a project typically requires assigning additional resources to tasks. To crash a project you can:  Shorten the duration or work on a task on the critical path.  Change a task constraint to allow for more scheduling flexibility.  Break a critical task into smaller tasks that can be worked on simultaneously by different resources.  Revise task dependencies to allow more scheduling flexibility.  Set lead time between dependent tasks where applicable.  Schedule overtime.  Assign additional resources to work on critical path tasks. Getting started with Microsoft Project 2010
  • 48. European Commission Create a project: basic steps Start a new project from a Start or Finish date Add tasks, recurring tasks and milestones Creating WBS with Summary Tasks Create dependencies Assign resources Close Project Find critical path Getting started with Microsoft Project 2010
  • 49. European Commission Close a project: key elements Identify Lesson learnt • The end of a project is a great time to sit back and reflect on achievements and identify and prepare to share what’s been learnt. Adopting an aura of constructive feedback, this can be done in a ‘lessons learnt session’ with resources, stakeholders and management involved. Review the project • There are several elements of the project that can be reviewed, but at least a Project Closure Report should be created. This report will provide confirmation that the project has met success criteria and can be used to request a sign-off from the sponsor to close the project. Archive project records • At least the following records should be archived:  Project Plan  Management Control Documents (Correspondence, Relevant meeting notes, Status reports)  Technical documents  Project Closure Report Getting started with Microsoft Project 2010
  • 50. European Commission Close a project: Print a view Getting started with Microsoft Project 2010
  • 51. European Commission Contents  Introduction  The MS Project interface  Basic steps to create a project  Let's practise!  Recommendations Getting started with Microsoft Project 2010
  • 52. European Commission Excercise 1/2 1. DRAFTING NEW REGULATION 1. 1 Assess new regulation 1.1.1 Create questionnaires 1.1.2 Send questionnaires (task starts when 1.1.1 finish) 1.1.3 Receive feedbacks (task starts when 1.1.2 finish) 1.1.4 Analyse questionnaires (task starts when 1.1.3 finish) 1.2 Verify impacts of new regulation (task starts when 1.1 finish) 1.3 Analyse impacts (task starts when 1.2 finish) 1.4 Create Report (task starts when 1.3 finish) 1.5 Propose Report to Parliament and Council (Task starts when 1.4 finish, and finishes 1/04/2016. Set as a deadline!) Getting started with Microsoft Project 2010  Create a project starting the 1st of February 2014 and ending on the 1st of April 2016  Add "Commission Easter holidays" to the Calendar (17th and 18th of April)  Create the following tasks and subtasks. Add dependencies.
  • 53. European Commission  Add a "Weekly Team meeting" recurring every Wednesday until the end of the project  Attach a document to the first meeting  Create a resource pool with your names  Assign resources to tasks  Set the timescale to view the entire project in the Gantt Chart Excercise 2/2 Getting started with Microsoft Project 2010
  • 54. European Commission Contents  Introduction  The MS Project interface  Basic steps to create a project  Let's practice!  Recommendations Getting started with Microsoft Project 2010
  • 55. European Commission Recommendations  Know the project goal before beginning  Know the required tasks before beginning  Identify resources before beginning  Identify task relationships before beginning  Refer to the tutorial as often as needed  Refer to help section as often as needed  Keep the configuration as simple as possible  Avoid losing touch with the project Getting started with Microsoft Project 2010
  • 56. European Commission Recommendations  MS Project is only a tool – it does not create or “own” the project – it reflects the data provided  The simpler the configuration, the easier the data will be to understand, for all involved  If the plan doesn’t look right, it probably isn’t!  Check resource and task assignments/relationships  Check constraints and dependencies  Look for what has changed in the plan and follow the clues - a small unintentional change can compromise the entire project Getting started with Microsoft Project 2010
  • 57. European Commission Useful links  Getting started with Project 2010 (Microsoft Office online training video)  Support on Project 2010 (Microsoft Office Support page)  Finding answers, sharing ideas and solving problems related to Project 2010 (Microsoft Community)  Microsoft Project 2010 – 1 (Course material from Georgia Technology Authority) Getting started with Microsoft Project 2010