SlideShare a Scribd company logo
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not
participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or
implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is
accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This
document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not
guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
PMP® Sample
Questions
This presentation will showcase free
sample PMP® questions that will help
and guide you in studying for your
PMP® exam
Find more free sample
questions when you visit
www.free-pm-exam-questions.com
and free.pm-exam-simulator.com
Your pharmaceutical drug manufacturing project is running late and you have
deadlines to meet on your project. You want to replace some of the inefficient
human resources with more talented human resources to finish the project on
time. What risk response strategy is being followed in this context?
a.Share
b.Accept
c.Transfer
d.Mitigate
Sample PMP® Exam Question
HINT: You are trying to reduce the
likelihood of the risk occurrence.
The correct answer is D
This is an example of Risk Mitigation. By
replacing the human resources you are
reducing the probability of the risk
Answer and Explanation
You are working at a steel manufacturing company as a project manager. There is
a department called Welding and Fabrication in your company. You are getting
ready to put together your project team and you want to see a hierarchical
representation of how many welders are working for your company in the Welding
and Fabrication Department. Which of the following illustrates this information?
a.Work Breakdown Structure
b.Organizational Breakdown Structure
c.RACI Chart
d.Resource Breakdown Structure
Sample PMP® Exam Question
HINT: A welder is a resource. The project manager wants
to see all welding resources in a hierarchical format.
The correct answer is D
A Resource Breakdown Structure is a
hierarchical structure of resources broken
down by resource category and resource type.
Answer and Explanation
You are the project manager for a large telecommunications project in Kenya,
which has an unstable economy. You cannot use common financial techniques
to predict the future costs of materials but you are required to provide an
estimate for each work package now so that the budget can be developed and
approved. What technique you can rely on to help you in this situation?
a.Expert Judgment
b.Reserve Analysis
c.Parametric Estimating
d.Analogous Estimating
Sample PMP® Exam Question
HINT: You have not executed any projects in Kenya
and you have no idea what future project costs may be.
The correct answer is B
Expert Judgment, Parametric Estimating, and
Analogous Estimating will not help you in this
situation of high uncertainty. To accommodate
the risk created by uncertainty, you must build
reserves into your estimates using Reserve
Analysis.
Answer and Explanation
You are currently planning your project and identifying various project risks.
One of the project tasks is new and unique. Neither you nor your company has
ever carried out such a task. Which of the following information gathering
technique is suitable for conclusively identifying risks associated with this new
task?
a.Delphi Technique
b.Brainstorming
c.Expert Judgment
d.Interviewing
Sample PMP® Exam Question
HINT: Neither you nor your company have any sort of
experience in carrying out similar activities. Consider choices A
and C since they involve subject matter experts. However, only
one is the best answer.
The correct answer is A
You can consider both Delphi Technique and Expert
Judgment as a good answer for this question.
However, the Delphi Technique is the better option
because the question asked you to conclusively
identify the risks. Expert Judgment will only give you
a list or risks as identified by one or more experts
without discussion. On the other hand, the Delphi
Technique is designed to result in a peer reviewed
list, which indicates a consensus among the
experts.
Answer and Explanation
Which of the following estimating techniques is generally less costly
and less time-consuming?
a.Parametric Estimating
b.Analogous Estimating
c.Reserve Analysis
d.Bottom-Up Estimating
Sample PMP® Exam Question
HINT: Which technique will you rely on for
developing a quick but rough estimate?
The correct answer is B
Analogous Estimating is generally less costly and
less time-consuming than other techniques but it is
also generally less accurate. Analogous duration
estimates can be applied to a total project or to
segments of a project and may be used in
conjunction with other estimating methods.
Analogous Estimating is most reliable when the
previous activities are similar in fact and not just in
appearance, and the project team members
preparing the estimates have the necessary expert
judgment.
Answer and Explanation

More Related Content

PPTX
PMP Sample Questions Set 5
PPTX
PMP Exam Sample Questions Set 6
PPT
PMP Exam Sample Questions Set 8
PPTX
PMP Exam Sample Questions Set 1
PDF
PMP Five Sample Questions - 3
PDF
PMP Sample Questions Set3
PDF
PMP Sample Questions Set 5
PDF
PMP Exam Sample Questions
PMP Sample Questions Set 5
PMP Exam Sample Questions Set 6
PMP Exam Sample Questions Set 8
PMP Exam Sample Questions Set 1
PMP Five Sample Questions - 3
PMP Sample Questions Set3
PMP Sample Questions Set 5
PMP Exam Sample Questions

What's hot (18)

PDF
PMP Sample Questions Set 3
PPTX
PMP Exam Sample Questions Set 4
PDF
Pmp sample questions
PDF
PMP Exam Sample Questions
PDF
PMP Exam Sample Questions
PDF
PMP Exam Sample Questions
PDF
PMP Exam Sample Questions
PDF
Free PMP Sample Q & A
PDF
Free PMP Sample Q & A
PDF
PMP® Sample Questions 5
PDF
PMP Five Sample Questions
PDF
PMP® Sample Questions 6
PDF
Free PMP Sample Q & A
PDF
Free PMP Sample Q & A
PDF
Pmp sample questions set2
PDF
PMP Exam Sample Questions
PDF
Free PMP Sample Q & A
PDF
PMP® Sample Questions Set #2
PMP Sample Questions Set 3
PMP Exam Sample Questions Set 4
Pmp sample questions
PMP Exam Sample Questions
PMP Exam Sample Questions
PMP Exam Sample Questions
PMP Exam Sample Questions
Free PMP Sample Q & A
Free PMP Sample Q & A
PMP® Sample Questions 5
PMP Five Sample Questions
PMP® Sample Questions 6
Free PMP Sample Q & A
Free PMP Sample Q & A
Pmp sample questions set2
PMP Exam Sample Questions
Free PMP Sample Q & A
PMP® Sample Questions Set #2
Ad

Viewers also liked (11)

PDF
PMP® Sample Questions 3
PPTX
PMP Exam Q&A
PPTX
PMP Sample Questions Set 2
PDF
Sample PMP Exam Questions
PDF
PMP 1600 Questions by TechFAQ360
PDF
PMP Exam Sample Questions 4
PDF
175 PMP Sample Questions
PDF
PMP Exam Sample Questions 9
PDF
PMP® Sample Questions and Answers
PDF
PMP® Sample Questions
PDF
The ITTO Memory Jogger
PMP® Sample Questions 3
PMP Exam Q&A
PMP Sample Questions Set 2
Sample PMP Exam Questions
PMP 1600 Questions by TechFAQ360
PMP Exam Sample Questions 4
175 PMP Sample Questions
PMP Exam Sample Questions 9
PMP® Sample Questions and Answers
PMP® Sample Questions
The ITTO Memory Jogger
Ad

Similar to PMP Exam Sample Questions Set 7 (11)

PDF
Pmp Five Sample Questions
PDF
Session 5 Everything You Should Know About PMP & CAPM Certifications
PDF
Free PMP Exam Sample Question of the Week
PDF
Excellent Learning Guide on Pega Decisioning Consultant (PCDC) Certification
PDF
50 secrets-of-the-pmp-exam-white-paper
PDF
Free PMP Exam Sample Question
PDF
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
PDF
50 secrets-of-the-pmp-exam-white-paper
PDF
50 secrets-of-the-pmp-exam-white-paper
Pmp Five Sample Questions
Session 5 Everything You Should Know About PMP & CAPM Certifications
Free PMP Exam Sample Question of the Week
Excellent Learning Guide on Pega Decisioning Consultant (PCDC) Certification
50 secrets-of-the-pmp-exam-white-paper
Free PMP Exam Sample Question
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
50 secrets-of-the-pmp-exam-white-paper
50 secrets-of-the-pmp-exam-white-paper

More from OSP International LLC (20)

PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week

Recently uploaded (20)

PDF
Classroom Observation Tools for Teachers
PDF
01-Introduction-to-Information-Management.pdf
PDF
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PPTX
Pharma ospi slides which help in ospi learning
PDF
Pre independence Education in Inndia.pdf
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PPTX
PPH.pptx obstetrics and gynecology in nursing
PPTX
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
PDF
102 student loan defaulters named and shamed – Is someone you know on the list?
PPTX
Introduction to Child Health Nursing – Unit I | Child Health Nursing I | B.Sc...
PDF
VCE English Exam - Section C Student Revision Booklet
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PPTX
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
PDF
Complications of Minimal Access Surgery at WLH
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PPTX
Cell Types and Its function , kingdom of life
Classroom Observation Tools for Teachers
01-Introduction-to-Information-Management.pdf
FourierSeries-QuestionsWithAnswers(Part-A).pdf
Pharma ospi slides which help in ospi learning
Pre independence Education in Inndia.pdf
Abdominal Access Techniques with Prof. Dr. R K Mishra
PPH.pptx obstetrics and gynecology in nursing
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
102 student loan defaulters named and shamed – Is someone you know on the list?
Introduction to Child Health Nursing – Unit I | Child Health Nursing I | B.Sc...
VCE English Exam - Section C Student Revision Booklet
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
Supply Chain Operations Speaking Notes -ICLT Program
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
Complications of Minimal Access Surgery at WLH
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
Renaissance Architecture: A Journey from Faith to Humanism
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Cell Types and Its function , kingdom of life

PMP Exam Sample Questions Set 7

  • 1. PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC. PMP® Sample Questions
  • 2. This presentation will showcase free sample PMP® questions that will help and guide you in studying for your PMP® exam Find more free sample questions when you visit www.free-pm-exam-questions.com and free.pm-exam-simulator.com
  • 3. Your pharmaceutical drug manufacturing project is running late and you have deadlines to meet on your project. You want to replace some of the inefficient human resources with more talented human resources to finish the project on time. What risk response strategy is being followed in this context? a.Share b.Accept c.Transfer d.Mitigate Sample PMP® Exam Question HINT: You are trying to reduce the likelihood of the risk occurrence.
  • 4. The correct answer is D This is an example of Risk Mitigation. By replacing the human resources you are reducing the probability of the risk Answer and Explanation
  • 5. You are working at a steel manufacturing company as a project manager. There is a department called Welding and Fabrication in your company. You are getting ready to put together your project team and you want to see a hierarchical representation of how many welders are working for your company in the Welding and Fabrication Department. Which of the following illustrates this information? a.Work Breakdown Structure b.Organizational Breakdown Structure c.RACI Chart d.Resource Breakdown Structure Sample PMP® Exam Question HINT: A welder is a resource. The project manager wants to see all welding resources in a hierarchical format.
  • 6. The correct answer is D A Resource Breakdown Structure is a hierarchical structure of resources broken down by resource category and resource type. Answer and Explanation
  • 7. You are the project manager for a large telecommunications project in Kenya, which has an unstable economy. You cannot use common financial techniques to predict the future costs of materials but you are required to provide an estimate for each work package now so that the budget can be developed and approved. What technique you can rely on to help you in this situation? a.Expert Judgment b.Reserve Analysis c.Parametric Estimating d.Analogous Estimating Sample PMP® Exam Question HINT: You have not executed any projects in Kenya and you have no idea what future project costs may be.
  • 8. The correct answer is B Expert Judgment, Parametric Estimating, and Analogous Estimating will not help you in this situation of high uncertainty. To accommodate the risk created by uncertainty, you must build reserves into your estimates using Reserve Analysis. Answer and Explanation
  • 9. You are currently planning your project and identifying various project risks. One of the project tasks is new and unique. Neither you nor your company has ever carried out such a task. Which of the following information gathering technique is suitable for conclusively identifying risks associated with this new task? a.Delphi Technique b.Brainstorming c.Expert Judgment d.Interviewing Sample PMP® Exam Question HINT: Neither you nor your company have any sort of experience in carrying out similar activities. Consider choices A and C since they involve subject matter experts. However, only one is the best answer.
  • 10. The correct answer is A You can consider both Delphi Technique and Expert Judgment as a good answer for this question. However, the Delphi Technique is the better option because the question asked you to conclusively identify the risks. Expert Judgment will only give you a list or risks as identified by one or more experts without discussion. On the other hand, the Delphi Technique is designed to result in a peer reviewed list, which indicates a consensus among the experts. Answer and Explanation
  • 11. Which of the following estimating techniques is generally less costly and less time-consuming? a.Parametric Estimating b.Analogous Estimating c.Reserve Analysis d.Bottom-Up Estimating Sample PMP® Exam Question HINT: Which technique will you rely on for developing a quick but rough estimate?
  • 12. The correct answer is B Analogous Estimating is generally less costly and less time-consuming than other techniques but it is also generally less accurate. Analogous duration estimates can be applied to a total project or to segments of a project and may be used in conjunction with other estimating methods. Analogous Estimating is most reliable when the previous activities are similar in fact and not just in appearance, and the project team members preparing the estimates have the necessary expert judgment. Answer and Explanation