D is the correct answer.
(N*(N-1))/2
(10*(10 - 1)) / 2 = 45
How many communication channels will be
required in a project in which 10 individual are
participating?
A 46 days
B 9 Days
C 14 Days
D 45 Days
1
A is the correct answer.
PV = FV / ( 1 + r) ^ n
It is to calculate Present
Value
where FV equals the
future value of cash
flows, r equals the
interest rate, and n
equals the number of
time period
What is formula for The value of future cash flows
in today’s dollars.
A PV = FV / ( 1 + r) ^ n
B FV = PV / ( 1 + r) ^ n
C PV = FV / ( 1 + n) ^ r
D None of the Above
2
A is the correct answer.
You have 'Mitigated' the
risk - by having the
trainees trained you
have created a Risk
response strategy.
Should this team
member go on leave the
trainees would execute
the task.
As a manager on a project your key outlook is to ensure that the project delivers
within the scheduled timelines. For some time now the project work is
proceeding smoothly with a CPI and SPI a perfect 1. One of your team members
approaches you and indicates that she might possibly need a long vacation on
account of personal grounds. She indicates this could possibly occur in two
months from now. You look up the schedule and as luck would have it - this
team member happens to be scheduled to execute activities which are on the
critical path - and her absence in two months time would cause a delay in
schedule. You decide to take some action and ask the team member to start
regular knowledge transfers to a couple of trainees. Your thought is though the
trainees would be relatively inexperienced they would more than make up for it
with two people rather than one person to perform these tasks should this team
member need to go on leave. What did you just do
A Mitigate the Risk
B Avoid the Risk
C Transfer the Risk
D Accept the Risk
3
D is the correct answer.
All of the above are
stakeholders in a Project
Project Stakeholders are defined as:
A Individuals and organizations who use the project's product
B Individuals and organizations whose interest may be positively
or negatively affected as a result of project execution or
successful project completion
C Individuals and organizations who provide the financial
resources
D All of the above
4
A is the correct answer.
It is important that you
do not compromise
when working on a
conflict. Compromise
often leads to
polarization. So it is best
to be collaborative and
find a win-win situation
What is the best technique to handle a conflict?
A Collaborative
B Compromise
C Strategic
D All of the Above
5
A is the correct answer.
It is Project Manager
Who is responsible for the creation of the final project
plan?
A Project Manager
B Team Leader
C Sponsor
D Project Team
6
D is the correct answer.
Channels of
communication: Upward
communication
(vertically or diagonally):
For higher management
Downward
communication
(vertically or diagonally):
For higher management
Lateral communication
(horizontally): For peers
Which statement is true about Channels of
communication?
A Upward communication (vertically or diagonally): For higher
management
B Downward communication (vertically or diagonally): For higher
management
C Lateral communication (horizontally): For peers
D All of the above
7
D is the correct answer.
Note that choosing this
option entails paying up
a stiff penalty for delay
in deliveries - but a
Project manager must
always uphold the tenets
of Professional and
Social Responsibility
Your company had won a large project for setting up a chemical factory for your
client. It has been a tough and grueling year and the final delivery has been
shipped. It consists of the Core Reactor along with the agitator that was
designed and manufactured in your premises and is now shipped to the clients
site. The contract includes stiff penalties for a delay even by a single day. You
now received a call indicating that the local authorities have held up the reactor
outside the city limits. Certain additional documentation is required which
would delay the delivery of the reactor thereby incurring heavy penalties. Your
companies on site representative indicates that should the authorities be paid
some money the reactor would be released and would then reach on time. What
should you do ?
A Do nothing
B Plead with the authorities to release the consignment
C Pay the incentive to the authorities to release the consignment
D Provide the additional documentation which though would cause a delay in
deliveries and penalties - but do not pay an incentive
8
A is the correct answer.
The statement defines
IRR.
The rate of return after the external factors
affecting cash flow (for example, interest or
cost of capital, and inflation) have been
deducted is called as ________?
A Internal Rate of Return
B Interim Rate of Return
C International Rate of Return
D Now of the above
9
A is the correct answer.
Means task is
completed.
Zero Schedule Variance (SV) means the task
is ______.
A Completed
B Not Started
C Running Fine
D Wrongly Calculated
10
A is the correct answer.
The correct answer is
Scope Verification which
deals with verifying that
what was delivered was
what was required
As a manager on a project you have identified and
created the WBS and WBS Dictionary. You also plan to
ensure that each deliverable gets the blessings of your
stakeholders and sponsors. Which process are you
planning to perform?
A Scope Verification
B Perform Quality Control
C Control Scope
D Define Scope
11
B is the correct answer.
A work package is the
lowest level of a work
breakdown structure.
What is the lowest level in a work breakdown structure?
A Project task
B Work package
C SOW
D None
12
A is right answer
PMI discusses procurement
focusing on the buyer or seller
relationship
PMI discusses procurement focusing on the ______
relationship.
A Buyer or seller
B Vendor or seller
C Purchasing
D Selling
13
C is right answer
This is a tricky one - the
question is asking who is
responsible for the
Project charter
definition.The charter's
definition is always done
by the Business
stakeholders who
envision expenditure
and understand the
business value.
Who is responsible for the definition of the
Project Charter ?
A Project Manager
B The Project team
C Business Stakeholders
D PMO
14
A is correct answer.
It is called EVA (Economic
Value Add)
The profit earned by the organization after the cost of
capital has been subtracted is known as ___________
A Economic Value Add (EVA)
B Profit Ratio
C Project Profitability
D Cost Vs Profit analysis
15
A is correct answer.
All change requests are made
against a project plan that has
the project baseline.
Change requests are made against the
____________?
A Project baseline
B SOW
C Charter
D Executive summary
16
A is correct answer.
In the Direct and Manage
Project Work process,
approved changes are
implemented but monitoring
of those changes is part of
monitoring OR controlling
project work
Which of the following activity is not performed
as part of the Direct and Manage Project Work
process?
A Monitor implementation of approved changes
B Validate deliverables
C Staff, train, and manage the project team
D Manage risks and implement risk responses
17
A is correct answer.
This explains BCR (BENEFIT
COST RATIO)
What is the ratio that looks at the financially
quantifiable benefits expected from the project
and weighs them against the cost of achieving
those benefits. If the benefits outweigh the costs,
then the project can be given the go-ahead
A Benefit Cost Ratio
B IRR
C Cost Analysis
D Benefits Analysis
18
C is correct answer.
Determine Budget: Allocating
the value of the overall cost
estimate to individual work
items, in order to establish a
cost baseline for measuring
project performance
Allocating the value of the overall cost
estimate to individual work items, in order
to establish a cost baseline for measuring
project performance is called ______.
A Resource planning
B Estimate Costs
C Determine Budget
D Control Costs
19
A is correct answer.
This is an example of
Confronting - since you set up
a discussion and solve the
problem. By solving the
problem there is no
difference of opinion and
hence it is the best possible
way of conflict resolution
Your development lead and QA lead are into an altercation
regarding the quality of code deliverables. Both feel the fault lies at
the other end which is causing Bad quality. You decide to
understand the details and get into a meeting with both of them.
On subsequent discussion it becomes apparent that both the
development and qa teams do not have a sound understanding of
what is required. It turns out that the Requirements itself were not
clearly defined. This is an example of ?
A Confronting
B Smoothing
C Forcing
D Compromise
20
Pmp questions and answers series #3

More Related Content

PPTX
Pmp questions and answers series #2
PDF
03 pmp project management processes exam
PPTX
CAPM Study Session 2
PDF
13 pmp professional responsibility exam
PPTX
15 Free PMP Exam Questions
PDF
Pmp questions and answers series #2
03 pmp project management processes exam
CAPM Study Session 2
13 pmp professional responsibility exam
15 Free PMP Exam Questions

What's hot (19)

DOCX
PMP assessment exam 1.1
PPT
D04 Why6Sigma
PPTX
PMP Exam Sample Questions Set 1
PDF
PDF
PMI ACP Classroom Question Paper
PPTX
Profittme pmp framweork questions
PPTX
Project Management Process
PPT
PMP Exam Sample Questions Set 8
PDF
PMI-ACP Lesson 08 Nugget 1 Agile & Scrum Value-based Prioritization
PDF
Free pmp answers
PDF
PROJ 586 RANK Education Counseling--proj586rank.com
PDF
A Legal Checklist
PDF
The Role of Documentation & The Key to Labor Management
DOCX
Project managment (pm) solved assignments summer 2015
PDF
PROJ 586 RANK Achievement Education / proj586rank.com
DOCX
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
PDF
The 25/10 Concept - Improving the Probability of Success
PDF
PMI-ACP Lesson 11 Agile Value Stream Analysis
DOCX
PROJ 586 Entire Course NEW
PMP assessment exam 1.1
D04 Why6Sigma
PMP Exam Sample Questions Set 1
PMI ACP Classroom Question Paper
Profittme pmp framweork questions
Project Management Process
PMP Exam Sample Questions Set 8
PMI-ACP Lesson 08 Nugget 1 Agile & Scrum Value-based Prioritization
Free pmp answers
PROJ 586 RANK Education Counseling--proj586rank.com
A Legal Checklist
The Role of Documentation & The Key to Labor Management
Project managment (pm) solved assignments summer 2015
PROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
The 25/10 Concept - Improving the Probability of Success
PMI-ACP Lesson 11 Agile Value Stream Analysis
PROJ 586 Entire Course NEW
Ad

Similar to Pmp questions and answers series #3 (20)

PDF
Pmp Questions and Answers series #1
PDF
Pmp test 03
PDF
Pmp test 02
DOCX
Pmp full mock test – 200 questions
PDF
Pmp sample qa3
PDF
Full length mock test useful for PMP Exam folks
PDF
PMP 1600 Questions by TechFAQ360
PDF
Pmp test 05
PDF
Pmp test 01
DOCX
PMI-RMP a test mod 00
PDF
1440 pmp exam question bank
PDF
Pmp test 04
PDF
Risk 1 actual test 7 (273 q)
PDF
01 pmp introduct to project management exam
PDF
ipma-level-d-mcq-sample-paper.pdf
PDF
PMP-Prep-Exam-Test-200_Questions.pdf
PDF
07 pmp cost management exam
PDF
10 pmp communication management exam
PPTX
PMP Certificate- introduction
Pmp Questions and Answers series #1
Pmp test 03
Pmp test 02
Pmp full mock test – 200 questions
Pmp sample qa3
Full length mock test useful for PMP Exam folks
PMP 1600 Questions by TechFAQ360
Pmp test 05
Pmp test 01
PMI-RMP a test mod 00
1440 pmp exam question bank
Pmp test 04
Risk 1 actual test 7 (273 q)
01 pmp introduct to project management exam
ipma-level-d-mcq-sample-paper.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
07 pmp cost management exam
10 pmp communication management exam
PMP Certificate- introduction
Ad

More from Knowledge Max (10)

PPTX
Check sheets 7 tools of quality
PPTX
Hindustan Jindabaad - A Series of Positivity
PPTX
What is new in pmbok ver 6
ODP
0%gst rate items. complete list
PPTX
Jio phone market in shock
PPTX
Jio new offer - Is Joi Selling SIM Card by Force ?
PPTX
Karnataka separate flag is it right
ODP
Can china attack india
PPTX
Bihar political drama prefect planning and execution example
PPTX
Bihar maha gathabandhan - Failed Saga
Check sheets 7 tools of quality
Hindustan Jindabaad - A Series of Positivity
What is new in pmbok ver 6
0%gst rate items. complete list
Jio phone market in shock
Jio new offer - Is Joi Selling SIM Card by Force ?
Karnataka separate flag is it right
Can china attack india
Bihar political drama prefect planning and execution example
Bihar maha gathabandhan - Failed Saga

Recently uploaded (20)

PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PPTX
human mycosis Human fungal infections are called human mycosis..pptx
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PPTX
Institutional Correction lecture only . . .
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PPTX
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PDF
Complications of Minimal Access Surgery at WLH
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
Classroom Observation Tools for Teachers
PDF
Computing-Curriculum for Schools in Ghana
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PDF
Anesthesia in Laparoscopic Surgery in India
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PPTX
Pharma ospi slides which help in ospi learning
PDF
01-Introduction-to-Information-Management.pdf
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
human mycosis Human fungal infections are called human mycosis..pptx
Module 4: Burden of Disease Tutorial Slides S2 2025
202450812 BayCHI UCSC-SV 20250812 v17.pptx
Institutional Correction lecture only . . .
Microbial disease of the cardiovascular and lymphatic systems
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Final Presentation General Medicine 03-08-2024.pptx
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
Complications of Minimal Access Surgery at WLH
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Classroom Observation Tools for Teachers
Computing-Curriculum for Schools in Ghana
STATICS OF THE RIGID BODIES Hibbelers.pdf
Anesthesia in Laparoscopic Surgery in India
Microbial diseases, their pathogenesis and prophylaxis
Supply Chain Operations Speaking Notes -ICLT Program
Pharma ospi slides which help in ospi learning
01-Introduction-to-Information-Management.pdf

Pmp questions and answers series #3

  • 1. AMAN VATS PMP®  Program and Project Management Professional.  Techno-Functional Engineer, serving since 1987.  TESOL Certified Trainer.  Objective of Channel is to Unleash the Knowledge through Sharing. Project Management Technical Tips Current Affairs Health and Home Making BusinessVLOGSocial With Supporting Explanation
  • 2. D is the correct answer. (N*(N-1))/2 (10*(10 - 1)) / 2 = 45 How many communication channels will be required in a project in which 10 individual are participating? A 46 days B 9 Days C 14 Days D 45 Days 1
  • 3. A is the correct answer. PV = FV / ( 1 + r) ^ n It is to calculate Present Value where FV equals the future value of cash flows, r equals the interest rate, and n equals the number of time period What is formula for The value of future cash flows in today’s dollars. A PV = FV / ( 1 + r) ^ n B FV = PV / ( 1 + r) ^ n C PV = FV / ( 1 + n) ^ r D None of the Above 2
  • 4. A is the correct answer. You have 'Mitigated' the risk - by having the trainees trained you have created a Risk response strategy. Should this team member go on leave the trainees would execute the task. As a manager on a project your key outlook is to ensure that the project delivers within the scheduled timelines. For some time now the project work is proceeding smoothly with a CPI and SPI a perfect 1. One of your team members approaches you and indicates that she might possibly need a long vacation on account of personal grounds. She indicates this could possibly occur in two months from now. You look up the schedule and as luck would have it - this team member happens to be scheduled to execute activities which are on the critical path - and her absence in two months time would cause a delay in schedule. You decide to take some action and ask the team member to start regular knowledge transfers to a couple of trainees. Your thought is though the trainees would be relatively inexperienced they would more than make up for it with two people rather than one person to perform these tasks should this team member need to go on leave. What did you just do A Mitigate the Risk B Avoid the Risk C Transfer the Risk D Accept the Risk 3
  • 5. D is the correct answer. All of the above are stakeholders in a Project Project Stakeholders are defined as: A Individuals and organizations who use the project's product B Individuals and organizations whose interest may be positively or negatively affected as a result of project execution or successful project completion C Individuals and organizations who provide the financial resources D All of the above 4
  • 6. A is the correct answer. It is important that you do not compromise when working on a conflict. Compromise often leads to polarization. So it is best to be collaborative and find a win-win situation What is the best technique to handle a conflict? A Collaborative B Compromise C Strategic D All of the Above 5
  • 7. A is the correct answer. It is Project Manager Who is responsible for the creation of the final project plan? A Project Manager B Team Leader C Sponsor D Project Team 6
  • 8. D is the correct answer. Channels of communication: Upward communication (vertically or diagonally): For higher management Downward communication (vertically or diagonally): For higher management Lateral communication (horizontally): For peers Which statement is true about Channels of communication? A Upward communication (vertically or diagonally): For higher management B Downward communication (vertically or diagonally): For higher management C Lateral communication (horizontally): For peers D All of the above 7
  • 9. D is the correct answer. Note that choosing this option entails paying up a stiff penalty for delay in deliveries - but a Project manager must always uphold the tenets of Professional and Social Responsibility Your company had won a large project for setting up a chemical factory for your client. It has been a tough and grueling year and the final delivery has been shipped. It consists of the Core Reactor along with the agitator that was designed and manufactured in your premises and is now shipped to the clients site. The contract includes stiff penalties for a delay even by a single day. You now received a call indicating that the local authorities have held up the reactor outside the city limits. Certain additional documentation is required which would delay the delivery of the reactor thereby incurring heavy penalties. Your companies on site representative indicates that should the authorities be paid some money the reactor would be released and would then reach on time. What should you do ? A Do nothing B Plead with the authorities to release the consignment C Pay the incentive to the authorities to release the consignment D Provide the additional documentation which though would cause a delay in deliveries and penalties - but do not pay an incentive 8
  • 10. A is the correct answer. The statement defines IRR. The rate of return after the external factors affecting cash flow (for example, interest or cost of capital, and inflation) have been deducted is called as ________? A Internal Rate of Return B Interim Rate of Return C International Rate of Return D Now of the above 9
  • 11. A is the correct answer. Means task is completed. Zero Schedule Variance (SV) means the task is ______. A Completed B Not Started C Running Fine D Wrongly Calculated 10
  • 12. A is the correct answer. The correct answer is Scope Verification which deals with verifying that what was delivered was what was required As a manager on a project you have identified and created the WBS and WBS Dictionary. You also plan to ensure that each deliverable gets the blessings of your stakeholders and sponsors. Which process are you planning to perform? A Scope Verification B Perform Quality Control C Control Scope D Define Scope 11
  • 13. B is the correct answer. A work package is the lowest level of a work breakdown structure. What is the lowest level in a work breakdown structure? A Project task B Work package C SOW D None 12
  • 14. A is right answer PMI discusses procurement focusing on the buyer or seller relationship PMI discusses procurement focusing on the ______ relationship. A Buyer or seller B Vendor or seller C Purchasing D Selling 13
  • 15. C is right answer This is a tricky one - the question is asking who is responsible for the Project charter definition.The charter's definition is always done by the Business stakeholders who envision expenditure and understand the business value. Who is responsible for the definition of the Project Charter ? A Project Manager B The Project team C Business Stakeholders D PMO 14
  • 16. A is correct answer. It is called EVA (Economic Value Add) The profit earned by the organization after the cost of capital has been subtracted is known as ___________ A Economic Value Add (EVA) B Profit Ratio C Project Profitability D Cost Vs Profit analysis 15
  • 17. A is correct answer. All change requests are made against a project plan that has the project baseline. Change requests are made against the ____________? A Project baseline B SOW C Charter D Executive summary 16
  • 18. A is correct answer. In the Direct and Manage Project Work process, approved changes are implemented but monitoring of those changes is part of monitoring OR controlling project work Which of the following activity is not performed as part of the Direct and Manage Project Work process? A Monitor implementation of approved changes B Validate deliverables C Staff, train, and manage the project team D Manage risks and implement risk responses 17
  • 19. A is correct answer. This explains BCR (BENEFIT COST RATIO) What is the ratio that looks at the financially quantifiable benefits expected from the project and weighs them against the cost of achieving those benefits. If the benefits outweigh the costs, then the project can be given the go-ahead A Benefit Cost Ratio B IRR C Cost Analysis D Benefits Analysis 18
  • 20. C is correct answer. Determine Budget: Allocating the value of the overall cost estimate to individual work items, in order to establish a cost baseline for measuring project performance Allocating the value of the overall cost estimate to individual work items, in order to establish a cost baseline for measuring project performance is called ______. A Resource planning B Estimate Costs C Determine Budget D Control Costs 19
  • 21. A is correct answer. This is an example of Confronting - since you set up a discussion and solve the problem. By solving the problem there is no difference of opinion and hence it is the best possible way of conflict resolution Your development lead and QA lead are into an altercation regarding the quality of code deliverables. Both feel the fault lies at the other end which is causing Bad quality. You decide to understand the details and get into a meeting with both of them. On subsequent discussion it becomes apparent that both the development and qa teams do not have a sound understanding of what is required. It turns out that the Requirements itself were not clearly defined. This is an example of ? A Confronting B Smoothing C Forcing D Compromise 20