A is the correct answer.
output of Initiation
process :
Project charter
PM assigned
Constraints Assumptions
Project manager is
assigned to a project
During the initiation
stage
In which phase, project manager is assigned to a
project?
A Project Initiation
B After the project is proven feasible
C After Budget finalised
D After the project is kicked off
1
D is the correct answer.
Avoid, Mitigate, Transfer
are Risk response
strategies. Where as Risk
Register update is an
action
Out of below mentioned risk responses, which
Risk Response is/are correct except
A Avoid
B Mitigate
C Transfer
D Risk Register Update
2
C is the correct answer.
It is best to decline but
in a tactful manner
without hurting anyone’s
sentiments. So it is best
to decline citing
company policy which is
a fact as well.
One of the Supplier is offering a gift in an expected
favour. It is beyond the gifting limits set by your
Organization. What should you do?
A Just refuse to accept
B Reciprocate the supplier with same value gift
C Decline Politely citing organization’s Policies.
D No Harm – Accept and Enjoy
3
B is the correct answer.
Parametric Estimating
States:- Estimating the
basis for activity
durations can be
quantitatively
determined by
multiplying the quantity
of work to be performed
by the productivity rate.
Which time estimating tools estimate the basis for
activity durations can be quantitatively determined
by multiplying the quantity of work to be
performed by the productivity rate?
A Funding limit reconciliation
B Parametric estimating
C Reserves analysis
D No Such Tool Exists.
4
C is the correct answer.
The correct answer is 45.
N*(N-1)/2
10*(10-1)/2
= 45
With 6 people in your team , 2 sponsors within your
company and a client . All of these need to be
communicated with and kept informed about the project.
How many communication channels will be there?
A 81
B 36
C 45
D 72
5
C is the correct answer.
This is an example of
Para lingual form of
communication
You are hiring staff in your team. In an interview an
applicant was sarcastic in her response to one of
the questions. What form of communication is this
?
A Feedback
B Decoding
C Para Lingual
D Non Verbal
6
A is the correct answer.
The sender has to make
sure that the receiver
acknowledges the
receipt and message is
understood, and the
receiver needs to ensure
that the sender received
the acknowledgement
Who is responsibility for making sure that A
message in the project team is clearly understood?.
Whose responsibility is this to ensure?
A Sender
B Sponsor
C Project Manager
D Project Coordinator.
7
B is the correct answer.
These activities are
carried out under
reserve analysis. If any
new or amended reserve
amounts are identified,
the risk register needs to
be updated to reflect it,
and a change request
might need to be
documented and
assessed
A contingency reserve for the project might have been developed
during the process of developing the risk register and performing
quantitative risk analysis. If so, it was built up using information
and assumptions relevant at the time. An important part of
completing the monitoring and controlling work associated with
project risk management is to analyze whether the amounts
calculated to be included in the contingency reserve are still
accurate? What is this analysis called?
A Contingency Fund Analysis
B Reserve Analysis
C Budget Control
D Cost Variance
8
C is the correct answer.
The archiving system can
be either physical or
electronic (or both),
depending on the
specific organizational
policies on archiving and
the future needs for
retrieval.
An organization’s archives can be either physical
storage of hard copies of documents or an
electronic record of project documents and plans.
A Only Hard Copies
B Only Electronic Mode
C Either Physical or Electronic
D None of the above
9
D is the correct answer.
Inputting data into a
spreadsheet is not
communication tool.
Memos belongs to push
communication.
Web conferencing
belongs to interactive
communication
Which of the following are communication tools
Except?
A Memos-Minutes of Meetings
B Verbal Circulation
C Web Conferencing
D Data Update in Spreadsheet
10
B is the correct answer.
All team members are
brought together in one
location is an example of
strong matrix.
A Strong Matrix Organization type is ?
A A Balanced Matrix
B Where all team members are brought together in one location
C Where functional managers operate in a dual reporting structure reporting
to both their own departments and to the project manager
D Power reset with Functional Manager
11
C is the correct answer.
Cumulative frequency is
main word here.
Which of the following can be presented
using a Pareto chart?
A Duration estimation of activities based on best, most likely and worst
estimations
B The rate of critical defects (20%) against the rate of other defects (80%)
C The cumulative frequency of software defects detected in each testing
rounds
D The rate at which schedule is slipping.
12
A is right answer
EVM is the least relevant
in understanding the
status of project scope.
Least is the catch here
The project manager is about to leave and the new
appointed manager wants to get updated with the
status of the project scope. Which of the following
resources is the least relevant for this purpose?
A Latest Cumulative Earned Value reports
B Project’s Work Breakdown Structure (WBS)
C The list of change requests to the project scope
D The list of approved changes to the project scope
13
D is right answer
Since it T&M contract
there Budget at
completion or BAC is not
applicable as the overall
cost is not fixed. Others
will apply.
A project is carried out under a Time and Material
contract. Which of the following is irrelevant to this
project?
A SOW
B WBS
C RBS
D BAC
14
B is correct answer.
Incentive fee criteria must be
agreed upon and documented
in the contract.
Incentive fee is determined
by buyer and option a is
unlikely to happen,
C is risk to supplier and will
not be accepted ,
likewise D is risk to buyer
since cost escalation will
mean they will end up paying
more incentive .)
Which should be the basis for determining the Incentive
Fee, if decided at all to be paid, at the end of the project?
A It should be paid anyway, according to the percentage agreed
upon during final negotiation with the chosen bidder
B According to criteria agreed-upon in the contract
C Based on the subjective assessment made by the project
manager at the end of the project
D As a percentage of the final cost of simulator development
15
B is correct answer.
Risk Audits
______ can have two purposes. Its first purpose is to enable the
project manager to determine the effectiveness of the overall risk
management processes being used on the project. The second
purpose is to examine whether a planned risk response has been
effective in dealing with an identified risk. This is done to determine
whether risk responses need to be amended for future risks. Fill in
the blanks?
A Risk Response Plan
B Risk Audits
C Risk Breakdown Structure
D Risk Management Plan
16
A is correct answer.
B, C and D can be true.
Risk’s probability / impact can
increase or decrease
throughout the life of project,
Hence we must re-assess
risks.
Cannot is catch here
A risk whose probability was assessed as 0.75 at the
beginning of the project was reassessed towards final
delivery and project closing to be 0.25 now. What cannot
be said?
A Re-assessing a risk towards project end is meaningless
B It is likely that the probability reduced as a result of risk
mitigation activities
C It is possible that the probability reduced although no risk
mitigation activities were performed
D The probability reduced, but the risk could still be high.
17
A is correct answer.
In both Functional and
Projectized
In which of the following project organizations every
member of the project team has exactly one manager?
A In both Functional and Projectized
B In all kinds of Matrix organizations
C In both Functional and Weak-matrix
D In both Projectized and Strong-matrix
18
C is correct answer.
Rewarding employees where
it is due is always a good
thing which ensures
motivation and appreciation.
However that does not mean
that we should bend the
rules. A project manager must
always do the right thing and
giving a compensatory off is
against the company rules -
so that would be unethical.
You are managing a project which is building a software algorithm for managing the
traffic signals. The team has been working hard and extending over weekends to ensure
deliverables are completed as per schedule. The project has now completed and well
received by the client. Your team members approach you with a request for a couple of
compensatory offs considering the various weekends that they have put in extra effort.
However your company has no such compensatory off policy - what should you do ?
A Allow the employees compensatory off since they have really worked hard
B Decline the compensatory offs
C Decline the request as it is against company policies and work with your
senior management in the best way possible to reward the employees
D Escalate to senior management
19
D is correct answer.
All the options except
schedule variance are true
regarding scope verification.
Note that this process can
also be done at the end of
each project phase in the
project lifecycle. So the
correct answer to the
question is option D since
scope verification has nothing
to do with schedule variance
Which of the following statements is not true regarding Scope
Verification ?
A Consists of conducting inspections , reviews and audits.
B Used to determine if results conform to requirements
C Used to get formal sign off from clients
D Used to determine schedule variance
20
C is correct answer.
Projectized organization : The
project manager has total control
of projects. Personnel are
assigned and report to a project
manager.
Functional organization : Project
Manager has least power and all
management is taken care by
functional manager like Finance
and Account Managers.
Matrix organization : The team
members report to two bosses
the project manager and the
functional manager
You are the Project Managers of XYZ company. The Project team
members are from the finance and accounts. The team members
report to Finance and Account Managers respectively, and you
have limited control over them. What type of organizational
hierarchy does company follow?
A Matrix organization
B Projectized organization
C Functional organization
D None
21
A is correct answer.
Validate Scope is the process of
formally accepting the
deliverable of a project or phase.
Customer formally accepts the deliverables of each project phase.
This process is known as ________.
A Validate Scope
B Quality Assurance
C Quality Control
D Quality Measurement
22
A is correct answer.
inclusion mode: Has become part
of the business processes.
Project just went into inclusion mode. This means
that project __________.
A Has become part of the business processes
B Has been accepted by the sponsor and the client
C Will be closed due to lack of resources
D None of the above
23
A is correct answer.
Aware project and potential
impacts and actively engaged in
ensuring the project is a success..
Which of the below engagement level is true
about "Aware project and potential impacts and
actively engaged in ensuring the project is a
success"?
A Leading
B Neutral
C Supportive
D Resistant
24
C is correct answer.
Regression analysis and Learning Curve are
ways of creating a Parametric Estimate.
Regression analysis is also known as
Scatter Diagram.
Scatter diagrams consist of a graphical
representation of two variables from a
data set. They are used to detect the
correlation between the variables being
examined.
Learning curve takes into consideration
that if the nature of the work is repetitive -
the person will perform subsequent work
faster as efficiency improves.
Option A has nothing to do with
Parametric Estimates while Option D
though is an estimation technique - it uses
simulation and three time estimates
You need to provide estimates for activities on the
project. You and your team discuss and conclude that as
detailed information is not yet available - the best option
would be to use Parametric Estimates. The various ways
to create Parametric Estimates are:
A Critical Path Method
B One Time Estimate
C Regression Analysis and Learning Curve
D Monte Carlo Analysis
25
Pmp Questions and Answers series #1

More Related Content

PPTX
Pmp questions and answers series #2
PDF
Pmp test 02
PDF
Pmp test 04
PDF
Pmp test 03
PDF
Pmi sp questions with answers
PDF
Pmstudy exam 2
PDF
Pmstudy exam 4
Pmp questions and answers series #2
Pmp test 02
Pmp test 04
Pmp test 03
Pmi sp questions with answers
Pmstudy exam 2
Pmstudy exam 4

What's hot (19)

PDF
Risk 3 simplelearn-exam2-ans
PDF
Risk 5 simplelearn-exam4-ans
PDF
Pmstudy exam 3
PDF
11 pmp risk management exam
PDF
Pmp test 01
PPTX
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
PDF
04 pmp integration management exam
PDF
10 pmp communication management exam
DOCX
Pmp full mock test – 200 questions
PDF
Pmp sample questions
PDF
PMP 1600 Questions by TechFAQ360
PDF
Pmp test 05
PDF
Pmp questions and answers series #3
PDF
03 pmp project management processes exam
DOCX
Pmp exam q&a
PDF
Risk 9-pm study project risk management-test
PDF
Pmstudy exam_1
PDF
Risk 4 simplelearn-exam3-ans
PDF
01 pmp introduct to project management exam
Risk 3 simplelearn-exam2-ans
Risk 5 simplelearn-exam4-ans
Pmstudy exam 3
11 pmp risk management exam
Pmp test 01
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
04 pmp integration management exam
10 pmp communication management exam
Pmp full mock test – 200 questions
Pmp sample questions
PMP 1600 Questions by TechFAQ360
Pmp test 05
Pmp questions and answers series #3
03 pmp project management processes exam
Pmp exam q&a
Risk 9-pm study project risk management-test
Pmstudy exam_1
Risk 4 simplelearn-exam3-ans
01 pmp introduct to project management exam
Ad

Similar to Pmp Questions and Answers series #1 (20)

PDF
Pmp sample qa3
PDF
PMP Lite Mock Exam2.pdf
PDF
Full length mock test useful for PMP Exam folks
DOC
Project Management
PDF
Introduction to Project Management 2nd Edition Schwalbe Test Bank
DOCX
1. Which of the following is more reflective of managerial taska..docx
PDF
Mb0033 mb0049
PDF
Introduction to Project Management 2nd Edition Schwalbe Test Bank
DOCX
150013826 pmp-questions
DOCX
150013826 pmp-questions - copy (3)
DOCX
150013826 pmp-questions - copy (2)
DOCX
1.A cumulative effort curve for a project generally has an S-shap.docx
PDF
CAPM Exam Study Session 1
DOCX
Page 9Introduction to Project Management Principles and Practices.docx
DOCX
QuizTop of FormNote It is recommended that you save your resp.docx
DOCX
1. A key objective of change control in configuration management i.docx
PDF
Introduction to Project Management 2nd Edition Schwalbe Test Bank
PDF
Information Technology Project Management 3rd ed Edition Kathy Schwalbe
DOCX
Chapter 2 Questionsand Answers1. There is a difference between t.docx
DOCX
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Pmp sample qa3
PMP Lite Mock Exam2.pdf
Full length mock test useful for PMP Exam folks
Project Management
Introduction to Project Management 2nd Edition Schwalbe Test Bank
1. Which of the following is more reflective of managerial taska..docx
Mb0033 mb0049
Introduction to Project Management 2nd Edition Schwalbe Test Bank
150013826 pmp-questions
150013826 pmp-questions - copy (3)
150013826 pmp-questions - copy (2)
1.A cumulative effort curve for a project generally has an S-shap.docx
CAPM Exam Study Session 1
Page 9Introduction to Project Management Principles and Practices.docx
QuizTop of FormNote It is recommended that you save your resp.docx
1. A key objective of change control in configuration management i.docx
Introduction to Project Management 2nd Edition Schwalbe Test Bank
Information Technology Project Management 3rd ed Edition Kathy Schwalbe
Chapter 2 Questionsand Answers1. There is a difference between t.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Ad

More from Knowledge Max (10)

PPTX
Check sheets 7 tools of quality
PPTX
Hindustan Jindabaad - A Series of Positivity
PPTX
What is new in pmbok ver 6
ODP
0%gst rate items. complete list
PPTX
Jio phone market in shock
PPTX
Jio new offer - Is Joi Selling SIM Card by Force ?
PPTX
Karnataka separate flag is it right
ODP
Can china attack india
PPTX
Bihar political drama prefect planning and execution example
PPTX
Bihar maha gathabandhan - Failed Saga
Check sheets 7 tools of quality
Hindustan Jindabaad - A Series of Positivity
What is new in pmbok ver 6
0%gst rate items. complete list
Jio phone market in shock
Jio new offer - Is Joi Selling SIM Card by Force ?
Karnataka separate flag is it right
Can china attack india
Bihar political drama prefect planning and execution example
Bihar maha gathabandhan - Failed Saga

Recently uploaded (20)

PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
VCE English Exam - Section C Student Revision Booklet
PPTX
Cell Types and Its function , kingdom of life
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PDF
01-Introduction-to-Information-Management.pdf
PDF
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PDF
Classroom Observation Tools for Teachers
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
RMMM.pdf make it easy to upload and study
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PPTX
Pharma ospi slides which help in ospi learning
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PPTX
GDM (1) (1).pptx small presentation for students
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
Final Presentation General Medicine 03-08-2024.pptx
VCE English Exam - Section C Student Revision Booklet
Cell Types and Its function , kingdom of life
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
01-Introduction-to-Information-Management.pdf
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
O5-L3 Freight Transport Ops (International) V1.pdf
STATICS OF THE RIGID BODIES Hibbelers.pdf
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
Classroom Observation Tools for Teachers
Chinmaya Tiranga quiz Grand Finale.pdf
RMMM.pdf make it easy to upload and study
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
Supply Chain Operations Speaking Notes -ICLT Program
Pharma ospi slides which help in ospi learning
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
GDM (1) (1).pptx small presentation for students
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc

Pmp Questions and Answers series #1

  • 1. AMAN VATS PMP®  Program and Project Management Professional.  Techno-Functional Engineer, serving since 1987.  TESOL Certified Trainer.  Objective of Channel is to Unleash the Knowledge through Sharing. Project Management Technical Tips Current Affairs Health and Home Making BusinessVLOGSocial
  • 2. A is the correct answer. output of Initiation process : Project charter PM assigned Constraints Assumptions Project manager is assigned to a project During the initiation stage In which phase, project manager is assigned to a project? A Project Initiation B After the project is proven feasible C After Budget finalised D After the project is kicked off 1
  • 3. D is the correct answer. Avoid, Mitigate, Transfer are Risk response strategies. Where as Risk Register update is an action Out of below mentioned risk responses, which Risk Response is/are correct except A Avoid B Mitigate C Transfer D Risk Register Update 2
  • 4. C is the correct answer. It is best to decline but in a tactful manner without hurting anyone’s sentiments. So it is best to decline citing company policy which is a fact as well. One of the Supplier is offering a gift in an expected favour. It is beyond the gifting limits set by your Organization. What should you do? A Just refuse to accept B Reciprocate the supplier with same value gift C Decline Politely citing organization’s Policies. D No Harm – Accept and Enjoy 3
  • 5. B is the correct answer. Parametric Estimating States:- Estimating the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate. Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate? A Funding limit reconciliation B Parametric estimating C Reserves analysis D No Such Tool Exists. 4
  • 6. C is the correct answer. The correct answer is 45. N*(N-1)/2 10*(10-1)/2 = 45 With 6 people in your team , 2 sponsors within your company and a client . All of these need to be communicated with and kept informed about the project. How many communication channels will be there? A 81 B 36 C 45 D 72 5
  • 7. C is the correct answer. This is an example of Para lingual form of communication You are hiring staff in your team. In an interview an applicant was sarcastic in her response to one of the questions. What form of communication is this ? A Feedback B Decoding C Para Lingual D Non Verbal 6
  • 8. A is the correct answer. The sender has to make sure that the receiver acknowledges the receipt and message is understood, and the receiver needs to ensure that the sender received the acknowledgement Who is responsibility for making sure that A message in the project team is clearly understood?. Whose responsibility is this to ensure? A Sender B Sponsor C Project Manager D Project Coordinator. 7
  • 9. B is the correct answer. These activities are carried out under reserve analysis. If any new or amended reserve amounts are identified, the risk register needs to be updated to reflect it, and a change request might need to be documented and assessed A contingency reserve for the project might have been developed during the process of developing the risk register and performing quantitative risk analysis. If so, it was built up using information and assumptions relevant at the time. An important part of completing the monitoring and controlling work associated with project risk management is to analyze whether the amounts calculated to be included in the contingency reserve are still accurate? What is this analysis called? A Contingency Fund Analysis B Reserve Analysis C Budget Control D Cost Variance 8
  • 10. C is the correct answer. The archiving system can be either physical or electronic (or both), depending on the specific organizational policies on archiving and the future needs for retrieval. An organization’s archives can be either physical storage of hard copies of documents or an electronic record of project documents and plans. A Only Hard Copies B Only Electronic Mode C Either Physical or Electronic D None of the above 9
  • 11. D is the correct answer. Inputting data into a spreadsheet is not communication tool. Memos belongs to push communication. Web conferencing belongs to interactive communication Which of the following are communication tools Except? A Memos-Minutes of Meetings B Verbal Circulation C Web Conferencing D Data Update in Spreadsheet 10
  • 12. B is the correct answer. All team members are brought together in one location is an example of strong matrix. A Strong Matrix Organization type is ? A A Balanced Matrix B Where all team members are brought together in one location C Where functional managers operate in a dual reporting structure reporting to both their own departments and to the project manager D Power reset with Functional Manager 11
  • 13. C is the correct answer. Cumulative frequency is main word here. Which of the following can be presented using a Pareto chart? A Duration estimation of activities based on best, most likely and worst estimations B The rate of critical defects (20%) against the rate of other defects (80%) C The cumulative frequency of software defects detected in each testing rounds D The rate at which schedule is slipping. 12
  • 14. A is right answer EVM is the least relevant in understanding the status of project scope. Least is the catch here The project manager is about to leave and the new appointed manager wants to get updated with the status of the project scope. Which of the following resources is the least relevant for this purpose? A Latest Cumulative Earned Value reports B Project’s Work Breakdown Structure (WBS) C The list of change requests to the project scope D The list of approved changes to the project scope 13
  • 15. D is right answer Since it T&M contract there Budget at completion or BAC is not applicable as the overall cost is not fixed. Others will apply. A project is carried out under a Time and Material contract. Which of the following is irrelevant to this project? A SOW B WBS C RBS D BAC 14
  • 16. B is correct answer. Incentive fee criteria must be agreed upon and documented in the contract. Incentive fee is determined by buyer and option a is unlikely to happen, C is risk to supplier and will not be accepted , likewise D is risk to buyer since cost escalation will mean they will end up paying more incentive .) Which should be the basis for determining the Incentive Fee, if decided at all to be paid, at the end of the project? A It should be paid anyway, according to the percentage agreed upon during final negotiation with the chosen bidder B According to criteria agreed-upon in the contract C Based on the subjective assessment made by the project manager at the end of the project D As a percentage of the final cost of simulator development 15
  • 17. B is correct answer. Risk Audits ______ can have two purposes. Its first purpose is to enable the project manager to determine the effectiveness of the overall risk management processes being used on the project. The second purpose is to examine whether a planned risk response has been effective in dealing with an identified risk. This is done to determine whether risk responses need to be amended for future risks. Fill in the blanks? A Risk Response Plan B Risk Audits C Risk Breakdown Structure D Risk Management Plan 16
  • 18. A is correct answer. B, C and D can be true. Risk’s probability / impact can increase or decrease throughout the life of project, Hence we must re-assess risks. Cannot is catch here A risk whose probability was assessed as 0.75 at the beginning of the project was reassessed towards final delivery and project closing to be 0.25 now. What cannot be said? A Re-assessing a risk towards project end is meaningless B It is likely that the probability reduced as a result of risk mitigation activities C It is possible that the probability reduced although no risk mitigation activities were performed D The probability reduced, but the risk could still be high. 17
  • 19. A is correct answer. In both Functional and Projectized In which of the following project organizations every member of the project team has exactly one manager? A In both Functional and Projectized B In all kinds of Matrix organizations C In both Functional and Weak-matrix D In both Projectized and Strong-matrix 18
  • 20. C is correct answer. Rewarding employees where it is due is always a good thing which ensures motivation and appreciation. However that does not mean that we should bend the rules. A project manager must always do the right thing and giving a compensatory off is against the company rules - so that would be unethical. You are managing a project which is building a software algorithm for managing the traffic signals. The team has been working hard and extending over weekends to ensure deliverables are completed as per schedule. The project has now completed and well received by the client. Your team members approach you with a request for a couple of compensatory offs considering the various weekends that they have put in extra effort. However your company has no such compensatory off policy - what should you do ? A Allow the employees compensatory off since they have really worked hard B Decline the compensatory offs C Decline the request as it is against company policies and work with your senior management in the best way possible to reward the employees D Escalate to senior management 19
  • 21. D is correct answer. All the options except schedule variance are true regarding scope verification. Note that this process can also be done at the end of each project phase in the project lifecycle. So the correct answer to the question is option D since scope verification has nothing to do with schedule variance Which of the following statements is not true regarding Scope Verification ? A Consists of conducting inspections , reviews and audits. B Used to determine if results conform to requirements C Used to get formal sign off from clients D Used to determine schedule variance 20
  • 22. C is correct answer. Projectized organization : The project manager has total control of projects. Personnel are assigned and report to a project manager. Functional organization : Project Manager has least power and all management is taken care by functional manager like Finance and Account Managers. Matrix organization : The team members report to two bosses the project manager and the functional manager You are the Project Managers of XYZ company. The Project team members are from the finance and accounts. The team members report to Finance and Account Managers respectively, and you have limited control over them. What type of organizational hierarchy does company follow? A Matrix organization B Projectized organization C Functional organization D None 21
  • 23. A is correct answer. Validate Scope is the process of formally accepting the deliverable of a project or phase. Customer formally accepts the deliverables of each project phase. This process is known as ________. A Validate Scope B Quality Assurance C Quality Control D Quality Measurement 22
  • 24. A is correct answer. inclusion mode: Has become part of the business processes. Project just went into inclusion mode. This means that project __________. A Has become part of the business processes B Has been accepted by the sponsor and the client C Will be closed due to lack of resources D None of the above 23
  • 25. A is correct answer. Aware project and potential impacts and actively engaged in ensuring the project is a success.. Which of the below engagement level is true about "Aware project and potential impacts and actively engaged in ensuring the project is a success"? A Leading B Neutral C Supportive D Resistant 24
  • 26. C is correct answer. Regression analysis and Learning Curve are ways of creating a Parametric Estimate. Regression analysis is also known as Scatter Diagram. Scatter diagrams consist of a graphical representation of two variables from a data set. They are used to detect the correlation between the variables being examined. Learning curve takes into consideration that if the nature of the work is repetitive - the person will perform subsequent work faster as efficiency improves. Option A has nothing to do with Parametric Estimates while Option D though is an estimation technique - it uses simulation and three time estimates You need to provide estimates for activities on the project. You and your team discuss and conclude that as detailed information is not yet available - the best option would be to use Parametric Estimates. The various ways to create Parametric Estimates are: A Critical Path Method B One Time Estimate C Regression Analysis and Learning Curve D Monte Carlo Analysis 25