1. Joel is managing a project that is three fourths complete when additional work is requested. The change control board has approved the change. The immediate course of action should be to update the scope and schedule baselines to reflect the approved change before implementing it.
2. A software development project implemented a code review checklist after issues were found in the air tunnel modelling module. This is an example of corrective action rather than preventive action.
3. Network diagrams are used to show interdependencies of activities and depict the workflow so the sequence is known, but they do not determine risks and causes of issues as they occur.