2. 2
2
Basic Definitions
Basic Definitions
CAPITAL COST ESTIMATE (CAPEX)
REPRESENTS THE TOTAL CAPITAL COST OF THE PROJECT, INCLUDING
ENGINEERING, MATERIAL, CONSTRUCTION, AND MANAGEMENT COSTS.
ALLOWANCES
USED TO REDUCE THE RISK OF OVERRUN DUE TO “KNOWN” UNCERTAINTIES
DESIGN GROWTH / DESIGN DEVELOPMENT
EXTRAORDINARY FREIGHT COST (AIR FREIGHT, SPECIAL CARGO ...etc)
FORWARD ESCALATION
CUT / WASTE (BULK MATERIALS)
CONTINGENCIES
USED TO REDUCE THE RISK OF OVERRUN DUE TO “POTENTIAL” UNCERTAINTIES
INCOMPLETE PROJECT DEFINITION
CURRENCY FLUCTUATION
ERRORS
DOES NOT COVER FORCE MAJEURE, SCOPE CHANGES, CLAIMS ETC.
3. 3
3
DIRECT COSTS
COSTS DIRECTLY ATTRIBUTED TO A JOB OR A PIECE OF PROJECT EQUIPMENT
Basic Definitions
Basic Definitions
4. 4
4
INDIRECT COSTS
THESE ARE OFTEN REFERRED TO AS “OVERHEAD” COSTS AND CANNOT EASILY
BE ALLOCATED TO ONE JOB OR PROJECTS.
THE PROCESS OF RECOVERING OVERHEADS IS KNOWN AS “ ABSORPTION
COSTING” . CLIENTS FOR LARGE CAPITAL PROJECTS ARE VERY INTERESTED IN
PROPOSED OVERHEAD RATES, CHARGEABLE TO PROJECTS AND REQUIRED
DETAILED OF HOW THE OVERHEADS ARE TO BE ALLOCATED.
Basic Definitions
Basic Definitions
5. 5
5
FIXED COSTS
COSTS ARE SAID TO BE FIXED WHEN THEY REMAIN UNCHANGED AND MUST
CONTINUE TO BE INCURRED, EVEN THOUGH THE WORKLOAD FLUCTUATES, (eg.
MANAGEMENT, SALARIES , RENT INSURANCE….ETC.
Basic Definitions
Basic Definitions
6. 6
6
VARIABLE COST
THESE ARE COSTS WHICH ARE INCURRED AT A RATE DEPENDING ON THE
LEVEL OF THE WORK ACTIVITY.
E.G - MATERIAL
- CONSUMABLES
- SPARE PARTS
- UTILITIES (POWER, WATER, STEAM)
Basic Definitions
Basic Definitions
7. 7
7
Cost Price model
Cost Price model
DIRECT INDIRECT PROFIT PRICE
+ + =
• LABOUR
• MATERIAL
• COMPONENTS
• TOOLING
• DESIGN
• MARKETING
• SALES
• ACCOUNTING
• PURCHASING
• MANAGEMENT
• WARRANTY
• LIABILITY
• ADMINISTRATION
• MATCH
INVESTMENT
COST
8. 8
8
Cost - Price model
Cost - Price model
CONSTRUCTION EQUIP.
+
LABOR COST
MATERIAL COST
DIRECT COST
INDIRECT COST
TOTAL COST
PRICE
=
+
=
DURATION (HOURS) X RATE $/HR X CONSUMABLE FACTOR
LABOR (MHRS) X $/HR X SUPERVISION FACTOR
MATERIAL COST + DELIVERY COST + PURCHASING &
INSPECTION COST
TOTAL DIRECT COST
OVERHEAD, MOB. & DEMOB., TEMPORARY
FACILITIES , INSURANCE, ADMINISTRATION,
MANAGEMENT, ENGINEERING,…ETC
COST
X
PROFIT FACTOR
PRICE
+
10. 10
10
Cost Estimating Process
Cost Estimating Process
2.0
2.0 Capital Cost Major Component
Capital Cost Major Component
DIRECT
COST
INDIRECT
COST
ENGINEERING
MATERIAL
CONSTRUCTION
• Screening Studies
• Basic Engineering (FEED)
• Detailed Engineering
• Procurement Services
• Major Equipment
• Bulk Material
• Freight & Transportation
• Preliminaries (Mobilisation, Site Facilities,
Site Running Costs)
• Civil, Mechanical, E&I Works etc.
• Pre-commissioning / Commissioning
• Owner Management
• Housing/Camp
• Fees
• Services
OWNER COST
11. 11
11
Cost Estimating Process
Cost Estimating Process
3.0
3.0 In-House Cost Estimate
In-House Cost Estimate
Review / Discuss
• Scope of Work
• Basis / Strategy
• Exclusions
• Estimate Methodology
• Required Accuracy
Develop
Cost
Estimate
Issue
Estimate
Review
&
Check
• Quality
• Risks
• Contingency
• Purchase Order
• Vendor Quotes
• Completed Projects
• Escalation Rates
• Construction Unit Rates
Cost Data
• Cost Est. Software
• Excel Worksheet
Computer Tools
Output
Customer
Input /
Request
12. 12
12
PREPARE ESTIMATING REQUIREMENTS
PLANNING THE ESTIMATE
STRUCTURE THE ESTIMATE
DEVELOPING THE ESTIMATE
DEVELOPING CONTINGENCY
DOCUMENTING
REVIEW / ISSUE ESTIMATE
Cost Estimating Process
Cost Estimating Process
4.0
4.0 Estimating Procedure
Estimating Procedure
13. 13
13
Cost Estimate Classification
Cost Estimate Classification
International Classification Practices
International Classification Practices
Class 5
Class 4
Class 3
Class 2
Class 1
Order of
Magnitude
Estimate
-30/+50
Order of
Magnitude
Estimate
Order of
Magnitude
Estimate
Class IV-30/+30
Exploration Estimate
Feasibility Estimate
Authorization
Estimate
Master Control
Estimate
Current Control
Estimate
Definitive
Estimate
Class I-5/+5
Budget
Estimate
Class II-10/+10
Study Estimate
Class III -20/+20
Level 6
Level 5
Level 4
Level 3
Level 2
Level 1
Detailed
Estimate
Definitive
Estimate
Preliminary
Estimate
Study
Estimate
Budget
Estimate
-15/+30
Definitive
Estimate
-5/+15
INCREASING
PROJECT
DEFINITION
ADCO
EMPD
Classification
Class 4
+40/-20%
Screening /
Feasibility
Class 3
+30/-15%
Conceptual /
Prelim. Budget
Class 2
+20/-10%
Master Budget
Class 1
+10/-5%
Definitive /
Control Budget
Extracted from “AACE International Recommended Practices and Standards”
AACE
Classification
Standard
ANSI
Standard
Z94.0
AACE
Pre-1972
Concession Estimate
Association
of Cost
Engineers (UK)
ACostE
Norwegian
Project
Management
Association (NFP)
American
Society of
Professional
Estimators
(ASPE)
14. 14
14
PREPARED BEFORE PROJECT STARTS
HAZY INFORMATION
DETAILS OF PROJECT YET TO BE DEVELOPED
USEFUL FOR QUICK SCREENING AND PLANNING DECISIONS
Estimating Classification
Estimating Classification
1.0 Order of Magnitude
1.0 Order of Magnitude
INTENDED ACCURACY + 35%
15. 15
15
PREPARED DURING PROJECT STUDY AND SCREENING PHASE
BASED ON A GOOD OUTLINE PROJECT DEFINITION
MAJOR PROJECT ELEMENTS
SIZE / CAPACITY /VOLUME /AREA
USEFUL FOR: SCREENING ALTERNATIVES /OPTIONS
PRELIMINARY FEASIBILITY STUDY
MANAGEMENT DECISION
Estimating Classification
Estimating Classification
2.0 Study Estimate
2.0 Study Estimate
INTENDED ACCURACY + 20%
16. 16
16
DEVELOPED DURING ENGINEERING PHASE 10-20% OF ENGINEERING
BASED ON - WELL DEFINED DESIGN CRITERIA.
INTENDED ACCURACY + 15%
Estimating Classification
Estimating Classification
3.0 Budget Estimate
3.0 Budget Estimate
17. 17
17
INTENDED ACCURACY + 5-10%
Estimating Classification
Estimating Classification
4.0 Definitive Estimate
4.0 Definitive Estimate
MOST DESIGN WORK COMPLETED.
ALL MAJOR CONTRACTS / PURCHASE ORDER HAVE BEEN PLACED.
USED TO UPDATE BUDGET FOR THE THE PURPOSE OF COST CONTROL.
19. 19
19
Cost Estimating Methodology
Cost Estimating Methodology
What is Process Equipment
What is Process Equipment
PROCESS
EQUIPMENT
Package Units
• chemical Dosing
• Water Treatment
• HVAC Equipment
Engineered Equipment
• Columns
• Vessels
• Reactors
• Tanks
Standard Equipment
• Pumps
• Compressors
• Fans
23. 23
23
Estimating Methodologies
Estimating Equipment Cost Calculation
L
SHELL
HEAD
NOZZLES
MANHOLE
D
VESSEL WIGHT
Shell weight = x D x L x t x s.g. = W1 Kg
Heads weight = 2 x 1.3 x D x t x s.g.= W2 Kg
Others:
• Internals = W3 Kg
• Supports = W4 Kg
• Nozzles = W5 Kg
• Manhole = W6 Kg
---------------
Total Weight W Kg
Estimated Cost = W (Kg) X Unit Cost (Cost/Kg)
24. 24
24
Material Selection Impact on Equipment
WEIGHT Kg
S.STEEL
C.STEEL
FOB-VALUE
FOB-COST VS WEIGHT CURVE - PRESS. VESSEL
W
V2
V1
25. 25
25
Factors Affecting Project Final Cost
Factors Affecting Project Final Cost
1.0 SCOPE OF WORK
CLARITY OF SCOPE DEFINITION
CHANGES IN SCOPE
2.0 TECHNICAL FACTORS
DESIGN STANDARDS & PRACTICES
SAFETY & ENVIRONMENT REQUIREMENTS
SKILLS/COMPETENCIES
3.0 OTHERS
PROJECT TIME FRAME/SCHEDULE
INTERFACES WITH OTHER OPCOS
PROJECT ORGANIZATION
CURRENCY EXCHANGE RATES
MARKET CONDITIONS
26. 26
26
Case Study 1
Case Study 1
+ 0.00 mtr
+ 0.00 mtr
+ 5.0 mtr
+ 5.0 mtr
T- 1001
T- 1001
TANK T-1001 NEEDS TO BE RE-PAINTED (EXTERNAL).
MAINTENANCE RECEIVED A QUOTATION FOR BLAST-CLEANING AND PAINTING OF
THE TANK. THE QUOTE EXCLUDES THE PROVISION OF THE SCAFFOLDING, ASSUMED
TO BE PROVIDED BY THE OWNER. THE JOB IS PLANNED TO START ON MONDAY 1ST
MAY AND WILL TAKE 10 WORKING DAYS.
THE MAINTENANCE DEPARTMENT REQUESTED YOU TO PROVIDE AN ESTIMATE OF
THE COST FOR THE SCAFFOLDING.
+ 7.00 mtr
+ 7.00 mtr
27. 27
27
INSTALLA
TIN AND DISMANTLING
CODE STANDARD SCAFFOLDING US$ Unit
S25 0 - 25 m3 6.96 m3
S50 25 - 50 m3 5.05 m3
S75 50 - 75 m3 4.80 m3
S100 75-100m3 4.15 m3
S150 100-150m3 3.95 m3
S200 150-200m3 3.65 m3
S400 200-400m3 3.40 m3
S000 400->m3 3.30 m3
CODE SPEICALS US$ UNIT
LA LADDER 2.50 M1
WFR WORK FLOOR 4.35 M2
Z FLEXIABLE SHEETING 4.80 M2
THERE IS A CURRENT ‘SCHEDULE OF RATES’ CONTRACT WITH A SPECIALIZE
COMPANY FOR PROVIDING OF SCAFFOLDING
Case Study 1
Case Study 1
28. 28
28
Case Study 1
Case Study 1
RENT
CODE TYPE US$ Unit
SR SCAFFOLDING 0.03 M3/DAY
LAR LADDER 0.04 M1/DAY
WFR WORK FLOOR 0.04 M2/DAY
ZR FLEXIBLE SHEETING 0.05 M2/DAY
29. 29
29
Case Study 1
Case Study 1
STEPS TO BE TAKEN
1.0 MAKE A (SIMPLE) WORK PLAN
2.0 DEVELOP SCOPE OF WORK
3.0 CALCULATE QUANTITY OF EACH ACTIVITY
4.0 APPLY APPLICABLE UNIT RATES
5.0 CALCULATE TOTAL COST
30. 30
30
Case Study 1
Case Study 1
WORKPLAN: SCAFFOLDING FOR BLASTING/PAINTING T-1001.Dia 5 Mtr H =7 Mtr
1.0 ERECT STANDARD SCAFFOLDING (NO HEAVY EQT. ETC. INVOLVED) AROUND
TANK.
2.0 PROVIDE WORKING FLOORS. FOR EASY WORKING AT VERTICAL CENTERS OF
2.0 Mtr.
3.0 FOR ENVIRONMENTAL REASONS PROVIDE FLEXIBLE SHEETING AROUND
SCAFFOLDING.
4.0 PROVIDE 3 LADDERS
5.0 APPROVAL SAFETY ADVISER
6.0 SCAFFOLDING SHOULD BE READY BEFORE START OF THE WORK ON MONDAY
1ST MAY (WK18).
31. 31
31
Case Study 1
Case Study 1
WORK SCHEDULE:
WK18 WK19 WK 20
WK17 1/5
Scaffolding Ready
Blasting/painting
Start Dismantling Scaffolding
Renting Period Scaffolding
(16 Calendar Days )
W/E
W/E
START
32. 32
32
Case Study 1
Case Study 1
d
D (=d+4)
Volume Scaffolding:
/4 (D2 -
d2
) x H
/4(92
- 52
) x 7 = 307 m3
(S400)
Work Floor:
each:
/4(D2
- d2
)
/4(92-
52
)= 44m2
Total 3 x44m2 = 132m2 (WFR)
Flexible Sheeting
D x H
x 9 x 9 - 254 m2 (ZR)
Ladder:
3 x 6 m1 = 18m1 (LA)
+9
+6
+4
+2
Work Floor
33. 33
33
Case Study 1
Case Study 1
Cost Estimate Details
Cost Estimate Details
# Activity Qty Unit Standard Norm Correction Total
1 Erection & dismantling scaffolding 307 m3 3.4 1,043.80
2 Erection & dismantling work Floor 132 m2 4.35 574.2
3 Erection & dismantling Sheeting 254 m2 4.8 1,219.20
4 Erection & dismantling Ladders 18 m1 2.5 45
5 Rent Scaffolding 4,912.00 m3d 0.03 147.36
6 Rent Work Floor 2,112.00 m2d 0.04 84.48
7 Rent Sheeting 4,064.00 m3d 0.05 203.2
8 Rent Ladders 288 m1d 0.04 11.52
Total 3,328.76
34. 34
34
POINTERS
UNDERSTAND PROJECT REQUIREMENTS BEFORE DEFINING SCOPE.
UNDERSTAND METHOD OF MEASUREMENT OF A ‘SCHEDULE OF RATE CONTRACT.
SELECT OPTIMUM IMPLEMENTATION PLAN.
Case Study 1
Case Study 1
35. 35
35
THE FOLLOWING COST INFORMATION IS AVAILABLE OF A SPECIFIC EQUIPMENT ITEM:
SIZE F.O.B COST
100 M3/hr US$ 50,000
200 M3/hr US$ 80,000
QUESTION:
WHAT IS THE ESTIMATED COST FOR THE EQUIPMENT ITEM WITH A CAPACITY OF 300
M3/HR?
Case Study 2
Case Study 2