Program Management
Framework
June 2010
Intake Process Summary
2
Committed Pipeline
Booked Slated Horizon 2 Horizon 3
Project Baseline Yes No No No
Resources Allocated Yes Yes No No
In Resource Tool Yes Yes Yes Maybe
Effort Final Final OOM +/- 100% Estimate
Documentation Signed SOW SOW issued Assumptions None
Timelines
In-flight to
< 5 weeks
< 8 weeks < 12 weeks < 6 months
Probability 100% 90% 75% 50%
Included in FinancialPlan Yes Yes Yes
Place hold amount not to
exceed forecast resource
capacity
Resource/Revenue Planning
Responsibility
Bruce Amson Bruce Amson
Bruce Amson/
Raegan Stuart
Raegan Stuart
Data Management
Torbjorn
Zetterlund
Torbjorn Zetterlund Rupali Das Raegan Stuart
Included in project dashboard Yes Yes No No
Product Development On Shelf
Near completion/ On
Shelf
Requirements
Complete
Road mapped
Intake Process Summary
3
H3 “Horizon 3”
≤ 6 months or ≥ 50% Probability
H2 “Horizon 2”
≤ 12 weeks or ≥ 75% Probability
Resource Assignment Gate
≤ 12 weeks or ≥ 75% Probability
Business Case & Prioritization
PipelineCommitted
Proceed
No
Slated ≤ 8 weeks SOW Issued
Booked ≤ 5 weeks SOW Signed
Project Start 0 weeks
Project– Plan and Design -
Entry/Exit Criteria
• Slide content
Entry Criteria Exit Criteria
•Project Charter / Project
Management Plan
•BRD Document
•Business Requirements
•Solution Architecture Design Doc
•DR Requirements
•Operational Gap Requirements
•Draft Functional Specifications
•Draft MS Project Schedule
•Signed Off BRD
•Functional Requirements
•Non-Functional Requirements
•Configuration Requirements
•Signed Off Test Strategy
•Infrastructure Plan
•End User Acceptance Criteria
•Baselined MS Project Schedule / Project Plan
•Detailed Cost Estimation
•Finalized Resource Plan
•Finalized WBS
•Training Plan
Project– Build and Configure -
Entry/Exit Criteria
• Slide content
Entry Criteria Exit Criteria
•Signed Off BRD
•Functional Requirements
•Non-Functional Requirements
•Configuration Requirements
•Signed Off Test Strategy
•Infrastructure Plan
•End User Acceptance Criteria
•Baselined MS Project Schedule / Project Plan
•Detailed Cost Estimation
•Finalized Resource Plan
•Finalized WBS
•Training Plan
•Completed Code/Configurations
•Code Sign Off
•Unit Test Cases Sign Off
•Technical Design Documents
•QC/SIT Test Plan Sign Off
•QC/SIT Test Cases Reviewed
•QC/SIT Test Scenarios and Requirements
•UAT Test Plan
•Implementation/Deployment Plan
•Deployment Change request(DCR)
•Revised BRD, revised Functional
specifications, revised Test Plans and Cases,
revised PMP, and revised MS Project
Schedule, as appropriate
Project Framework– QA Test -
Entry/Exit Criteria
• Slide content
Entry Criteria Exit Criteria
•Completed Code/Configurations
•Code Sign Off
•Unit Test Cases Sign Off
•Technical Design Documents
•QC/SIT Test Plan Sign Off
•QC/SIT Test Cases Reviewed
•QC/SIT Test Scenarios and Requirements
•UAT Test Plan
•Implementation/Deployment Plan
•Deployment Change request(DCR)
•Revised BRD, revised Functional specifications,
revised Test Plans and Cases, revised PMP, and
revised MS Project Schedule, as appropriate
•QC Test Results Summary
•Software Integration Test Results Summary
•QC Performance Test Results Summary
•Bug Reviews/Triage Meetings
•QC Release Regression Testing
•QC Signoff
• Deployment Change Request (DCR) to UAT
• Deployment to UAT environment
•Revised BRD, revised Functional specifications,
revised Test Plans and Cases, revised PMP, and
revised MS Project Schedule, as appropriate
Project Framework– UAT -
Entry/Exit Criteria
• Slide content
Entry Criteria Exit Criteria
•QC Test Results Summary
•Software Integration Test Results Summary
•QC Performance Test Results Summary
•Bug Reviews/Triage Meetings
•QC Release Regression Testing
•QC Signoff
• Deployment Change Request (DCR) to UAT
• Deployment to UAT environment
•Revised BRD, revised Functional
specifications, revised Test Plans and Cases,
revised PMP, and revised MS Project
Schedule, as appropriate
•UAT Test Result Summary
•Bug Review/Triage Meetings
•UAT Signoff
•Signed Implementation Plan
•Code Freeze Date
•Training Artifact Signoff
•Revised BRD, revised Functional specifications,
revised Test Plans and Cases, revised PMP, and
revised MS Project Schedule, as appropriate
Project Framework– Deployment -
Entry/Exit Criteria
• Slide content
Entry Criteria Exit Criteria
•UAT Test Result Summary
•Bug Review/Triage Meetings
•UAT Signoff
•Signed Implementation Plan
•Code Freeze Date
•Training Artifact Signoff
•Revised BRD, revised Functional
specifications, revised Test Plans and Cases,
revised PMP, and revised MS Project
Schedule, as appropriate
•RFC Approvals
•Master Release Document (MRD)
•Dry Run Signoff
•Rollback signoff
•RM After Action Report
•Final Product Release to Production
•BAT (Business Acceptance Testing) Signoff
•Finalized Transition to Support Plan and activity
•Revised BRD, revised Functional specifications,
revised Test Plans and Cases, revised PMP, and
revised MS Project Schedule, as appropriate
Project Management Framework–
Warranty and Close - Entry/Exit Criteria
• Slide content
Entry Criteria Exit Criteria
•RFC Approvals
•Master Release Document (MRD)
•Dry Run Signoff
•Rollback signoff
•RM After Action Report
•Final Product Release to Production
•BAT (Business Acceptance Testing) Signoff
•Finalized Transition to Support Plan and activity
•Revised BRD, revised Functional specifications, revised
Test Plans and Cases, revised PMP, and revised MS
Project Schedule, as appropriate
•Transition to Support
•Closure Report
•Lessons Learned
•Completed Project Surveys
•Official disbandment of Project Team
•Closing resource ticket
•All Project documentation submitted to
Document Repository (SharePoint)
Project Framework - Risk Management
• Program Level Risk Management
Risk Identification and Mitigation/Contingency Planning
Who Program Manager/Customer/TM/BM
When Program Planning/Monthly /Event Driven/LAM
(look ahead meetings)
Inputs Risks identified during Proposal/Contract Phase,
Issues List and Review Meetings
Output Risk Management and Tracking Sheet (Risks
identified, Risk Analysis, Risk Owner)

More Related Content

PPTX
Mcom Ba Training Module 1
PDF
Project case study
PDF
Babok20overview
PPTX
Software Team Roles
DOCX
40411923 business-analyst
PDF
Ba course content in mind q systems
DOCX
Senior IT Business Analyst
PPTX
projec kickoff presentation template
Mcom Ba Training Module 1
Project case study
Babok20overview
Software Team Roles
40411923 business-analyst
Ba course content in mind q systems
Senior IT Business Analyst
projec kickoff presentation template

What's hot (20)

PPT
Template kick off-meeting
PPTX
Company project kick off
PPTX
Kick Off Meeting Presentation
PDF
Kick off meeting presentation
PDF
Project Closure Process Steps PowerPoint Presentation Slides
PPT
SAP sample
PPT
How To Review Software Requirements
PDF
Presentation Moscow December 2014
PDF
IT Project Control
PPT
Project Planning Basics - Everything you need to start managing a project
PPT
Pres 2 planning a project assignment
PDF
Software Project Management - Introduction and fundamentals
PPTX
Introduction project management software
PPT
Software project managment
PPT
Project kick off
PDF
Intro to Project Management/Waterfall 2022
PPT
Project managment
PPTX
The Project Charter Ensuring Quality
PPTX
Project characteristics
PDF
P01 - Project Kick-Off
Template kick off-meeting
Company project kick off
Kick Off Meeting Presentation
Kick off meeting presentation
Project Closure Process Steps PowerPoint Presentation Slides
SAP sample
How To Review Software Requirements
Presentation Moscow December 2014
IT Project Control
Project Planning Basics - Everything you need to start managing a project
Pres 2 planning a project assignment
Software Project Management - Introduction and fundamentals
Introduction project management software
Software project managment
Project kick off
Intro to Project Management/Waterfall 2022
Project managment
The Project Charter Ensuring Quality
Project characteristics
P01 - Project Kick-Off
Ad

Viewers also liked (20)

PDF
Big Data Certification
PDF
InfosysPublicServices - Healthcare SOA | Program Management Framework
PDF
Framework for Data Informed Science Policy
PDF
R Cheat Sheet – Data Management
PDF
Research Support in an Open Science Framework - Ron Dekker, seconded national...
PPTX
The Framework Program for the Sustainable Management of La Plata Basin's Wate...
PDF
R Cheat Sheet
PDF
Open Source Framework for Deploying Data Science Models and Cloud Based Appli...
PDF
Big data framework
PPTX
Business Analyst Training - Gain America
PPTX
Scientific Data Cataloging Framework
PPTX
Chicago finance-big-data
PDF
Open Science Framework (OSF)
PPTX
Project management fundamentals
PPTX
Project Management vs. Program Management: Strategies for Transition Success
PDF
Big Data University DS0103EN Certificate _ Data Science Methodology
PPT
Data Center Program Integrated Commissioning Program Baseline
PDF
cloudera data science certificate
PDF
Best Practices Frameworks 101
PPTX
SAFe portfolio management @ Knowit nov 28
Big Data Certification
InfosysPublicServices - Healthcare SOA | Program Management Framework
Framework for Data Informed Science Policy
R Cheat Sheet – Data Management
Research Support in an Open Science Framework - Ron Dekker, seconded national...
The Framework Program for the Sustainable Management of La Plata Basin's Wate...
R Cheat Sheet
Open Source Framework for Deploying Data Science Models and Cloud Based Appli...
Big data framework
Business Analyst Training - Gain America
Scientific Data Cataloging Framework
Chicago finance-big-data
Open Science Framework (OSF)
Project management fundamentals
Project Management vs. Program Management: Strategies for Transition Success
Big Data University DS0103EN Certificate _ Data Science Methodology
Data Center Program Integrated Commissioning Program Baseline
cloudera data science certificate
Best Practices Frameworks 101
SAFe portfolio management @ Knowit nov 28
Ad

Similar to Program Mgmt Framework (20)

PDF
Project Schedule Management
PPTX
BRQ_PortfolioMgmt BRQPresentation
PPTX
2014 sdlc project and gate process rollout published v6
PDF
Undestand PMBok 5th, Section 4
PDF
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
PPT
L2_Scope Management.ppt
PDF
Deployment Methodology
PDF
Do it, sf state project lifecycle management (plm) v1.19 091012
PDF
Savic executive summary sm
PPT
L2_Scope Management.ppt
PPTX
SDLC Process_Document.pptx
PPT
Training on ASAP Methodology.ppt
PPTX
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
PPTX
PM_210 (1).pptx
PDF
Project Management Methodology Including Planning
PPT
Training on ASAP Methodology_11.10.2020.ppt
PPTX
2015 Toronto Section Presentation
PPS
Lunch time presentation scope management
PDF
Project Controls Framework
PDF
Governance - Project Management Office Professional Services
Project Schedule Management
BRQ_PortfolioMgmt BRQPresentation
2014 sdlc project and gate process rollout published v6
Undestand PMBok 5th, Section 4
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
L2_Scope Management.ppt
Deployment Methodology
Do it, sf state project lifecycle management (plm) v1.19 091012
Savic executive summary sm
L2_Scope Management.ppt
SDLC Process_Document.pptx
Training on ASAP Methodology.ppt
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
PM_210 (1).pptx
Project Management Methodology Including Planning
Training on ASAP Methodology_11.10.2020.ppt
2015 Toronto Section Presentation
Lunch time presentation scope management
Project Controls Framework
Governance - Project Management Office Professional Services

Program Mgmt Framework

  • 2. Intake Process Summary 2 Committed Pipeline Booked Slated Horizon 2 Horizon 3 Project Baseline Yes No No No Resources Allocated Yes Yes No No In Resource Tool Yes Yes Yes Maybe Effort Final Final OOM +/- 100% Estimate Documentation Signed SOW SOW issued Assumptions None Timelines In-flight to < 5 weeks < 8 weeks < 12 weeks < 6 months Probability 100% 90% 75% 50% Included in FinancialPlan Yes Yes Yes Place hold amount not to exceed forecast resource capacity Resource/Revenue Planning Responsibility Bruce Amson Bruce Amson Bruce Amson/ Raegan Stuart Raegan Stuart Data Management Torbjorn Zetterlund Torbjorn Zetterlund Rupali Das Raegan Stuart Included in project dashboard Yes Yes No No Product Development On Shelf Near completion/ On Shelf Requirements Complete Road mapped
  • 3. Intake Process Summary 3 H3 “Horizon 3” ≤ 6 months or ≥ 50% Probability H2 “Horizon 2” ≤ 12 weeks or ≥ 75% Probability Resource Assignment Gate ≤ 12 weeks or ≥ 75% Probability Business Case & Prioritization PipelineCommitted Proceed No Slated ≤ 8 weeks SOW Issued Booked ≤ 5 weeks SOW Signed Project Start 0 weeks
  • 4. Project– Plan and Design - Entry/Exit Criteria • Slide content Entry Criteria Exit Criteria •Project Charter / Project Management Plan •BRD Document •Business Requirements •Solution Architecture Design Doc •DR Requirements •Operational Gap Requirements •Draft Functional Specifications •Draft MS Project Schedule •Signed Off BRD •Functional Requirements •Non-Functional Requirements •Configuration Requirements •Signed Off Test Strategy •Infrastructure Plan •End User Acceptance Criteria •Baselined MS Project Schedule / Project Plan •Detailed Cost Estimation •Finalized Resource Plan •Finalized WBS •Training Plan
  • 5. Project– Build and Configure - Entry/Exit Criteria • Slide content Entry Criteria Exit Criteria •Signed Off BRD •Functional Requirements •Non-Functional Requirements •Configuration Requirements •Signed Off Test Strategy •Infrastructure Plan •End User Acceptance Criteria •Baselined MS Project Schedule / Project Plan •Detailed Cost Estimation •Finalized Resource Plan •Finalized WBS •Training Plan •Completed Code/Configurations •Code Sign Off •Unit Test Cases Sign Off •Technical Design Documents •QC/SIT Test Plan Sign Off •QC/SIT Test Cases Reviewed •QC/SIT Test Scenarios and Requirements •UAT Test Plan •Implementation/Deployment Plan •Deployment Change request(DCR) •Revised BRD, revised Functional specifications, revised Test Plans and Cases, revised PMP, and revised MS Project Schedule, as appropriate
  • 6. Project Framework– QA Test - Entry/Exit Criteria • Slide content Entry Criteria Exit Criteria •Completed Code/Configurations •Code Sign Off •Unit Test Cases Sign Off •Technical Design Documents •QC/SIT Test Plan Sign Off •QC/SIT Test Cases Reviewed •QC/SIT Test Scenarios and Requirements •UAT Test Plan •Implementation/Deployment Plan •Deployment Change request(DCR) •Revised BRD, revised Functional specifications, revised Test Plans and Cases, revised PMP, and revised MS Project Schedule, as appropriate •QC Test Results Summary •Software Integration Test Results Summary •QC Performance Test Results Summary •Bug Reviews/Triage Meetings •QC Release Regression Testing •QC Signoff • Deployment Change Request (DCR) to UAT • Deployment to UAT environment •Revised BRD, revised Functional specifications, revised Test Plans and Cases, revised PMP, and revised MS Project Schedule, as appropriate
  • 7. Project Framework– UAT - Entry/Exit Criteria • Slide content Entry Criteria Exit Criteria •QC Test Results Summary •Software Integration Test Results Summary •QC Performance Test Results Summary •Bug Reviews/Triage Meetings •QC Release Regression Testing •QC Signoff • Deployment Change Request (DCR) to UAT • Deployment to UAT environment •Revised BRD, revised Functional specifications, revised Test Plans and Cases, revised PMP, and revised MS Project Schedule, as appropriate •UAT Test Result Summary •Bug Review/Triage Meetings •UAT Signoff •Signed Implementation Plan •Code Freeze Date •Training Artifact Signoff •Revised BRD, revised Functional specifications, revised Test Plans and Cases, revised PMP, and revised MS Project Schedule, as appropriate
  • 8. Project Framework– Deployment - Entry/Exit Criteria • Slide content Entry Criteria Exit Criteria •UAT Test Result Summary •Bug Review/Triage Meetings •UAT Signoff •Signed Implementation Plan •Code Freeze Date •Training Artifact Signoff •Revised BRD, revised Functional specifications, revised Test Plans and Cases, revised PMP, and revised MS Project Schedule, as appropriate •RFC Approvals •Master Release Document (MRD) •Dry Run Signoff •Rollback signoff •RM After Action Report •Final Product Release to Production •BAT (Business Acceptance Testing) Signoff •Finalized Transition to Support Plan and activity •Revised BRD, revised Functional specifications, revised Test Plans and Cases, revised PMP, and revised MS Project Schedule, as appropriate
  • 9. Project Management Framework– Warranty and Close - Entry/Exit Criteria • Slide content Entry Criteria Exit Criteria •RFC Approvals •Master Release Document (MRD) •Dry Run Signoff •Rollback signoff •RM After Action Report •Final Product Release to Production •BAT (Business Acceptance Testing) Signoff •Finalized Transition to Support Plan and activity •Revised BRD, revised Functional specifications, revised Test Plans and Cases, revised PMP, and revised MS Project Schedule, as appropriate •Transition to Support •Closure Report •Lessons Learned •Completed Project Surveys •Official disbandment of Project Team •Closing resource ticket •All Project documentation submitted to Document Repository (SharePoint)
  • 10. Project Framework - Risk Management • Program Level Risk Management Risk Identification and Mitigation/Contingency Planning Who Program Manager/Customer/TM/BM When Program Planning/Monthly /Event Driven/LAM (look ahead meetings) Inputs Risks identified during Proposal/Contract Phase, Issues List and Review Meetings Output Risk Management and Tracking Sheet (Risks identified, Risk Analysis, Risk Owner)