Project Closeout and
Assessment Report
Version 2 ● 9-Mar-15
Approval of the Project Closeout and Assessment Report indicates an understanding and formal
agreement that the project is ready to be closed. By signing this document, each individual agrees all
administrative, financial, and logistical aspects of the project should be concluded, executed, and
documented as described herein.
Approver Name Title Signature Date
Paul-Lattaer Rutledge Project Manager 4-April-15
Gerod Brown Legal 4-April-15
Group Wise INC. Project Sponsor 4-April-15
Section 1. General Information
Project Name
All Singles Social Media Website
Project Start Date Project End Date
12-Jan-15 20-April-15
Project Sponsor(s) Title Department Division
Group Wise INC. NA NA NA
Project Manager Title Department Division
Paul-Lattaer Rutledge PM NA NA
Section 2. Final Deliverable/Deployment Checklist
Respond to each question. For each “no” response, include an issue in Open Issues section.
Item Question Response
2.1 Do you agree that the product and/or service are ready to be deployed? Yes No
2.2 Do you agree the product and/or service has sufficiently met the stated business goals
and objectives?
Yes No
2.3 Do you fully understand and agree to accept all operational requirements, operational
risks, maintenance costs, and other limitations and/or constraints imposed as a result of
ongoing operations of the product and/or service?
Yes No
2.4 Do you agree the project should be closed? If no, please explain: Yes No
Rate your level of satisfaction with regards to the project outcomes listed below
2.5 Project Quality Yes No
2.6 Product and/or Service Performance Yes No
2.7 Scope Yes No
2.8 Cost (Budget) Yes No
2.9 Schedule Yes No
<Insert Project Name> Page 3 of 8
GNU Project Closeout and Assessment
Section 3. Project Documentation Checklist
Respond to each question. For each “no” response, include an issue in Open Issues section.
Item Question Response
3.1 Have project documentation and other items (e.g., Business Case, Project Plan,
Charter, Budget Documents, Status Reports) been prepared, collected, filed, and/or
disposed?
Yes No
3.3 Were audits (e.g., project closeout audit) completed and results documented for future
reference?
Yes No
3.4 Identify the storage location for the following project documents items:
Item Document Location (e.g., Google Docs, Webspace) Format
3.4a Business Case (1)On Backups in ABC Smart LLC. Vault
(2)Hard copy with Group Wise INC.
Electronic
Manual
3.4b Project Charter (1)On Backups in ABC Smart LLC. Vault
(2)Hard copy with Group Wise INC.
Electronic
Manual
3.4c Project Plan (1)Hard copy with Group Wise INC. Electronic
Manual
3.4d Budget Documentation and Invoices (1)Hard copy with Group Wise INC. Electronic
Manual
3.4e Status Reports (1)On Backups in ABC Smart LLC. Vault Electronic
Manual
3.4f Risks and Issues Log (1)On Backups in ABC Smart LLC. Vault Electronic
Manual
3.4g Final deliverable (1)On Backups in ABC Smart LLC. Vault
(2)Hard copy with Group Wise INC.
Electronic
Manual
3.4h If applicable, verify that final project deliverable for the project is attached or storage location is identified in
3.4.
Section 4. Project Team
List resources specified in the Project Plan and used by the project.
<Insert Project Name> Page 4 of 8
GNU Project Closeout and Assessment
Name Role Type
(e.g., Contractor,
Employee)
Paul-Lattaer Rutledge Project Manager Employee
Shakim White Design Employee
Tina Rome Team Leader Employee
Joseph L Howard III Engineer Employee
Gerod Brown Legal Employee
Latarsh Williams Financial Employee
Section 5. Project Lessons Learned
Identify lessons learned specifically for the project. State the lessons learned in terms of a problem
(issue). Describe the problem and include any project documentation references (e.g., Project Plan,
Issues Log) that provide additional details. Identify recommended improvements to correct a similar
problem in the future.
Problem Statement Problem Description References Recommendation
Delivery’s Servers not on site on time PM Order Eelier
Stakeholder wanted top
end server.
Top end servers over
budget
Stakeholder/PM Increase Budget
Section 6. Post-Implementation Support Plans
Identify plans for post-implementation activities after project closeout. Refer to the Benefits Realization
review gate for information about the Post-Implementation Review of Business Outcomes deliverable.
Action Planned
Date
Assigned To Frequency
Post-Implementation Review of Business Outcomes
(actual review)
Post-Implementation Review of Business Outcomes
(approval)
<Insert Project Name> Page 5 of 8
GNU Project Closeout and Assessment
Section 7. Open Issues
Describe any open issues and plans for resolution within the context of project closeout. Include an open
issue for any “no” responses in the Final Product and/or Service Acceptance Checklist and the Project
Artifacts Checklist sections.
Issue Planned Resolution
NA NA
NA NA
NA NA
NA NA
<Insert Project Name> Page 6 of 8
GNU Project Closeout and Assessment
Section 7. Open Issues
Describe any open issues and plans for resolution within the context of project closeout. Include an open
issue for any “no” responses in the Final Product and/or Service Acceptance Checklist and the Project
Artifacts Checklist sections.
Issue Planned Resolution
NA NA
NA NA
NA NA
NA NA
<Insert Project Name> Page 6 of 8
GNU Project Closeout and Assessment

More Related Content

DOC
Project closeout transition checklist
PDF
Dissertation Hardcopy (My Version)
DOCX
Project Closure Report
DOC
Project closure template v3.0
PPTX
Mg6088 spm unit-5
PPT
6.3 sequence activities
Project closeout transition checklist
Dissertation Hardcopy (My Version)
Project Closure Report
Project closure template v3.0
Mg6088 spm unit-5
6.3 sequence activities

What's hot (20)

PPS
MS Project Svcs Productivity
PDF
Ms project 2010 level 1&amp;2
DOCX
CMGT 410 HOMEWORK Education Planning--cmgt410homework.com
PPTX
Eot claims hr__may2012
PDF
Building Formulas And Dashboard In Ms Project
PDF
MGT 402 help A Guide to career/Snaptutorial
PPTX
00 Introduction of project scheduling
PPT
Product Management Training - MS Project Training
PPTX
Primavera Project Management P6 Course session 5
DOCX
MGT 402 Effective Communication/tutorialrank.com
PDF
Primavera P6 manual
PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
DOC
Status reports
PPTX
Project closure
PDF
Introduction to Primavera Reflections
PPSX
MS Project 2010 Training
PDF
CMGT 410 AID Achievement Education--cmgt410aid.com
PDF
CMGT 410 AID Inspiring Innovation--cmgt410aid.com
DOC
Mgt 402 Success Begins / snaptutorial.com
MS Project Svcs Productivity
Ms project 2010 level 1&amp;2
CMGT 410 HOMEWORK Education Planning--cmgt410homework.com
Eot claims hr__may2012
Building Formulas And Dashboard In Ms Project
MGT 402 help A Guide to career/Snaptutorial
00 Introduction of project scheduling
Product Management Training - MS Project Training
Primavera Project Management P6 Course session 5
MGT 402 Effective Communication/tutorialrank.com
Primavera P6 manual
Extension of time (E.O.T) By Ahmed Ibarhim
Status reports
Project closure
Introduction to Primavera Reflections
MS Project 2010 Training
CMGT 410 AID Achievement Education--cmgt410aid.com
CMGT 410 AID Inspiring Innovation--cmgt410aid.com
Mgt 402 Success Begins / snaptutorial.com
Ad

Similar to Project Closeout_joe (20)

DOC
Project proposal document template
PDF
Post mortem report
DOC
Project scope statement template v2.3
PPTX
Project charter sample
DOCX
Part 3A· After creating the resource pool, copy the screen image.docx
PDF
Project Charter - Outreach Events for the Company
DOCX
EXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
DOC
Charter template 17.01.15
PPT
Essential Project Documents
DOCX
Small projectlifecycleplantemplatev
PPT
Integrating agile into sdlc presentation pmi v2
DOCX
Daycare construction project
PDF
SDLC
DOCX
83 Chapter 5 PROJECT.docx
DOCX
Scope and Work Breakdown StructuresBased on the knowledge you ha.docx
DOC
Sow template
PPT
Capello Pw 2011
PPT
Capello Pw 2011
DOCX
Appendix C – Project Close-out ChecklistSection 1.General Inf.docx
Project proposal document template
Post mortem report
Project scope statement template v2.3
Project charter sample
Part 3A· After creating the resource pool, copy the screen image.docx
Project Charter - Outreach Events for the Company
EXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
Charter template 17.01.15
Essential Project Documents
Small projectlifecycleplantemplatev
Integrating agile into sdlc presentation pmi v2
Daycare construction project
SDLC
83 Chapter 5 PROJECT.docx
Scope and Work Breakdown StructuresBased on the knowledge you ha.docx
Sow template
Capello Pw 2011
Capello Pw 2011
Appendix C – Project Close-out ChecklistSection 1.General Inf.docx
Ad

Project Closeout_joe

  • 1. All Singles Social Media Website Project Closeout and Assessment Report Version 2 ● 9-Mar-15
  • 2. Approval of the Project Closeout and Assessment Report indicates an understanding and formal agreement that the project is ready to be closed. By signing this document, each individual agrees all administrative, financial, and logistical aspects of the project should be concluded, executed, and documented as described herein. Approver Name Title Signature Date Paul-Lattaer Rutledge Project Manager 4-April-15 Gerod Brown Legal 4-April-15 Group Wise INC. Project Sponsor 4-April-15
  • 3. Section 1. General Information Project Name All Singles Social Media Website Project Start Date Project End Date 12-Jan-15 20-April-15 Project Sponsor(s) Title Department Division Group Wise INC. NA NA NA Project Manager Title Department Division Paul-Lattaer Rutledge PM NA NA Section 2. Final Deliverable/Deployment Checklist Respond to each question. For each “no” response, include an issue in Open Issues section. Item Question Response 2.1 Do you agree that the product and/or service are ready to be deployed? Yes No 2.2 Do you agree the product and/or service has sufficiently met the stated business goals and objectives? Yes No 2.3 Do you fully understand and agree to accept all operational requirements, operational risks, maintenance costs, and other limitations and/or constraints imposed as a result of ongoing operations of the product and/or service? Yes No 2.4 Do you agree the project should be closed? If no, please explain: Yes No Rate your level of satisfaction with regards to the project outcomes listed below 2.5 Project Quality Yes No 2.6 Product and/or Service Performance Yes No 2.7 Scope Yes No 2.8 Cost (Budget) Yes No 2.9 Schedule Yes No <Insert Project Name> Page 3 of 8 GNU Project Closeout and Assessment
  • 4. Section 3. Project Documentation Checklist Respond to each question. For each “no” response, include an issue in Open Issues section. Item Question Response 3.1 Have project documentation and other items (e.g., Business Case, Project Plan, Charter, Budget Documents, Status Reports) been prepared, collected, filed, and/or disposed? Yes No 3.3 Were audits (e.g., project closeout audit) completed and results documented for future reference? Yes No 3.4 Identify the storage location for the following project documents items: Item Document Location (e.g., Google Docs, Webspace) Format 3.4a Business Case (1)On Backups in ABC Smart LLC. Vault (2)Hard copy with Group Wise INC. Electronic Manual 3.4b Project Charter (1)On Backups in ABC Smart LLC. Vault (2)Hard copy with Group Wise INC. Electronic Manual 3.4c Project Plan (1)Hard copy with Group Wise INC. Electronic Manual 3.4d Budget Documentation and Invoices (1)Hard copy with Group Wise INC. Electronic Manual 3.4e Status Reports (1)On Backups in ABC Smart LLC. Vault Electronic Manual 3.4f Risks and Issues Log (1)On Backups in ABC Smart LLC. Vault Electronic Manual 3.4g Final deliverable (1)On Backups in ABC Smart LLC. Vault (2)Hard copy with Group Wise INC. Electronic Manual 3.4h If applicable, verify that final project deliverable for the project is attached or storage location is identified in 3.4. Section 4. Project Team List resources specified in the Project Plan and used by the project. <Insert Project Name> Page 4 of 8 GNU Project Closeout and Assessment
  • 5. Name Role Type (e.g., Contractor, Employee) Paul-Lattaer Rutledge Project Manager Employee Shakim White Design Employee Tina Rome Team Leader Employee Joseph L Howard III Engineer Employee Gerod Brown Legal Employee Latarsh Williams Financial Employee Section 5. Project Lessons Learned Identify lessons learned specifically for the project. State the lessons learned in terms of a problem (issue). Describe the problem and include any project documentation references (e.g., Project Plan, Issues Log) that provide additional details. Identify recommended improvements to correct a similar problem in the future. Problem Statement Problem Description References Recommendation Delivery’s Servers not on site on time PM Order Eelier Stakeholder wanted top end server. Top end servers over budget Stakeholder/PM Increase Budget Section 6. Post-Implementation Support Plans Identify plans for post-implementation activities after project closeout. Refer to the Benefits Realization review gate for information about the Post-Implementation Review of Business Outcomes deliverable. Action Planned Date Assigned To Frequency Post-Implementation Review of Business Outcomes (actual review) Post-Implementation Review of Business Outcomes (approval) <Insert Project Name> Page 5 of 8 GNU Project Closeout and Assessment
  • 6. Section 7. Open Issues Describe any open issues and plans for resolution within the context of project closeout. Include an open issue for any “no” responses in the Final Product and/or Service Acceptance Checklist and the Project Artifacts Checklist sections. Issue Planned Resolution NA NA NA NA NA NA NA NA <Insert Project Name> Page 6 of 8 GNU Project Closeout and Assessment
  • 7. Section 7. Open Issues Describe any open issues and plans for resolution within the context of project closeout. Include an open issue for any “no” responses in the Final Product and/or Service Acceptance Checklist and the Project Artifacts Checklist sections. Issue Planned Resolution NA NA NA NA NA NA NA NA <Insert Project Name> Page 6 of 8 GNU Project Closeout and Assessment