CONSTRUCTION OF
SIGNATURE BRIDGE OVER
YAMUNA RIVER
SUBMITTED BY -
SANDEEP KUMAR (08515603414)
INTRODUCTION
India’s first “Signature Bridge” being constructed across the Yamuna at Wazirabad
promised to be a great attraction of Delhi.
 An ambitious project of the Delhi tourism the cable stayed bridge will link National
Highway Number 1 near exiting T-point at wazirabad on Western bank and Marginal
bund road at khajuri khas on eastern bank of river Yamuna , thus connecting north Delhi
with east Delhi .
The Proposed Signature Bridge would have a Bow Shaped Pylon in the middle. Two
high tower will be there to provide double cable support in the inner periphery of the
carriageway.
The Signature Bridge would be length of about 675 meter and height 154 meter with
8 lanes.
The deck will be composite ( steel and concrete) while pylon will be in steel.
Signature bridge is cable stayed bridge.
WHY WE NEED TO BUILD THE
SIGNATURE BRIDGE ?
 Signature bridge will eventually improve access between North and West Delhi.
 To prevent the heavy traffic jam in the peak hours.
 To facilitate the movement of vehicular traffic new express lanes will be
constructed to Connect Ring Road with the Bridge.
OVERVIEW OF PROJECT
 PROJECT NAME – SIGNATURE BRIDGE (YAMUNA BRIDGE AT WAZIRABAD)
 CLINET – DELHI TOURISM & TRANSPORTATION DEVELOPMENT CORPORATION
LTD.
 AGENCY – J.V. OF M/S GAMMON INDIA & CONSTRUTORA CIDADE,TENSACCIAI
 EARTHQUAKE ANALYSIS – IIT ROORKEE & STRUCTURE ENGG. RESEARCH
CENTER,CHENNAI
 PERIOD OF CONSTRUCTION – 20/03/2013 TO 19/12/2016 (ESTIMATED)
 COST OF PROJECT – 1591 CRORE (REVISED)
 TOTAL LENGTH – 675 METER (8 LANES)
 PYLON HEIGHT – 154 METER (5400 TON)
 FOUNDATIONS – 6 OPEN & 18 WELL FOUNDATION
Signature bridge
WHY WE CONSTRUCT CABLE STAYED BRIDGE
IN SIGNATURE BRIDGE PROJECT ?
SKETCH OF SIGNATURE BRIDGE
MATERIAL USED IN CONSTRUCTION
• For kerb M35 & M50 For deck
• M35 in well & M30 in pile
Concrete
• Fe415 & Fe500 reinforcement
• TMT and CRS Bars
Steel Bars
• Coarse aggregate
• Fine aggregate
Aggregate
Steel and Concrete (Composite Section)
• River gravels
& crushed
stones
• Start from 6
mm dia &
range 8 to
20mm dia
• which pass
through 4.75
IS Sieve no.
• OPC(OF
GRADE
33,43,53)
Cement Fine aggregate
Coarse
aggregate
Reinforcement(s
teel)
BATCHING PLANT
 The signature bridge site at wazirabad had a batching plant of capacity 60
cubic meter/hr. The plant can deliver the 60 cubic meter/hr output as each
and every operation of the plant has been sequenced to achieve this
output.
 The batching mixers mixes the following-
1. Cement
2. Sand
3. Aggregate
4. Admixture
5. Fly ash
6. water
FOUNDATION
SHALLOW FOUNDATION
• FOUNDATION ARE USED FOR
SHALLOW(SMALL) DEPTH
DEEP FOUNDATION
• FOUNDATION ARE USED UPTO 20
METER(GREATER DEPTH)
o WELL FOUNDATION – Well foundation are the most common
type foundation used in India.
PILEFOUNDATION
BEARING PILE
FRICTION PILE
FRICTION CUM
BEARING PILE
Signature bridge
CASING IN PILE
 20mm dia bars are used.
 Pitch of helical striupps are 200mm.
 4 master ring, 3 pair square rings,
16 long bars
 Dia of helical bar 10mm
 Length of cage-1050mm
 Lap length – 72* dia of bar
cartaise www.slideshare.com
TESTS ON SITE
Sieve analysis of all
aggregates
• Silt content
• Moisture content
Impact value test
• Crushing value test
• Water testing
Cement physical
• TMT Bars rusting
inspection
• Specific gravity &
density test
cartaise www.slideshare.com
STATUS OF CONSTRUCTION WORK
CHART OF WORK COMPLETE
0%
20%
40%
60%
80%
100%
PROJECT BRIDGE
82
45
12
55
SIGNATURE BRIDGE PROJECT (TILL JANUARY 2016)
COMPLETE UNCOMPLETE
Signature bridge
Signature bridge
THANK YOU

More Related Content

PPTX
Signature bridge presentation
PPTX
Signature bridge ppt2
PPT
Training report - RCC Bridge
PPTX
Rail and Road Over Rail Bridge
PDF
Industrial project report ppt CIVIL ENGINEERING
PPTX
Railway Track Maintenance
PPTX
signature bridge short presentation
PPTX
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
Signature bridge presentation
Signature bridge ppt2
Training report - RCC Bridge
Rail and Road Over Rail Bridge
Industrial project report ppt CIVIL ENGINEERING
Railway Track Maintenance
signature bridge short presentation
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)

What's hot (20)

PDF
flyover internship 2
PPTX
Training report of road construction
PDF
CABLE STAYED BRIDGE-SIGNATURE BRIDGE
PPTX
Paving machines
PDF
Signature bridge pdf
PPTX
Sky bus technology
DOCX
Training report done on Bridge Construction
PPTX
PDF
101804898 project-report-of-pre-engineered-steel-building
PPTX
Summer training ppt on cc road construction
PPTX
Village networking ppt
PDF
Undergraduate major project_-_design_of
PPTX
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
PPTX
Unit 1 anchorage systems
DOCX
Industrial Summer Training Report at Construction Site of CPWD
PDF
Internship Report on metro project
PPTX
Submerged Floating Tunnel
PPTX
Analysis of Flexible Pavement Using IIT PAVE software
PPTX
Metro presentation
PPTX
Construction sequence for metro Project (Elevated and Underground) and Time c...
flyover internship 2
Training report of road construction
CABLE STAYED BRIDGE-SIGNATURE BRIDGE
Paving machines
Signature bridge pdf
Sky bus technology
Training report done on Bridge Construction
101804898 project-report-of-pre-engineered-steel-building
Summer training ppt on cc road construction
Village networking ppt
Undergraduate major project_-_design_of
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Unit 1 anchorage systems
Industrial Summer Training Report at Construction Site of CPWD
Internship Report on metro project
Submerged Floating Tunnel
Analysis of Flexible Pavement Using IIT PAVE software
Metro presentation
Construction sequence for metro Project (Elevated and Underground) and Time c...
Ad

Similar to Signature bridge (20)

PPTX
lmrc presentation
PDF
Pamban Bridge - a presentation by Rajesh Prasad
PPTX
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PDF
Report CHENAB BRIDGE 46,47,48,49 ....pdf
PPTX
Saurabhk601
PPTX
Munger rail cum road bridge
PPT
Presentation on construction of cable stay bridge - a modern technique for su...
PPTX
CHENAB BRIDGE
PPTX
Bhupen hazarika setu
PDF
Training
PDF
Bandra Worli sea link
PPTX
Bridge Construction Kalia Bhomara Setu
PPT
B.S.P VOCATIONAL TRAINING PRESENTATION by Anirudh.
PPTX
BOGIBEEL BRIDGE
PDF
my project on chenab bridge
PPTX
Chenab bridge ppt
PDF
Gudur Rail Flyover to remove yard congestion.pdf
PDF
Gudur Rail Flyover to avoid congestion in yard
PPTX
Howrah bridge ppt
PPTX
Final Presentation
lmrc presentation
Pamban Bridge - a presentation by Rajesh Prasad
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
Report CHENAB BRIDGE 46,47,48,49 ....pdf
Saurabhk601
Munger rail cum road bridge
Presentation on construction of cable stay bridge - a modern technique for su...
CHENAB BRIDGE
Bhupen hazarika setu
Training
Bandra Worli sea link
Bridge Construction Kalia Bhomara Setu
B.S.P VOCATIONAL TRAINING PRESENTATION by Anirudh.
BOGIBEEL BRIDGE
my project on chenab bridge
Chenab bridge ppt
Gudur Rail Flyover to remove yard congestion.pdf
Gudur Rail Flyover to avoid congestion in yard
Howrah bridge ppt
Final Presentation
Ad

Recently uploaded (20)

PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PPTX
Software Engineering and software moduleing
PPTX
Feature types and data preprocessing steps
PPTX
ai_satellite_crop_management_20250815030350.pptx
PDF
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PPTX
Module 8- Technological and Communication Skills.pptx
PDF
Soil Improvement Techniques Note - Rabbi
PPTX
Chapter 2 -Technology and Enginerring Materials + Composites.pptx
PDF
Design Guidelines and solutions for Plastics parts
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PDF
20250617 - IR - Global Guide for HR - 51 pages.pdf
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PPTX
Information Storage and Retrieval Techniques Unit III
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PDF
Computer organization and architecuture Digital Notes....pdf
PPTX
Petroleum Refining & Petrochemicals.pptx
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
PPTX
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
PDF
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
PPTX
Amdahl’s law is explained in the above power point presentations
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
Software Engineering and software moduleing
Feature types and data preprocessing steps
ai_satellite_crop_management_20250815030350.pptx
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
Module 8- Technological and Communication Skills.pptx
Soil Improvement Techniques Note - Rabbi
Chapter 2 -Technology and Enginerring Materials + Composites.pptx
Design Guidelines and solutions for Plastics parts
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
20250617 - IR - Global Guide for HR - 51 pages.pdf
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
Information Storage and Retrieval Techniques Unit III
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
Computer organization and architecuture Digital Notes....pdf
Petroleum Refining & Petrochemicals.pptx
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
Amdahl’s law is explained in the above power point presentations

Signature bridge

  • 1. CONSTRUCTION OF SIGNATURE BRIDGE OVER YAMUNA RIVER SUBMITTED BY - SANDEEP KUMAR (08515603414)
  • 2. INTRODUCTION India’s first “Signature Bridge” being constructed across the Yamuna at Wazirabad promised to be a great attraction of Delhi.  An ambitious project of the Delhi tourism the cable stayed bridge will link National Highway Number 1 near exiting T-point at wazirabad on Western bank and Marginal bund road at khajuri khas on eastern bank of river Yamuna , thus connecting north Delhi with east Delhi . The Proposed Signature Bridge would have a Bow Shaped Pylon in the middle. Two high tower will be there to provide double cable support in the inner periphery of the carriageway. The Signature Bridge would be length of about 675 meter and height 154 meter with 8 lanes. The deck will be composite ( steel and concrete) while pylon will be in steel.
  • 3. Signature bridge is cable stayed bridge.
  • 4. WHY WE NEED TO BUILD THE SIGNATURE BRIDGE ?  Signature bridge will eventually improve access between North and West Delhi.  To prevent the heavy traffic jam in the peak hours.  To facilitate the movement of vehicular traffic new express lanes will be constructed to Connect Ring Road with the Bridge.
  • 5. OVERVIEW OF PROJECT  PROJECT NAME – SIGNATURE BRIDGE (YAMUNA BRIDGE AT WAZIRABAD)  CLINET – DELHI TOURISM & TRANSPORTATION DEVELOPMENT CORPORATION LTD.  AGENCY – J.V. OF M/S GAMMON INDIA & CONSTRUTORA CIDADE,TENSACCIAI  EARTHQUAKE ANALYSIS – IIT ROORKEE & STRUCTURE ENGG. RESEARCH CENTER,CHENNAI  PERIOD OF CONSTRUCTION – 20/03/2013 TO 19/12/2016 (ESTIMATED)  COST OF PROJECT – 1591 CRORE (REVISED)  TOTAL LENGTH – 675 METER (8 LANES)  PYLON HEIGHT – 154 METER (5400 TON)  FOUNDATIONS – 6 OPEN & 18 WELL FOUNDATION
  • 7. WHY WE CONSTRUCT CABLE STAYED BRIDGE IN SIGNATURE BRIDGE PROJECT ?
  • 9. MATERIAL USED IN CONSTRUCTION • For kerb M35 & M50 For deck • M35 in well & M30 in pile Concrete • Fe415 & Fe500 reinforcement • TMT and CRS Bars Steel Bars • Coarse aggregate • Fine aggregate Aggregate
  • 10. Steel and Concrete (Composite Section)
  • 11. • River gravels & crushed stones • Start from 6 mm dia & range 8 to 20mm dia • which pass through 4.75 IS Sieve no. • OPC(OF GRADE 33,43,53) Cement Fine aggregate Coarse aggregate Reinforcement(s teel)
  • 12. BATCHING PLANT  The signature bridge site at wazirabad had a batching plant of capacity 60 cubic meter/hr. The plant can deliver the 60 cubic meter/hr output as each and every operation of the plant has been sequenced to achieve this output.  The batching mixers mixes the following- 1. Cement 2. Sand 3. Aggregate 4. Admixture 5. Fly ash 6. water
  • 13. FOUNDATION SHALLOW FOUNDATION • FOUNDATION ARE USED FOR SHALLOW(SMALL) DEPTH DEEP FOUNDATION • FOUNDATION ARE USED UPTO 20 METER(GREATER DEPTH)
  • 14. o WELL FOUNDATION – Well foundation are the most common type foundation used in India.
  • 17. CASING IN PILE  20mm dia bars are used.  Pitch of helical striupps are 200mm.  4 master ring, 3 pair square rings, 16 long bars  Dia of helical bar 10mm  Length of cage-1050mm  Lap length – 72* dia of bar cartaise www.slideshare.com
  • 18. TESTS ON SITE Sieve analysis of all aggregates • Silt content • Moisture content Impact value test • Crushing value test • Water testing Cement physical • TMT Bars rusting inspection • Specific gravity & density test
  • 21. CHART OF WORK COMPLETE 0% 20% 40% 60% 80% 100% PROJECT BRIDGE 82 45 12 55 SIGNATURE BRIDGE PROJECT (TILL JANUARY 2016) COMPLETE UNCOMPLETE