SlideShare a Scribd company logo
Time and Schedule
Lecture 7a
American University in Cairo School of Sciences and Engineering
Department of Architectural Engineering
AENG441 – Professional Practice, Design Management and Codes
1
Topics
2
Design Scheduling
3
Design Scheduling
• Phases of production from Conceptual Planning  Start of
Construction.
• Efficient use of Manpower and Resources
• To achieve an economical, functional and harmonious
design
• Executed within a reasonable period of time
• With an efficient utilization of personnel.
• Experience and Judgment
4
Design Scheduling
• Phases (AIA standard owner-architect agreement)
• Schematic Design: Drawings + Cost Estimate
• Design Development: Drawings +Outline Specifications, + Cost
Estimate
• Construction Documents: Working Drawings +Final Specifications
+ Final Cost Estimate
• Bidding and Negotiation: Receipt and Evaluation of Bids +
Addenda
• Construction Administration: Services after bidding or negotiation
to assure that the structure is built in accordance with the
construction documents.
5
Design Scheduling
• Estimate time required for reach phase.
• Schematic Design phase is the most difficult to
estimate - Greatest amount of variability. (1-12
months!)
• Size and Complexity
• Quality and Completeness of the Program Information
• Decision Making Ability of the Client.(committees!)
• Nature of the Design Team.
6
Design Scheduling
• Design Development and Construction Documents:
• More predictable
• Project Architect and/or Job Captain
• From Schematic Design into Preliminary Design Drawings then
Working Drawings
• Complexity not Size determines scheduling and staffing
requirements.
• Coordination between consultants, client and designers is vital!
• From 2 - 4 months
• Construction Documents 3-7 months.
• Bidding or Negotiation 6 weeks.
7
Design Scheduling
• Project financing to convert design into reality.
• Client review and approval between phases depends on
the size and complexity of the project- usually between
one week. And one month.
• Approvals by building department and public agencies
varies considerably.
8
Design Scheduling
9
Contingencies
• Unexpected Problems:
• Building Department
• Consultants
• Staffing problems
• Client
• 10% average additional time
• Flexible and Responsive to changing conditions
10
Working with a Builder
• Working with contractor to Guarantee Maximum Project
Cost (GMP: Guaranteed Maximum Price)
• Time is generally shortened
• Risk that design is not fully developed
• Documents less specific
• No bidding and negotiation phase
11
Extending the Schedule
• Change of staff
• Increase cost due to inflation
12
Shortening the Schedule
• Optimum Use of staff effort and resources
• Work overtime - costly and inefficient
• Hire more people - Part time or freelance or subcontract to
another firm - costly and inefficient.
• Hire new staff - Not familiar with office procedures or projects -
Expensive
• Reduce man-hours - lower quality job, incomplete, unclear
,errors and inconsistencies.
• Higher cost, lower quality.
• Quality work requires time and staff.
13
Construction Scheduling
14
Establishing a Schedule
• Construction Projects are Complicated
• They involve the work of numerous trades and
subcontractors
• Coordination
• Equipment and Materials
• Time schedules and Cost recording
15
Considerations
1. The construction documents - Well or Poorly prepared.
2. The architect-engineer -More or Less demanding
3. The subcontractors - coordination
4. The contractor’s organization - Project manager, field
superintendent, Office and Field staff, … workload
5. Material dealers - Reliability in meeting deliverability
6. Size and complexity of the project - Most critical.
7. Site conditions - Size and Accessibility
8. The Weather
9. The possibility of labor troubles
10. The possibility of material shortage.
16
CPM (Critical Path Method)
17
CPM (Critical Path Method)
• Planning Phase - Diagram is drawn indicating the order in
which various operations are to be accomplished - Called
Activities.
• Activity Start and Finish referred to as “events” or “nodes”
• Event: That moment when a preceding activity has been
completed and the following activity may begin.
• Milestone Events - Important points in the construction process.
• No indication of time - arrows are not indicating time.
• No gaps of discontinuities
• CPM is known as a network diagram
18
CPM (Critical Path Method)
19
Event
Activity
CPM (Critical Path Method)
20
CPM Scheduling
• Time!
• Time is estimated based on past
experience.
• Working day is taken as a unit of time.
• Consult with subcontractors.
21
CPM (Critical Path Method)
22
1 1 1 1 2 1 1
2
2
14
Critical Path
Critical Path
• Critical Path is the longest path!
• Critical activities along the path must be monitored.
23
Float Path
• Paths that are not on the CP.
• The float is a measure of the extra time available for an
activity or group of activities.
24
Project Calendar
• Multiply by 7/5 (5 working days in each 7 days)
• 16 days x 7/5 = 22.4 or 23 calendar days.
• Starting date  Completion date
• Project Calendar
• Critical Activities noted in color or boldface
• Most building construction projects require 9 - 18 months.
25
Contingencies
• Allowance for project delays (weather, …)
• Some contractors add a fixed percentage!
26
CPM Calculations
• CPM Programming
• Programs.
27
Bar Graphs
• Start and finish dates of major phases.
• They don’t indicate relationships nor dependencies!
• Inferior to CPM as a management tool but superior as a
means of visual communication.
• Continue to be widely used.
28
29
Shortening the Schedule
• Business demands.
• Minimize effect of inflation, weather, interest, …
• Reduce CP time.
• Critical activities 25-30% of all activities.
• Shorter time increases direct cost. Less efficiency in supervision
and coordination. Errors are more likely to occur.
• Less time - More direct cost!
• Less time - Less overhead!
• Analyze the effects and determine a balance.
30
Fast-Track Scheduling
• Fast-Track - Accelerated - Telescoped scheduling.
• Determine major building elements.
• Produce detailed working drawings for a portion of work on
which the contractor may begin construction
• Further details continue
• Requires close coordination:
Architect - Engineers - Client - Contractor
• Oversights expected, Correction of errors
• Staged bidding awarded to different contractors
• Cost and Time control by CM (Construction Manager)
31
32
Time Management
• Fabrication Time
• Erection Time
• Sequence of
Construction
Trades
• Scheduling of
Construction
Trades
33
Submittals - Site Visit,
Testing and Inspection
Lecture 7b
American University in Cairo School of Sciences and Engineering
Department of Architectural Engineering
AENG441 – Professional Practice, Design Management and Codes
34
Topics
35
Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Introduction
36
Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Introduction
37
Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Basic Concepts
38
Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Basic Concepts
39
Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Basic Concepts
40
Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Basic Concepts
• Shop drawings are not part of the contract documents.
41
42
Contractor’s Responsibilities
43
Architect’s Responsibilities
44
Procedures
• Recordkeeping
• Dates received and returned
• Action taken: Approves, corrected, revised, resubmit
• Retain copies of all submittals
• Timeliness
• Within a reasonable time
• 10 working days or two weeks
• Changes and Revisions
• Change orders
• Standard Formats for processing submittals
45
Procedures
46
Procedures
47
10 - 15 working days
Procedures
48
Procedures
49
50
Site Visits
• Contract Requirements
• Architect's Role
• Advise owner whether the contractor is performing the work in
accordance with the contract documents.
• Meeting Reports
• Pre-Bid Meetings
• Pre-Construction Meeting
• During Construction
51
Site Visits
52
Site Visits
53
Site Visits
54
Site Visits
55
Site Visits
56
Site Visits
57
Site Visits
Site Visits
• Safety
• Architect’s Role
59
Site Visits
• Safety
• Architect’s Role
60
Site Visits
• Safety
• Contract’s Role
61
Site Visits
• Evaluating Work Against
Contract Documents
62
Site Visits
• Evaluating Work Against
Contract Documents
63
Site Visits
• Evaluating Work Against
Contract Documents
64
Site Visits
• Testing and Inspection
65
Site Visits
• Testing and Inspection
66
Site Visits
• Testing and Inspection
67
Site Visits
• Testing and Inspection
Site Visits
• Testing and Inspection
69
Site Visits
• Testing and Inspection
70
Thank You.
71

More Related Content

PPTX
Project management procurement
PPTX
Project scope management
PDF
Project scope management
PDF
Project Management Professional (PMP) / 42 Processes
PPT
07. Project Integration Management
PPTX
Strategies in building procurement (summarized)
PDF
Pmp quality chapter 8
PPTX
Project Quality Management PPT.pptx
Project management procurement
Project scope management
Project scope management
Project Management Professional (PMP) / 42 Processes
07. Project Integration Management
Strategies in building procurement (summarized)
Pmp quality chapter 8
Project Quality Management PPT.pptx

What's hot (20)

PPTX
Project control & Monitoring
PPTX
Introduction to construction project management
PPTX
Project Schedule Management - Sequence Activities - PMP Workgroup
PPTX
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
PPTX
03 Construction Project Planning and Scheduling
PPTX
Construction Documents
PPTX
Lec 03 project life cycle
PPT
09. Project Cost Management
PPTX
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
PDF
05 project scope management
PPT
3. construction planning. construction project management
PPTX
Construction Contracts: Basics of Contracts and Contract Administration
PDF
Primavera - Tutorial
PDF
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PPT
Defining The Project
PPTX
Construction project management
PDF
Project Charter Guide
PPTX
An Introduction to Project Management
PPT
Lecture 2 tender process n documentation
PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
Project control & Monitoring
Introduction to construction project management
Project Schedule Management - Sequence Activities - PMP Workgroup
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
03 Construction Project Planning and Scheduling
Construction Documents
Lec 03 project life cycle
09. Project Cost Management
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
05 project scope management
3. construction planning. construction project management
Construction Contracts: Basics of Contracts and Contract Administration
Primavera - Tutorial
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
Defining The Project
Construction project management
Project Charter Guide
An Introduction to Project Management
Lecture 2 tender process n documentation
Extension of time (E.O.T) By Ahmed Ibarhim
Ad

Similar to Time & Schedule, Submittals, Site visits, Testing and Inspection (20)

PPTX
Chapter 3-Construction Planning and Scheduling.pptx
PDF
Chapter 3- Construction Project mgt body of knowledge AC (1).pdf
PDF
Chapter 3- Construction Project mgt body of knowledge AC.pdf
PDF
Project_Planning_and_Scheduling_1742364195.pdf
PDF
1 Introduction.pdf
PPTX
CHAPTER 1.pptx
PPTX
CHAPTER 1.pptx
PPTX
chapter-1.pptx scheduling for construction
PPTX
CPM Scheduling best practicies within the Construction Indistry
PPTX
Parthiv_Scheduling_Presentation_One.pptx
PPT
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
PDF
Construction Technology & Project Management - Notes - 01.pdf
PDF
Mastering the Critical Path and Mitigation Actions
PDF
Construction Design Project for HND Quantity Surveying
PDF
A Contractors Guide To Planning Scheduling And Control 1st Edition Len Holm
PPTX
Chapter 5-Project Management.pptx
PPT
ACH 216 Lecture 08 (Scheduling)
PPT
SAB4113 Intro to Planning & Scheduling
PPTX
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
PDF
50 Planning Fundamentals V5.0 - procedures only
Chapter 3-Construction Planning and Scheduling.pptx
Chapter 3- Construction Project mgt body of knowledge AC (1).pdf
Chapter 3- Construction Project mgt body of knowledge AC.pdf
Project_Planning_and_Scheduling_1742364195.pdf
1 Introduction.pdf
CHAPTER 1.pptx
CHAPTER 1.pptx
chapter-1.pptx scheduling for construction
CPM Scheduling best practicies within the Construction Indistry
Parthiv_Scheduling_Presentation_One.pptx
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Construction Technology & Project Management - Notes - 01.pdf
Mastering the Critical Path and Mitigation Actions
Construction Design Project for HND Quantity Surveying
A Contractors Guide To Planning Scheduling And Control 1st Edition Len Holm
Chapter 5-Project Management.pptx
ACH 216 Lecture 08 (Scheduling)
SAB4113 Intro to Planning & Scheduling
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
50 Planning Fundamentals V5.0 - procedures only
Ad

More from Galala University (20)

PDF
Architecture and Architects in Egypt b
PDF
Architecture and Architects in Egypt a
PDF
Impact of Climate and Environment Changes on the Sustainability of the Coasta...
PDF
Sustainability of Tourism Development in the city of Ain-Sukhna, Egypt
PDF
Sustainability of Tourism Development in Al Ain Al Sukhna, Egypt Yasser Mahgo...
PDF
Typologies of Urban Development in Sukhna-Zaafarana Area.pdf
PDF
AI-Human Dialogue for Architectural Design Concept Generation presentation 26...
PPTX
Arc341 building 3 spring 2019 lecture 5 - surface active - chapter 4
PPTX
Arc341 building 3 spring 2019 lecture 4 - section active - chapter 3
PPTX
Arc341 building 3 spring 2019 lecture 3 - vector-active - chapter 2
PPTX
Arc341 building 3 spring 2019 lecture 2 - basics - chapter 0
PPTX
Arc341 building 3 spring 2019 lecture 1 - introduction to structures
PPTX
Fue theory 4 2018 lecture 5 - the formulation and analysis of architectural...
PPTX
Fue theory 4 2018 lecture 4 - the formulation and analysis of architectural...
PPTX
Fue theory 4 2018 lecture 3 - architectural timeline
PPTX
Fue theory 4 2018 lecture 2 - history of theory
PPTX
Fue theory 4 2018 lecture 1- introduction
PPTX
Fue theory 4 2018 lecture 6 - synthesis of the design concept- different te...
PPTX
Arc 323 human studies in architecture fall 2018 lecture 9-topics 2
PPTX
Arc 323 human studies in architecture fall 2018 lecture 8-topics 1
Architecture and Architects in Egypt b
Architecture and Architects in Egypt a
Impact of Climate and Environment Changes on the Sustainability of the Coasta...
Sustainability of Tourism Development in the city of Ain-Sukhna, Egypt
Sustainability of Tourism Development in Al Ain Al Sukhna, Egypt Yasser Mahgo...
Typologies of Urban Development in Sukhna-Zaafarana Area.pdf
AI-Human Dialogue for Architectural Design Concept Generation presentation 26...
Arc341 building 3 spring 2019 lecture 5 - surface active - chapter 4
Arc341 building 3 spring 2019 lecture 4 - section active - chapter 3
Arc341 building 3 spring 2019 lecture 3 - vector-active - chapter 2
Arc341 building 3 spring 2019 lecture 2 - basics - chapter 0
Arc341 building 3 spring 2019 lecture 1 - introduction to structures
Fue theory 4 2018 lecture 5 - the formulation and analysis of architectural...
Fue theory 4 2018 lecture 4 - the formulation and analysis of architectural...
Fue theory 4 2018 lecture 3 - architectural timeline
Fue theory 4 2018 lecture 2 - history of theory
Fue theory 4 2018 lecture 1- introduction
Fue theory 4 2018 lecture 6 - synthesis of the design concept- different te...
Arc 323 human studies in architecture fall 2018 lecture 9-topics 2
Arc 323 human studies in architecture fall 2018 lecture 8-topics 1

Recently uploaded (20)

PPTX
UI UX Elective Course S1 Sistem Informasi RPS.pptx
PPT
robotS AND ROBOTICSOF HUMANS AND MACHINES
PPTX
VERNACULAR_DESIGN_PPT FINAL WITH PROPOSED PLAN.pptx
PPT
EthicsNotesSTUDENTCOPYfghhnmncssssx sjsjsj
PPTX
Introduction to Building Information Modeling
PPTX
LITERATURE CASE STUDY DESIGN SEMESTER 5.pptx
PDF
Test slideshare presentation for blog post
PDF
2025_AIFG_Akane_Kikuchi_Empathy_Design.PDF
PDF
321 LIBRARY DESIGN.pdf43354445t6556t5656
PPTX
CLASS_11_BUSINESS_STUDIES_PPT_CHAPTER_1_Business_Trade_Commerce.pptx
PDF
1 Introduction to Networking (06).pdfbsbsbsb
PPTX
Acoustics new a better way to learn sound science
PDF
Chalkpiece Annual Report from 2019 To 2025
PDF
2025CategoryRanking of technology university
PDF
The Complete Guide to Buying Verified Stripe Accounts 2025.pdf
PDF
THEORY OF ID MODULE (Interior Design Subject)
PPTX
timber basics in structure mechanics (dos)
PPTX
Bitcoin predictor project presentation
PDF
trenching-standard-drawings procedure rev
PDF
Social Media USAGE .............................................................
UI UX Elective Course S1 Sistem Informasi RPS.pptx
robotS AND ROBOTICSOF HUMANS AND MACHINES
VERNACULAR_DESIGN_PPT FINAL WITH PROPOSED PLAN.pptx
EthicsNotesSTUDENTCOPYfghhnmncssssx sjsjsj
Introduction to Building Information Modeling
LITERATURE CASE STUDY DESIGN SEMESTER 5.pptx
Test slideshare presentation for blog post
2025_AIFG_Akane_Kikuchi_Empathy_Design.PDF
321 LIBRARY DESIGN.pdf43354445t6556t5656
CLASS_11_BUSINESS_STUDIES_PPT_CHAPTER_1_Business_Trade_Commerce.pptx
1 Introduction to Networking (06).pdfbsbsbsb
Acoustics new a better way to learn sound science
Chalkpiece Annual Report from 2019 To 2025
2025CategoryRanking of technology university
The Complete Guide to Buying Verified Stripe Accounts 2025.pdf
THEORY OF ID MODULE (Interior Design Subject)
timber basics in structure mechanics (dos)
Bitcoin predictor project presentation
trenching-standard-drawings procedure rev
Social Media USAGE .............................................................

Time & Schedule, Submittals, Site visits, Testing and Inspection

  • 1. Time and Schedule Lecture 7a American University in Cairo School of Sciences and Engineering Department of Architectural Engineering AENG441 – Professional Practice, Design Management and Codes 1
  • 4. Design Scheduling • Phases of production from Conceptual Planning  Start of Construction. • Efficient use of Manpower and Resources • To achieve an economical, functional and harmonious design • Executed within a reasonable period of time • With an efficient utilization of personnel. • Experience and Judgment 4
  • 5. Design Scheduling • Phases (AIA standard owner-architect agreement) • Schematic Design: Drawings + Cost Estimate • Design Development: Drawings +Outline Specifications, + Cost Estimate • Construction Documents: Working Drawings +Final Specifications + Final Cost Estimate • Bidding and Negotiation: Receipt and Evaluation of Bids + Addenda • Construction Administration: Services after bidding or negotiation to assure that the structure is built in accordance with the construction documents. 5
  • 6. Design Scheduling • Estimate time required for reach phase. • Schematic Design phase is the most difficult to estimate - Greatest amount of variability. (1-12 months!) • Size and Complexity • Quality and Completeness of the Program Information • Decision Making Ability of the Client.(committees!) • Nature of the Design Team. 6
  • 7. Design Scheduling • Design Development and Construction Documents: • More predictable • Project Architect and/or Job Captain • From Schematic Design into Preliminary Design Drawings then Working Drawings • Complexity not Size determines scheduling and staffing requirements. • Coordination between consultants, client and designers is vital! • From 2 - 4 months • Construction Documents 3-7 months. • Bidding or Negotiation 6 weeks. 7
  • 8. Design Scheduling • Project financing to convert design into reality. • Client review and approval between phases depends on the size and complexity of the project- usually between one week. And one month. • Approvals by building department and public agencies varies considerably. 8
  • 10. Contingencies • Unexpected Problems: • Building Department • Consultants • Staffing problems • Client • 10% average additional time • Flexible and Responsive to changing conditions 10
  • 11. Working with a Builder • Working with contractor to Guarantee Maximum Project Cost (GMP: Guaranteed Maximum Price) • Time is generally shortened • Risk that design is not fully developed • Documents less specific • No bidding and negotiation phase 11
  • 12. Extending the Schedule • Change of staff • Increase cost due to inflation 12
  • 13. Shortening the Schedule • Optimum Use of staff effort and resources • Work overtime - costly and inefficient • Hire more people - Part time or freelance or subcontract to another firm - costly and inefficient. • Hire new staff - Not familiar with office procedures or projects - Expensive • Reduce man-hours - lower quality job, incomplete, unclear ,errors and inconsistencies. • Higher cost, lower quality. • Quality work requires time and staff. 13
  • 15. Establishing a Schedule • Construction Projects are Complicated • They involve the work of numerous trades and subcontractors • Coordination • Equipment and Materials • Time schedules and Cost recording 15
  • 16. Considerations 1. The construction documents - Well or Poorly prepared. 2. The architect-engineer -More or Less demanding 3. The subcontractors - coordination 4. The contractor’s organization - Project manager, field superintendent, Office and Field staff, … workload 5. Material dealers - Reliability in meeting deliverability 6. Size and complexity of the project - Most critical. 7. Site conditions - Size and Accessibility 8. The Weather 9. The possibility of labor troubles 10. The possibility of material shortage. 16
  • 17. CPM (Critical Path Method) 17
  • 18. CPM (Critical Path Method) • Planning Phase - Diagram is drawn indicating the order in which various operations are to be accomplished - Called Activities. • Activity Start and Finish referred to as “events” or “nodes” • Event: That moment when a preceding activity has been completed and the following activity may begin. • Milestone Events - Important points in the construction process. • No indication of time - arrows are not indicating time. • No gaps of discontinuities • CPM is known as a network diagram 18
  • 19. CPM (Critical Path Method) 19 Event Activity
  • 20. CPM (Critical Path Method) 20
  • 21. CPM Scheduling • Time! • Time is estimated based on past experience. • Working day is taken as a unit of time. • Consult with subcontractors. 21
  • 22. CPM (Critical Path Method) 22 1 1 1 1 2 1 1 2 2 14 Critical Path
  • 23. Critical Path • Critical Path is the longest path! • Critical activities along the path must be monitored. 23
  • 24. Float Path • Paths that are not on the CP. • The float is a measure of the extra time available for an activity or group of activities. 24
  • 25. Project Calendar • Multiply by 7/5 (5 working days in each 7 days) • 16 days x 7/5 = 22.4 or 23 calendar days. • Starting date  Completion date • Project Calendar • Critical Activities noted in color or boldface • Most building construction projects require 9 - 18 months. 25
  • 26. Contingencies • Allowance for project delays (weather, …) • Some contractors add a fixed percentage! 26
  • 27. CPM Calculations • CPM Programming • Programs. 27
  • 28. Bar Graphs • Start and finish dates of major phases. • They don’t indicate relationships nor dependencies! • Inferior to CPM as a management tool but superior as a means of visual communication. • Continue to be widely used. 28
  • 29. 29
  • 30. Shortening the Schedule • Business demands. • Minimize effect of inflation, weather, interest, … • Reduce CP time. • Critical activities 25-30% of all activities. • Shorter time increases direct cost. Less efficiency in supervision and coordination. Errors are more likely to occur. • Less time - More direct cost! • Less time - Less overhead! • Analyze the effects and determine a balance. 30
  • 31. Fast-Track Scheduling • Fast-Track - Accelerated - Telescoped scheduling. • Determine major building elements. • Produce detailed working drawings for a portion of work on which the contractor may begin construction • Further details continue • Requires close coordination: Architect - Engineers - Client - Contractor • Oversights expected, Correction of errors • Staged bidding awarded to different contractors • Cost and Time control by CM (Construction Manager) 31
  • 32. 32
  • 33. Time Management • Fabrication Time • Erection Time • Sequence of Construction Trades • Scheduling of Construction Trades 33
  • 34. Submittals - Site Visit, Testing and Inspection Lecture 7b American University in Cairo School of Sciences and Engineering Department of Architectural Engineering AENG441 – Professional Practice, Design Management and Codes 34
  • 36. Material and Equipment Submittals • Shop Drawings, Product Data, and Samples • Introduction 36
  • 37. Material and Equipment Submittals • Shop Drawings, Product Data, and Samples • Introduction 37
  • 38. Material and Equipment Submittals • Shop Drawings, Product Data, and Samples • Basic Concepts 38
  • 39. Material and Equipment Submittals • Shop Drawings, Product Data, and Samples • Basic Concepts 39
  • 40. Material and Equipment Submittals • Shop Drawings, Product Data, and Samples • Basic Concepts 40
  • 41. Material and Equipment Submittals • Shop Drawings, Product Data, and Samples • Basic Concepts • Shop drawings are not part of the contract documents. 41
  • 42. 42
  • 45. Procedures • Recordkeeping • Dates received and returned • Action taken: Approves, corrected, revised, resubmit • Retain copies of all submittals • Timeliness • Within a reasonable time • 10 working days or two weeks • Changes and Revisions • Change orders • Standard Formats for processing submittals 45
  • 47. Procedures 47 10 - 15 working days
  • 50. 50
  • 51. Site Visits • Contract Requirements • Architect's Role • Advise owner whether the contractor is performing the work in accordance with the contract documents. • Meeting Reports • Pre-Bid Meetings • Pre-Construction Meeting • During Construction 51
  • 59. Site Visits • Safety • Architect’s Role 59
  • 60. Site Visits • Safety • Architect’s Role 60
  • 61. Site Visits • Safety • Contract’s Role 61
  • 62. Site Visits • Evaluating Work Against Contract Documents 62
  • 63. Site Visits • Evaluating Work Against Contract Documents 63
  • 64. Site Visits • Evaluating Work Against Contract Documents 64
  • 65. Site Visits • Testing and Inspection 65
  • 66. Site Visits • Testing and Inspection 66
  • 67. Site Visits • Testing and Inspection 67
  • 68. Site Visits • Testing and Inspection
  • 69. Site Visits • Testing and Inspection 69
  • 70. Site Visits • Testing and Inspection 70