Project Management Process
Dr. Huy Nguyen
Project Management Process
• Two categories of project process:
– Product-oriented process;
 Should be considered in project but not explained in detail in PMBOK.
– Project management process.
2
Project and Development Life Cycle
• 5 categories of development life cycle:
– Predictive: Project scope, time, and cost are determined in the early phases of the life
cycle. Any changes to the scope are carefully managed. Predictive life cycles may also
be referred to as waterfall life cycles.
– Iterative: Project scope is generally determined early in the project life cycle, but time
and cost estimates are routinely modified as the project team’s understanding of the
product increases. Iterations develop the product through a series of repeated cycles,
while increments successively add to the functionality of the product.
– Incremental: Deliverable is produced through a series of iterations that successively add
functionality within a predetermined time frame. The deliverable contains the necessary
and sufficient capability to be considered complete only after the final iteration.
– Adaptive: Agile, iterative, or incremental. The detailed scope is defined and approved
before the start of an iteration. Adaptive life cycles are also referred to as agile or change-
driven life cycles.
– Hybrid: Combination of a predictive and an adaptive life cycle. Those elements of the
project that are well known or have fixed requirements follow a predictive development
life cycle, and those elements that are still evolving follow an adaptive development life
cycle.
3
Process Interaction
• Project management
processes are represented
as discrete elements with
well-defined interface.
• In practice, they overlap
and interact.
I
E
C
P
M&C
4
Process Phase
• A project phase is a collection of logically related project activities that
culminates in the completion of one or more deliverables.
• The phases in a life cycle can be described by a variety of attributes which is
measurable and unique, such as:
– Name, number, duration, resource requirements, entrance and exit
criteria…
• The phase names should indicate the type of work done in that phase, such as:
– Concept development,
– Feasibility study,
– Customer requirements,
– Solution development,
– Design, prototype, build, test, transition,
– Commissioning,
– Milestone review, and
– Lessons learned.
5
Process Gate
• A phase gate is held at the end of a phase. The project’s performance and
progress are compared to project and business documents including but not
limited to:
– Project business case,
– Project charter,
– Project management plan, and
– Benefits management plan.
• A decision (e.g., go/no-go decision) is made as a result of this comparison to:
– Continue to the next phase,
– Continue to the next phase with modification,
– End the project,
– Remain in the phase, or
– Repeat the phase or elements of it.
6
Project Management Process
• 3 categories of project management processes:
– Processes used once or at predefined points in the project: The
processes Develop Project Charter and Close Project or Phase are
examples.
– Processes that are performed periodically as needed: The process
Acquire Resources is performed as resources are needed. The process
Conduct Procurements is performed prior to needing the procured item.
– Processes that are performed continuously throughout the project:
The process Define Activities may occur throughout the project life cycle,
especially if the project uses rolling wave planning or an adaptive
development approach. Many of the monitoring and control processes are
ongoing from the start of the project, until it is closed out.
7
Project Management Process Groups
• 5 project management process groups:
– Initiating: Define a new project or a new phase of an existing project by
obtaining authorization to start the project or phase.
– Planning: Establish the scope of the project, refine the objectives, and
define the course of action required to attain the objectives that the project
was undertaken to achieve.
– Executing: Complete the work defined in the project management plan to
satisfy the project requirements.
– Monitoring and Controlling: Track, review, and regulate the progress and
performance of the project; identify any areas in which changes to the plan
are required; and initiate the corresponding changes.
– Closing: Formally complete or close the project, phase, or contract.
8
Process Groups & Knowledge Areas Mapping
9
Knowledge
Areas
Process Groups
Initiating Planning Executing Monitoring & Controlling Closing
Integration
Develop Project
Charter
Develop Project Management Plan
Direct and Manage Project Work
Manage Project Knowledge
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase
Scope
Plan Scope Management
Collect Requirements
Define Scope
Create WBS
Validate Scope
Control Scope
Schedule
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Durations
Develop Schedule
Control Schedule
Cost
Plan Cost Management
Estimate Costs
Determine Budget
Control Costs
Quality Plan Quality Management Manage Quality Control Quality
Resource
Plan Resource Management
Estimate Activity Resources
Acquire Resources
Develop Team
Manage Team
Control Resources
Communications Plan Communications Management Manage Communications Monitor Communications
Risk
Plan Risk Management
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Responses
Implement Risk Responses Monitor Risks
Procurement Plan Procurement Management Conduct Procurements Control Procurements
Stakeholder Identify Stakeholders Plan Stakeholder Engagement Manage Stakeholder Engagement Monitor Stakeholder Engagement
Process Groups & Knowledge Areas Mapping
10
Structure of Project Management Activities in
Different Knowledge Areas
• Activities according to Project Processes;
• Each activity include:
– Inputs;
– Tools and Techniques;
– Outputs.
• Tools and Techniques are not specified in detail enough to follow as a
schedule or a series of steps:
 Need to be defined by practitioners.
11
Initiating Process Group
12
Planning Process Group
13
Executing Process Group
14
Monitoring & Controlling Process Group
15
Closing Process Group
16
Project Management Data and Information
• Project data are regularly collected and analyzed throughout the project life
cycle. Key project data and information include:
– Work performance data: The raw observations and measurements identified
during activities performed to carry out the project work. Examples include
reported percent of work physically completed, quality and technical performance
measures, start and finish dates of schedule activities, number of change
requests, number of defects, actual costs, actual durations, etc.
– Work performance information: The performance data collected from various
controlling processes, analyzed in context and integrated based on relationships
across areas. Examples of performance information are status of deliverables,
implementation status for change requests, and forecast estimates to complete.
– Work performance reports: The physical or electronic representation of work
performance information compiled in project documents, which is intended to
generate decisions or raise issues, actions, or awareness. Examples include
status reports, memos, justifications, information notes, electronic dashboards,
recommendations, and updates.
17
Project Management Data and Information
18
Project Management Business Documents
• Project business case: A documented economic feasibility study used to establish
the validity of the benefits of a selected component lacking sufficient definition and that
is used as a basis for the authorization of further project management activities.
• Project benefits management plan: The documented explanation defining the
processes for creating, maximizing, and sustaining the benefits provided by a project.
19
Project Management Business Documents
• Project business case may include:
– Business needs:
• Determination of what is prompting the need for action;
• Situational statement documenting the business problem or opportunity to be addressed including the value to
be delivered to the organization;
• Identification of stakeholders affected; and identification of the scope.
– Analysis of the situation:
• Identification of organizational strategies, goals, and objectives;
• Identification of root cause(s) of the problem or main contributors of an opportunity;
• Gap analysis of capabilities needed for the project versus existing capabilities of the organization;
• Identification of known risks, critical success factors;
• Identification of decision criteria by which the various courses of action may be assessed;
• Identification of a set of options to be considered for addressing the business problem or opportunity.
– Recommendation:
• A statement of the recommended option to pursue in the project;
• Items to include in the statement;
• An implementation approach.
– Evaluation:
• Statement describing the plan for measuring benefits the project will deliver. 20
Project Benefits Management Plan
• Project benefits management plan may include:
– Target benefits;
– Strategic alignment;
– Timeframe for realizing benefits;
– Benefits owner;
– Metrics;
– Assumptions;
– Risks.
21
Project Success Measures
• Project success may include additional criteria linked to the organizational
strategy and to the delivery of business results that may include but are not
limited to:
– Completing the project benefits management plan;
– Meeting the agreed-upon financial measures documented in the business case;
– Meeting business case nonfinancial objectives;
– Completing movement of an organization from its current state to the desired
future state;
– Fulfilling contract terms and conditions;
– Meeting organizational strategy, goals, and objectives;
– Achieving stakeholder satisfaction;
– Acceptable customer/end-user adoption;
– Integration of deliverables into the organization’s operating environment;
– Achieving agreed-upon quality of delivery;
– Meeting governance criteria; and
– Achieving other agreed-upon success measures or criteria.
22
Thank You
Next topic:
Project Planning
23

More Related Content

PPTX
Project Implementation.pptx
DOC
Change Management Plan
PPT
Logical framework
PPTX
assignment on project planning
PPTX
Project Termination.pptx
PPT
Monotoring and evaluation principles and theories
PPTX
Monitoring and evaluation frameworks logical framework
PPT
Monitoring & evaluation presentation[1]
Project Implementation.pptx
Change Management Plan
Logical framework
assignment on project planning
Project Termination.pptx
Monotoring and evaluation principles and theories
Monitoring and evaluation frameworks logical framework
Monitoring & evaluation presentation[1]

What's hot (20)

PPTX
Project Control
PPTX
Monitoring process
DOC
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
PDF
M&e system
PPTX
Monitoring and evaluation of Projects
PPTX
PROJECT ORGANIZATION
PDF
recomendation letter from UNHCR
DOC
CURRICULUM VITAE
PPTX
Monitoring and Evaluation
PPTX
Difference between monitoring and evaluation
PPT
Project monitoring and evaluation by Samuel Obino Mokaya
PPTX
Project Quality Control
PPTX
Project Monitoring and Evaluation
PDF
Gender Mainstreaming (Meaning and role and importance)
PDF
CURRICULUM VITAE, monitoring and evaluation
PDF
Cost Management PowerPoint Presentation Slides
PPT
Project Formulation Step by Step
PPTX
Different project management methodologies
PPTX
Theory of change
PPT
Logical framework-and-project-proposal-119679674017067-2
Project Control
Monitoring process
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
M&e system
Monitoring and evaluation of Projects
PROJECT ORGANIZATION
recomendation letter from UNHCR
CURRICULUM VITAE
Monitoring and Evaluation
Difference between monitoring and evaluation
Project monitoring and evaluation by Samuel Obino Mokaya
Project Quality Control
Project Monitoring and Evaluation
Gender Mainstreaming (Meaning and role and importance)
CURRICULUM VITAE, monitoring and evaluation
Cost Management PowerPoint Presentation Slides
Project Formulation Step by Step
Different project management methodologies
Theory of change
Logical framework-and-project-proposal-119679674017067-2
Ad

Similar to Topic 4 - Project Management Process.pdf (20)

PDF
APM Practitioner Qualification revision cards
PPTX
04 projectintegrationmanagement
PPTX
Project Management - PMI Approach
PPTX
THE PLACE OF M&E IN PM CYCLE- STEP BY STEP
PPTX
CAPM Exam preparation - series 1
PPSX
DISE - Introduction to Project Management
PPT
04 project integration management
PPT
06. Project Management Process Groups
PDF
Business case writing presentation
PPTX
Project Management and Control Techniques
PDF
Topic 7 - Project Scope Management.pdf
PPTX
Lecture 2.pptx
PPTX
Project Life Cycle.pptx
PPTX
Project planning.pptx
PPTX
Project planning.pptx
PPTX
Project Management basics PMBOK 6 (1).pptx
PPT
04. Project Management
PPTX
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
PDF
Software Engineering unit 4 personal notes.pdf
PPTX
3 scope Management
APM Practitioner Qualification revision cards
04 projectintegrationmanagement
Project Management - PMI Approach
THE PLACE OF M&E IN PM CYCLE- STEP BY STEP
CAPM Exam preparation - series 1
DISE - Introduction to Project Management
04 project integration management
06. Project Management Process Groups
Business case writing presentation
Project Management and Control Techniques
Topic 7 - Project Scope Management.pdf
Lecture 2.pptx
Project Life Cycle.pptx
Project planning.pptx
Project planning.pptx
Project Management basics PMBOK 6 (1).pptx
04. Project Management
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Software Engineering unit 4 personal notes.pdf
3 scope Management
Ad

More from HuyNguyen657394 (18)

PPTX
Application of IT in the food and beverage industry - Increasing performance ...
PDF
Topic 15 - Leadership in Project Management.pdf
PDF
Topic 14 - Project Team Management.pdf
PDF
Tips - IT Project Management.pdf
PDF
Topic 13 - Project Resource Management.pdf
PDF
Topic 12 - Project Cost Management.pdf
PDF
Topic 11 - Project Schedule Management.pdf
PDF
Topic 10 - Project Performance Management.pdf
PDF
Topic 9 - Project Stakeholder Management.pdf
PDF
Topic 8 - Project Quality Management.pdf
PDF
Topic 6 - Project Integration Management.pdf
PDF
Topic 5 - Project Planning.pdf
PDF
Topic 3 - Project Selection & Portfolio Management.pdf
PDF
Topic 2 - Project Life Cycle and Project Management Organization.pdf
PDF
Topic 1 - Introduction of Project Management.pdf
PDF
Topic 0 - General Information.pdf
PDF
Topic 0 - General Information New.pdf
PDF
Nhan thuc ve chuyen doi so.pdf
Application of IT in the food and beverage industry - Increasing performance ...
Topic 15 - Leadership in Project Management.pdf
Topic 14 - Project Team Management.pdf
Tips - IT Project Management.pdf
Topic 13 - Project Resource Management.pdf
Topic 12 - Project Cost Management.pdf
Topic 11 - Project Schedule Management.pdf
Topic 10 - Project Performance Management.pdf
Topic 9 - Project Stakeholder Management.pdf
Topic 8 - Project Quality Management.pdf
Topic 6 - Project Integration Management.pdf
Topic 5 - Project Planning.pdf
Topic 3 - Project Selection & Portfolio Management.pdf
Topic 2 - Project Life Cycle and Project Management Organization.pdf
Topic 1 - Introduction of Project Management.pdf
Topic 0 - General Information.pdf
Topic 0 - General Information New.pdf
Nhan thuc ve chuyen doi so.pdf

Recently uploaded (20)

PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
Sustainable Sites - Green Building Construction
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PPTX
OOP with Java - Java Introduction (Basics)
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
web development for engineering and engineering
PDF
Arduino robotics embedded978-1-4302-3184-4.pdf
PPT
Mechanical Engineering MATERIALS Selection
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
UNIT 4 Total Quality Management .pptx
PPT
Project quality management in manufacturing
PPTX
Lecture Notes Electrical Wiring System Components
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
Welding lecture in detail for understanding
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
bas. eng. economics group 4 presentation 1.pptx
Model Code of Practice - Construction Work - 21102022 .pdf
CYBER-CRIMES AND SECURITY A guide to understanding
Sustainable Sites - Green Building Construction
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
OOP with Java - Java Introduction (Basics)
Strings in CPP - Strings in C++ are sequences of characters used to store and...
Internet of Things (IOT) - A guide to understanding
web development for engineering and engineering
Arduino robotics embedded978-1-4302-3184-4.pdf
Mechanical Engineering MATERIALS Selection
UNIT-1 - COAL BASED THERMAL POWER PLANTS
UNIT 4 Total Quality Management .pptx
Project quality management in manufacturing
Lecture Notes Electrical Wiring System Components
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
Welding lecture in detail for understanding
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Embodied AI: Ushering in the Next Era of Intelligent Systems
bas. eng. economics group 4 presentation 1.pptx

Topic 4 - Project Management Process.pdf

  • 2. Project Management Process • Two categories of project process: – Product-oriented process;  Should be considered in project but not explained in detail in PMBOK. – Project management process. 2
  • 3. Project and Development Life Cycle • 5 categories of development life cycle: – Predictive: Project scope, time, and cost are determined in the early phases of the life cycle. Any changes to the scope are carefully managed. Predictive life cycles may also be referred to as waterfall life cycles. – Iterative: Project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as the project team’s understanding of the product increases. Iterations develop the product through a series of repeated cycles, while increments successively add to the functionality of the product. – Incremental: Deliverable is produced through a series of iterations that successively add functionality within a predetermined time frame. The deliverable contains the necessary and sufficient capability to be considered complete only after the final iteration. – Adaptive: Agile, iterative, or incremental. The detailed scope is defined and approved before the start of an iteration. Adaptive life cycles are also referred to as agile or change- driven life cycles. – Hybrid: Combination of a predictive and an adaptive life cycle. Those elements of the project that are well known or have fixed requirements follow a predictive development life cycle, and those elements that are still evolving follow an adaptive development life cycle. 3
  • 4. Process Interaction • Project management processes are represented as discrete elements with well-defined interface. • In practice, they overlap and interact. I E C P M&C 4
  • 5. Process Phase • A project phase is a collection of logically related project activities that culminates in the completion of one or more deliverables. • The phases in a life cycle can be described by a variety of attributes which is measurable and unique, such as: – Name, number, duration, resource requirements, entrance and exit criteria… • The phase names should indicate the type of work done in that phase, such as: – Concept development, – Feasibility study, – Customer requirements, – Solution development, – Design, prototype, build, test, transition, – Commissioning, – Milestone review, and – Lessons learned. 5
  • 6. Process Gate • A phase gate is held at the end of a phase. The project’s performance and progress are compared to project and business documents including but not limited to: – Project business case, – Project charter, – Project management plan, and – Benefits management plan. • A decision (e.g., go/no-go decision) is made as a result of this comparison to: – Continue to the next phase, – Continue to the next phase with modification, – End the project, – Remain in the phase, or – Repeat the phase or elements of it. 6
  • 7. Project Management Process • 3 categories of project management processes: – Processes used once or at predefined points in the project: The processes Develop Project Charter and Close Project or Phase are examples. – Processes that are performed periodically as needed: The process Acquire Resources is performed as resources are needed. The process Conduct Procurements is performed prior to needing the procured item. – Processes that are performed continuously throughout the project: The process Define Activities may occur throughout the project life cycle, especially if the project uses rolling wave planning or an adaptive development approach. Many of the monitoring and control processes are ongoing from the start of the project, until it is closed out. 7
  • 8. Project Management Process Groups • 5 project management process groups: – Initiating: Define a new project or a new phase of an existing project by obtaining authorization to start the project or phase. – Planning: Establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve. – Executing: Complete the work defined in the project management plan to satisfy the project requirements. – Monitoring and Controlling: Track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes. – Closing: Formally complete or close the project, phase, or contract. 8
  • 9. Process Groups & Knowledge Areas Mapping 9 Knowledge Areas Process Groups Initiating Planning Executing Monitoring & Controlling Closing Integration Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Manage Project Knowledge Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase Scope Plan Scope Management Collect Requirements Define Scope Create WBS Validate Scope Control Scope Schedule Plan Schedule Management Define Activities Sequence Activities Estimate Activity Durations Develop Schedule Control Schedule Cost Plan Cost Management Estimate Costs Determine Budget Control Costs Quality Plan Quality Management Manage Quality Control Quality Resource Plan Resource Management Estimate Activity Resources Acquire Resources Develop Team Manage Team Control Resources Communications Plan Communications Management Manage Communications Monitor Communications Risk Plan Risk Management Identify Risks Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Responses Implement Risk Responses Monitor Risks Procurement Plan Procurement Management Conduct Procurements Control Procurements Stakeholder Identify Stakeholders Plan Stakeholder Engagement Manage Stakeholder Engagement Monitor Stakeholder Engagement
  • 10. Process Groups & Knowledge Areas Mapping 10
  • 11. Structure of Project Management Activities in Different Knowledge Areas • Activities according to Project Processes; • Each activity include: – Inputs; – Tools and Techniques; – Outputs. • Tools and Techniques are not specified in detail enough to follow as a schedule or a series of steps:  Need to be defined by practitioners. 11
  • 15. Monitoring & Controlling Process Group 15
  • 17. Project Management Data and Information • Project data are regularly collected and analyzed throughout the project life cycle. Key project data and information include: – Work performance data: The raw observations and measurements identified during activities performed to carry out the project work. Examples include reported percent of work physically completed, quality and technical performance measures, start and finish dates of schedule activities, number of change requests, number of defects, actual costs, actual durations, etc. – Work performance information: The performance data collected from various controlling processes, analyzed in context and integrated based on relationships across areas. Examples of performance information are status of deliverables, implementation status for change requests, and forecast estimates to complete. – Work performance reports: The physical or electronic representation of work performance information compiled in project documents, which is intended to generate decisions or raise issues, actions, or awareness. Examples include status reports, memos, justifications, information notes, electronic dashboards, recommendations, and updates. 17
  • 18. Project Management Data and Information 18
  • 19. Project Management Business Documents • Project business case: A documented economic feasibility study used to establish the validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities. • Project benefits management plan: The documented explanation defining the processes for creating, maximizing, and sustaining the benefits provided by a project. 19
  • 20. Project Management Business Documents • Project business case may include: – Business needs: • Determination of what is prompting the need for action; • Situational statement documenting the business problem or opportunity to be addressed including the value to be delivered to the organization; • Identification of stakeholders affected; and identification of the scope. – Analysis of the situation: • Identification of organizational strategies, goals, and objectives; • Identification of root cause(s) of the problem or main contributors of an opportunity; • Gap analysis of capabilities needed for the project versus existing capabilities of the organization; • Identification of known risks, critical success factors; • Identification of decision criteria by which the various courses of action may be assessed; • Identification of a set of options to be considered for addressing the business problem or opportunity. – Recommendation: • A statement of the recommended option to pursue in the project; • Items to include in the statement; • An implementation approach. – Evaluation: • Statement describing the plan for measuring benefits the project will deliver. 20
  • 21. Project Benefits Management Plan • Project benefits management plan may include: – Target benefits; – Strategic alignment; – Timeframe for realizing benefits; – Benefits owner; – Metrics; – Assumptions; – Risks. 21
  • 22. Project Success Measures • Project success may include additional criteria linked to the organizational strategy and to the delivery of business results that may include but are not limited to: – Completing the project benefits management plan; – Meeting the agreed-upon financial measures documented in the business case; – Meeting business case nonfinancial objectives; – Completing movement of an organization from its current state to the desired future state; – Fulfilling contract terms and conditions; – Meeting organizational strategy, goals, and objectives; – Achieving stakeholder satisfaction; – Acceptable customer/end-user adoption; – Integration of deliverables into the organization’s operating environment; – Achieving agreed-upon quality of delivery; – Meeting governance criteria; and – Achieving other agreed-upon success measures or criteria. 22