Ingredients for success deployment of Earned-Value Management in projects
Culture shift is essential – every Project Team  must understand the working of EVM model Also, culture shift needs to be managed and supported well
Besides  accurate WBS, accurate planning, scheduling and proper costing of work packages(PV) at frequency points of measurement is the first step towards successful EVM implementation. Costing to include all the costs that will be incurred (Direct, Indirect, Fixed and Variable costs covering all resources including human resources )
It is absolutely essential to measure the work completed(earned back ie EV) at each task level and at the project level either in terms of % of work scheduled, or absolute $ value
To get a true picture of all Costs incurred (AC) between two frequency of measurement points, all costs – Direct, Indirect, Fixed and Variable incurred at every task level must be recorded .
Replanning the work at every change is critical. Use of automated tools will ease out this process
Frequency of measurement of PV, EV and AC is critical. It must be optimum suiting the duration of the project, neither low nor high
It is absolutely essential to record all project costs on a daily basis or at an appropriate frequency in line with the Frequency of measurement of EVM values
 

More Related Content

PPTX
Cost & value management
PPTX
Update Project Progress (MS PROJECT)
PPTX
Project monitoring activity
PPTX
Project cost control
PPTX
Project cost control techniques
PPTX
Project monitoring lecture 1
PPT
Ils management overview
PPTX
break even analysis
Cost & value management
Update Project Progress (MS PROJECT)
Project monitoring activity
Project cost control
Project cost control techniques
Project monitoring lecture 1
Ils management overview
break even analysis

What's hot (16)

PPTX
Construction Cost Control
PDF
Seven Finance Activities Every Manufacturing Company Needs
PPT
P ex cost management-1
PPSX
Project Management 5 Cost Management
PPTX
Cost analysis
PPTX
Value management presentation
PPTX
Project cost & control
DOCX
PPTX
Standard costing
PDF
4. project cost management
DOCX
Pm0015 summer-2016
PPTX
Cost management
PPT
factors affecting prodution
PDF
Odoo experience 2015 earned value management
PPT
PDF
Project cost control system in SAP
Construction Cost Control
Seven Finance Activities Every Manufacturing Company Needs
P ex cost management-1
Project Management 5 Cost Management
Cost analysis
Value management presentation
Project cost & control
Standard costing
4. project cost management
Pm0015 summer-2016
Cost management
factors affecting prodution
Odoo experience 2015 earned value management
Project cost control system in SAP
Ad

Similar to Vijay Prasad’S Views On Earned Value Management In Project (20)

PDF
Using Earned Value Management to Measure Project Performance
PDF
Increasing the probability of project success using Earned Value Management
PPT
Earned value Project Management (evpm)
PPTX
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
PDF
Tracking a Typical Apartment Construction using Earned Value Management
PPTX
Presentation Relating to Earned Value
PDF
Knowing the Project Health using Earned Value Management (EVM)
PPTX
Earned value analysis (1)
PDF
Earned Value Management
PDF
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
PDF
Project monitoring and controlling with earned value management
PDF
EVM of Project Management...
PDF
An introduction to an effective earned value management system (EVMS) webinar...
PDF
Earned Value Management Variance
PPT
Earned Value Analysis
PDF
Application of Earned Value Method and Delay Analysis on Construction Project...
PPTX
Earned Value Management
PPTX
Track Project Performance - Earned Value Management
PDF
Agile Project Management Meets Earned Value Management
PDF
Earned Value Management | K2 Consulting..
Using Earned Value Management to Measure Project Performance
Increasing the probability of project success using Earned Value Management
Earned value Project Management (evpm)
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Tracking a Typical Apartment Construction using Earned Value Management
Presentation Relating to Earned Value
Knowing the Project Health using Earned Value Management (EVM)
Earned value analysis (1)
Earned Value Management
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
Project monitoring and controlling with earned value management
EVM of Project Management...
An introduction to an effective earned value management system (EVMS) webinar...
Earned Value Management Variance
Earned Value Analysis
Application of Earned Value Method and Delay Analysis on Construction Project...
Earned Value Management
Track Project Performance - Earned Value Management
Agile Project Management Meets Earned Value Management
Earned Value Management | K2 Consulting..
Ad

Recently uploaded (20)

DOCX
The AUB Centre for AI in Media Proposal.docx
PDF
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
PDF
Network Security Unit 5.pdf for BCA BBA.
PPTX
Big Data Technologies - Introduction.pptx
PPTX
MYSQL Presentation for SQL database connectivity
PDF
KodekX | Application Modernization Development
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PDF
NewMind AI Weekly Chronicles - August'25 Week I
PDF
Unlocking AI with Model Context Protocol (MCP)
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PPTX
sap open course for s4hana steps from ECC to s4
PDF
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
PDF
Electronic commerce courselecture one. Pdf
PPT
Teaching material agriculture food technology
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PPTX
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
PDF
MIND Revenue Release Quarter 2 2025 Press Release
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
The AUB Centre for AI in Media Proposal.docx
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
Network Security Unit 5.pdf for BCA BBA.
Big Data Technologies - Introduction.pptx
MYSQL Presentation for SQL database connectivity
KodekX | Application Modernization Development
Agricultural_Statistics_at_a_Glance_2022_0.pdf
NewMind AI Weekly Chronicles - August'25 Week I
Unlocking AI with Model Context Protocol (MCP)
Per capita expenditure prediction using model stacking based on satellite ima...
sap open course for s4hana steps from ECC to s4
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
Electronic commerce courselecture one. Pdf
Teaching material agriculture food technology
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
MIND Revenue Release Quarter 2 2025 Press Release
Mobile App Security Testing_ A Comprehensive Guide.pdf
“AI and Expert System Decision Support & Business Intelligence Systems”
Diabetes mellitus diagnosis method based random forest with bat algorithm

Vijay Prasad’S Views On Earned Value Management In Project

  • 1. Ingredients for success deployment of Earned-Value Management in projects
  • 2. Culture shift is essential – every Project Team must understand the working of EVM model Also, culture shift needs to be managed and supported well
  • 3. Besides accurate WBS, accurate planning, scheduling and proper costing of work packages(PV) at frequency points of measurement is the first step towards successful EVM implementation. Costing to include all the costs that will be incurred (Direct, Indirect, Fixed and Variable costs covering all resources including human resources )
  • 4. It is absolutely essential to measure the work completed(earned back ie EV) at each task level and at the project level either in terms of % of work scheduled, or absolute $ value
  • 5. To get a true picture of all Costs incurred (AC) between two frequency of measurement points, all costs – Direct, Indirect, Fixed and Variable incurred at every task level must be recorded .
  • 6. Replanning the work at every change is critical. Use of automated tools will ease out this process
  • 7. Frequency of measurement of PV, EV and AC is critical. It must be optimum suiting the duration of the project, neither low nor high
  • 8. It is absolutely essential to record all project costs on a daily basis or at an appropriate frequency in line with the Frequency of measurement of EVM values
  • 9.