Document Objective: This document focuses on several key areas where the
concepts of PMBOK Guide 5th edition have been revised. It highlights the
changes in Knowledge Areas/Process Groups/Processes as per PMBOK®
Guide 6th Edition.
Background – The Project Management Institute (PMI)® performs a
“Role Delineation Study (RDS)” periodically, every 5 to 7 years . The goal
of this study is to identify what are the project managers around the
world doing in their current projects and the changing trends and
practices in project Management and it updates the content of the exam
as per the result of the study. After the most recent RDS, PMI now has a
list of tasks that the project managers perform, as well as the knowledge
and skills required for the job and upgraded the exam syllabus for PMP
certification and that is why there is an upgrade in PMBOK® Guide as
well which is the single most important publication by the PMI® for
PMP® Certification aspirants to study and prepare for the PMP® Exam.
PMBOK® 6th Edition
• The 6th edition of the Project Management Body of Knowledge
(PMBOK®) Guide was released in September 2017 and PMP®
certification exam format has been revised from March 26,
2018.
• There are several new sections included in the PMBOK® 6th
edition which are as per the changing trends and practices in
project management and they’re all packed into a 976-page
book, The PMBOK® Guide, 6th Edition.
• The most significant addition in PMBOK® 6th edition is a section
containing Agile Development. The Agile concept is
incorporated in all 10 knowledge areas. Each knowledge area
will contain a section entitled Approaches for Agile, Iterative
and Adaptive Environments, describing how these practices
integrate in project settings.
PMBOK® 6th Edition vs. PMBOK® 5th
Edition: What’s Changed?
• Changes in Process Groups
 The number of process groups remains the same in 5th and 6th edition.
• Changes In Knowledge Area
 Two Knowledge Areas names were changed to more closely reflect the work that is
done.
 Project Time Management was changed to Project Schedule Management to
reflect that the project schedule is defined and managed during the project,
whereas time is not managed.
 Both team resources and physical resources are addressed in the Sixth Edition.
Thus, the Knowledge Area Project Human Resource Management was changed
to Project Resource Management.
…as per PMBOK®
• Changes in the number of Processes
There are total 49 processes now in 6th edition as compared to 47
in 5th edition. One process was removed and three new processes
were added in 6th edition, to reflect changes in the way projects
are managed in practice. One process was moved between
Knowledge Areas. These changes are summarized below :
 Manage Project Knowledge —Added.
 Estimate Activity Resources —Moved to Project Resource
Management.
 Control Resources —Added.
 Implement Risk Responses —Added.
 Close Procurements —Eliminated.
…as per
PMBOK®
What’s Changed ? Continued...
• Changes in the name of existing processes
Several process names were changed to improve consistency across the processes
and to improve clarity. Research ndicates that project managers tend to monitor,
facilitate, and manage rather than control, particularly in processes that involve
interactions with people. Therefore, process names for Control Communications,
Control Risks, and Control Stakeholder Engagement were changed to Monitor
Communications, Monitor Risks, and Monitor Stakeholder Engagement. The list
below summarizes all the process name changes:
 Perform Quality Assurance (Section 8.2)—Changed to Manage Quality.
 Plan Human Resource Management (Section 9.1)—Changed to Plan Resource Management.
 Acquire Project Team (Section 9.2)—Changed to Acquire Resources.
 Develop Project Team (Section 9.3)—Changed to Develop Team.
 Manage Project Team (Section 9.4)—Changed to Manage Team.
 Control Communications (Section 10.3)—Changed to Monitor Communications
 Control Risks (Section 11.6)—Changed to Monitor Risks.
 Plan Stakeholder Management (Section 13.2)—Changed to Plan Stakeholder Engagement.
 Control Stakeholder Engagement (Section 13.4)—Changed to Monitor Stakeholder Engagement.
…as per PMBOK®
What’s Changed ? Continued...
• THE ROLE OF THE PROJECT MANAGER - New section in
6th Edition
This is a new section that outlines the project manager’s
role in the team. It includes information on the project
manager’s sphere of influence and competencies. PMI’s
Talent Triangle® is discussed with its emphasis on strategic
and business management skills, technical project
management skills, and leadership skills. Leadership styles
and personality are also discussed as part of this section.
The final part of this section focuses on the project
manager as an integrator.
…as per PMBOK®
What’s Changed ? Continued...
• AGILE – New Section added in 6th edition
Since the Fifth Edition of the PMBOK® Guide
there has been more adoption of agile and
adaptive methodologies in the management of
projects. The Sixth Edition has included a
subsection called Considerations for Adaptive
Environments at the beginning of Sections 4
through 13. Some agile-specific tools and
techniques have been introduced into the
PMBOK® Guide, such as sprint and iteration
planning.
What’s Changed ? Continued...
What's new in pmbok guide 6th edition

More Related Content

PDF
PMBOK 6TH
PPTX
UPDATE: PMP Exam Changes From Jan 11, 2016. What You Need To Know?
PDF
PMBOK 5th Edition Project Management Processes and Knowledge Areas
PPTX
7.0 Delivering in an Agile Environment
PDF
Discussion PMBoK Fifth Edition vs Fourth Edition vs ISO 21500 Project Management
PPTX
PMP : Change is Coming - Know how it affects you
PDF
Pmp 簡易快速記憶圖法
PDF
Pmbok6 to 7 transformation
PMBOK 6TH
UPDATE: PMP Exam Changes From Jan 11, 2016. What You Need To Know?
PMBOK 5th Edition Project Management Processes and Knowledge Areas
7.0 Delivering in an Agile Environment
Discussion PMBoK Fifth Edition vs Fourth Edition vs ISO 21500 Project Management
PMP : Change is Coming - Know how it affects you
Pmp 簡易快速記憶圖法
Pmbok6 to 7 transformation

What's hot (20)

PDF
Value of PMP Certification and PMI Membership
PPTX
Project Management Class ( based on PMBOK) - Day 3
PPTX
Section 1: introduction
PPTX
PMP Exam Changes
PPTX
Pmbok6 changes
PDF
PMP Chap4-Project Integration Management Details: Part-2
PDF
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
PPTX
PMBOK® Guide Sixth Edition Update
PPTX
Process groups and knowledge areas PMBOK 5th Edition
PDF
KCS Academy PMP Exam Prep Course Chapter 2 - Organizational Influences and Pr...
PPTX
10.1 Plan Communication Management
PPTX
5.1 Plan Scope Management
PDF
PMP PMBOK 6th
PPTX
9.5 Manage Team
PDF
Pmbok 5cartulinas
PPT
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
PDF
KCS Academy PMP Exam Prep Course Chapter 1 - Introduction
PDF
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PPTX
Project Management: Cost Management Knowledge Area
PPTX
7.2 Estimate Cost
Value of PMP Certification and PMI Membership
Project Management Class ( based on PMBOK) - Day 3
Section 1: introduction
PMP Exam Changes
Pmbok6 changes
PMP Chap4-Project Integration Management Details: Part-2
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
PMBOK® Guide Sixth Edition Update
Process groups and knowledge areas PMBOK 5th Edition
KCS Academy PMP Exam Prep Course Chapter 2 - Organizational Influences and Pr...
10.1 Plan Communication Management
5.1 Plan Scope Management
PMP PMBOK 6th
9.5 Manage Team
Pmbok 5cartulinas
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
KCS Academy PMP Exam Prep Course Chapter 1 - Introduction
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
Project Management: Cost Management Knowledge Area
7.2 Estimate Cost
Ad

Similar to What's new in pmbok guide 6th edition (20)

PDF
14 key changes in pmbok ® guide sixth edition
PPTX
Pmi chapter 29.11.2017
PDF
PMPBOK 5th Edition Vs PMBOK 6th Edition, Knowledge Area Changes and New Proce...
PPTX
Section 1: introduction
PPT
Pmp Prep Session 1 Overview
PDF
Overview pmbok guide4thedition
PPS
PMBOK 4th Edtions Changes
PDF
PMP EXAM PREPARATION.pdf
PPTX
PMP as per PMBOK 6
PDF
Day 1 framework
DOCX
Pmbok 6 th Edition
PDF
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
DOCX
White paper changes to the pmbok 4th edition
PPTX
Day 1 - Poject Management Framework.pptx
PPT
Capello Pw 2011
PPT
Capello Pw 2011
PPTX
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
PDF
DOCX
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
PPTX
PM FrameWork: Module 1
14 key changes in pmbok ® guide sixth edition
Pmi chapter 29.11.2017
PMPBOK 5th Edition Vs PMBOK 6th Edition, Knowledge Area Changes and New Proce...
Section 1: introduction
Pmp Prep Session 1 Overview
Overview pmbok guide4thedition
PMBOK 4th Edtions Changes
PMP EXAM PREPARATION.pdf
PMP as per PMBOK 6
Day 1 framework
Pmbok 6 th Edition
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
White paper changes to the pmbok 4th edition
Day 1 - Poject Management Framework.pptx
Capello Pw 2011
Capello Pw 2011
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
PM FrameWork: Module 1
Ad

Recently uploaded (20)

PPTX
Strategic Plan 2023-2024 Presentation.pptx
PPTX
Concluding Session_Wrapup-India Jun 5 2024-Oct 5 2025 ZS.pptx
PPTX
Human Resources management _HR structure
PDF
Human resources management is a best management
PPTX
Effective_communication._(strategy).pptx
PPTX
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
PDF
1_Corporate Goverance presentation topic
PPTX
Leadership for Industry 4.0 And Industry 5.0
PPTX
Improved_Leadership_in_Total_Quality_Lesson.pptx
PDF
The Cyber SwarmShield by Stéphane Nappo
PPTX
Chapter Three for international political
PPTX
Mangeroal Finance for Strategic Management
PPTX
_ISO_Presentation_ISO 9001 and 45001.pptx
PPTX
Project Management Methods PERT-and-CPM.pptx
PDF
The-Power-of-Communication (1).pdf......
PPTX
Empowering Project Management Through Servant Leadership - PMI UK.pptx
PPTX
School Annual day Presentation, Logo, Animation
PDF
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf
PDF
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
PDF
Features of Effective decision making in Management
Strategic Plan 2023-2024 Presentation.pptx
Concluding Session_Wrapup-India Jun 5 2024-Oct 5 2025 ZS.pptx
Human Resources management _HR structure
Human resources management is a best management
Effective_communication._(strategy).pptx
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
1_Corporate Goverance presentation topic
Leadership for Industry 4.0 And Industry 5.0
Improved_Leadership_in_Total_Quality_Lesson.pptx
The Cyber SwarmShield by Stéphane Nappo
Chapter Three for international political
Mangeroal Finance for Strategic Management
_ISO_Presentation_ISO 9001 and 45001.pptx
Project Management Methods PERT-and-CPM.pptx
The-Power-of-Communication (1).pdf......
Empowering Project Management Through Servant Leadership - PMI UK.pptx
School Annual day Presentation, Logo, Animation
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
Features of Effective decision making in Management

What's new in pmbok guide 6th edition

  • 1. What’s new in PMBOK® Guide 6th Edition
  • 2. Document Objective: This document focuses on several key areas where the concepts of PMBOK Guide 5th edition have been revised. It highlights the changes in Knowledge Areas/Process Groups/Processes as per PMBOK® Guide 6th Edition. Background – The Project Management Institute (PMI)® performs a “Role Delineation Study (RDS)” periodically, every 5 to 7 years . The goal of this study is to identify what are the project managers around the world doing in their current projects and the changing trends and practices in project Management and it updates the content of the exam as per the result of the study. After the most recent RDS, PMI now has a list of tasks that the project managers perform, as well as the knowledge and skills required for the job and upgraded the exam syllabus for PMP certification and that is why there is an upgrade in PMBOK® Guide as well which is the single most important publication by the PMI® for PMP® Certification aspirants to study and prepare for the PMP® Exam.
  • 3. PMBOK® 6th Edition • The 6th edition of the Project Management Body of Knowledge (PMBOK®) Guide was released in September 2017 and PMP® certification exam format has been revised from March 26, 2018. • There are several new sections included in the PMBOK® 6th edition which are as per the changing trends and practices in project management and they’re all packed into a 976-page book, The PMBOK® Guide, 6th Edition. • The most significant addition in PMBOK® 6th edition is a section containing Agile Development. The Agile concept is incorporated in all 10 knowledge areas. Each knowledge area will contain a section entitled Approaches for Agile, Iterative and Adaptive Environments, describing how these practices integrate in project settings.
  • 4. PMBOK® 6th Edition vs. PMBOK® 5th Edition: What’s Changed? • Changes in Process Groups  The number of process groups remains the same in 5th and 6th edition. • Changes In Knowledge Area  Two Knowledge Areas names were changed to more closely reflect the work that is done.  Project Time Management was changed to Project Schedule Management to reflect that the project schedule is defined and managed during the project, whereas time is not managed.  Both team resources and physical resources are addressed in the Sixth Edition. Thus, the Knowledge Area Project Human Resource Management was changed to Project Resource Management. …as per PMBOK®
  • 5. • Changes in the number of Processes There are total 49 processes now in 6th edition as compared to 47 in 5th edition. One process was removed and three new processes were added in 6th edition, to reflect changes in the way projects are managed in practice. One process was moved between Knowledge Areas. These changes are summarized below :  Manage Project Knowledge —Added.  Estimate Activity Resources —Moved to Project Resource Management.  Control Resources —Added.  Implement Risk Responses —Added.  Close Procurements —Eliminated. …as per PMBOK® What’s Changed ? Continued...
  • 6. • Changes in the name of existing processes Several process names were changed to improve consistency across the processes and to improve clarity. Research ndicates that project managers tend to monitor, facilitate, and manage rather than control, particularly in processes that involve interactions with people. Therefore, process names for Control Communications, Control Risks, and Control Stakeholder Engagement were changed to Monitor Communications, Monitor Risks, and Monitor Stakeholder Engagement. The list below summarizes all the process name changes:  Perform Quality Assurance (Section 8.2)—Changed to Manage Quality.  Plan Human Resource Management (Section 9.1)—Changed to Plan Resource Management.  Acquire Project Team (Section 9.2)—Changed to Acquire Resources.  Develop Project Team (Section 9.3)—Changed to Develop Team.  Manage Project Team (Section 9.4)—Changed to Manage Team.  Control Communications (Section 10.3)—Changed to Monitor Communications  Control Risks (Section 11.6)—Changed to Monitor Risks.  Plan Stakeholder Management (Section 13.2)—Changed to Plan Stakeholder Engagement.  Control Stakeholder Engagement (Section 13.4)—Changed to Monitor Stakeholder Engagement. …as per PMBOK® What’s Changed ? Continued...
  • 7. • THE ROLE OF THE PROJECT MANAGER - New section in 6th Edition This is a new section that outlines the project manager’s role in the team. It includes information on the project manager’s sphere of influence and competencies. PMI’s Talent Triangle® is discussed with its emphasis on strategic and business management skills, technical project management skills, and leadership skills. Leadership styles and personality are also discussed as part of this section. The final part of this section focuses on the project manager as an integrator. …as per PMBOK® What’s Changed ? Continued...
  • 8. • AGILE – New Section added in 6th edition Since the Fifth Edition of the PMBOK® Guide there has been more adoption of agile and adaptive methodologies in the management of projects. The Sixth Edition has included a subsection called Considerations for Adaptive Environments at the beginning of Sections 4 through 13. Some agile-specific tools and techniques have been introduced into the PMBOK® Guide, such as sprint and iteration planning. What’s Changed ? Continued...