Construction Cost Engineering:
Work Breakdown
Structure (WBS)
NCE_4402
Work Breakdown Structure
1. Define Work Breakdown Structure (WBS)
2. Identify the levels of Work Breakdown Structure (WBS)
3. Identify the types of Work Breakdown Structure (WBS)
At the end of the lesson, the learner will be able to:
Work Breakdown Structure of Construction Work
Work Breakdown Structure of Construction Work
Work Breakdown Structure of Construction Work
In planning a project, the project manager must structure the work
into smaller elements that are:
Independent
Integratable
Measureable
Work Breakdown
Structure (WBS)
Is a product-oriented family tree subdivision of
the materials, activities, and data required to
produce the end product.
Work Breakdown
Structure (WBS)
Preparation of the WBS also considers other
areas that require structured data, such as
scheduling, configuration management,
contract funding, and technical performance
parameters.
Level of WBS
Total Project
Project
Task
Subtask
01
02
03
04
Work Package
05
Level of Effort
06
Managerial
Levels
Technical
Levels
Level of WBS
Total Project
Project
Task
01
02
03
Managerial
Levels
Used for the
authorization and
release of all
work
Budgets are
prepared
Schedules are
prepared
Types of WBS
Deliverable-Based Work
Breakdown Structure
Phase-Based Work
Breakdown Structure
Deliverable-Based Work
Breakdown Structure
01
Clearly demonstrates the relationship between the project deliverables
and the scope.
• Interim Deliverables
• Ultimate Deliverables
Deliverable-Based Work Breakdown Structure Sample
Construction
of a House
Work = 100%
Budget = Php 2,000,000.00
Foundation
Work = 24%
Budget = 480,000.00
Excavation
Work = 18.2%
Budget = 364,000.00
Steel
Works
Work = 5.8%
Budget = 116,000.00
External
Work = 30.4%
Budget = 608,000.00
Masonry
Works
Work = 16.2%
Budget = 324,000.00
Building
Finishes
Work = 14.2%
Budget = 284,000.00
Internal
Work = 45.60%
Budget = 912,000.00
Electrical
Work = 11.8%
Budget = 236,000.00
Plumbing
Work = 33.8%
Budget = 676,000.00
Phase-Based Work
Breakdown Structure
02
Is also referred to as Verb-oriented, Activity or Task-oriented, or
Process-oriented WBS. The project deliverables are defined in terms of
actions to be taken to attain the final product.
Phase-Based Work Breakdown Structure Sample
Construction
of a House
Design
Land
Acquisition
Permits
Detailed
Design
Bidding
Procurement
Electrical
Plumbing
HVAC
Construction
Structural
Interior
Finishing
Exterior
Finishing
Roofing
Works
Quality
Assurance
Inspection
Masonry Work
Building
Finishes
Turnover
Punchlisting
Closing
COMMON FRAMEWORK OF A WBS
1. The total program can be described as a summation of subdivided
elements.
2. Planning can be performed.
3. Costs and budgets can be established.
4. Time, cost, and performance can be tracked.
5. Objectives can be linked to company resources in a logical manner.
6. Schedules and status-reporting procedures can be established.
7. Network construction and control planning can be initiated.
8. The responsibility assignments for each element can be established.
How to Make a Work Breakdown Structure
Gather
Documents
1 Identify Key
Personnel
2 Define
Level 1
Elements
3
Decompose
(Breakdown)
Elements
4 Create
WBS
Dictionary
5 Create
GANTT
Chart
Schedule
6
WBS
Dictionary
No. Item Code Description
1 WBS Code Enter the WBS Title and identify it as a Work Package, Planning and/or Control Account.
2 Responsible
Organization/
Individual
Name the single organization, group or individual that has been assigned sole responsibility for
making sure the Work Package is completed. Include contact information.
3 Description Define Work Package boundaries. Frame the scope content so that it is clear what scope is
included and excluded. If it is a Planning Package, describe the known and unknown scope.
4 Deliverables Identify the product, service or results created when all of the work in this Work Package is
complete. Include any critical intermediate deliverables.
5 Acceptance
Criteria
Describe the functional and physical requirements in order to meet customer expectations and
quality requirements. Include any unique approvals required for acceptance.
6 Budget Designate the budget for this Work Package, plus any critical resource information and
assumptions.
7 Milestones List any Start Dates, End Dates, Intermediate Milestones, Interdependencies, Constraints and
any assumption for the deliverables.
8 Risks Include any known threats and opportunities with response strategies.
9 Additional
Information
Describe any additional information, such as references, related work packages, etc.
10 Approvals: Date and Revision Date
Work Breakdown Structure of Construction Work
Work Breakdown Structure of Construction Work
Work Breakdown Structure of Construction Work
Work Breakdown Structure of Construction Work
The work breakdown structure can be used to
provide the basis for:
Responsibility
matrix
Network
scheduling
Costing Risk analysis
01 02 03 04
Organizational
structure
Coordination
of objectives
Control
(including contract
administration)
05 06 07
Helpful Tips in Creating WBS
Too much detail
can be
intimidating and
can render the
schedule
useless as a
management
tool. Participants
will ignore it.
With too little
detail, tasks are
omitted. Vague
schedules
cannot be used
as a
management
tool.
More detail is
required at
extremely critical
stages or
sequences.
Tasks that lead
to a milestone
should be
detailed so
nothing is
omitted that
might prevent
the milestone
from occurring.
Tasks that are
performed by
owners,
inspectors, and
design team
membersshould
also be listed.

More Related Content

PPTX
Types of tender and their processing.
PPTX
Tender & Tender Notice
PDF
time cost trade off
PPT
Causes & Damage Detection
PPTX
Subbase Construction.pptx
PDF
Principles of Planning for Residential Buildings
PPTX
Tacheometry ppt
PPTX
Airport lighting
Types of tender and their processing.
Tender & Tender Notice
time cost trade off
Causes & Damage Detection
Subbase Construction.pptx
Principles of Planning for Residential Buildings
Tacheometry ppt
Airport lighting

What's hot (20)

PPSX
Chapter 2 construction project planning and scheduling
PPTX
Price variation in works contracts
ODP
Critical path method
PPTX
Construction planning & management
PPTX
Classification and importance of hill roads
PPTX
6.5 Resource Leveling and Resource Smoothing
PPTX
ch. 5 traffic Island.pptx
PPTX
Canal outlets and modules
PDF
12. Canal Head Regulators.2.pdf
PDF
Float in Projects
PPTX
Estimating and Costing
PPTX
Valuation - Estimation, Costing and Valuation Engineering
PPTX
Point and crossing of railway
PPT
Building Drawing ch 1
PPTX
Estimating, administrative approval, technical sanction, budget provision
PPTX
tendering
PPTX
Types of estimates
PPT
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
PPTX
Tenders and procedure of tendering
PPT
Construction scheduling & Cost control
Chapter 2 construction project planning and scheduling
Price variation in works contracts
Critical path method
Construction planning & management
Classification and importance of hill roads
6.5 Resource Leveling and Resource Smoothing
ch. 5 traffic Island.pptx
Canal outlets and modules
12. Canal Head Regulators.2.pdf
Float in Projects
Estimating and Costing
Valuation - Estimation, Costing and Valuation Engineering
Point and crossing of railway
Building Drawing ch 1
Estimating, administrative approval, technical sanction, budget provision
tendering
Types of estimates
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Tenders and procedure of tendering
Construction scheduling & Cost control
Ad

Similar to Work Breakdown Structure of Construction Work (20)

PPT
Chapter 2 Work Break down Structure1.ppt
PPT
Chapter 2 Work Break down Structure (1).ppt
PPT
project Development Management (Scope Management )
PPT
Lecture 3 Project Management.ppt
PPTX
Team Final_Scope Management
PPTX
2.05 scope management 1
PPT
Chap004
PPT
Chap004
PDF
DOCX
Chapter FourDefining the Project© 2021 McGraw Hill. All ri.docx
PPTX
3 how to scope a project to achieve the quality
PPT
PM Session 4
PDF
workbreakdownstructureppt-130410021152-phpapp02 (1).pdf
PDF
Workbreakdownstructureppt 130410021152-phpapp02
DOCX
83 Chapter 5 PROJECT.docx
PPT
Final_Module_2.ppt
PPTX
Work breakdown structure ppt
PPTX
Work Breakdown Structure Aritrya Kumar.pptx
PDF
Project scope management 2
Chapter 2 Work Break down Structure1.ppt
Chapter 2 Work Break down Structure (1).ppt
project Development Management (Scope Management )
Lecture 3 Project Management.ppt
Team Final_Scope Management
2.05 scope management 1
Chap004
Chap004
Chapter FourDefining the Project© 2021 McGraw Hill. All ri.docx
3 how to scope a project to achieve the quality
PM Session 4
workbreakdownstructureppt-130410021152-phpapp02 (1).pdf
Workbreakdownstructureppt 130410021152-phpapp02
83 Chapter 5 PROJECT.docx
Final_Module_2.ppt
Work breakdown structure ppt
Work Breakdown Structure Aritrya Kumar.pptx
Project scope management 2
Ad

Recently uploaded (20)

PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPT
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
PDF
Abrasive, erosive and cavitation wear.pdf
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PDF
86236642-Electric-Loco-Shed.pdf jfkduklg
PDF
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
PPT
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
PPTX
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
PPTX
Fundamentals of Mechanical Engineering.pptx
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
COURSE DESCRIPTOR OF SURVEYING R24 SYLLABUS
PPT
introduction to datamining and warehousing
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PDF
Soil Improvement Techniques Note - Rabbi
PDF
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
PDF
Integrating Fractal Dimension and Time Series Analysis for Optimized Hyperspe...
PPTX
Information Storage and Retrieval Techniques Unit III
PPTX
communication and presentation skills 01
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
Automation-in-Manufacturing-Chapter-Introduction.pdf
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
Abrasive, erosive and cavitation wear.pdf
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
86236642-Electric-Loco-Shed.pdf jfkduklg
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
Fundamentals of Mechanical Engineering.pptx
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
COURSE DESCRIPTOR OF SURVEYING R24 SYLLABUS
introduction to datamining and warehousing
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
Soil Improvement Techniques Note - Rabbi
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
Integrating Fractal Dimension and Time Series Analysis for Optimized Hyperspe...
Information Storage and Retrieval Techniques Unit III
communication and presentation skills 01
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems

Work Breakdown Structure of Construction Work

  • 1. Construction Cost Engineering: Work Breakdown Structure (WBS) NCE_4402
  • 2. Work Breakdown Structure 1. Define Work Breakdown Structure (WBS) 2. Identify the levels of Work Breakdown Structure (WBS) 3. Identify the types of Work Breakdown Structure (WBS) At the end of the lesson, the learner will be able to:
  • 6. In planning a project, the project manager must structure the work into smaller elements that are: Independent Integratable Measureable
  • 7. Work Breakdown Structure (WBS) Is a product-oriented family tree subdivision of the materials, activities, and data required to produce the end product.
  • 8. Work Breakdown Structure (WBS) Preparation of the WBS also considers other areas that require structured data, such as scheduling, configuration management, contract funding, and technical performance parameters.
  • 9. Level of WBS Total Project Project Task Subtask 01 02 03 04 Work Package 05 Level of Effort 06 Managerial Levels Technical Levels
  • 10. Level of WBS Total Project Project Task 01 02 03 Managerial Levels Used for the authorization and release of all work Budgets are prepared Schedules are prepared
  • 11. Types of WBS Deliverable-Based Work Breakdown Structure Phase-Based Work Breakdown Structure
  • 12. Deliverable-Based Work Breakdown Structure 01 Clearly demonstrates the relationship between the project deliverables and the scope. • Interim Deliverables • Ultimate Deliverables
  • 13. Deliverable-Based Work Breakdown Structure Sample Construction of a House Work = 100% Budget = Php 2,000,000.00 Foundation Work = 24% Budget = 480,000.00 Excavation Work = 18.2% Budget = 364,000.00 Steel Works Work = 5.8% Budget = 116,000.00 External Work = 30.4% Budget = 608,000.00 Masonry Works Work = 16.2% Budget = 324,000.00 Building Finishes Work = 14.2% Budget = 284,000.00 Internal Work = 45.60% Budget = 912,000.00 Electrical Work = 11.8% Budget = 236,000.00 Plumbing Work = 33.8% Budget = 676,000.00
  • 14. Phase-Based Work Breakdown Structure 02 Is also referred to as Verb-oriented, Activity or Task-oriented, or Process-oriented WBS. The project deliverables are defined in terms of actions to be taken to attain the final product.
  • 15. Phase-Based Work Breakdown Structure Sample Construction of a House Design Land Acquisition Permits Detailed Design Bidding Procurement Electrical Plumbing HVAC Construction Structural Interior Finishing Exterior Finishing Roofing Works Quality Assurance Inspection Masonry Work Building Finishes Turnover Punchlisting Closing
  • 16. COMMON FRAMEWORK OF A WBS 1. The total program can be described as a summation of subdivided elements. 2. Planning can be performed. 3. Costs and budgets can be established. 4. Time, cost, and performance can be tracked. 5. Objectives can be linked to company resources in a logical manner. 6. Schedules and status-reporting procedures can be established. 7. Network construction and control planning can be initiated. 8. The responsibility assignments for each element can be established.
  • 17. How to Make a Work Breakdown Structure Gather Documents 1 Identify Key Personnel 2 Define Level 1 Elements 3 Decompose (Breakdown) Elements 4 Create WBS Dictionary 5 Create GANTT Chart Schedule 6
  • 18. WBS Dictionary No. Item Code Description 1 WBS Code Enter the WBS Title and identify it as a Work Package, Planning and/or Control Account. 2 Responsible Organization/ Individual Name the single organization, group or individual that has been assigned sole responsibility for making sure the Work Package is completed. Include contact information. 3 Description Define Work Package boundaries. Frame the scope content so that it is clear what scope is included and excluded. If it is a Planning Package, describe the known and unknown scope. 4 Deliverables Identify the product, service or results created when all of the work in this Work Package is complete. Include any critical intermediate deliverables. 5 Acceptance Criteria Describe the functional and physical requirements in order to meet customer expectations and quality requirements. Include any unique approvals required for acceptance. 6 Budget Designate the budget for this Work Package, plus any critical resource information and assumptions. 7 Milestones List any Start Dates, End Dates, Intermediate Milestones, Interdependencies, Constraints and any assumption for the deliverables. 8 Risks Include any known threats and opportunities with response strategies. 9 Additional Information Describe any additional information, such as references, related work packages, etc. 10 Approvals: Date and Revision Date
  • 23. The work breakdown structure can be used to provide the basis for: Responsibility matrix Network scheduling Costing Risk analysis 01 02 03 04 Organizational structure Coordination of objectives Control (including contract administration) 05 06 07
  • 24. Helpful Tips in Creating WBS Too much detail can be intimidating and can render the schedule useless as a management tool. Participants will ignore it. With too little detail, tasks are omitted. Vague schedules cannot be used as a management tool. More detail is required at extremely critical stages or sequences. Tasks that lead to a milestone should be detailed so nothing is omitted that might prevent the milestone from occurring. Tasks that are performed by owners, inspectors, and design team membersshould also be listed.