Work
Measurement
and
Productivity


    Presented by:

        MD. NAZIR ANSARI

            ANSHUL GARG
Work Measurement
 Work Measurement: establish a
  measurable work standard upon which
  to evaluate, compare and improve labor
  productivity.
 Work (labor) Standard: Determine on
  average-how many labor-hour are
  required to produce one unit of desired
  output for a well-trained worker under
  normal operating conditions
Work Measurement Continue…
 Level of standard:
    * Operations/Department/Plant standards
    * Element/Operations/Product standards
 Use of work standard:
    * Work and personnel planning
    * Cost estimation for labor and machine
 Techniques to set work standard:
    * Time study
    * Work sampling
    * Elemental timing
    * Predetermined motion-time study
Three Levels of Standards
 Production and operations standards:
  individuals job standards
 Department standards: sum of
  performance of the individual and team
  in a department
 Plant standards: quantity and labor
  standards of the plant are the goals
  management strives to meet
Evaluation Performance
   Evaluating individual performance:
    subsequent compensation
   Evaluating department performance:
    subsequent supervisor compensation
   Evaluating process design, layout, and
    work methods
   Estimating expense and revenue streams
    in equipment evaluation as alternative are
    compared
   Formulating standards costs
Predicting, Planning, and
     Controlling Operations
 Aggregate planning of work force levels
  and production rates
 Capacity planning and utilization
 Scheduling operations: time sequencing
  jobs
 Cost estimating of products and
  production lots
 Planning types of labor skills necessary
  and budgeting labor expenses
Work Measurement- Average
             Worker
 Determined by observing several
  workers and estimating their average
  performance
 Sampling costs increase with number of
  workers sampled: accuracy of estimate
  increases as sample size increases
 Must tradeoff sampling cost and
  accuracy
How to Determine “Average Worker” Standard
                    ?
         Example from Distribution of 100 Workers Sample

   Number of          Performance in Units
   Workers Sampled
                      Per Hour        Mean

   5                  10-14           12         *5%       =0.6
   20                 15-19           17         *20%      =3.4
   45                 20-24           22         *45%      =9.9
   25                 25-29           27         *25%      =6.75
   5                  30-34           32         *5%       =1.6
   100                                           Total =   22.5
Work Measurement Time
             Study
                           Normal time
   Standards time=
                          (1-allowance)

   Normal time= (average cycle time)* (rating factor)
                       Time recorded to perform an element
   Average cycle time=
                           Number of cycles observed

   Allowance fraction= fraction of time for personal
    needs, unavoidable work delays, fatigue
Work Measurement- Work
Sampling
   Purpose:
      To estimate what proportion of a worker’s time
       is devoted to work activities
   Main Issues:
      What level of statistical confidence is desired
       in the results?
      How many observations are necessary

   Primary Applications:
      Time standards: to obtain the standards time
       for a task
Work Measurement- Work Sampling
              Formulas
                                  Proportion of
                                  Time Employee      Performance
               Total Study Time * Observed Working * Rating Factor
Normal Time=
                            Number of Units Produced




 Proportional of       Number of observations in which working occurred
 Time Employee    =
 Observed Working                  Number of Observations

                        x
        Or
                  P=
                        n
Work Measurement- Work
     Sampling Formulas
Example:    N= 100 (observations)
            X= 83 (sampled worker is working)
            P= 83/100 = 0.83

Given:           Total Study Time = 37.5
  (hours)
            Rating Factor = 1.05
            Number of Units Produced = 100

Normal Time:     = (37.5*0.83*1.05)/100
                 = 1/3 (hours)
                 = 20 (min)
Work Measurement- Elemental
       Standards- Time Data

 Elemental Standards- time data tables
  contain performance time for operations
  that are common to many applications
 Used where numerous configuration of
  product make detailed time study of each
  configuration impractical
Work Measurement- Predetermined
      Motion- Time Study
   Description: used in the planning process
    when the jobs are not currently being
    performed
   Can also be an alternative to observed
    time studies
   Basis in the historical information on basic
    human movement and motion such as
    reaching, gasping, lifting, etc.
   Elemental times have been developed for
    the basic human motion
   Commonly industry specific
Measurement Problems
   Quality may change while the quantity
    of inputs and outputs remains
    constant
   External elements may cause an
    increase or decrease in productivity
   Precise units of measure may be
    lacking
Productivity

                      Units produced
     Productivity =
                        Input used

   Measure of process improvement
   Represents output relative to input
   Only through productivity increases
    can our standard of living improve
Productivity Calculation

 Labour Productivity
                          Units produced
   Productivity =
                        Labour-hours used

                        1,000
                    =           = 4 units/labour-hour
                        250

One resource input  single-factor productivity
Example
Multi-Factor Productivity
                               Output
 Productivity =
                    Labor + Material + Energy +
                      Capital + Miscellaneous
      Also known as total factor productivity
      Output and inputs are often expressed in
       dollars

Multiple resource inputs  multi-factor productivity
Example
Productivity Variables
   Labor - contributes about 10% of the
    annual increase

   Capital - contributes about 38% of the
    annual increase

   Management - contributes about 52%
    of the annual increase
Key Variables for Improved
Labor Productivity
   Basic education appropriate for the labor
    force
   Diet of the labor force
   Social overhead that makes labor
    available
   Maintaining and enhancing skills in the
    midst of rapidly changing technology and
    knowledge
Service Productivity
   Typically labor intensive
   Frequently focused on unique individual
    attributes or desires
   Often an intellectual task performed by
    professionals
   Often difficult to mechanize
   Often difficult to evaluate for quality
Conclusion
Work measurement and productivity

More Related Content

PPTX
Work measurement
PPT
17.maintenance and reliability
PPT
Work Study
PPTX
Recording techniques in method study
PDF
Work study method study-work measurement
PPTX
Maintenance management
PPTX
Applied Operation Research (AOR) Replacement Theory
PPTX
Tools for capacity planning, measurement of capacity, capacity planning process
Work measurement
17.maintenance and reliability
Work Study
Recording techniques in method study
Work study method study-work measurement
Maintenance management
Applied Operation Research (AOR) Replacement Theory
Tools for capacity planning, measurement of capacity, capacity planning process

What's hot (20)

PPT
Work study - production and operations management
PPTX
Contemporary issues in hrm
PPT
Work measurement
PPTX
Assembly line balancing
PPTX
TIME STUDY
PPTX
Forecasting and methods of forecasting
PPT
Method Study
PPT
Time And Motion Study
PPT
Inventory models
PPTX
Cost Control & Cost Reduction ppt
PPT
PPTX
Time study
PPT
Work sample
PPTX
Inventory model (operation research)
PPTX
Line balancing
PPTX
AGGREGATE PRODUCTION PLANNING
PPT
Incentive plan presentation
PDF
4.4 wage and wage incentive plans
PPT
Aggregate Planning
Work study - production and operations management
Contemporary issues in hrm
Work measurement
Assembly line balancing
TIME STUDY
Forecasting and methods of forecasting
Method Study
Time And Motion Study
Inventory models
Cost Control & Cost Reduction ppt
Time study
Work sample
Inventory model (operation research)
Line balancing
AGGREGATE PRODUCTION PLANNING
Incentive plan presentation
4.4 wage and wage incentive plans
Aggregate Planning
Ad

Viewers also liked (20)

PDF
Work measurement
PPTX
Productivity
PPTX
Work measurement (1)
PPTX
Basic of work study, work measurement & job design om
PPTX
Work study work measurement
PPTX
cycle time, normal time and standard allowance
PPT
Work Study: Method Study & Work Measurement
PPT
Work Measurement and Operational Effectiveness
PPT
work measurement_operation management
PDF
Productivity, Productivity, Productivity
PPT
Job Design and Work Measurement
PPTX
1. productivity concept and calculation.
PPTX
7. work study and method measurement
PDF
Work measurement
PPTX
Techniques for measurement of productivity
PPTX
Work study
PPTX
Productivity
PDF
Motion and time study
PPT
Ch11
Work measurement
Productivity
Work measurement (1)
Basic of work study, work measurement & job design om
Work study work measurement
cycle time, normal time and standard allowance
Work Study: Method Study & Work Measurement
Work Measurement and Operational Effectiveness
work measurement_operation management
Productivity, Productivity, Productivity
Job Design and Work Measurement
1. productivity concept and calculation.
7. work study and method measurement
Work measurement
Techniques for measurement of productivity
Work study
Productivity
Motion and time study
Ch11
Ad

Similar to Work measurement and productivity (20)

PPT
Production & Operation Management
PPT
Work study method and time study-final - copy
PPT
Work study method-and_time_study-final
PPT
Introduction to Work Study .ppt
PPT
module 3 OM.ppt
PPTX
Improving the productivity_and_introducing_the_work_study
PPTX
Chapter-7 Job Design and Work Measurement Final.pptx
PDF
Good work measurement
PPT
What is Industial Engineering
PPTX
Chapter 11 Work System Design discussion.pptx
PPTX
Chapter 11 Work System Design Discussion.pptx
PDF
WORK STUDY -method study & time study all in one.pdf
DOC
Employee productivity and Role of HR
DOC
Employee productivity
PPTX
dr. ibrahima abdi hassan this is the 535472485-Productivity-1.pptx
PPTX
Work study and productivity index
PPTX
Efficiency
PDF
OPERATION UNIT 1.pdf VERY USEFUL TO LEARN
PPT
P roduction ppt
PPTX
Work study ......operational management presentation
Production & Operation Management
Work study method and time study-final - copy
Work study method-and_time_study-final
Introduction to Work Study .ppt
module 3 OM.ppt
Improving the productivity_and_introducing_the_work_study
Chapter-7 Job Design and Work Measurement Final.pptx
Good work measurement
What is Industial Engineering
Chapter 11 Work System Design discussion.pptx
Chapter 11 Work System Design Discussion.pptx
WORK STUDY -method study & time study all in one.pdf
Employee productivity and Role of HR
Employee productivity
dr. ibrahima abdi hassan this is the 535472485-Productivity-1.pptx
Work study and productivity index
Efficiency
OPERATION UNIT 1.pdf VERY USEFUL TO LEARN
P roduction ppt
Work study ......operational management presentation

Recently uploaded (20)

PPTX
DPT-MAY24.pptx for review and ucploading
PPTX
Overview Planner of Soft Skills in a single ppt
PDF
Daisia Frank: Strategy-Driven Real Estate with Heart.pdf
PPT
Gsisgdkddkvdgjsjdvdbdbdbdghjkhgcvvkkfcxxfg
PPTX
PE3-WEEK-3sdsadsadasdadadwadwdsdddddd.pptx
PDF
Blue-Modern-Elegant-Presentation (1).pdf
PDF
Entrepreneurship PowerPoint for students
PPTX
PMP (Project Management Professional) course prepares individuals
PPTX
A slide for students with the advantagea
PPTX
OnePlus 13R – ⚡ All-Rounder King Performance: Snapdragon 8 Gen 3 – same as iQ...
PPTX
ESD MODULE-5hdbdhbdbdbdbbdbdbbdndbdbdbdbbdbd
PPTX
Definition and Relation of Food Science( Lecture1).pptx
PPTX
Principles of Inheritance and variation class 12.pptx
PPTX
chapter 3_bem.pptxKLJLKJLKJLKJKJKLJKJKJKHJH
PPTX
Your Guide to a Winning Interview Aug 2025.
DOC
field study for teachers graduating samplr
PDF
APNCET2025RESULT Result Result 2025 2025
PDF
Why Today’s Brands Need ORM & SEO Specialists More Than Ever.pdf
DOCX
How to Become a Criminal Profiler or Behavioural Analyst.docx
PPTX
microtomy kkk. presenting to cryst in gl
DPT-MAY24.pptx for review and ucploading
Overview Planner of Soft Skills in a single ppt
Daisia Frank: Strategy-Driven Real Estate with Heart.pdf
Gsisgdkddkvdgjsjdvdbdbdbdghjkhgcvvkkfcxxfg
PE3-WEEK-3sdsadsadasdadadwadwdsdddddd.pptx
Blue-Modern-Elegant-Presentation (1).pdf
Entrepreneurship PowerPoint for students
PMP (Project Management Professional) course prepares individuals
A slide for students with the advantagea
OnePlus 13R – ⚡ All-Rounder King Performance: Snapdragon 8 Gen 3 – same as iQ...
ESD MODULE-5hdbdhbdbdbdbbdbdbbdndbdbdbdbbdbd
Definition and Relation of Food Science( Lecture1).pptx
Principles of Inheritance and variation class 12.pptx
chapter 3_bem.pptxKLJLKJLKJLKJKJKLJKJKJKHJH
Your Guide to a Winning Interview Aug 2025.
field study for teachers graduating samplr
APNCET2025RESULT Result Result 2025 2025
Why Today’s Brands Need ORM & SEO Specialists More Than Ever.pdf
How to Become a Criminal Profiler or Behavioural Analyst.docx
microtomy kkk. presenting to cryst in gl

Work measurement and productivity

  • 1. Work Measurement and Productivity Presented by: MD. NAZIR ANSARI ANSHUL GARG
  • 2. Work Measurement  Work Measurement: establish a measurable work standard upon which to evaluate, compare and improve labor productivity.  Work (labor) Standard: Determine on average-how many labor-hour are required to produce one unit of desired output for a well-trained worker under normal operating conditions
  • 3. Work Measurement Continue…  Level of standard: * Operations/Department/Plant standards * Element/Operations/Product standards  Use of work standard: * Work and personnel planning * Cost estimation for labor and machine  Techniques to set work standard: * Time study * Work sampling * Elemental timing * Predetermined motion-time study
  • 4. Three Levels of Standards  Production and operations standards: individuals job standards  Department standards: sum of performance of the individual and team in a department  Plant standards: quantity and labor standards of the plant are the goals management strives to meet
  • 5. Evaluation Performance  Evaluating individual performance: subsequent compensation  Evaluating department performance: subsequent supervisor compensation  Evaluating process design, layout, and work methods  Estimating expense and revenue streams in equipment evaluation as alternative are compared  Formulating standards costs
  • 6. Predicting, Planning, and Controlling Operations  Aggregate planning of work force levels and production rates  Capacity planning and utilization  Scheduling operations: time sequencing jobs  Cost estimating of products and production lots  Planning types of labor skills necessary and budgeting labor expenses
  • 7. Work Measurement- Average Worker  Determined by observing several workers and estimating their average performance  Sampling costs increase with number of workers sampled: accuracy of estimate increases as sample size increases  Must tradeoff sampling cost and accuracy
  • 8. How to Determine “Average Worker” Standard ? Example from Distribution of 100 Workers Sample Number of Performance in Units Workers Sampled Per Hour Mean 5 10-14 12 *5% =0.6 20 15-19 17 *20% =3.4 45 20-24 22 *45% =9.9 25 25-29 27 *25% =6.75 5 30-34 32 *5% =1.6 100 Total = 22.5
  • 9. Work Measurement Time Study Normal time  Standards time= (1-allowance)  Normal time= (average cycle time)* (rating factor) Time recorded to perform an element  Average cycle time= Number of cycles observed  Allowance fraction= fraction of time for personal needs, unavoidable work delays, fatigue
  • 10. Work Measurement- Work Sampling  Purpose:  To estimate what proportion of a worker’s time is devoted to work activities  Main Issues:  What level of statistical confidence is desired in the results?  How many observations are necessary  Primary Applications:  Time standards: to obtain the standards time for a task
  • 11. Work Measurement- Work Sampling Formulas Proportion of Time Employee Performance Total Study Time * Observed Working * Rating Factor Normal Time= Number of Units Produced Proportional of Number of observations in which working occurred Time Employee = Observed Working Number of Observations x Or P= n
  • 12. Work Measurement- Work Sampling Formulas Example: N= 100 (observations) X= 83 (sampled worker is working) P= 83/100 = 0.83 Given: Total Study Time = 37.5 (hours) Rating Factor = 1.05 Number of Units Produced = 100 Normal Time: = (37.5*0.83*1.05)/100 = 1/3 (hours) = 20 (min)
  • 13. Work Measurement- Elemental Standards- Time Data  Elemental Standards- time data tables contain performance time for operations that are common to many applications  Used where numerous configuration of product make detailed time study of each configuration impractical
  • 14. Work Measurement- Predetermined Motion- Time Study  Description: used in the planning process when the jobs are not currently being performed  Can also be an alternative to observed time studies  Basis in the historical information on basic human movement and motion such as reaching, gasping, lifting, etc.  Elemental times have been developed for the basic human motion  Commonly industry specific
  • 15. Measurement Problems  Quality may change while the quantity of inputs and outputs remains constant  External elements may cause an increase or decrease in productivity  Precise units of measure may be lacking
  • 16. Productivity Units produced Productivity = Input used  Measure of process improvement  Represents output relative to input  Only through productivity increases can our standard of living improve
  • 17. Productivity Calculation Labour Productivity Units produced Productivity = Labour-hours used 1,000 = = 4 units/labour-hour 250 One resource input  single-factor productivity
  • 19. Multi-Factor Productivity Output Productivity = Labor + Material + Energy + Capital + Miscellaneous  Also known as total factor productivity  Output and inputs are often expressed in dollars Multiple resource inputs  multi-factor productivity
  • 21. Productivity Variables  Labor - contributes about 10% of the annual increase  Capital - contributes about 38% of the annual increase  Management - contributes about 52% of the annual increase
  • 22. Key Variables for Improved Labor Productivity  Basic education appropriate for the labor force  Diet of the labor force  Social overhead that makes labor available  Maintaining and enhancing skills in the midst of rapidly changing technology and knowledge
  • 23. Service Productivity  Typically labor intensive  Frequently focused on unique individual attributes or desires  Often an intellectual task performed by professionals  Often difficult to mechanize  Often difficult to evaluate for quality