SlideShare a Scribd company logo
Building Structures [ARC 2522]
Project 2 [Extension of a Reinforced Concrete Bungalow]
No.3 Bukit Tiara 1, Taman Billion, 56100, Kuala Lumpur,
Malaysia
Name Student ID
Tan Wen Yee 0315155
Jeremy Tay Eujin 0312228
Lecturer: Ms Norita
Submission Date: Week 12 (19th June 2014, Friday)
Introduction
The project is an integrated component where it involves structural theory, force
calculation and basic structural proposal. This project is designed to allow the
demonstration of knowledge and understanding of building structure.
Objectives of Project
The objectives of this project are as follows:
1. To introduce the basic process of building structures design process to the
students.
2. To enable the students to have a holistic experience including Concept and
Structure Layout Design, Building Structure Engineering Considerations,
Structure Members Sizing and Calculations, Final Report and Presentation.
Learning Outcomes
1. Produce a complete documentation on structural systemof a case study
2. Explore and understand the concept of structural analysis
3. Identification of structural components
4. Recognize, Execute and implement basic procedures of building structure design
5. Produce a structural proposal
Ground Floor
Extension Plan
Scale 1:150
First Floor
Extension Plan
Scale 1:150
Foundation
Extension Plan
Scale 1:150
Ground Floor
Structural Plan
Scale 1:150
First Floor
Structural Plan
Scale 1:150
Roof
Structural Plan
Scale 1:150
Building Structure Project 2
Quantity DeadLoads Acting On
Structure
GroundFloor
Extended Dining Room
Slab thickness = 150mm
Slab self-weight = 0.15m x 24kN/m³
= 3.6 kN/m²
Extended Kitchen
Slab thickness = 150mm
Slab self-weight = 0.15m x 24kN/m³
= 3.6 kN/m²
Tearoom
Slab thickness = 150mm
Slab self-weight = 0.15m x 24kN/m³
= 3.6 kN/m²
First Floor
Library
Slab thickness = 150mm
Slab self-weight = 0.15m x 24kN/m³
= 3.6 kN/m²
Corridor
Slab thickness = 150mm
Slab self-weight = 0.15m x 24kN/m³
= 3.6 kN/m²
Balcony
Slab thickness = 100mm
Slab self-weight = 0.1m x 24kN/m³
= 2.4 kN/m²
Gymnasium
Slab thickness = 150mm
Slab self-weight = 0.15m x 24kN/m³
= 3.6 kN/m²
Brick Wall:
=Wall Height x Thickness x Density
=3.4m x0.15m x19kN/ m³
=10kN/m
Beam SelfWeight:
(Assume that initial beamsize125mmx600mm)
=Beam Size x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Quantity Live Loads Acting On
Structure
GroundFloor
Diningroom:
2.0 kN/m²
Kitchen:
2.0 kN/m²
Tearoom:
2.0 kN/m²
First Floor
Library:
2.5 kN/m²
Corridor
1.5 kN/m²
Balcony
1.5 kN/m²
Gymnasium:
5.0 kN/m²
(According to 4th Schedule of UBBL for live
load according to the function of the space)
Identify One Way or Two Way Slab
Indicating the Distribution of Load from Slab to Beam
Ly= Longer side of slab
Lx= Shorter side of slab
When Ly / Lx >2 or =2, it is a one way slab.
When Ly / Lx <2, it is a two way slab.
Ground Floor
ExtendedDiningRoom
=4025 ÷ 3500
=1.15 < 2 (TwoWay Slab)
ExtendedKitchen
=3500 ÷ 2975
=1.18 < 2 (TwoWay Slab)
=2500 ÷ 2000
=1.25 < 2 (TwoWay Slab)
Tearoom
=9000 ÷ 3500
=2.57 > 2 (One Way Slab)
First Floor
Library
=4025 ÷ 3500
=1.15 < 2 (TwoWay Slab)
Corridor
=3500 ÷ 2975
=1.18 < 2 (TwoWay Slab)
Balcony
= 6000 ÷ 2000
=3 > 2 (One Way Slab)
Gymnasium
=7000 ÷ 3500
=2= 2 (TwoWay Slab)
Beam Analysis Calculation
Ground Floor Beam, A /1-4
1) Carries Self Weight – Dead Load
2) Slab- Dead Load & Live Load
 A-B/1-4 ( One Way)
3) Brick Wall – Dead Load
Beam Self Weight =Beam Size x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Brick Wall =Wall Height x Thickness x Density
=3.4m x0.15m x19kN/ m³
=10kN/m
Dead Load on Slab A-B/1-4 ( One Way Slab)
Load is transferred to beam A/1-4 in UDL form.
Dead Load from Slab A-B/1-4 = Dead Load on Slab x ( Lx/2)
= 3.6 kN/m²x (3.5/2)
= 6.3kN/m
Total Deal Load
= BeamSelf Weight + Dead Load on Slab + Brick Wall
= 1.8kN/m + 6.3kN/m + 10kN/m
= 18.1kN/m
Total Dead Load Diagram
9000
1 4
Beam self-weight = 1.8 kN/m
Brick wall weight = 10 kN/m
DL from slab A-B /1-4=6.3kN/m
Total DL = 18.1kN/m
Live Load on Slab A-B/1-4 ( One Way Slab)
Load is transferred to beam A/1-4 in UDL form.
Live Load from slab A-B/1-4 = Live Load on Slab x ( Lx/2)
= 2.0 kN/m² x (3.5/2)
= 3.5 kN/m
Total Live Load
= Live Load on Slab
= 3.5 kN/m
Total Live Load Diagram
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab A-B/1-4 =18.1kN/m x 1.4
= 25.34kN/m
Live Load on Slab A-B/1-4 = 3.5kN/m x 1.6
= 5.6kN/m
Ultimate Load = 25.34kN/m + 5.6kN/m
=30.94kN/m
9000
1 4
Total Live load = 3.5 kN/m
9000
1 4
Ultimate Load = 30.94 kN/m
Reaction Force
ΣM = 0
= R4 (9) – 30.94 kN/m (9) (9/2)
= 9 R4-1253.07
9 R4=1253.07
R4 =139.23kN
ΣFY = 0
= R4 + R1 – 30.94kN/m (9)
=139.23 + R1 – 278.46
R1 =278.46-139.23
=139.23kN
9000
1 4
Ultimate Load = 30.94 kN/m
139.23 kN
-139.23 kN
313.26
139.23 kN 139.23 kN
Load Diagram
Shear Force
Diagram
BendingMoment
Diagram
Beam Analysis Calculation
Ground Floor Beam, B-D /3
1) Carries Self Weight – Dead Load
2) Slab- Dead Load & Live Load
 B-D/2-3 ( Two Way)
 B-D/3-4 ( Two Way)
 Brick Wall – Dead Load
Beam Self Weight =Beam Size x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Brick Wall =Wall Height x Thickness x Density
=3.4m x0.15m x19kN/ m³
=10kN/m
Dead Load on Slab B-D/2-3 (Two Way Slab)
Load is transferred to beam B-D/3 a trapezoidal form.
Convert trapezoidal load into UDL.
Dead Load from Slab A-B/1-4 = Dead Load on Slab x (Lx/2)
= 3.6 kN/m² x (2.975/2)
= 5.355kN/m
Dead Load on Slab B-D/3-4 (Two Way Slab)
Load is transferred to beam B-D/3 a triangular form.
Dead Load from Slab A-B/1-4 = Dead Load on Slab x (Lx/2)
= 3.6 kN/m² x (3.5/2)
= 6.3kN/m
Convert triangular load into UDL by applying factor of 2/3.
Dead load =2/3 x 6.3kN/m
=4.2kN/m
Total Deal Load
= BeamSelf Weight + Dead Load on Slab + Brick Wall
= 1.8kN/m + 5.355kN/m+ 4.2kN/m + 10kN/m
= 21.355kN/m
Total Dead Load Diagram
3500
B D
Beam Self Weight=1.8kN/m
weWEoghtWEight
Brick wall weight = 10 kN/m
DL from slab B-D/2-3=5.355kN/m
DL from slab B-D/3-4=4.2kN/m
Total Dead Load=21.355kN/m
Live Load on Slab B-D/2-3 ( Two Way Slab)
Load is transferred to beam B-D/3 in a trapezoidal form.
Convert trapezoidal load into UDL.
Live load from Slab B-D/3-4 = Live load on slab x ( Lx/2)
= 2.0kN/m²x ( 2.975/2)
= 2.975kN/m
Live Load on Slab B-D/3-4 ( Two Way Slab)
Load is transferred to beam B-D/3 in a triangular form.
Live load from Slab B-D/2-3 = Live load on slab x ( Lx/2)
= 2.0kN/m²x ( 3.5/2)
= 3.5kN/m
Convert triangular load into UDL by applying factor of 2/3.
Live load =2/3 x 3.5kN/m
=2.333kN/m
Total Live Load
= Live Load on Slab
=2.975kN/m+2.333kN/m
=5.308kN/m
Total Live Load Diagram
3500
B D
LL fromslabB-D/2-3 =2.975kN/m
LL fromslabB-D/3-4=2.333kN/m
Total Live Load=5.308kN/m
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab B-D/2-4 =21.355kN/m x 1.4
= 29.897kN/m
Live Load on Slab B-D/2-4 = 5.308kN/m x 1.6
= 8.493kN/m
Ultimate Load = 29.897kN/m + 8.493kN/m
=38.39kN/m
Ultimate Load Diagram
3500
B D
Ultimate Load=38.39kN/m
Reaction Force
ΣM = 0
= Rd (3.5) – 38.39 kN/m (3.5) (3.5/2)
= 3.5 Rb-235.14
3.5 Rd =235.14
Rd =67.18kN
ΣFY = 0
= Rd + Rb– 38.39kN/m (3.5)
=67.18 + Rb -134.37
Rb =134.37-67.18
=67.19kN
3500
B D
67.19 kN
-67.18 kN
57.78
Ultimate Load=38.39kN/m
67.19 kN 67.18 kN
Load Diagram
Shear Force
Diagram
BendingMoment
Diagram
Beam Analysis Calculation
Ground Floor Beam, B /1-4
1. Carries Self Weight – Dead Load
2. Slab- Dead Load & Live Load
 A-B/1-4 ( One Way)
 B-C/1-2 ( Two Way)
 B-D/2-3 (Two Way)
 B-D/3-4 (Two Way)
3. Brick Wall – Dead Load
Beam Self Weight =BeamSize x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Brick Wall =Wall Height x Thickness x Density
=3.4m x0.15m x19kN/ m³
=10kN/m
Dead Load on Slab A-B/1-4 ( One Way Slab)
Load is transferred to beam A/1-4 in UDL form.
Dead Load from Slab A-B/1-4 = Dead Load on Slab x ( Lx/2)
= 3.6 kN/m² x (3.5/2)
= 6.3kN/m
Dead Load on Slab B-C/1-2 ( Two Way Slab)
Load is transferred to beam B/1-4 in a triangular form.
Dead load from Slab B-C/1-2 = Dead load on slab x ( Lx/2)
= 3.6kN/m²x ( 2/2)
= 3.6kN/m
Convert triangular load into UDL by applying factor of 2/3.
Dead load =2/3 x 3.6kN/m
=2.4kN/m
Dead Load on Slab B-D/2-3 ( Two Way Slab)
Load is transferred to beam B/1-4 in a triangular form.
Dead load from Slab B-D/2-3 = Dead load on slab x ( Lx/2)
= 3.6kN/m²x ( 2.975/2)
= 5.355kN/m
Convert triangular load into UDL by applying factor of 2/3.
Dead load =2/3 x 5.355kN/m
=3.57kN/m
Dead Load on Slab B-D/3-4 ( Two Way Slab)
Load is transferred to beam B/1-4 in a trapezoidal form.
Convert trapezoidal load into UDL.
Dead load from Slab B-C/1-2 = Dead load on slab x ( Lx/2)
= 3.6kN/m²x ( 3.5/2)
= 6.3kN/m
Total Dead Load
Total for 1-2= Beam Self Weight + Dead Load on Slab + Brick Wall
= 1.8kN/m + 6.3kN/m+2.4kN/m + 10kN/m
= 20.5kN/m
Total for 2-3 = Beam Self Weight + Dead Load on Slab + Brick Wall
=1.8kN/m + 6.3kN/m + 3.57kN/m + 10kN/m
=21.67kN/m
Total for 3-4 = Beam Self Weight + Dead Load on Slab+Brick Wall
=1.8kN/m + 6.3kN/m+6.3kN/m+10kN/m
=24.4kN/m
Total Dead Load Diagram
2000
1 4
Beam Self Weight=1.8kN/m
weWEoghtWEight
Brick wall weight = 10 kN/m
DL from slab A-B/1-4=6.3kN/m
DL from slab B-C/1-2=2.4kN/m
DL fromslabB-D/2-3=3.57kN/m
2
1
3
12975 4025
2000
1 4
DL from slab B-D/3-4=6.3kN/m
Total Dead Load
2
1
3
12975 4025
20.5kN/m 21.67kN/m 24.4kN/m
Live Load on Slab A-B/1-4 ( One Way Slab)
Load is transferred to beam A/1-4 in UDL form.
Live Load from slab A-B/1-4 = Live Load on Slab x ( Lx/2)
= 2.0 kN/m² x (3.5/2)
= 3.5 kN/m
Live Load on Slab B-C/1-2 ( Two Way Slab)
Load is transferred to beam B/1-4 in a triangular form.
Live load from Slab B-C/1-2 = Live load on slab x ( Lx/2)
= 2.0kN/m²x ( 2/2)
= 2.0kN/m
Convert triangular load into UDL by applying factor of 2/3.
Live load =2/3 x 2.0kN/m
=1.33kN/m
Live Load on Slab B-D/2-3 ( Two Way Slab)
Load is transferred to beam B/1-4 in a triangular form.
Live load from Slab B-D/2-3 = Live load on slab x ( Lx/2)
= 2.0kN/m²x ( 2.975/2)
= 2.975kN/m
Convert triangular load into UDL by applying factor of 2/3.
Dead load =2/3 x 2.975kN/m
=1.983kN/m
Live Load on Slab B-D/3-4 ( Two Way Slab)
Load is transferred to beam B/1-4 in a trapezoidal form.
Convert trapezoidal load into UDL.
Live load from Slab B-D/3-4 = Live load on slab x ( Lx/2)
= 2.0kN/m²x ( 3.5/2)
= 3.5kN/m
Total Live Load
Total for 1-2 = 3.5kN/m+1.33kN/m
=4.83kN/m
Total for 2-3 = 3.5kN/m+1.983kN/m
=5.483kN/m
Total for 3-4 = 3.5kN/m+3.5kN/m
=7.0kN/m
Live Load Diagram
2000
1 4
LL from A-B/1-4=3.5kN/m
weWEoghtWEight
LL from B-C/1-2=1.33kN/m
LL fromslabB-D/3-4=3.5kN/m
2
1
3
12975 4025
LL from B-D/2-3=1.983kN/m
Total Live Load
4.83kN/m 5.483kN/m 7.0kN/m
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab 1-2 = 20.5kN/m x 1.4
= 28.7kN/m
Dead Load on Slab 2-3 =21.67kN/m x 1.4
= 30.34kN/m
Dead Load on Slab 3-4 =24.4kN/m x 1.4
= 34.16kN/m
Live Load on Slab 1-2 = 4.83kN/m x 1.6
= 7.73kN/m
Live Load on Slab 2-3 = 5.483kN/m x 1.6
= 8.77kN/m
Live Load on Slab 3-4 = 7.0kN/m x 1.6
= 11.2kN/m
Ultimate Load for 1-2 = 28.7kN/m+7.73kN/m
= 36.43kN/m
Ultimate Load for 2-3 = 30.34kN/m+8.77kN/m
= 39.11kN/m
Ultimate Load for 3-4 = 34.16kN/m+11.2kN/m
= 45.36kN/m
2000
1 42
1
3
12975 4025
Ultimate Load
36.43kN/
m
39.11kN/m 45.36kN/m
Reaction Force
ΣM = 0
= R4 (9) – 45.36 kN/m (4.025) (6.99) – 39.11kN/m(2.975)(2.538)- 36.43kN/m (2)(1)-
67.19(4.975)
= 9R4 – 1276.19-295.3-72.86-334.27
9R4 =1978.62
R4 =219.85kN
ΣFY = 0
= R4 + R1–45.36(4.025)-39.11(2.975)-36.43(2)-67.19(4.975)
=219.85 + R1-706.05
R1 =706.05-219.85
=486.2kN
2000
1 42
1
3
12975 4025
36.43kN/m 39.11kN/m 45.36kN/m
413.24kN
296.99kN
-37.28kN
-163.5kN
Load Diagram
Shear Force
Diagram
BendingMoment
Diagram
Beam Analysis Calculation
Ground Floor Beam, B-C /1
1)Carries Self Weight – Dead Load
2)Slab- Dead Load & Live Load
 B-C/1-2 ( Two Way)
3)Brick Wall – Dead Load
Beam Self Weight =Beam Size x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Brick Wall =Wall Height x Thickness x Density
=3.4m x0.15m x19kN/ m³
=10kN/m
Dead Load on Slab B-C/1-2 ( Two Way Slab)
Load is transferred to beam B-C/1 in trapezoidal form.
Convert trapezoidal load into UDL.
Dead Load from Slab B-C/1-2 = Dead Load on Slab x ( Lx/2)
= 3.6 kN/m² x (2/2)
= 3.6 kN/m
Total Deal Load
= BeamSelf Weight + Dead Load on Slab + Brick Wall
= 1.8kN/m + 3.6kN/m + 10kN/m
= 15.4kN/m
Total Dead Load Diagram
2500
B C
Beam self-weight = 1.8 kN/m
Brick wall weight = 10 kN/m
DL from slab B-C/1-2=3.6kN/m
Total DL = 15.4kN/m
Live Load on Slab B-C/1-2 ( Two Way Slab)
Load is transferred to beam B-C/1 in trapezoidal form.
Convert the trapezoidal load into UDL.
Live Load from slab A-B/1-4 = Live Load on Slab x ( Lx/2)
= 2.0 kN/m² x (2/2)
= 2.0 kN/m
Total Live Load
= Live Load on Slab
= 2.0 kN/m
Total Live Load Diagram
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab B-C/1-2 =15.4kN/m x 1.4
= 21.56kN/m
Live Load on Slab B-C/1-2 = 2.0kN/m x 1.6
= 3.2kN/m
Ultimate Load = 21.56kN/m + 3.2kN/m
=24.76kN/m
2500
B C
C
C
sa
d
Total Live load = 2.0 kN/m
2500
B C
C
C
sa
dUltimate Load=24.76 kN/m
Reaction Force
ΣM = 0
= Rb (2.5) – 24.76 kN/m (2.5) (2.5/2)
= 2.5 Rb-77.375kN/m
2.5 Rb=77.375
Rb =30.95kN
ΣFY = 0
= Rb + Rc – 24.76kN/m (2.5)
=30.95 + Rc –61.9kN/m
Rc =61.9-30.95
=30.95kN
Load Diagram
2500
B C
Ultimate Load = 24.76 kN/m
30.95 kN
-30.95 kN
19.34
30.95 kN 30.95 kN
Shear Force
Diagram
BendingMoment
Diagram
Beam Analysis Calculation
Ground Floor Beam, D /3-4
1) Carries Self Weight – Dead Load
2) Slab- Dead Load & Live Load
 B-D/3-4 ( Two Way)
Beam Self Weight =Beam Size x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Dead Load on Slab B-D/3-4 ( Two Way Slab)
Load is transferred to beam D/3-4 in trapezoidal form.
Convert trapezoidal load into UDL.
Dead Load from Slab B-C/1-2 = Dead Load on Slab x ( Lx/2)
= 3.6 kN/m² x (3.5/2)
= 6.3 kN/m
Total Deal Load
= BeamSelf Weight + Dead Load on Slab
= 1.8kN/m + 6.3kN/m
= 8.1kN/m
Total Dead Load Diagram
4025
B C
Beam self-weight = 1.8 kN/m
DL from slab B-D/3-4=6.3kN/m
Total DL=8.1kN/m
Live Load on Slab B-D/3-4 ( Two Way Slab)
Load is transferred to beam D/3-4 in trapezoidal form.
Convert the trapezoidal load into UDL.
Live Load from slab A-B/1-4 = Live Load on Slab x ( Lx/2)
= 2.0 kN/m² x (3.5/2)
= 3.5 kN/m
Total Live Load
= Live Load on Slab
= 3.5 kN/m
Total Live Load Diagram
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab B-D/3-4 =8.1kN/m x 1.4
= 11.34kN/m
Live Load on Slab B-D/3-4 = 3.5kN/m x 1.6
= 5.6kN/m
Ultimate Load = 11.34kN/m + 5.6kN/m
=16.94kN/m
4025
B C
Total Live load = 3.5 kN/m
4025
B C
Ultimate Load= 16.94kN/m
Reaction Force
ΣM = 0
= Rb (4.025) – 16.94 kN/m (4.025) (4.025/2)
= 4.025 Rb-137.22kN/m
4.025Rb =137.22
R4b=34.09kN
ΣFY = 0
= R4 + R1 – 16.94kN/m (4.025)
=34.09 + R1 –68.18kN/m
Rc =68.18-34.09
=34.09kN
Load Diagram
4025
B C
Ultimate Load = 16.94 kN/m
34.09 kN
-34.09 kN
34.09 kN 34.09 kN
Shear Force
Diagram
BendingMoment
Diagram
34.26 kN
Beam Analysis Calculation
Ground Floor Beam, B-D /4
1)Carries Self Weight – Dead Load
2)Slab- Dead Load & Live Load
 B-D/3-4 ( Two Way)
3)Brick Wall – Dead Load
Beam Self Weight =Beam Size x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Brick Wall =Wall Height x Thickness x Density
=3.4m x0.15m x19kN/ m³
=10kN/m
Dead Load on Slab B-D/3-4 ( Two Way Slab)
Load is transferred to beam B-D/4 in triangular form.
Dead Load from Slab B-D/3-4 = Dead Load on Slab x ( Lx/2)
= 3.6 kN/m² x (3.5/2)
= 6.3 kN/m
Convert triangular load into UDL by applying factor of 2/3.
Dead load =2/3 x 6.3kN/m
=4.2kN/m
Total Deal Load
= BeamSelf Weight + Dead Load on Slab+ Brick Wall
= 1.8kN/m + 4.2kN/m+ 10kN/m
= 16kN/m
Total Dead Load Diagram
3500
B D
Beam self-weight = 1.8 kN/m
Brick wall weight = 10 kN/m
DL from slab B-D/3-4=4.2kN/m
Total DL = 16.0kN/m
Live Load on Slab B-D/3-4 ( Two Way Slab)
Load is transferred to beam B-D/4 in triangular form.
Live Load from Slab B-D/3-4 = Live Load on Slab x ( Lx/2)
= 2.0 kN/m² x (3.5/2)
= 3.5 kN/m
Convert triangular load into UDL by applying factor of 2/3.
Live load =2/3 x 3.5kN/m
=2.333kN/m
Total Live Load
= Live Load on Slab
= 2.333 kN/m
Total Live Load Diagram
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab B-D/3-4 =16kN/m x 1.4
= 22.4kN/m
Live Load on Slab B-D/3-4 = 2.333kN/m x 1.6
= 3.73kN/m
Ultimate Load = 22.4kN/m + 3.73kN/m
=26.13kN/m
3500
B D
Total Live load = 2.333 kN/m
3500
B D
Ultimate load = 26.13 kN/m
Reaction Force
ΣM = 0
= Rd (3.5) – 26.13 kN/m (3.5) (3.5/2)
= 3.5 Rd-160.05kN/m
3.5Rd =160.05
Rd =45.73kN
ΣFY = 0
= Rd + Rb – 26.13kN/m (3.5)
=45.73 + R1 –91.46kN/m
Rb =91.46-45.73
=45.73kN
3500
B D
45.73 kN
Ultimate Load=26.13kN/m
45.73 kN 45.73 kN
Load Diagram
Shear Force
Diagram
BendingMoment
Diagram
-45.73 kN
40 kN
Column Analysis Calculation (Tributary Area Method)
To identifyhowmuchloadwouldbe transferredfromslabtocolumn.
GroundFloor (Dead Load)
Column Area (m²) Load(kN)
1 4.5x1.747=7.862 7.862m²x3.6kN/m²=28.3kN (TeaRoom)
2 3.063x4.5=13.78 13.78m²x3.6 kN/m²=49.61kN(TeaRoom)
3 1.68x1.969=3.308 3.308m²x3.6 kN/m²=11.91kN(DiningRoom)
4 (2.193x1.056)+(2.531x1.58) 6.316m²x3.6 kN/m²=22.74kN(DiningRoom)
=6.316
GroundFloor (Live Load)
Column Area (m²) Load(kN)
1 4.5x1.747=7.862 7.862m²x2.0kN/m²=15.724kN (Tea Room)
2 3.063x4.5=13.78 13.78m²x2.0 kN/m²=27.56kN(TeaRoom)
3 1.68x1.969=3.308 3.308m²x2.0 kN/m²=6.616kN(DiningRoom)
4 (2.193x1.056)+(2.531x1.58) 6.316m²x2.0 kN/m²=12.632kN(DiningRoom)
=6.316
JEREMY TAY [0312228]
Beam Analysis Calculation
First Floor Beam, A-C/1
1)Carries Self Weight – Dead Load
2)Slab- Dead Load & Live Load
 A-C/1-2 ( One Way)
Beam Self Weight =Beam Size x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Dead Load on Slab A-C/1-2 ( One Way Slab)
Load is transferred to beam A-C/1 in UDL form.
Dead Load from Slab A-B/1-4 = Dead Load on Slab x ( Lx/2)
= 2.4 kN/m² x (2/2)
= 2.4kN/m
Total Deal Load
= BeamSelf Weight + Dead Load on Slab
= 1.8kN/m + 2.4kN/m
= 4.2kN/m
Total Dead Load Diagram
6000
A C
Beam self-weight = 1.8 kN/m
DL from slab A-B/1-4=2.4kN/m
Total DL= 4.2kN/m
Live Load on Slab A-C/1-2 ( One Way Slab)
Load is transferred to beam A-C/1 in UDL form.
Live Load from slab A-B/1-4 = Live Load on Slab x ( Lx/2)
= 1.5 kN/m² x (2/2)
= 1.5 kN/m
Total Live Load
= Live Load on Slab
= 1.5 kN/m
Total Live Load Diagram
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab A-C/1-2 =4.2kN/m x 1.4
= 5.88kN/m
Live Load on Slab A-C/1-2 = 1.5 kN/m x 1.6
= 2.4kN/m
Ultimate Load = 5.88kN/m + 2.4kN/m
=14.112kN/m
6000
A C
Total Live load = 1.5 kN/m
6000
A C
Ultimate Load = 14.112 kN/m
Reaction Force
ΣM = 0
= Rc (6) – 14.112 kN/m (6) (6/2)
= 6 Rc-254.02
6 Rc=254.02
Rc =42.34kN
ΣFY = 0
= Rc + Ra – 14.112kN/m (6)
=42.34 + Ra – 84.672
Ra =84.672-42.34
=42.33kN
6000
A C
42.33 kN
Ultimate Load=14.112kN/m
42.33 kN 42.34 kN
Load Diagram
Shear Force
Diagram
BendingMoment
Diagram
-42.34 kN
63.5 kN
Beam Analysis Calculation
First Floor Beam, A /2-4
1)Carries Self Weight – Dead Load
2)Slab- Dead Load & Live Load
 A-B/2-4 ( Two Way)
3)Brick Wall – Dead Load
Beam Self Weight =Beam Size x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Brick Wall =Wall Height x Thickness x Density
=3.4m x0.15m x19kN/ m³
=10kN/m
Dead Load on Slab A-B/2-4 ( Two Way Slab)
Load is transferred to beam A/2-4 in trapezoidal form.
Convert trapezoidal load into UDL.
Dead Load from Slab A-B/12 = Dead Load on Slab x ( Lx/2)
= 3.6 kN/m² x (3.5/2)
= 6.3kN/m
Total Deal Load
= BeamSelf Weight + Dead Load on Slab + Brick Wall
= 1.8kN/m + 6.3kN/m + 10kN/m
= 18.1kN/m
Total Dead Load Diagram
7000
2 4
Beam self-weight = 1.8 kN/m
Brick wall weight = 10 kN/m
DL from slab A-B/2-4= 6.3kN/m
Total DL = 18.1kN/m
Live Load on Slab A-B/2-4 ( Two Way Slab)
Load is transferred to beam A/2-4 in trapezoidal form.
Convert trapezoidal load into UDL.
Live Load from slab A-B/2-4 = Live Load on Slab x ( Lx/2)
= 5.0 kN/m² x (3.5/2)
= 8.75 kN/m
Total Live Load
= Live Load on Slab
= 8.75 kN/m
Total Live Load Diagram
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab A-B/1-4 =18.1kN/m x 1.4
= 25.34kN/m
Live Load on Slab A-B/1-4 = 8.75kN/m x 1.6
= 14 kN/m
Ultimate Load = 25.34kN/m + 14kN/m
=39.34kN/m
7000
2 4
Total Live load = 8.75 kN/m
7000
2 4
Ultimate Load = 39.34 kN/m
Reaction Force
ΣM = 0
= R4 (7) – 39.34 kN/m (7) (7/2)
= 7 R4-963.83
7 R4=963.83
R4 =137.69kN
ΣFY = 0
= R4 + R2 – 39.34kN/m (7)
=137.69 + R2 – 275.38
R2 =275.38-137.69
=137.69kN
7000
2 4
137.69 kN
Ultimate Load=39.34kN/m
137.69 kN 137.69 kN
Load Diagram
Shear Force
Diagram
BendingMoment
Diagram
-137.69 kN
240.96
Beam Analysis Calculation
First Floor Beam, B-D /3
1) Carries Self Weight – Dead Load
2) Slab- Dead Load & Live Load
 B-D/2-3 ( Two Way)
 B-D/3-4 ( Two Way)
3)Brick Wall – Dead Load
Beam Self Weight =Beam Sizex Concrete Density
=0.125mx 0.6mx 24kN/m³
=1.8kN/m
Brick Wall =Wall Height x Thickness x Density
=3.4mx0.15mx19kN/ m³
=10kN/m
Dead Load on Slab B-D/2-3 ( Two Way Slab)
Load is transferred to beam B-D/3 a trapezoidal form.
Convert trapezoidal load into UDL.
Dead Load from Slab A-B/1-4 = Dead Load on Slab x ( Lx/2)
= 3.6 kN/m² x (2.975/2)
= 5.355kN/m
Dead Load on Slab B-D/3-4 ( Two Way Slab)
Load is transferred to beam B-D/3 a triangular form.
Dead Load from Slab A-B/1-4 = Dead Load on Slab x ( Lx/2)
= 3.6 kN/m² x (3.5/2)
= 6.3kN/m
Convert triangular load into UDL by applying factor of 2/3.
Dead load =2/3 x 6.3kN/m
=4.2kN/m
Total Deal Load
= BeamSelf Weight + Dead Load on Slab + Brick Wall
= 1.8kN/m + 5.355kN/m+ 4.2kN/m + 10kN/m
= 21.355kN/m
Total Dead Load Diagram
3500
B D
Beam Self Weight=1.8kN/m
weWEoghtWEight
Brick wall weight = 10 kN/m
DL from slab B-D/2-3=5.355kN/m
DL from slab B-D/3-4=4.2kN/m
Total Dead Load=21.355kN/m
Live Load on Slab B-D/2-3 ( Two Way Slab)
Load is transferred to beam B-D/3 in a trapezoidal form.
Convert trapezoidal load into UDL.
Live load from Slab B-D/3-4 = Live load on slab x ( Lx/2)
= 1.5kN/m²x ( 2.975/2)
= 2.231kN/m
Live Load on Slab B-D/3-4 ( Two Way Slab)
Load is transferred to beam B-D/3 in a triangular form.
Live load from Slab B-D/2-3 = Live load on slab x ( Lx/2)
= 2.5kN/m²x ( 3.5/2)
= 4.375kN/m
Convert triangular load into UDL by applying factor of 2/3.
Live load =2/3 x 4.375kN/m
=2.92kN/m
Total Live Load
= Live Load on Slab
=2.231kN/m+2.92kN/m
=5.151kN/m
Total Live Load Diagram
3500
B D
LL fromslabB-D/2-3 =2.231kN/m
LL fromslabB-D/3-4=2.92kN/m
Total Live Load=5.151kN/m
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab B-D/2-4 =21.355kN/m x 1.4
= 29.897kN/m
Live Load on Slab B-D/2-4 = 5.151kN/m x 1.6
= 8.242kN/m
Ultimate Load = 29.897kN/m + 8.242kN/m
=38.139kN/m
3500
B D
Ultimate Load=38.139kN/m
Reaction Force
ΣM = 0
= Rd (3.5) – 38.139 kN/m (3.5) (3.5/2)
= 3.5 Rb-233.6
3.5 Rd =233.6
Rd =66.74kN
ΣFY = 0
= Rd + Rb– 38.139kN/m (3.5)
=66.74 + Rb -133.49
Rb =133.49-66.74
=66.75kN
3500
B D
66.75 kN
Ultimate Load=38.139kN/m
66.75 kN 66.74 kN
Load Diagram
Shear Force
Diagram
BendingMoment
Diagram
-66.74 kN
58.41
Beam Analysis Calculation
First FloorBeam, B /2-4
1. CarriesSelf Weight–Dead Load
2. Slab- DeadLoad & Live Load
 A-B/2-4( Two Way)
 B-D/2-3 (TwoWay)
 B-D/3-4 (TwoWay)
3. Brick Wall – Dead Load
Beam SelfWeight=BeamSize x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Brick Wall =Wall Heightx Thicknessx Density
=3.4m x0.15m x19kN/ m³
=10kN/m
Dead Load on Slab A-B/2-4 ( Two WaySlab)
Load istransferredtobeamB/2-4 ina trapezoidal form.
Convert trapezoidal load into UDL.
Deadload fromSlabB-C/1-2 = Dead loadon slabx ( Lx/2)
= 3.6kN/m²x ( 3.5/2)
= 6.3kN/m
Dead Load on Slab B-D/2-3 ( Two Way Slab)
Load istransferredtobeamB/1-4 ina triangularform.
Deadload fromSlab B-D/2-3 = Deadloadon slabx ( Lx/2)
= 3.6kN/m²x ( 2.975/2)
= 5.355kN/m
ConverttriangularloadintoUDL by applyingfactorof 2/3.
Deadload =2/3 x 5.355kN/m
=3.57kN/m
Dead Load on Slab B-D/3-4 ( Two Way Slab)
Load istransferredtobeamB/1-4 ina trapezoidal form.
Convert trapezoidal load into UDL.
Deadload fromSlab B-C/1-2 = Dead loadon slabx ( Lx/2)
= 3.6kN/m²x ( 3.5/2)
= 6.3kN/m
Total Dead Load
Total for2-3 = Beam Self Weight+Dead Load onSlab + Brick Wall
=1.8kN/m + 6.3kN/m+ 3.57kN/m + 10kN/m
=21.67kN/m
Total for3-4 = Beam Self Weight+Dead Load onSlab
=1.8kN/m + 6.3kN/m+6.3kN/m
=14.4kN/m
2 4
Beam Self Weight=1.8kN/m
weWEoghtWEight
Brick wall weight = 10 kN/m
DL from slab A-B/2-4=6.3kN/m
DL from slab B-D/2-3=3.57kN/m
DL fromslabB-D/2-3=6.3kN/m
3
1
2975 4025
Live Load on Slab A-B/2-4 ( Two Way Slab)
Load istransferredtobeamB/2-4 ina trapezoidal form.
Convert trapezoidal load into UDL.
Live loadfromSlabA-B/2-4 = Live loadonslab x ( Lx/2)
= 5.0kN/m²x ( 3.5/2)
= 8.75kN/m
Live Load on Slab B-D/2-3 ( Two Way Slab)
Load istransferredtobeamB/2-4 ina triangularform.
Live loadfromSlab B-D/2-3 = Live loadon slabx ( Lx/2)
= 1.5kN/m²x ( 2.975/2)
= 2.231kN/m
ConverttriangularloadintoUDL by applyingfactorof 2/3.
Deadload =2/3 x 2.231kN/m
=1.487kN/m
Live Load on Slab B-D/3-4 ( Two Way Slab)
Load istransferredtobeamB/2-4 ina trapezoidal form.
Convert trapezoidal load into UDL.
Live loadfromSlab B-D/3-4 = Live loadonslabx ( Lx/2)
= 2.5kN/m²x ( 3.5/2)
= 4.375kN/m
Total Live Load
Total for2-3 = 8.75kN/m+1.487kN/m
=10.237kN/m
Total for3-4 = 8.75kN/m+4.375kN/m
=13.125kN/m
2975
2 4
Total DeadLoad
3
4025
21.67kN/m 14.4kN/m
Live Load Diagram
2975
2 4
LL fromslabA-B/2-4 = 8.75kN/m
3
4025
LL fromslabB-D/2-3 = 1.487kN/m
LL fromslabB-D/3-4 =4.375kN/m
Total LL = 13.125 kN/m
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab 2-3 =21.67kN/m x 1.4
= 30.34kN/m
Dead Load on Slab 3-4 =14.4kN/m x 1.4
= 20.16kN/m
Live Load on Slab 2-3 = 10.237kN/m x 1.6
= 16.38kN/m
Live Load on Slab 3-4 = 13.125kN/m x 1.6
= 21kN/m
Ultimate Load for 2-3 = 30.34kN/m+16.38kN/m
= 46.72kN/m
Ultimate Load for 3-4 = 20.16kN/m+21kN/m
= 41.16kN/m
2975
2 4
Total Ultimate Load=87.88kN/m
3
4025
46.72kN/m 41.16kN/m
Reaction Force
ΣM = 0
= R4 (7) – 41.16 kN/m (4.025) (4.988) –46.72kN/m (2.975)(1.488)- 66.75(2.975) [point
load]
= 7R4 – 826.36 – 206.82-198.58
7R4 =1231.76
R4 =175.97kN
ΣFY = 0
= R4 + R2–46.72(2.975)-41.16(4.025)-66.75(2.975)
=175.97 + R2-503.24
R2 =503.24-175.97
=327.27kN
2975
2 43
4025
46.72kN/m 41.16kN/m
327.27kN
188.28kN
-10.3kN
-175.97kN
Load Diagram
Shear Force
Diagram
BendingMoment
Diagram
Beam Analysis Calculation
First Floor Beam, A-B /4
1) Carries Self Weight – Dead Load
2) Slab- Dead Load & Live Load
 A-B/2-4 ( Two Way)
3) Brick Wall – Dead Load
Beam Self Weight =Beam Size x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Brick Wall =Wall Height x Thickness x Density
=3.4m x0.15m x19kN/ m³
=10kN/m
Dead Load on Slab A-B/2-4 ( Two Way Slab)
Load is transferred to beam A-B/4 in triangular form.
Dead Load from Slab A-B/2-4 = Dead Load on Slab x ( Lx/2)
= 3.6 kN/m² x (3.5/2)
= 6.3 kN/m
Convert triangular load into UDL by applying factor of 2/3.
Dead load =2/3 x 6.3kN/m
=4.2kN/m
Total Deal Load
= BeamSelf Weight + Dead Load on Slab+ Brick Wall
= 1.8kN/m + 4.2kN/m+ 10kN/m
= 16kN/m
Total Dead Load Diagram
Live Load on Slab A-B/2-4 ( Two Way Slab)
Load is transferred to beam A-B/4 in triangular form.
Live Load from Slab A-B/2-4 = Live Load on Slab x ( Lx/2)
= 5.0 kN/m² x (3.5/2)
= 8.75 kN/m
Convert triangular load into UDL by applying factor of 2/3.
Live load =2/3 x 8.75kN/m
=5.833kN/m
Total Live Load
= Live Load on Slab
= 5.833 kN/m
3500
A B
Beam self-weight = 1.8 kN/m
Brick wall weight = 10 kN/m
DL from slab A-B/2-4= 4.2kN/m
Total DL = 16.0kN/m
Total Live Load Diagram
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab B-D/3-4 =16kN/m x 1.4
= 22.4kN/m
Live Load on Slab B-D/3-4 = 5.833kN/m x 1.6
= 9.33kN/m
Ultimate Load = 22.4kN/m + 9.33kN/m
=31.73kN/m
3500
A B
Total Live load = 5.833 kN/m
3500
A B
Ultimate Load = 31.73 kN/m
Reaction Force
ΣM = 0
= Rb (3.5) – 31.73 kN/m (3.5) (3.5/2)
= 3.5 Rd-194.35kN/m
3.5Rb =194.35
Rb =55.53kN
ΣFY = 0
= Rb + Ra – 31.73kN/m (3.5)
=55.53 + Ra –111.06kN/m
Ra =111.06-55.53
=55.53kN
3500
A B
55.53 kN
Ultimate Load=31.73kN/m
55.53 kN 55.53 kN
Load Diagram
Shear Force
Diagram
BendingMoment
Diagram
-55.53 kN
48.59
Beam Analysis Calculation
First Floor Beam, B-D /4
1)Carries Self Weight – Dead Load
2)Slab- Dead Load & Live Load
 B-D/3-4 ( Two Way)
3)Brick Wall – Dead Load
Beam Self Weight =Beam Size x Concrete Density
=0.125m x 0.6m x 24kN/m³
=1.8kN/m
Brick Wall =Wall Height x Thickness x Density
=3.4m x0.15m x19kN/ m³
=10kN/m
Dead Load on Slab B-D/3-4 ( Two Way Slab)
Load is transferred to beam B-D/4 in triangular form.
Dead Load from Slab B-D/3-4 = Dead Load on Slab x ( Lx/2)
= 3.6 kN/m² x (3.5/2)
= 6.3 kN/m
Convert triangular load into UDL by applying factor of 2/3.
Dead load =2/3 x 6.3kN/m
=4.2kN/m
Total Deal Load
= BeamSelf Weight + Dead Load on Slab+ Brick Wall
= 1.8kN/m + 4.2kN/m+ 10kN/m
= 16kN/m
Total Dead Load Diagram
Live Load on Slab B-D/3-4 ( Two Way Slab)
Load is transferred to beam B-D/4 in triangular form.
Live Load from Slab B-D /3-4 = Live Load on Slab x ( Lx/2)
= 2.5 kN/m² x (3.5/2)
= 4.375 kN/m
Convert triangular load into UDL by applying factor of 2/3.
Live load =2/3 x 4.375kN/m
=2.92kN/m
Total Live Load
= Live Load on Slab
= 2.92 kN/m
3500
B D
Beam self-weight = 1.8 kN/m
Brick wall weight = 10 kN/m
DL from slab B-D/3-4=4.2kN/m
Total DL = 16.0kN/m
Total Live Load Diagram
Ultimate Load
Apply factor 1.4 and 1.6 to dead load and live load respectively.
Dead Load on Slab B-D/3-4 =16kN/m x 1.4
= 22.4kN/m
Live Load on Slab B-D/3-4 = 2.92kN/m x 1.6
= 4.672kN/m
Ultimate Load = 22.4kN/m + 4.672kN/m
=27.07kN/m
3500
B D
Total Live load = 2.92 kN/m
3500
B D
Ultimate Load = 27.07kN/m
Reaction Force
ΣM = 0
= Rd (3.5) – 27.07 kN/m (3.5) (3.5/2)
= 3.5 Rd-165.8kN/m
3.5Rd =165.8
Rd =47.37kN
ΣFY = 0
= Rd + Rb – 27.07kN/m (3.5)
=47.37 + R1 –94.75kN/m
Rb =94.75-47.37
=47.38kN
3500
B D
47.38 kN
Ultimate Load=27.07kN/m
47.38 kN 47.37 kN
Load Diagram
Shear Force
Diagram
BendingMoment
Diagram
-47.37 kN
41.46
Column Analysis Calculation (Tributary Area Method)
To identifyhowmuchloadwouldbe transferredfromslabtocolumn.
First Floor(Dead Load)
Column Area (m²) Load(kN)
1 3.5x1=3.5 3.5m²x2.4kN/m²=8.4kN (Balcony)
2 4.544x3.5=15.904 15.904m²x3.6 kN/m²=57.25kN(Gymnasium)
3 4.5x3.572=16.074 16.074m²x3.6 kN/m²=57.87kN(Library)
4 1.969x1.68=3.308 3.308 m²x3.6 kN/m²=11.91kN(Library)
First Floor(Live Load)
Column Area (m²) Load(kN)
1 3.5x1=3.5 3.5m²x1.5kN/m²=5.25kN (Balcony)
2 4.544x3.5=15.904 15.904m²x5 kN/m²=79.52kN(Gymnasium)
3 4.5x3.572=16.074 16.074m²x2.5 kN/m²=40.19kN(Library)
4 1.969x1.68=3.308 3.308 m²x2.5 kN/m²=8.27kN(Library)

More Related Content

PPTX
Building Structures Report
PPTX
Oscar individual b structure report
PDF
Building Structure Project 2
DOCX
Chong yu xuan bstruc indi
PDF
Hb structure
PDF
Final structure report
PDF
Structure extension jun
PDF
Building Structure Project 2 (Taylor's lakeside campus)
Building Structures Report
Oscar individual b structure report
Building Structure Project 2
Chong yu xuan bstruc indi
Hb structure
Final structure report
Structure extension jun
Building Structure Project 2 (Taylor's lakeside campus)

What's hot (16)

PDF
B structure
PDF
Building Structure Project 2 report
PDF
Individual Caluculation
PDF
Building Structures_Project_02
PDF
individual part
PDF
Structural Analysis of a Bungalow Report
PDF
Building Structures Report (Group and Individual)
PDF
Structural Analysis of a Bungalow
PDF
Gb22, 23, 24, 20 shensin
PDF
Beam Analysis
PDF
Lamyu 3
PDF
BStructure calculation
PPTX
Rcc box culvert
DOCX
Floor Plan calculation
PDF
Benchmark 6 Update
PPTX
Structure Final Assignment
B structure
Building Structure Project 2 report
Individual Caluculation
Building Structures_Project_02
individual part
Structural Analysis of a Bungalow Report
Building Structures Report (Group and Individual)
Structural Analysis of a Bungalow
Gb22, 23, 24, 20 shensin
Beam Analysis
Lamyu 3
BStructure calculation
Rcc box culvert
Floor Plan calculation
Benchmark 6 Update
Structure Final Assignment
Ad

Similar to Building Structure Project 2 (19)

PDF
Building structure real
PDF
Building structures final
DOCX
Beam and Column Analysis | Individual Component
PDF
B.structure report
DOCX
Yung Part, structure
PDF
Building Structure Project 2
PDF
Building Structure
PDF
Building Structure Final report
PDF
Structures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
PDF
Lamyu 2
DOCX
Dead load of structure
PDF
Building structure
PDF
Building Structures Final Compilation
PDF
B structure final final
PDF
B structure final_c
PDF
Building Structure calculation
PPTX
B structure power point
PPTX
Structures
PDF
Structural analysis of a bungalow report
Building structure real
Building structures final
Beam and Column Analysis | Individual Component
B.structure report
Yung Part, structure
Building Structure Project 2
Building Structure
Building Structure Final report
Structures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
Lamyu 2
Dead load of structure
Building structure
Building Structures Final Compilation
B structure final final
B structure final_c
Building Structure calculation
B structure power point
Structures
Structural analysis of a bungalow report
Ad

Recently uploaded (20)

PPT
pump pump is a mechanism that is used to transfer a liquid from one place to ...
DOCX
actividad 20% informatica microsoft project
PDF
Facade & Landscape Lighting Techniques and Trends.pptx.pdf
PPTX
joggers park landscape assignment bandra
PDF
Urban Design Final Project-Site Analysis
PPTX
6- Architecture design complete (1).pptx
PPTX
BSCS lesson 3.pptxnbbjbb mnbkjbkbbkbbkjb
PPTX
Fundamental Principles of Visual Graphic Design.pptx
PPTX
areprosthodontics and orthodonticsa text.pptx
PDF
Emailing DDDX-MBCaEiB.pdf DDD_Europe_2022_Intro_to_Context_Mapping_pdf-165590...
PPT
WHY_R12 Uaafafafpgradeaffafafafaffff.ppt
PPTX
ANATOMY OF ANTERIOR CHAMBER ANGLE AND GONIOSCOPY.pptx
PPTX
Special finishes, classification and types, explanation
PPT
Machine printing techniques and plangi dyeing
PDF
The Advantages of Working With a Design-Build Studio
DOCX
The story of the first moon landing.docx
PDF
Design Thinking - Module 1 - Introduction To Design Thinking - Dr. Rohan Dasg...
PDF
UNIT 1 Introduction fnfbbfhfhfbdhdbdto Java.pptx.pdf
PDF
Interior Structure and Construction A1 NGYANQI
PDF
Quality Control Management for RMG, Level- 4, Certificate
pump pump is a mechanism that is used to transfer a liquid from one place to ...
actividad 20% informatica microsoft project
Facade & Landscape Lighting Techniques and Trends.pptx.pdf
joggers park landscape assignment bandra
Urban Design Final Project-Site Analysis
6- Architecture design complete (1).pptx
BSCS lesson 3.pptxnbbjbb mnbkjbkbbkbbkjb
Fundamental Principles of Visual Graphic Design.pptx
areprosthodontics and orthodonticsa text.pptx
Emailing DDDX-MBCaEiB.pdf DDD_Europe_2022_Intro_to_Context_Mapping_pdf-165590...
WHY_R12 Uaafafafpgradeaffafafafaffff.ppt
ANATOMY OF ANTERIOR CHAMBER ANGLE AND GONIOSCOPY.pptx
Special finishes, classification and types, explanation
Machine printing techniques and plangi dyeing
The Advantages of Working With a Design-Build Studio
The story of the first moon landing.docx
Design Thinking - Module 1 - Introduction To Design Thinking - Dr. Rohan Dasg...
UNIT 1 Introduction fnfbbfhfhfbdhdbdto Java.pptx.pdf
Interior Structure and Construction A1 NGYANQI
Quality Control Management for RMG, Level- 4, Certificate

Building Structure Project 2

  • 1. Building Structures [ARC 2522] Project 2 [Extension of a Reinforced Concrete Bungalow] No.3 Bukit Tiara 1, Taman Billion, 56100, Kuala Lumpur, Malaysia Name Student ID Tan Wen Yee 0315155 Jeremy Tay Eujin 0312228 Lecturer: Ms Norita Submission Date: Week 12 (19th June 2014, Friday)
  • 2. Introduction The project is an integrated component where it involves structural theory, force calculation and basic structural proposal. This project is designed to allow the demonstration of knowledge and understanding of building structure. Objectives of Project The objectives of this project are as follows: 1. To introduce the basic process of building structures design process to the students. 2. To enable the students to have a holistic experience including Concept and Structure Layout Design, Building Structure Engineering Considerations, Structure Members Sizing and Calculations, Final Report and Presentation. Learning Outcomes 1. Produce a complete documentation on structural systemof a case study 2. Explore and understand the concept of structural analysis 3. Identification of structural components 4. Recognize, Execute and implement basic procedures of building structure design 5. Produce a structural proposal
  • 3. Ground Floor Extension Plan Scale 1:150 First Floor Extension Plan Scale 1:150
  • 4. Foundation Extension Plan Scale 1:150 Ground Floor Structural Plan Scale 1:150
  • 5. First Floor Structural Plan Scale 1:150 Roof Structural Plan Scale 1:150
  • 7. Quantity DeadLoads Acting On Structure GroundFloor Extended Dining Room Slab thickness = 150mm Slab self-weight = 0.15m x 24kN/m³ = 3.6 kN/m² Extended Kitchen Slab thickness = 150mm Slab self-weight = 0.15m x 24kN/m³ = 3.6 kN/m² Tearoom Slab thickness = 150mm Slab self-weight = 0.15m x 24kN/m³ = 3.6 kN/m² First Floor Library Slab thickness = 150mm Slab self-weight = 0.15m x 24kN/m³ = 3.6 kN/m² Corridor Slab thickness = 150mm Slab self-weight = 0.15m x 24kN/m³ = 3.6 kN/m² Balcony Slab thickness = 100mm Slab self-weight = 0.1m x 24kN/m³ = 2.4 kN/m² Gymnasium Slab thickness = 150mm Slab self-weight = 0.15m x 24kN/m³ = 3.6 kN/m² Brick Wall: =Wall Height x Thickness x Density =3.4m x0.15m x19kN/ m³ =10kN/m Beam SelfWeight: (Assume that initial beamsize125mmx600mm) =Beam Size x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Quantity Live Loads Acting On Structure GroundFloor Diningroom: 2.0 kN/m² Kitchen: 2.0 kN/m² Tearoom: 2.0 kN/m² First Floor Library: 2.5 kN/m² Corridor 1.5 kN/m² Balcony 1.5 kN/m² Gymnasium: 5.0 kN/m² (According to 4th Schedule of UBBL for live load according to the function of the space)
  • 8. Identify One Way or Two Way Slab Indicating the Distribution of Load from Slab to Beam Ly= Longer side of slab Lx= Shorter side of slab When Ly / Lx >2 or =2, it is a one way slab. When Ly / Lx <2, it is a two way slab. Ground Floor ExtendedDiningRoom =4025 ÷ 3500 =1.15 < 2 (TwoWay Slab) ExtendedKitchen =3500 ÷ 2975 =1.18 < 2 (TwoWay Slab) =2500 ÷ 2000 =1.25 < 2 (TwoWay Slab) Tearoom =9000 ÷ 3500 =2.57 > 2 (One Way Slab) First Floor Library =4025 ÷ 3500 =1.15 < 2 (TwoWay Slab) Corridor =3500 ÷ 2975 =1.18 < 2 (TwoWay Slab) Balcony = 6000 ÷ 2000 =3 > 2 (One Way Slab) Gymnasium =7000 ÷ 3500 =2= 2 (TwoWay Slab)
  • 9. Beam Analysis Calculation Ground Floor Beam, A /1-4 1) Carries Self Weight – Dead Load 2) Slab- Dead Load & Live Load  A-B/1-4 ( One Way) 3) Brick Wall – Dead Load Beam Self Weight =Beam Size x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Brick Wall =Wall Height x Thickness x Density =3.4m x0.15m x19kN/ m³ =10kN/m Dead Load on Slab A-B/1-4 ( One Way Slab) Load is transferred to beam A/1-4 in UDL form. Dead Load from Slab A-B/1-4 = Dead Load on Slab x ( Lx/2) = 3.6 kN/m²x (3.5/2) = 6.3kN/m Total Deal Load = BeamSelf Weight + Dead Load on Slab + Brick Wall = 1.8kN/m + 6.3kN/m + 10kN/m = 18.1kN/m
  • 10. Total Dead Load Diagram 9000 1 4 Beam self-weight = 1.8 kN/m Brick wall weight = 10 kN/m DL from slab A-B /1-4=6.3kN/m Total DL = 18.1kN/m
  • 11. Live Load on Slab A-B/1-4 ( One Way Slab) Load is transferred to beam A/1-4 in UDL form. Live Load from slab A-B/1-4 = Live Load on Slab x ( Lx/2) = 2.0 kN/m² x (3.5/2) = 3.5 kN/m Total Live Load = Live Load on Slab = 3.5 kN/m Total Live Load Diagram Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab A-B/1-4 =18.1kN/m x 1.4 = 25.34kN/m Live Load on Slab A-B/1-4 = 3.5kN/m x 1.6 = 5.6kN/m Ultimate Load = 25.34kN/m + 5.6kN/m =30.94kN/m 9000 1 4 Total Live load = 3.5 kN/m 9000 1 4 Ultimate Load = 30.94 kN/m
  • 12. Reaction Force ΣM = 0 = R4 (9) – 30.94 kN/m (9) (9/2) = 9 R4-1253.07 9 R4=1253.07 R4 =139.23kN ΣFY = 0 = R4 + R1 – 30.94kN/m (9) =139.23 + R1 – 278.46 R1 =278.46-139.23 =139.23kN 9000 1 4 Ultimate Load = 30.94 kN/m 139.23 kN -139.23 kN 313.26 139.23 kN 139.23 kN Load Diagram Shear Force Diagram BendingMoment Diagram
  • 13. Beam Analysis Calculation Ground Floor Beam, B-D /3 1) Carries Self Weight – Dead Load 2) Slab- Dead Load & Live Load  B-D/2-3 ( Two Way)  B-D/3-4 ( Two Way)  Brick Wall – Dead Load Beam Self Weight =Beam Size x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Brick Wall =Wall Height x Thickness x Density =3.4m x0.15m x19kN/ m³ =10kN/m Dead Load on Slab B-D/2-3 (Two Way Slab) Load is transferred to beam B-D/3 a trapezoidal form. Convert trapezoidal load into UDL. Dead Load from Slab A-B/1-4 = Dead Load on Slab x (Lx/2) = 3.6 kN/m² x (2.975/2) = 5.355kN/m Dead Load on Slab B-D/3-4 (Two Way Slab) Load is transferred to beam B-D/3 a triangular form. Dead Load from Slab A-B/1-4 = Dead Load on Slab x (Lx/2) = 3.6 kN/m² x (3.5/2) = 6.3kN/m Convert triangular load into UDL by applying factor of 2/3. Dead load =2/3 x 6.3kN/m =4.2kN/m Total Deal Load = BeamSelf Weight + Dead Load on Slab + Brick Wall = 1.8kN/m + 5.355kN/m+ 4.2kN/m + 10kN/m = 21.355kN/m
  • 14. Total Dead Load Diagram 3500 B D Beam Self Weight=1.8kN/m weWEoghtWEight Brick wall weight = 10 kN/m DL from slab B-D/2-3=5.355kN/m DL from slab B-D/3-4=4.2kN/m Total Dead Load=21.355kN/m
  • 15. Live Load on Slab B-D/2-3 ( Two Way Slab) Load is transferred to beam B-D/3 in a trapezoidal form. Convert trapezoidal load into UDL. Live load from Slab B-D/3-4 = Live load on slab x ( Lx/2) = 2.0kN/m²x ( 2.975/2) = 2.975kN/m Live Load on Slab B-D/3-4 ( Two Way Slab) Load is transferred to beam B-D/3 in a triangular form. Live load from Slab B-D/2-3 = Live load on slab x ( Lx/2) = 2.0kN/m²x ( 3.5/2) = 3.5kN/m Convert triangular load into UDL by applying factor of 2/3. Live load =2/3 x 3.5kN/m =2.333kN/m Total Live Load = Live Load on Slab =2.975kN/m+2.333kN/m =5.308kN/m Total Live Load Diagram 3500 B D LL fromslabB-D/2-3 =2.975kN/m LL fromslabB-D/3-4=2.333kN/m Total Live Load=5.308kN/m
  • 16. Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab B-D/2-4 =21.355kN/m x 1.4 = 29.897kN/m Live Load on Slab B-D/2-4 = 5.308kN/m x 1.6 = 8.493kN/m Ultimate Load = 29.897kN/m + 8.493kN/m =38.39kN/m Ultimate Load Diagram 3500 B D Ultimate Load=38.39kN/m
  • 17. Reaction Force ΣM = 0 = Rd (3.5) – 38.39 kN/m (3.5) (3.5/2) = 3.5 Rb-235.14 3.5 Rd =235.14 Rd =67.18kN ΣFY = 0 = Rd + Rb– 38.39kN/m (3.5) =67.18 + Rb -134.37 Rb =134.37-67.18 =67.19kN 3500 B D 67.19 kN -67.18 kN 57.78 Ultimate Load=38.39kN/m 67.19 kN 67.18 kN Load Diagram Shear Force Diagram BendingMoment Diagram
  • 18. Beam Analysis Calculation Ground Floor Beam, B /1-4 1. Carries Self Weight – Dead Load 2. Slab- Dead Load & Live Load  A-B/1-4 ( One Way)  B-C/1-2 ( Two Way)  B-D/2-3 (Two Way)  B-D/3-4 (Two Way) 3. Brick Wall – Dead Load Beam Self Weight =BeamSize x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Brick Wall =Wall Height x Thickness x Density =3.4m x0.15m x19kN/ m³ =10kN/m Dead Load on Slab A-B/1-4 ( One Way Slab) Load is transferred to beam A/1-4 in UDL form. Dead Load from Slab A-B/1-4 = Dead Load on Slab x ( Lx/2) = 3.6 kN/m² x (3.5/2) = 6.3kN/m Dead Load on Slab B-C/1-2 ( Two Way Slab) Load is transferred to beam B/1-4 in a triangular form. Dead load from Slab B-C/1-2 = Dead load on slab x ( Lx/2) = 3.6kN/m²x ( 2/2) = 3.6kN/m Convert triangular load into UDL by applying factor of 2/3. Dead load =2/3 x 3.6kN/m =2.4kN/m Dead Load on Slab B-D/2-3 ( Two Way Slab) Load is transferred to beam B/1-4 in a triangular form. Dead load from Slab B-D/2-3 = Dead load on slab x ( Lx/2) = 3.6kN/m²x ( 2.975/2) = 5.355kN/m
  • 19. Convert triangular load into UDL by applying factor of 2/3. Dead load =2/3 x 5.355kN/m =3.57kN/m Dead Load on Slab B-D/3-4 ( Two Way Slab) Load is transferred to beam B/1-4 in a trapezoidal form. Convert trapezoidal load into UDL. Dead load from Slab B-C/1-2 = Dead load on slab x ( Lx/2) = 3.6kN/m²x ( 3.5/2) = 6.3kN/m Total Dead Load Total for 1-2= Beam Self Weight + Dead Load on Slab + Brick Wall = 1.8kN/m + 6.3kN/m+2.4kN/m + 10kN/m = 20.5kN/m Total for 2-3 = Beam Self Weight + Dead Load on Slab + Brick Wall =1.8kN/m + 6.3kN/m + 3.57kN/m + 10kN/m =21.67kN/m Total for 3-4 = Beam Self Weight + Dead Load on Slab+Brick Wall =1.8kN/m + 6.3kN/m+6.3kN/m+10kN/m =24.4kN/m
  • 20. Total Dead Load Diagram 2000 1 4 Beam Self Weight=1.8kN/m weWEoghtWEight Brick wall weight = 10 kN/m DL from slab A-B/1-4=6.3kN/m DL from slab B-C/1-2=2.4kN/m DL fromslabB-D/2-3=3.57kN/m 2 1 3 12975 4025
  • 21. 2000 1 4 DL from slab B-D/3-4=6.3kN/m Total Dead Load 2 1 3 12975 4025 20.5kN/m 21.67kN/m 24.4kN/m
  • 22. Live Load on Slab A-B/1-4 ( One Way Slab) Load is transferred to beam A/1-4 in UDL form. Live Load from slab A-B/1-4 = Live Load on Slab x ( Lx/2) = 2.0 kN/m² x (3.5/2) = 3.5 kN/m Live Load on Slab B-C/1-2 ( Two Way Slab) Load is transferred to beam B/1-4 in a triangular form. Live load from Slab B-C/1-2 = Live load on slab x ( Lx/2) = 2.0kN/m²x ( 2/2) = 2.0kN/m Convert triangular load into UDL by applying factor of 2/3. Live load =2/3 x 2.0kN/m =1.33kN/m Live Load on Slab B-D/2-3 ( Two Way Slab) Load is transferred to beam B/1-4 in a triangular form. Live load from Slab B-D/2-3 = Live load on slab x ( Lx/2) = 2.0kN/m²x ( 2.975/2) = 2.975kN/m Convert triangular load into UDL by applying factor of 2/3. Dead load =2/3 x 2.975kN/m =1.983kN/m Live Load on Slab B-D/3-4 ( Two Way Slab) Load is transferred to beam B/1-4 in a trapezoidal form. Convert trapezoidal load into UDL. Live load from Slab B-D/3-4 = Live load on slab x ( Lx/2) = 2.0kN/m²x ( 3.5/2) = 3.5kN/m Total Live Load Total for 1-2 = 3.5kN/m+1.33kN/m =4.83kN/m Total for 2-3 = 3.5kN/m+1.983kN/m =5.483kN/m Total for 3-4 = 3.5kN/m+3.5kN/m =7.0kN/m
  • 23. Live Load Diagram 2000 1 4 LL from A-B/1-4=3.5kN/m weWEoghtWEight LL from B-C/1-2=1.33kN/m LL fromslabB-D/3-4=3.5kN/m 2 1 3 12975 4025 LL from B-D/2-3=1.983kN/m Total Live Load 4.83kN/m 5.483kN/m 7.0kN/m
  • 24. Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab 1-2 = 20.5kN/m x 1.4 = 28.7kN/m Dead Load on Slab 2-3 =21.67kN/m x 1.4 = 30.34kN/m Dead Load on Slab 3-4 =24.4kN/m x 1.4 = 34.16kN/m Live Load on Slab 1-2 = 4.83kN/m x 1.6 = 7.73kN/m Live Load on Slab 2-3 = 5.483kN/m x 1.6 = 8.77kN/m Live Load on Slab 3-4 = 7.0kN/m x 1.6 = 11.2kN/m Ultimate Load for 1-2 = 28.7kN/m+7.73kN/m = 36.43kN/m Ultimate Load for 2-3 = 30.34kN/m+8.77kN/m = 39.11kN/m Ultimate Load for 3-4 = 34.16kN/m+11.2kN/m = 45.36kN/m 2000 1 42 1 3 12975 4025 Ultimate Load 36.43kN/ m 39.11kN/m 45.36kN/m
  • 25. Reaction Force ΣM = 0 = R4 (9) – 45.36 kN/m (4.025) (6.99) – 39.11kN/m(2.975)(2.538)- 36.43kN/m (2)(1)- 67.19(4.975) = 9R4 – 1276.19-295.3-72.86-334.27 9R4 =1978.62 R4 =219.85kN ΣFY = 0 = R4 + R1–45.36(4.025)-39.11(2.975)-36.43(2)-67.19(4.975) =219.85 + R1-706.05 R1 =706.05-219.85 =486.2kN 2000 1 42 1 3 12975 4025 36.43kN/m 39.11kN/m 45.36kN/m 413.24kN 296.99kN -37.28kN -163.5kN Load Diagram Shear Force Diagram BendingMoment Diagram
  • 26. Beam Analysis Calculation Ground Floor Beam, B-C /1 1)Carries Self Weight – Dead Load 2)Slab- Dead Load & Live Load  B-C/1-2 ( Two Way) 3)Brick Wall – Dead Load Beam Self Weight =Beam Size x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Brick Wall =Wall Height x Thickness x Density =3.4m x0.15m x19kN/ m³ =10kN/m Dead Load on Slab B-C/1-2 ( Two Way Slab) Load is transferred to beam B-C/1 in trapezoidal form. Convert trapezoidal load into UDL. Dead Load from Slab B-C/1-2 = Dead Load on Slab x ( Lx/2) = 3.6 kN/m² x (2/2) = 3.6 kN/m Total Deal Load = BeamSelf Weight + Dead Load on Slab + Brick Wall = 1.8kN/m + 3.6kN/m + 10kN/m = 15.4kN/m
  • 27. Total Dead Load Diagram 2500 B C Beam self-weight = 1.8 kN/m Brick wall weight = 10 kN/m DL from slab B-C/1-2=3.6kN/m Total DL = 15.4kN/m
  • 28. Live Load on Slab B-C/1-2 ( Two Way Slab) Load is transferred to beam B-C/1 in trapezoidal form. Convert the trapezoidal load into UDL. Live Load from slab A-B/1-4 = Live Load on Slab x ( Lx/2) = 2.0 kN/m² x (2/2) = 2.0 kN/m Total Live Load = Live Load on Slab = 2.0 kN/m Total Live Load Diagram Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab B-C/1-2 =15.4kN/m x 1.4 = 21.56kN/m Live Load on Slab B-C/1-2 = 2.0kN/m x 1.6 = 3.2kN/m Ultimate Load = 21.56kN/m + 3.2kN/m =24.76kN/m 2500 B C C C sa d Total Live load = 2.0 kN/m 2500 B C C C sa dUltimate Load=24.76 kN/m
  • 29. Reaction Force ΣM = 0 = Rb (2.5) – 24.76 kN/m (2.5) (2.5/2) = 2.5 Rb-77.375kN/m 2.5 Rb=77.375 Rb =30.95kN ΣFY = 0 = Rb + Rc – 24.76kN/m (2.5) =30.95 + Rc –61.9kN/m Rc =61.9-30.95 =30.95kN Load Diagram 2500 B C Ultimate Load = 24.76 kN/m 30.95 kN -30.95 kN 19.34 30.95 kN 30.95 kN Shear Force Diagram BendingMoment Diagram
  • 30. Beam Analysis Calculation Ground Floor Beam, D /3-4 1) Carries Self Weight – Dead Load 2) Slab- Dead Load & Live Load  B-D/3-4 ( Two Way) Beam Self Weight =Beam Size x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Dead Load on Slab B-D/3-4 ( Two Way Slab) Load is transferred to beam D/3-4 in trapezoidal form. Convert trapezoidal load into UDL. Dead Load from Slab B-C/1-2 = Dead Load on Slab x ( Lx/2) = 3.6 kN/m² x (3.5/2) = 6.3 kN/m Total Deal Load = BeamSelf Weight + Dead Load on Slab = 1.8kN/m + 6.3kN/m = 8.1kN/m
  • 31. Total Dead Load Diagram 4025 B C Beam self-weight = 1.8 kN/m DL from slab B-D/3-4=6.3kN/m Total DL=8.1kN/m
  • 32. Live Load on Slab B-D/3-4 ( Two Way Slab) Load is transferred to beam D/3-4 in trapezoidal form. Convert the trapezoidal load into UDL. Live Load from slab A-B/1-4 = Live Load on Slab x ( Lx/2) = 2.0 kN/m² x (3.5/2) = 3.5 kN/m Total Live Load = Live Load on Slab = 3.5 kN/m Total Live Load Diagram Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab B-D/3-4 =8.1kN/m x 1.4 = 11.34kN/m Live Load on Slab B-D/3-4 = 3.5kN/m x 1.6 = 5.6kN/m Ultimate Load = 11.34kN/m + 5.6kN/m =16.94kN/m 4025 B C Total Live load = 3.5 kN/m 4025 B C Ultimate Load= 16.94kN/m
  • 33. Reaction Force ΣM = 0 = Rb (4.025) – 16.94 kN/m (4.025) (4.025/2) = 4.025 Rb-137.22kN/m 4.025Rb =137.22 R4b=34.09kN ΣFY = 0 = R4 + R1 – 16.94kN/m (4.025) =34.09 + R1 –68.18kN/m Rc =68.18-34.09 =34.09kN Load Diagram 4025 B C Ultimate Load = 16.94 kN/m 34.09 kN -34.09 kN 34.09 kN 34.09 kN Shear Force Diagram BendingMoment Diagram 34.26 kN
  • 34. Beam Analysis Calculation Ground Floor Beam, B-D /4 1)Carries Self Weight – Dead Load 2)Slab- Dead Load & Live Load  B-D/3-4 ( Two Way) 3)Brick Wall – Dead Load Beam Self Weight =Beam Size x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Brick Wall =Wall Height x Thickness x Density =3.4m x0.15m x19kN/ m³ =10kN/m Dead Load on Slab B-D/3-4 ( Two Way Slab) Load is transferred to beam B-D/4 in triangular form. Dead Load from Slab B-D/3-4 = Dead Load on Slab x ( Lx/2) = 3.6 kN/m² x (3.5/2) = 6.3 kN/m Convert triangular load into UDL by applying factor of 2/3. Dead load =2/3 x 6.3kN/m =4.2kN/m Total Deal Load = BeamSelf Weight + Dead Load on Slab+ Brick Wall = 1.8kN/m + 4.2kN/m+ 10kN/m = 16kN/m
  • 35. Total Dead Load Diagram 3500 B D Beam self-weight = 1.8 kN/m Brick wall weight = 10 kN/m DL from slab B-D/3-4=4.2kN/m Total DL = 16.0kN/m
  • 36. Live Load on Slab B-D/3-4 ( Two Way Slab) Load is transferred to beam B-D/4 in triangular form. Live Load from Slab B-D/3-4 = Live Load on Slab x ( Lx/2) = 2.0 kN/m² x (3.5/2) = 3.5 kN/m Convert triangular load into UDL by applying factor of 2/3. Live load =2/3 x 3.5kN/m =2.333kN/m Total Live Load = Live Load on Slab = 2.333 kN/m Total Live Load Diagram Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab B-D/3-4 =16kN/m x 1.4 = 22.4kN/m Live Load on Slab B-D/3-4 = 2.333kN/m x 1.6 = 3.73kN/m Ultimate Load = 22.4kN/m + 3.73kN/m =26.13kN/m 3500 B D Total Live load = 2.333 kN/m 3500 B D Ultimate load = 26.13 kN/m
  • 37. Reaction Force ΣM = 0 = Rd (3.5) – 26.13 kN/m (3.5) (3.5/2) = 3.5 Rd-160.05kN/m 3.5Rd =160.05 Rd =45.73kN ΣFY = 0 = Rd + Rb – 26.13kN/m (3.5) =45.73 + R1 –91.46kN/m Rb =91.46-45.73 =45.73kN 3500 B D 45.73 kN Ultimate Load=26.13kN/m 45.73 kN 45.73 kN Load Diagram Shear Force Diagram BendingMoment Diagram -45.73 kN 40 kN
  • 38. Column Analysis Calculation (Tributary Area Method) To identifyhowmuchloadwouldbe transferredfromslabtocolumn. GroundFloor (Dead Load) Column Area (m²) Load(kN) 1 4.5x1.747=7.862 7.862m²x3.6kN/m²=28.3kN (TeaRoom) 2 3.063x4.5=13.78 13.78m²x3.6 kN/m²=49.61kN(TeaRoom) 3 1.68x1.969=3.308 3.308m²x3.6 kN/m²=11.91kN(DiningRoom) 4 (2.193x1.056)+(2.531x1.58) 6.316m²x3.6 kN/m²=22.74kN(DiningRoom) =6.316 GroundFloor (Live Load) Column Area (m²) Load(kN) 1 4.5x1.747=7.862 7.862m²x2.0kN/m²=15.724kN (Tea Room) 2 3.063x4.5=13.78 13.78m²x2.0 kN/m²=27.56kN(TeaRoom) 3 1.68x1.969=3.308 3.308m²x2.0 kN/m²=6.616kN(DiningRoom) 4 (2.193x1.056)+(2.531x1.58) 6.316m²x2.0 kN/m²=12.632kN(DiningRoom) =6.316
  • 39. JEREMY TAY [0312228] Beam Analysis Calculation First Floor Beam, A-C/1 1)Carries Self Weight – Dead Load 2)Slab- Dead Load & Live Load  A-C/1-2 ( One Way) Beam Self Weight =Beam Size x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Dead Load on Slab A-C/1-2 ( One Way Slab) Load is transferred to beam A-C/1 in UDL form. Dead Load from Slab A-B/1-4 = Dead Load on Slab x ( Lx/2) = 2.4 kN/m² x (2/2) = 2.4kN/m Total Deal Load = BeamSelf Weight + Dead Load on Slab = 1.8kN/m + 2.4kN/m = 4.2kN/m
  • 40. Total Dead Load Diagram 6000 A C Beam self-weight = 1.8 kN/m DL from slab A-B/1-4=2.4kN/m Total DL= 4.2kN/m
  • 41. Live Load on Slab A-C/1-2 ( One Way Slab) Load is transferred to beam A-C/1 in UDL form. Live Load from slab A-B/1-4 = Live Load on Slab x ( Lx/2) = 1.5 kN/m² x (2/2) = 1.5 kN/m Total Live Load = Live Load on Slab = 1.5 kN/m Total Live Load Diagram Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab A-C/1-2 =4.2kN/m x 1.4 = 5.88kN/m Live Load on Slab A-C/1-2 = 1.5 kN/m x 1.6 = 2.4kN/m Ultimate Load = 5.88kN/m + 2.4kN/m =14.112kN/m 6000 A C Total Live load = 1.5 kN/m 6000 A C Ultimate Load = 14.112 kN/m
  • 42. Reaction Force ΣM = 0 = Rc (6) – 14.112 kN/m (6) (6/2) = 6 Rc-254.02 6 Rc=254.02 Rc =42.34kN ΣFY = 0 = Rc + Ra – 14.112kN/m (6) =42.34 + Ra – 84.672 Ra =84.672-42.34 =42.33kN 6000 A C 42.33 kN Ultimate Load=14.112kN/m 42.33 kN 42.34 kN Load Diagram Shear Force Diagram BendingMoment Diagram -42.34 kN 63.5 kN
  • 43. Beam Analysis Calculation First Floor Beam, A /2-4 1)Carries Self Weight – Dead Load 2)Slab- Dead Load & Live Load  A-B/2-4 ( Two Way) 3)Brick Wall – Dead Load Beam Self Weight =Beam Size x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Brick Wall =Wall Height x Thickness x Density =3.4m x0.15m x19kN/ m³ =10kN/m Dead Load on Slab A-B/2-4 ( Two Way Slab) Load is transferred to beam A/2-4 in trapezoidal form. Convert trapezoidal load into UDL. Dead Load from Slab A-B/12 = Dead Load on Slab x ( Lx/2) = 3.6 kN/m² x (3.5/2) = 6.3kN/m Total Deal Load = BeamSelf Weight + Dead Load on Slab + Brick Wall = 1.8kN/m + 6.3kN/m + 10kN/m = 18.1kN/m
  • 44. Total Dead Load Diagram 7000 2 4 Beam self-weight = 1.8 kN/m Brick wall weight = 10 kN/m DL from slab A-B/2-4= 6.3kN/m Total DL = 18.1kN/m
  • 45. Live Load on Slab A-B/2-4 ( Two Way Slab) Load is transferred to beam A/2-4 in trapezoidal form. Convert trapezoidal load into UDL. Live Load from slab A-B/2-4 = Live Load on Slab x ( Lx/2) = 5.0 kN/m² x (3.5/2) = 8.75 kN/m Total Live Load = Live Load on Slab = 8.75 kN/m Total Live Load Diagram Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab A-B/1-4 =18.1kN/m x 1.4 = 25.34kN/m Live Load on Slab A-B/1-4 = 8.75kN/m x 1.6 = 14 kN/m Ultimate Load = 25.34kN/m + 14kN/m =39.34kN/m 7000 2 4 Total Live load = 8.75 kN/m 7000 2 4 Ultimate Load = 39.34 kN/m
  • 46. Reaction Force ΣM = 0 = R4 (7) – 39.34 kN/m (7) (7/2) = 7 R4-963.83 7 R4=963.83 R4 =137.69kN ΣFY = 0 = R4 + R2 – 39.34kN/m (7) =137.69 + R2 – 275.38 R2 =275.38-137.69 =137.69kN 7000 2 4 137.69 kN Ultimate Load=39.34kN/m 137.69 kN 137.69 kN Load Diagram Shear Force Diagram BendingMoment Diagram -137.69 kN 240.96
  • 47. Beam Analysis Calculation First Floor Beam, B-D /3 1) Carries Self Weight – Dead Load 2) Slab- Dead Load & Live Load  B-D/2-3 ( Two Way)  B-D/3-4 ( Two Way) 3)Brick Wall – Dead Load Beam Self Weight =Beam Sizex Concrete Density =0.125mx 0.6mx 24kN/m³ =1.8kN/m Brick Wall =Wall Height x Thickness x Density =3.4mx0.15mx19kN/ m³ =10kN/m Dead Load on Slab B-D/2-3 ( Two Way Slab) Load is transferred to beam B-D/3 a trapezoidal form. Convert trapezoidal load into UDL. Dead Load from Slab A-B/1-4 = Dead Load on Slab x ( Lx/2) = 3.6 kN/m² x (2.975/2) = 5.355kN/m Dead Load on Slab B-D/3-4 ( Two Way Slab) Load is transferred to beam B-D/3 a triangular form. Dead Load from Slab A-B/1-4 = Dead Load on Slab x ( Lx/2) = 3.6 kN/m² x (3.5/2) = 6.3kN/m Convert triangular load into UDL by applying factor of 2/3. Dead load =2/3 x 6.3kN/m =4.2kN/m
  • 48. Total Deal Load = BeamSelf Weight + Dead Load on Slab + Brick Wall = 1.8kN/m + 5.355kN/m+ 4.2kN/m + 10kN/m = 21.355kN/m Total Dead Load Diagram 3500 B D Beam Self Weight=1.8kN/m weWEoghtWEight Brick wall weight = 10 kN/m DL from slab B-D/2-3=5.355kN/m DL from slab B-D/3-4=4.2kN/m Total Dead Load=21.355kN/m
  • 49. Live Load on Slab B-D/2-3 ( Two Way Slab) Load is transferred to beam B-D/3 in a trapezoidal form. Convert trapezoidal load into UDL. Live load from Slab B-D/3-4 = Live load on slab x ( Lx/2) = 1.5kN/m²x ( 2.975/2) = 2.231kN/m Live Load on Slab B-D/3-4 ( Two Way Slab) Load is transferred to beam B-D/3 in a triangular form. Live load from Slab B-D/2-3 = Live load on slab x ( Lx/2) = 2.5kN/m²x ( 3.5/2) = 4.375kN/m Convert triangular load into UDL by applying factor of 2/3. Live load =2/3 x 4.375kN/m =2.92kN/m Total Live Load = Live Load on Slab =2.231kN/m+2.92kN/m =5.151kN/m Total Live Load Diagram 3500 B D LL fromslabB-D/2-3 =2.231kN/m LL fromslabB-D/3-4=2.92kN/m Total Live Load=5.151kN/m
  • 50. Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab B-D/2-4 =21.355kN/m x 1.4 = 29.897kN/m Live Load on Slab B-D/2-4 = 5.151kN/m x 1.6 = 8.242kN/m Ultimate Load = 29.897kN/m + 8.242kN/m =38.139kN/m 3500 B D Ultimate Load=38.139kN/m
  • 51. Reaction Force ΣM = 0 = Rd (3.5) – 38.139 kN/m (3.5) (3.5/2) = 3.5 Rb-233.6 3.5 Rd =233.6 Rd =66.74kN ΣFY = 0 = Rd + Rb– 38.139kN/m (3.5) =66.74 + Rb -133.49 Rb =133.49-66.74 =66.75kN 3500 B D 66.75 kN Ultimate Load=38.139kN/m 66.75 kN 66.74 kN Load Diagram Shear Force Diagram BendingMoment Diagram -66.74 kN 58.41
  • 52. Beam Analysis Calculation First FloorBeam, B /2-4 1. CarriesSelf Weight–Dead Load 2. Slab- DeadLoad & Live Load  A-B/2-4( Two Way)  B-D/2-3 (TwoWay)  B-D/3-4 (TwoWay) 3. Brick Wall – Dead Load Beam SelfWeight=BeamSize x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Brick Wall =Wall Heightx Thicknessx Density =3.4m x0.15m x19kN/ m³ =10kN/m Dead Load on Slab A-B/2-4 ( Two WaySlab) Load istransferredtobeamB/2-4 ina trapezoidal form. Convert trapezoidal load into UDL. Deadload fromSlabB-C/1-2 = Dead loadon slabx ( Lx/2) = 3.6kN/m²x ( 3.5/2) = 6.3kN/m Dead Load on Slab B-D/2-3 ( Two Way Slab) Load istransferredtobeamB/1-4 ina triangularform. Deadload fromSlab B-D/2-3 = Deadloadon slabx ( Lx/2) = 3.6kN/m²x ( 2.975/2) = 5.355kN/m ConverttriangularloadintoUDL by applyingfactorof 2/3. Deadload =2/3 x 5.355kN/m =3.57kN/m Dead Load on Slab B-D/3-4 ( Two Way Slab) Load istransferredtobeamB/1-4 ina trapezoidal form. Convert trapezoidal load into UDL. Deadload fromSlab B-C/1-2 = Dead loadon slabx ( Lx/2) = 3.6kN/m²x ( 3.5/2) = 6.3kN/m
  • 53. Total Dead Load Total for2-3 = Beam Self Weight+Dead Load onSlab + Brick Wall =1.8kN/m + 6.3kN/m+ 3.57kN/m + 10kN/m =21.67kN/m Total for3-4 = Beam Self Weight+Dead Load onSlab =1.8kN/m + 6.3kN/m+6.3kN/m =14.4kN/m 2 4 Beam Self Weight=1.8kN/m weWEoghtWEight Brick wall weight = 10 kN/m DL from slab A-B/2-4=6.3kN/m DL from slab B-D/2-3=3.57kN/m DL fromslabB-D/2-3=6.3kN/m 3 1 2975 4025
  • 54. Live Load on Slab A-B/2-4 ( Two Way Slab) Load istransferredtobeamB/2-4 ina trapezoidal form. Convert trapezoidal load into UDL. Live loadfromSlabA-B/2-4 = Live loadonslab x ( Lx/2) = 5.0kN/m²x ( 3.5/2) = 8.75kN/m Live Load on Slab B-D/2-3 ( Two Way Slab) Load istransferredtobeamB/2-4 ina triangularform. Live loadfromSlab B-D/2-3 = Live loadon slabx ( Lx/2) = 1.5kN/m²x ( 2.975/2) = 2.231kN/m ConverttriangularloadintoUDL by applyingfactorof 2/3. Deadload =2/3 x 2.231kN/m =1.487kN/m Live Load on Slab B-D/3-4 ( Two Way Slab) Load istransferredtobeamB/2-4 ina trapezoidal form. Convert trapezoidal load into UDL. Live loadfromSlab B-D/3-4 = Live loadonslabx ( Lx/2) = 2.5kN/m²x ( 3.5/2) = 4.375kN/m Total Live Load Total for2-3 = 8.75kN/m+1.487kN/m =10.237kN/m Total for3-4 = 8.75kN/m+4.375kN/m =13.125kN/m 2975 2 4 Total DeadLoad 3 4025 21.67kN/m 14.4kN/m
  • 55. Live Load Diagram 2975 2 4 LL fromslabA-B/2-4 = 8.75kN/m 3 4025 LL fromslabB-D/2-3 = 1.487kN/m LL fromslabB-D/3-4 =4.375kN/m Total LL = 13.125 kN/m
  • 56. Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab 2-3 =21.67kN/m x 1.4 = 30.34kN/m Dead Load on Slab 3-4 =14.4kN/m x 1.4 = 20.16kN/m Live Load on Slab 2-3 = 10.237kN/m x 1.6 = 16.38kN/m Live Load on Slab 3-4 = 13.125kN/m x 1.6 = 21kN/m Ultimate Load for 2-3 = 30.34kN/m+16.38kN/m = 46.72kN/m Ultimate Load for 3-4 = 20.16kN/m+21kN/m = 41.16kN/m 2975 2 4 Total Ultimate Load=87.88kN/m 3 4025 46.72kN/m 41.16kN/m
  • 57. Reaction Force ΣM = 0 = R4 (7) – 41.16 kN/m (4.025) (4.988) –46.72kN/m (2.975)(1.488)- 66.75(2.975) [point load] = 7R4 – 826.36 – 206.82-198.58 7R4 =1231.76 R4 =175.97kN ΣFY = 0 = R4 + R2–46.72(2.975)-41.16(4.025)-66.75(2.975) =175.97 + R2-503.24 R2 =503.24-175.97 =327.27kN 2975 2 43 4025 46.72kN/m 41.16kN/m 327.27kN 188.28kN -10.3kN -175.97kN Load Diagram Shear Force Diagram BendingMoment Diagram
  • 58. Beam Analysis Calculation First Floor Beam, A-B /4 1) Carries Self Weight – Dead Load 2) Slab- Dead Load & Live Load  A-B/2-4 ( Two Way) 3) Brick Wall – Dead Load Beam Self Weight =Beam Size x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Brick Wall =Wall Height x Thickness x Density =3.4m x0.15m x19kN/ m³ =10kN/m Dead Load on Slab A-B/2-4 ( Two Way Slab) Load is transferred to beam A-B/4 in triangular form. Dead Load from Slab A-B/2-4 = Dead Load on Slab x ( Lx/2) = 3.6 kN/m² x (3.5/2) = 6.3 kN/m Convert triangular load into UDL by applying factor of 2/3. Dead load =2/3 x 6.3kN/m =4.2kN/m Total Deal Load = BeamSelf Weight + Dead Load on Slab+ Brick Wall = 1.8kN/m + 4.2kN/m+ 10kN/m = 16kN/m
  • 59. Total Dead Load Diagram Live Load on Slab A-B/2-4 ( Two Way Slab) Load is transferred to beam A-B/4 in triangular form. Live Load from Slab A-B/2-4 = Live Load on Slab x ( Lx/2) = 5.0 kN/m² x (3.5/2) = 8.75 kN/m Convert triangular load into UDL by applying factor of 2/3. Live load =2/3 x 8.75kN/m =5.833kN/m Total Live Load = Live Load on Slab = 5.833 kN/m 3500 A B Beam self-weight = 1.8 kN/m Brick wall weight = 10 kN/m DL from slab A-B/2-4= 4.2kN/m Total DL = 16.0kN/m
  • 60. Total Live Load Diagram Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab B-D/3-4 =16kN/m x 1.4 = 22.4kN/m Live Load on Slab B-D/3-4 = 5.833kN/m x 1.6 = 9.33kN/m Ultimate Load = 22.4kN/m + 9.33kN/m =31.73kN/m 3500 A B Total Live load = 5.833 kN/m 3500 A B Ultimate Load = 31.73 kN/m
  • 61. Reaction Force ΣM = 0 = Rb (3.5) – 31.73 kN/m (3.5) (3.5/2) = 3.5 Rd-194.35kN/m 3.5Rb =194.35 Rb =55.53kN ΣFY = 0 = Rb + Ra – 31.73kN/m (3.5) =55.53 + Ra –111.06kN/m Ra =111.06-55.53 =55.53kN 3500 A B 55.53 kN Ultimate Load=31.73kN/m 55.53 kN 55.53 kN Load Diagram Shear Force Diagram BendingMoment Diagram -55.53 kN 48.59
  • 62. Beam Analysis Calculation First Floor Beam, B-D /4 1)Carries Self Weight – Dead Load 2)Slab- Dead Load & Live Load  B-D/3-4 ( Two Way) 3)Brick Wall – Dead Load Beam Self Weight =Beam Size x Concrete Density =0.125m x 0.6m x 24kN/m³ =1.8kN/m Brick Wall =Wall Height x Thickness x Density =3.4m x0.15m x19kN/ m³ =10kN/m Dead Load on Slab B-D/3-4 ( Two Way Slab) Load is transferred to beam B-D/4 in triangular form. Dead Load from Slab B-D/3-4 = Dead Load on Slab x ( Lx/2) = 3.6 kN/m² x (3.5/2) = 6.3 kN/m Convert triangular load into UDL by applying factor of 2/3. Dead load =2/3 x 6.3kN/m =4.2kN/m Total Deal Load = BeamSelf Weight + Dead Load on Slab+ Brick Wall = 1.8kN/m + 4.2kN/m+ 10kN/m = 16kN/m
  • 63. Total Dead Load Diagram Live Load on Slab B-D/3-4 ( Two Way Slab) Load is transferred to beam B-D/4 in triangular form. Live Load from Slab B-D /3-4 = Live Load on Slab x ( Lx/2) = 2.5 kN/m² x (3.5/2) = 4.375 kN/m Convert triangular load into UDL by applying factor of 2/3. Live load =2/3 x 4.375kN/m =2.92kN/m Total Live Load = Live Load on Slab = 2.92 kN/m 3500 B D Beam self-weight = 1.8 kN/m Brick wall weight = 10 kN/m DL from slab B-D/3-4=4.2kN/m Total DL = 16.0kN/m
  • 64. Total Live Load Diagram Ultimate Load Apply factor 1.4 and 1.6 to dead load and live load respectively. Dead Load on Slab B-D/3-4 =16kN/m x 1.4 = 22.4kN/m Live Load on Slab B-D/3-4 = 2.92kN/m x 1.6 = 4.672kN/m Ultimate Load = 22.4kN/m + 4.672kN/m =27.07kN/m 3500 B D Total Live load = 2.92 kN/m 3500 B D Ultimate Load = 27.07kN/m
  • 65. Reaction Force ΣM = 0 = Rd (3.5) – 27.07 kN/m (3.5) (3.5/2) = 3.5 Rd-165.8kN/m 3.5Rd =165.8 Rd =47.37kN ΣFY = 0 = Rd + Rb – 27.07kN/m (3.5) =47.37 + R1 –94.75kN/m Rb =94.75-47.37 =47.38kN 3500 B D 47.38 kN Ultimate Load=27.07kN/m 47.38 kN 47.37 kN Load Diagram Shear Force Diagram BendingMoment Diagram -47.37 kN 41.46
  • 66. Column Analysis Calculation (Tributary Area Method) To identifyhowmuchloadwouldbe transferredfromslabtocolumn. First Floor(Dead Load) Column Area (m²) Load(kN) 1 3.5x1=3.5 3.5m²x2.4kN/m²=8.4kN (Balcony) 2 4.544x3.5=15.904 15.904m²x3.6 kN/m²=57.25kN(Gymnasium) 3 4.5x3.572=16.074 16.074m²x3.6 kN/m²=57.87kN(Library) 4 1.969x1.68=3.308 3.308 m²x3.6 kN/m²=11.91kN(Library) First Floor(Live Load) Column Area (m²) Load(kN) 1 3.5x1=3.5 3.5m²x1.5kN/m²=5.25kN (Balcony) 2 4.544x3.5=15.904 15.904m²x5 kN/m²=79.52kN(Gymnasium) 3 4.5x3.572=16.074 16.074m²x2.5 kN/m²=40.19kN(Library) 4 1.969x1.68=3.308 3.308 m²x2.5 kN/m²=8.27kN(Library)