SlideShare a Scribd company logo
BUILDING SCIENCE (BLD 61303)
SCHOOL OF ARCHITECTURE, BUILDING & DESIGN
Bachelor of Science (Honours) in Architecture
PROJECT INTEGRATION WITH
COMMUNITY LIBRARY
BUILDING SCIENCE (BLD 61303)
PROJECT 02 INTEGRATION PROJECT
Prepared by:
Tan Jo Lynn (0318518)
Tutor: Mr. Azim Sulaiman
PROJECT 02 INTEGRATION PROJECT Page ! of !1 26
BUILDING SCIENCE (BLD 61303)
TABLE OF CONTENT
CHAPTER 1.0 INTRODUCTION 3
Section 1.1 Objectives 3
Section 1.2 Project Introduction 3
Section 1.3 Floor plans 4
Section 1.4 Sun Shading Diagrams 9
CHAPTER 2.0 SPACE A . E-LEARNING DEPARTMENT
Section 2.1 Introduction 12
Section 2.2 Daylight Analysis 13
Section 2.3 Artificial light Analysis 15
CHAPTER 3.0 SPACE B . CASUAL READING SPACE
Section 3.1 Introduction 19
Section 3.2 Daylight Analysis 20
Section 3.3 Artificial light Analysis 22
Section 3.4 PSALI 24
CHAPTER 6.0 REFERENCES 26
PROJECT 02 INTEGRATION PROJECT Page ! of !2 26
BUILDING SCIENCE (BLD 61303)
CHAPTER 1.0 INTRODUCTION
1.1 Objectives
The intention of this project is to incorporate the lighting analysis and design in to the community
library project to presents the understanding of artificial lighting and daylighting strategies to solve
environment problems in relation to sustainability and user comfort, at the same time practice use of
potential natural lighting. As the position of site selected faces the East - West, where daylighting is
an critical issue if not adopted appropriately, utilisation of natural lighting is encouraged but at the
same time provide a comfortable spatial qualities for each functional area.
1.2 Project Introduction
The community library is located at Jalan Tuanku Abdul Rahman, Kuala Lumpur, an infill project
between the Coliseum Cafe and Wisma Harwan. The design intention of my proposed library is to
congregate experiences and to redefine perceptions of Malaysians towards the immigrants
community. Thus, forming a humanistic library, a library beyond the collection of books and written
knowledge.
The application of natural lighting through facade, skylight and light wells to enhance the spatial
lighting quality aims to reduce the use of artificial lighting, enabling users to experience the details
of Jalan Tuanku Abdul Rahman through tactile senses. Therefore, well integration of artificial
lighting and daylighting is required to achieved the poetics of space and structure as well as to
provide sufficient luminance to the functional space according to its purposes in order to maintain
the comfortable visual condition for users.
PROJECT 02 INTEGRATION PROJECT Page ! of !3 26
BUILDING SCIENCE (BLD 61303)
1.3 Floor Plans
PROJECT 02 INTEGRATION PROJECT Page ! of !4 26
1
Ground Floor Floor Plan
Scale 1:200
BUILDING SCIENCE (BLD 61303)
PROJECT 02 INTEGRATION PROJECT Page ! of !5 26
1
First Floor Floor Plan
Scale 1:200
BUILDING SCIENCE (BLD 61303)
PROJECT 02 INTEGRATION PROJECT Page ! of !6 26
1
Second Floor Floor Plan
Scale 1:200
BUILDING SCIENCE (BLD 61303)
PROJECT 02 INTEGRATION PROJECT Page ! of !7 26
1
Third Floor Floor Plan
Scale 1:200
BUILDING SCIENCE (BLD 61303)
PROJECT 02 INTEGRATION PROJECT Page ! of !8 26
1
Fourth Floor Floor Plan
Scale 1:200
BUILDING SCIENCE (BLD 61303)
1.4 Sun Shading Diagrams
At this hour, incident light travels from the East direction, which penetrates through the front facade
in to the interior spaces. The front spaces of the library like casual reading space, young adult’s
department, and antique archive gallery will be affected throughly. Therefore, the front facade will
be installed with varieties of sun shading system depending on the function of the space. Light
travels in to the spaces though light well will not affect the lighting condition much at this hour.
Date Time Weather
16th July 2017 0830hr Sunny
PROJECT 02 INTEGRATION PROJECT Page ! of !9 26
BUILDING SCIENCE (BLD 61303)
At this hour, the incident light is coming dominantly from the top of the East direction. Spaces
affected by the source of light will be Lounge, which is located at the top floor. This issue is solved
by using sun screens as continuation of roof design over the facade exposed to sunlight. Other
spaces were not seriously affected by the sunlight at this point of time as light travels through light
well in to these spaces, reducing glares and thermal discomfort by avoiding direct light and
reflecting light.
Date Time Weather
16th July 2017 1300hr Sunny
PROJECT 02 INTEGRATION PROJECT Page ! of !10 26
BUILDING SCIENCE (BLD 61303)
The late afternoon sun affects mainly on the spaces located at the back of the building. For example,
the meeting room that is located at the top floor. Spaces located below are protected by wall built
for privacy of restrooms as well as the adjacent building. However, it is still important to provide
sun shading system to reduce direct penetration of light in to the the space mentioned above. The
application of operable solid wooden panels and louvers are used to prevent direct light at the same
time, provide flexibility when natural light is needed. Light traveling through light well is diffused
by the office spaces and the green wall installed in between two spaces to provide boundary.
Therefore, the flexibility of use of facade is vital for the utilisation of natural lighting.
Date Time Weather
16th July 2017 1700hr Sunny
PROJECT 02 INTEGRATION PROJECT Page ! of !11 26
BUILDING SCIENCE (BLD 61303)
CHAPTER 2.0 SPACE A . E-LEARNING DEPARTMENT
2.1 Introduction
Figure 2.1.1 Second floor floor plan with indication of location of Space A.
The chosen space is a semi open area located on the second floor. Curtain is applied on one end of
the space to avoid indirect light that reflects from the devices’ screen, causing discomfort like
glares. Natural light received by the space through the light well is insufficient for a computer room
based of the standard stated in MS 1525. Therefore, artificial lighting is needed throughout the day
to provide sufficient illuminance level for the assigned activity in the space.
PROJECT 02 INTEGRATION PROJECT Page ! of !12 26
1
BUILDING SCIENCE (BLD 61303)
2.2 Daylight Analysis
Daylight Factor Analysis
Based on the daylight factors and distribution table stated by the Department of standards Malaysia,
2007, the space is fairly lit by the natural lighting.
As from the calculation stated above, daylight received was just enough to achieved the requirement
of illuminance level as stated in MS 1525.
Floor Area (m²) 7.1 x 5.7 = 40.21m²
Area of Facade exposed to Sunlight (m²) (0.9 x 3.5) + (2.141 x 3.5) = 23.625
Daylight Factor, DF DF = 40.21 / 23.625 x 100
DF = 17.02 x 0.1
DF = 1.7%
Zone DF (%) Distribution
Very Bright > 6 Large (including thermal and glare problem)
Bright 3 - 6 Good
Average 1 - 3 Fair
Dark 0 -1 Poor
Standard room Illumination recommendation by MS 1525 for computer rooms: 300 lux -
400 lux
External Illumination (Shade illuminated by the
entire clear blue sky)
20000 lux
DF = Ei (indoor illuminance) x 100%
Eo (outdoor illuminance)
1.7 = Ei x 100%
20000
Ei = 340 lux
PROJECT 02 INTEGRATION PROJECT Page ! of !13 26
DF = Ei (indoor illuminance) x 100%
Eo (outdoor illuminance)
BUILDING SCIENCE (BLD 61303)
Daylight Lux Contour Diagram Diagram
Figure 2.2.1 Daylight contour of Space A.
Based on the daylight analysis diagram, it is presented that the light enters the E-learning space
from the openings towards the light well. The natural light received gradually decreases as it travels
deeper in to the space. Thus, incorporation of artificial lighting is needed.
Section analysis Diagram
Figure 2.2.2 Section of Space A with shadow casting.
The E-learning Department has daylight factor of 1.7%, which achieved a fairly lit environment due
to the opening towards the light well that allows reflectance of natural light in to the space. The
indoor illuminance of space is at 340 lux, positioned at the mid point of range 300 lux - 400 lux a
stated in MS 1525. Thus, artificial lighting is needed throughout the day to achieved even
distribution of light throughput the space as well as to provide sufficient illuminance level when
daylight is not available when weather changes.
PROJECT 02 INTEGRATION PROJECT Page ! of !14 26
BUILDING SCIENCE (BLD 61303)
2.3 Artificial light Analysis
Lumen Method
Where,
N = Number of lamps required
E = Illuminance level required (lux)
A = Area at working plane (m²)
F = Average luminous flux from each fitting (lumen)
UF = Utilisation factor, an allowance for light distribution of the luminaire and room surfaces
MF = Maintenance factor, an allowance for reduced light output because of deterioration and dirt
Room Index
Where,
L = Length of room
W = Width of room
Hm = Mounting height, the vertical distance between the working plane and luminaire
PROJECT 02 INTEGRATION PROJECT Page ! of !15 26
N = E x A
F x UF x EF
RI = L x W
Hm x (L + W)
BUILDING SCIENCE (BLD 61303)
Types of Fixture 1-Light Pendant Light
Image of Fixture
Product Dimension (mm) 100mm DIA.
Type of Luminous Cool White
Luminous flux (lumen) 1100 lumen
Power (Watt) 11W
Color Temperature (Kelvin) 4000
Color Rendering Index (CRI) 80
Average life rate (hours) 25000
Dimension of Room (m) Length = 7.1
Width = 5.7
Total floor area (m²) 40.21
Height of Ceiling (m) 4
Type of Light Fixture A19 LED Bulb
Luminous flux of Lighting, F (lumen) 1100
Height of Luminaire (m) 3
Height of Working Plane (m) 0.77
Mounting Height (Hm) 4.00 - 1.00 - 0.77 = 1.73m
Standard Illumination required according to
MS1525
300 lux
Reflectance factor Ceiling (wood panelling) = 0.7
Wall (green wall + curtain) = 0.5
Floor (timber cladding) = 0.2
Room Index, RI (K) RI = L x W
Hm x (L+W)
RI = (5.7 x 7.1) / [ 1.73 x (5.7+7.1) ]
RI = 1.821
Utilisation Factor, UF 0.62
Maintenance Factor, MF 0.8 (standard)
PROJECT 02 INTEGRATION PROJECT Page ! of !16 26
BUILDING SCIENCE (BLD 61303)
Lighting Layout
Figure 2.3.1 Light fittings layout arranged based on analysis and calculation above.
There area total amount of 22 light fixtures used to achieved the required illuminance level of 300
lux as stated in MS 1525 in the space with an area of 40.21m². As shown in the diagram, every 10
lighting fixtures are controlled by a one-way-two-gang switch.
Number of Fittings required, N N = E x A
F x UF x MF
N = (300 x 40.21) / (1100 x 0.62 x 0.8)
N = 22.1081
N = 22 bulbs
Maximum spacing between Luminaire (m) Smax = 1.0 x Hm
Smax = 1.0 x 1.6
Smax = 1.6
Fitting Layout Fitting required along 7.1m wall,
(7.1 / 1.6 )m = 4.437 (5 rows)
Number of Lamps in each row,
22lamps / 5 rows = 4.4 (4 lamps per row with 2
lamps on the sixth )
PROJECT 02 INTEGRATION PROJECT Page ! of !17 26
BUILDING SCIENCE (BLD 61303)
Artificial light Lux Contour Diagram
Figure 2.3.2 Artificial light contour of Space A.
The contour diagram shown above presents the lighting condition after the artificial lighting is
installed and planned according to the analysis and calculation above. The light source is more
evenly distributed to the working plane as compared to the light contour diagram in Figure 2.2.1.
Bulb colour of cool white is chosen to create a more formal ambience for the working space.
Pendant light is used to reduce the amount of light needed as it is in relation of the figure of
Utilisation factor, UF, where it is indirectly proportional to the number of light fittings needed.
Section analysis Diagram
Figure 2.3.3 Section of Space A after application of artificial lighting.
The inner portion of the e-learning space has no direct opening due to the location of restrooms that
blocks the exposed area of back facade. Thus, the deeper part of space are mainly brighten up by the
installation of artificial lighting to introduce balance distribution of light.
PROJECT 02 INTEGRATION PROJECT Page ! of !18 26
BUILDING SCIENCE (BLD 61303)
CHAPTER 03 SPACE B . CASUAL READING SPACE
3.1 Introduction
Figure 3.1.1 First floor floor plan with indication of location of Space B.
The chosen space is a semi open area located on the first floor. Facade with installation of sun
shading system is positioned on one end of the space to avoid direct light penetrating in to the
space, causing discomfort like glares and thermal discomfort. Natural light received by the space
through the light well exceeds the the requirements as stated in MS 1525. Therefore, design
strategies are needed to be applied to prevent regrade of spatial experiences and working ambience.
PROJECT 02 INTEGRATION PROJECT Page ! of !19 26
1
BUILDING SCIENCE (BLD 61303)
3.2 Daylight Analysis
Average Daylight Factor
Where,
W = Area of windows (m²)
A = Total area of internal surfaces (m²)
T = Glass transmittance corrected for dirt
θ = Visible sky angle in degrees from the centre of the window
R = Average reflectance of area A
Figure 3.2.1 Diagram showing method of achieving figure for visible sky degree, θ.
Floor Area, A (m²) A = (8.915 x 6.8) + (6.915 x 6.8) + (9.345 x 4.0
x 2)
A = 182.204m²
Area of Facade exposed to Sunlight, W (m²) W = [(1.95 x 3.245) + (3.25 x 1.0) + (0.85 x
1.15 x 4)] + (3.0 x 3.06)
W = 22.67m²
Average Transmittance, T T = (0.3 + 0.35 + 0.7)
T = 0.35
Average Reflectance of surface area, R R = (0.7 + 0.5 + 0.2) / 3
R = 0,467
Daylight Factor, DF DF = W x Tθ
A (1-R)
DF = 22.67 / 182.204 x (0.35 x 74) / (1 - 0.467)
DF = 6.1%
PROJECT 02 INTEGRATION PROJECT Page ! of !20 26
DF = W x Tθ
A (1 - R)
from centre point of
exposed facade
opposite building
BUILDING SCIENCE (BLD 61303)
Based on the daylight factors and distribution table stated by the Department of standards Malaysia,
2007, the space is brightly lit by the natural daylight.
As stated in the calculation above, daylight received has slightly exceeds requirement of
illuminance level as stated in MS 1525.
Daylight Lux Contour Diagram
Figure 3.2.2 Daylight contour diagram of Space B.
Zone DF (%) Distribution
Very Bright > 6 Large (including thermal and glare problem)
Bright 3 - 6 Good
Average 1 - 3 Fair
Dark 0 -1 Poor
Standard room Illumination recommendation by MS 1525 for reading rooms: 300 lux - 500
lux
External Illumination (Shade illuminated by the
entire clear blue sky)
20000 lux
DF = Ei (indoor illuminance) x 100%
Eo (outdoor illuminance)
6.1 = Ei x 100%
20000
Ei = 1220 lux
PROJECT 02 INTEGRATION PROJECT Page ! of !21 26
BUILDING SCIENCE (BLD 61303)
The light contour diagram shows that the space lit up by daylight from the expose facade area on
one end and from the light well on the other. It is presented that the illuminance level decreases as it
reaches the centre of space, forming unbalance light distribution throughout the space.
Section analysis Diagram
Figure 3.2.3 Section of Space B with shadow casting.
The casual reading space achieved daylight factor of 6.1% and natural illuminance level of 1220
lux. Based on the standards stated in MS 1525, the space is bright lit by daylight as both figure
exceeds the required figure. For instance, the bright daylight factor range from 3% - 6% and the
suggested light level for reading space is 300 lux - 500 lux. Therefore, design strategies are require
to reduce sun exposure to prevent issues of discomfort like glares and thermal discomfort.
3.3 Artificial light Analysis
Types of Fixture Recessed Downlight
Image of Fixture
Product Dimension (mm) 160mm x 160mm
Type of Luminous Neutral White
PROJECT 02 INTEGRATION PROJECT Page ! of !22 26
BUILDING SCIENCE (BLD 61303)
Artificial light Lux Contour Diagram
Figure 3.3.1 Artificial light contour diagram of Space B.
The lux contour diagram presents that the light fittings installed are able to illuminate the casual
reading space when daylight is not available as well as to provide an even distribution of light
throughout the working plane. However, corners of the room are relatively dark as compared to the
front and centre area of the space.
Luminous flux (lumen) 1000 lumen
Power (Watt) 14.2W
Color Temperature (Kelvin) 3500
Color Rendering Index (CRI) 80
Average life rate (hours) 50000
Type of Light Fixture J-Box LED
Luminous flux of Lighting, F (lumen) 1100
PROJECT 02 INTEGRATION PROJECT Page ! of !23 26
BUILDING SCIENCE (BLD 61303)
3.4 PSALI Scheme
Figure 3.4.1 Lighting layout arranged to incorporate with daylight utilisation.
Figure 3.4.2 Section showing the lighting layout of artificial lighting system.
PROJECT 02 INTEGRATION PROJECT Page ! of !24 26
BUILDING SCIENCE (BLD 61303)
The artificial lighting introduced to enhance the illumination of chosen space when natural lighting
is not sufficient to cater with requirement as per listed in MS 1525. The total of 20 light fittings are
controlled by a one-way-two-gang switch, and two single switches. During the brightest portion of
the day, daylight factor at its highest, only row B needs to be switched on. The series of row C can
be turned on in place of row B to increase the illuminance level of space. Row A and D all only be
switch on when daylight factor is at its lowest, at night or during the dark days.
Design Strategies
Figure 3.4.3 Front facade of building with indication of material used.
To reduce possibility of issues like thermal discomfort and glares, louvers and double glazing low-E
glass panels have been applied to the front facade exposed to daylight. The floor platforms have
been set back by 1000mm to form a buffer some to allow natural ventilation to eliminate heat gain
by building facade. Double skin facade fired was also able to improve the comfort ambience of
space as well as reduce consumption of energy.
PROJECT 02 INTEGRATION PROJECT Page ! of !25 26
BUILDING SCIENCE (BLD 61303)
CHAPTER 4.0 REFERENCES
1. Philips SlimSurface Dimmable 14.2W 3000K 6" LED Downlight | S6S830K10. (n.d.).
Retrieved July 16, 2017, from http://www.bulbs.com/product/S6S830K10
2. F., H., P., S., S., P., . . . F. (2017, May 16). Globe Electric 1-Light Vintage Edison Matte Black
Mini Pendant-64906. Retrieved July 16, 2017, from http://www.homedepot.com/p/Globe-
Electric-1-Light-Vintage-Edison-Matte-Black-Mini-Pendant-64906/205320312
3. Maxlite Dimmable 11W 4000K A19 LED Bulb, GU24 Base | 11A19GUDLED40/G4. (n.d.).
Retrieved July 16, 2017, from http://www.bulbs.com/product/11A19GUDLED40-G4
4. Passionate About Sound - Healthcare. (n.d.). Retrieved July 16, 2017, from https://
www.armstrongceilings.com/commercial/en-us/commercial-ceilings-walls/woodworks-
concealed-ceiling-tiles.html
5. Ceiling Wall System . (n.d.). Retrieved July 17, 2017, from http://www.armstrong.com/assets/
global/commclgeu/files/Literature/1709.PDF
PROJECT 02 INTEGRATION PROJECT Page ! of !26 26

More Related Content

PDF
Bscience
PDF
Building Science Project 2 Report
PDF
Bscience report
DOCX
Calculations report
PDF
Building Science_02_Report_Integration Project
DOCX
Bscience
PDF
REPORT AND CALCULATION
PDF
BUILDING SCIENCE II: ACOUSTICS AND LIGHTING ANALYSIS OF DONUTES CAFE, SS15
Bscience
Building Science Project 2 Report
Bscience report
Calculations report
Building Science_02_Report_Integration Project
Bscience
REPORT AND CALCULATION
BUILDING SCIENCE II: ACOUSTICS AND LIGHTING ANALYSIS OF DONUTES CAFE, SS15

What's hot (20)

PDF
Bb science project 2
PDF
Project 2 integration project
PDF
Building Science II : Project 1
DOCX
Final l
PDF
Light Analysis of Building Science II
DOCX
Building Science II: Lighting Integration Report
PDF
BUILDING SCIENCE INTEGRATION PROJECT
PDF
Building Science II
PDF
Building Science 1 (Project 1)
PDF
BSCIENCE LIGHTING REPORT
PDF
Building Science II
PDF
Bscience 2-project-2
PDF
Building Science II Project 2 (Integration) Final Report
PDF
Building Science 2 Project 2 Report
PDF
Lighting report
PDF
B science Project 2
DOCX
Building Science II Project 2: Report
PDF
Building science 2 project 1
DOCX
Building science 2
PDF
Building science 2 report pdf
Bb science project 2
Project 2 integration project
Building Science II : Project 1
Final l
Light Analysis of Building Science II
Building Science II: Lighting Integration Report
BUILDING SCIENCE INTEGRATION PROJECT
Building Science II
Building Science 1 (Project 1)
BSCIENCE LIGHTING REPORT
Building Science II
Bscience 2-project-2
Building Science II Project 2 (Integration) Final Report
Building Science 2 Project 2 Report
Lighting report
B science Project 2
Building Science II Project 2: Report
Building science 2 project 1
Building science 2
Building science 2 report pdf
Ad

Similar to DEGREE SEM 5 BUILDING SCIENCE PROJECT 2 INTEGRATION PROJECT (20)

PDF
Bscience ii
PDF
BSCIENCE PROJECT 2 FINAL REPORT
PDF
Building science 2 project 2
PDF
Building Science 2 Final Project Report
PDF
community lib bsci
PDF
Bscience report
PDF
Building science ii final report
DOCX
Building Science 2 - Integration Project - Community Library
PDF
Building Science P02
PDF
Building Science Project 1 : Lighting & Acoustic Performance Evaluation & Design
PDF
Building Science 2
PDF
Building Science II Project 2
PDF
Lighting Integration Project
DOCX
School of architecture
PDF
A4 report
PDF
Building Science II Integration Project Report
PDF
Building Science 2 Project 2
PDF
Project 2: Integration Project
PDF
Final bscience report compilation
PDF
Final bscience report compilation
Bscience ii
BSCIENCE PROJECT 2 FINAL REPORT
Building science 2 project 2
Building Science 2 Final Project Report
community lib bsci
Bscience report
Building science ii final report
Building Science 2 - Integration Project - Community Library
Building Science P02
Building Science Project 1 : Lighting & Acoustic Performance Evaluation & Design
Building Science 2
Building Science II Project 2
Lighting Integration Project
School of architecture
A4 report
Building Science II Integration Project Report
Building Science 2 Project 2
Project 2: Integration Project
Final bscience report compilation
Final bscience report compilation
Ad

More from jolynnTJL (20)

PDF
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
PDF
ARCHITECTURAL DESIGN PROJECT PRE DESIGN ANALYSIS TITIWANGSA
PDF
DEGREE SEM 5 THEORIES OF ARCHI. & URBANISM COMPARATIVE ESSAY
PDF
DEGREE SEM 5 BUILDING TECHNOLOGY PROJECT 02 IBS REPORT
PDF
DEGREE SEM 5 BUILDING SCIENCE PROJECT 01 ACOUSTIC CASE STUDY
PDF
DEGREE SEM 5 TALES OF 3 CITIES PROJECT 2 JLN H.S. LEE, KUALA LUMPUR
PDF
DEGREE SEM 5 TALES OF 3 CITIES PROJECT 1B URBAN JOURNAL
PDF
DEGREE SEM 5 TALES OF 3 CITIES PROJECT 1A GEORGETOWN
PDF
DEGREEM SEM 5 CSI REFLECTIVE JOURNAL
PDF
BSC (H) ARCHITECTURE DEGREE SEM 4.5 INTERNSHIP REPORT FINAL
PDF
BSC (H) ARCHITECTURE DEGREE SEM 4.5 INTERNSHIP REPORT
PDF
BUILDING STRUCTURE FINAL REPORT
PDF
BUIDLING STRUCUTRE BEAM & COLUMN CALCULATION
PDF
BSC (H) ARCHITECTURE DEGREE SEM 4 ASIAN ARCHITECTURE CASE STUDY PAPER KHX
PDF
BSC (H) ARCHITECTURE DEGREE SEM 4 ASIAN ARCHITECTURE CASE STUDY PAPER
PDF
BSC (H) ARCHITECTURE DEGREE SEM 4 BUIDLING SERVICES REPORT FINAL
PDF
Menara Dayabumi Analysis Report
PDF
Final site a analysis
PDF
Building Construction Project 01 Final Report
PDF
PSY Presentation1 Comic
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
ARCHITECTURAL DESIGN PROJECT PRE DESIGN ANALYSIS TITIWANGSA
DEGREE SEM 5 THEORIES OF ARCHI. & URBANISM COMPARATIVE ESSAY
DEGREE SEM 5 BUILDING TECHNOLOGY PROJECT 02 IBS REPORT
DEGREE SEM 5 BUILDING SCIENCE PROJECT 01 ACOUSTIC CASE STUDY
DEGREE SEM 5 TALES OF 3 CITIES PROJECT 2 JLN H.S. LEE, KUALA LUMPUR
DEGREE SEM 5 TALES OF 3 CITIES PROJECT 1B URBAN JOURNAL
DEGREE SEM 5 TALES OF 3 CITIES PROJECT 1A GEORGETOWN
DEGREEM SEM 5 CSI REFLECTIVE JOURNAL
BSC (H) ARCHITECTURE DEGREE SEM 4.5 INTERNSHIP REPORT FINAL
BSC (H) ARCHITECTURE DEGREE SEM 4.5 INTERNSHIP REPORT
BUILDING STRUCTURE FINAL REPORT
BUIDLING STRUCUTRE BEAM & COLUMN CALCULATION
BSC (H) ARCHITECTURE DEGREE SEM 4 ASIAN ARCHITECTURE CASE STUDY PAPER KHX
BSC (H) ARCHITECTURE DEGREE SEM 4 ASIAN ARCHITECTURE CASE STUDY PAPER
BSC (H) ARCHITECTURE DEGREE SEM 4 BUIDLING SERVICES REPORT FINAL
Menara Dayabumi Analysis Report
Final site a analysis
Building Construction Project 01 Final Report
PSY Presentation1 Comic

Recently uploaded (20)

PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PPTX
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PPTX
GDM (1) (1).pptx small presentation for students
PDF
VCE English Exam - Section C Student Revision Booklet
PDF
O7-L3 Supply Chain Operations - ICLT Program
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PDF
102 student loan defaulters named and shamed – Is someone you know on the list?
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PDF
01-Introduction-to-Information-Management.pdf
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
Module 4: Burden of Disease Tutorial Slides S2 2025
Abdominal Access Techniques with Prof. Dr. R K Mishra
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
STATICS OF THE RIGID BODIES Hibbelers.pdf
GDM (1) (1).pptx small presentation for students
VCE English Exam - Section C Student Revision Booklet
O7-L3 Supply Chain Operations - ICLT Program
Final Presentation General Medicine 03-08-2024.pptx
Supply Chain Operations Speaking Notes -ICLT Program
FourierSeries-QuestionsWithAnswers(Part-A).pdf
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
102 student loan defaulters named and shamed – Is someone you know on the list?
Microbial diseases, their pathogenesis and prophylaxis
01-Introduction-to-Information-Management.pdf

DEGREE SEM 5 BUILDING SCIENCE PROJECT 2 INTEGRATION PROJECT

  • 1. BUILDING SCIENCE (BLD 61303) SCHOOL OF ARCHITECTURE, BUILDING & DESIGN Bachelor of Science (Honours) in Architecture PROJECT INTEGRATION WITH COMMUNITY LIBRARY BUILDING SCIENCE (BLD 61303) PROJECT 02 INTEGRATION PROJECT Prepared by: Tan Jo Lynn (0318518) Tutor: Mr. Azim Sulaiman PROJECT 02 INTEGRATION PROJECT Page ! of !1 26
  • 2. BUILDING SCIENCE (BLD 61303) TABLE OF CONTENT CHAPTER 1.0 INTRODUCTION 3 Section 1.1 Objectives 3 Section 1.2 Project Introduction 3 Section 1.3 Floor plans 4 Section 1.4 Sun Shading Diagrams 9 CHAPTER 2.0 SPACE A . E-LEARNING DEPARTMENT Section 2.1 Introduction 12 Section 2.2 Daylight Analysis 13 Section 2.3 Artificial light Analysis 15 CHAPTER 3.0 SPACE B . CASUAL READING SPACE Section 3.1 Introduction 19 Section 3.2 Daylight Analysis 20 Section 3.3 Artificial light Analysis 22 Section 3.4 PSALI 24 CHAPTER 6.0 REFERENCES 26 PROJECT 02 INTEGRATION PROJECT Page ! of !2 26
  • 3. BUILDING SCIENCE (BLD 61303) CHAPTER 1.0 INTRODUCTION 1.1 Objectives The intention of this project is to incorporate the lighting analysis and design in to the community library project to presents the understanding of artificial lighting and daylighting strategies to solve environment problems in relation to sustainability and user comfort, at the same time practice use of potential natural lighting. As the position of site selected faces the East - West, where daylighting is an critical issue if not adopted appropriately, utilisation of natural lighting is encouraged but at the same time provide a comfortable spatial qualities for each functional area. 1.2 Project Introduction The community library is located at Jalan Tuanku Abdul Rahman, Kuala Lumpur, an infill project between the Coliseum Cafe and Wisma Harwan. The design intention of my proposed library is to congregate experiences and to redefine perceptions of Malaysians towards the immigrants community. Thus, forming a humanistic library, a library beyond the collection of books and written knowledge. The application of natural lighting through facade, skylight and light wells to enhance the spatial lighting quality aims to reduce the use of artificial lighting, enabling users to experience the details of Jalan Tuanku Abdul Rahman through tactile senses. Therefore, well integration of artificial lighting and daylighting is required to achieved the poetics of space and structure as well as to provide sufficient luminance to the functional space according to its purposes in order to maintain the comfortable visual condition for users. PROJECT 02 INTEGRATION PROJECT Page ! of !3 26
  • 4. BUILDING SCIENCE (BLD 61303) 1.3 Floor Plans PROJECT 02 INTEGRATION PROJECT Page ! of !4 26 1 Ground Floor Floor Plan Scale 1:200
  • 5. BUILDING SCIENCE (BLD 61303) PROJECT 02 INTEGRATION PROJECT Page ! of !5 26 1 First Floor Floor Plan Scale 1:200
  • 6. BUILDING SCIENCE (BLD 61303) PROJECT 02 INTEGRATION PROJECT Page ! of !6 26 1 Second Floor Floor Plan Scale 1:200
  • 7. BUILDING SCIENCE (BLD 61303) PROJECT 02 INTEGRATION PROJECT Page ! of !7 26 1 Third Floor Floor Plan Scale 1:200
  • 8. BUILDING SCIENCE (BLD 61303) PROJECT 02 INTEGRATION PROJECT Page ! of !8 26 1 Fourth Floor Floor Plan Scale 1:200
  • 9. BUILDING SCIENCE (BLD 61303) 1.4 Sun Shading Diagrams At this hour, incident light travels from the East direction, which penetrates through the front facade in to the interior spaces. The front spaces of the library like casual reading space, young adult’s department, and antique archive gallery will be affected throughly. Therefore, the front facade will be installed with varieties of sun shading system depending on the function of the space. Light travels in to the spaces though light well will not affect the lighting condition much at this hour. Date Time Weather 16th July 2017 0830hr Sunny PROJECT 02 INTEGRATION PROJECT Page ! of !9 26
  • 10. BUILDING SCIENCE (BLD 61303) At this hour, the incident light is coming dominantly from the top of the East direction. Spaces affected by the source of light will be Lounge, which is located at the top floor. This issue is solved by using sun screens as continuation of roof design over the facade exposed to sunlight. Other spaces were not seriously affected by the sunlight at this point of time as light travels through light well in to these spaces, reducing glares and thermal discomfort by avoiding direct light and reflecting light. Date Time Weather 16th July 2017 1300hr Sunny PROJECT 02 INTEGRATION PROJECT Page ! of !10 26
  • 11. BUILDING SCIENCE (BLD 61303) The late afternoon sun affects mainly on the spaces located at the back of the building. For example, the meeting room that is located at the top floor. Spaces located below are protected by wall built for privacy of restrooms as well as the adjacent building. However, it is still important to provide sun shading system to reduce direct penetration of light in to the the space mentioned above. The application of operable solid wooden panels and louvers are used to prevent direct light at the same time, provide flexibility when natural light is needed. Light traveling through light well is diffused by the office spaces and the green wall installed in between two spaces to provide boundary. Therefore, the flexibility of use of facade is vital for the utilisation of natural lighting. Date Time Weather 16th July 2017 1700hr Sunny PROJECT 02 INTEGRATION PROJECT Page ! of !11 26
  • 12. BUILDING SCIENCE (BLD 61303) CHAPTER 2.0 SPACE A . E-LEARNING DEPARTMENT 2.1 Introduction Figure 2.1.1 Second floor floor plan with indication of location of Space A. The chosen space is a semi open area located on the second floor. Curtain is applied on one end of the space to avoid indirect light that reflects from the devices’ screen, causing discomfort like glares. Natural light received by the space through the light well is insufficient for a computer room based of the standard stated in MS 1525. Therefore, artificial lighting is needed throughout the day to provide sufficient illuminance level for the assigned activity in the space. PROJECT 02 INTEGRATION PROJECT Page ! of !12 26 1
  • 13. BUILDING SCIENCE (BLD 61303) 2.2 Daylight Analysis Daylight Factor Analysis Based on the daylight factors and distribution table stated by the Department of standards Malaysia, 2007, the space is fairly lit by the natural lighting. As from the calculation stated above, daylight received was just enough to achieved the requirement of illuminance level as stated in MS 1525. Floor Area (m²) 7.1 x 5.7 = 40.21m² Area of Facade exposed to Sunlight (m²) (0.9 x 3.5) + (2.141 x 3.5) = 23.625 Daylight Factor, DF DF = 40.21 / 23.625 x 100 DF = 17.02 x 0.1 DF = 1.7% Zone DF (%) Distribution Very Bright > 6 Large (including thermal and glare problem) Bright 3 - 6 Good Average 1 - 3 Fair Dark 0 -1 Poor Standard room Illumination recommendation by MS 1525 for computer rooms: 300 lux - 400 lux External Illumination (Shade illuminated by the entire clear blue sky) 20000 lux DF = Ei (indoor illuminance) x 100% Eo (outdoor illuminance) 1.7 = Ei x 100% 20000 Ei = 340 lux PROJECT 02 INTEGRATION PROJECT Page ! of !13 26 DF = Ei (indoor illuminance) x 100% Eo (outdoor illuminance)
  • 14. BUILDING SCIENCE (BLD 61303) Daylight Lux Contour Diagram Diagram Figure 2.2.1 Daylight contour of Space A. Based on the daylight analysis diagram, it is presented that the light enters the E-learning space from the openings towards the light well. The natural light received gradually decreases as it travels deeper in to the space. Thus, incorporation of artificial lighting is needed. Section analysis Diagram Figure 2.2.2 Section of Space A with shadow casting. The E-learning Department has daylight factor of 1.7%, which achieved a fairly lit environment due to the opening towards the light well that allows reflectance of natural light in to the space. The indoor illuminance of space is at 340 lux, positioned at the mid point of range 300 lux - 400 lux a stated in MS 1525. Thus, artificial lighting is needed throughout the day to achieved even distribution of light throughput the space as well as to provide sufficient illuminance level when daylight is not available when weather changes. PROJECT 02 INTEGRATION PROJECT Page ! of !14 26
  • 15. BUILDING SCIENCE (BLD 61303) 2.3 Artificial light Analysis Lumen Method Where, N = Number of lamps required E = Illuminance level required (lux) A = Area at working plane (m²) F = Average luminous flux from each fitting (lumen) UF = Utilisation factor, an allowance for light distribution of the luminaire and room surfaces MF = Maintenance factor, an allowance for reduced light output because of deterioration and dirt Room Index Where, L = Length of room W = Width of room Hm = Mounting height, the vertical distance between the working plane and luminaire PROJECT 02 INTEGRATION PROJECT Page ! of !15 26 N = E x A F x UF x EF RI = L x W Hm x (L + W)
  • 16. BUILDING SCIENCE (BLD 61303) Types of Fixture 1-Light Pendant Light Image of Fixture Product Dimension (mm) 100mm DIA. Type of Luminous Cool White Luminous flux (lumen) 1100 lumen Power (Watt) 11W Color Temperature (Kelvin) 4000 Color Rendering Index (CRI) 80 Average life rate (hours) 25000 Dimension of Room (m) Length = 7.1 Width = 5.7 Total floor area (m²) 40.21 Height of Ceiling (m) 4 Type of Light Fixture A19 LED Bulb Luminous flux of Lighting, F (lumen) 1100 Height of Luminaire (m) 3 Height of Working Plane (m) 0.77 Mounting Height (Hm) 4.00 - 1.00 - 0.77 = 1.73m Standard Illumination required according to MS1525 300 lux Reflectance factor Ceiling (wood panelling) = 0.7 Wall (green wall + curtain) = 0.5 Floor (timber cladding) = 0.2 Room Index, RI (K) RI = L x W Hm x (L+W) RI = (5.7 x 7.1) / [ 1.73 x (5.7+7.1) ] RI = 1.821 Utilisation Factor, UF 0.62 Maintenance Factor, MF 0.8 (standard) PROJECT 02 INTEGRATION PROJECT Page ! of !16 26
  • 17. BUILDING SCIENCE (BLD 61303) Lighting Layout Figure 2.3.1 Light fittings layout arranged based on analysis and calculation above. There area total amount of 22 light fixtures used to achieved the required illuminance level of 300 lux as stated in MS 1525 in the space with an area of 40.21m². As shown in the diagram, every 10 lighting fixtures are controlled by a one-way-two-gang switch. Number of Fittings required, N N = E x A F x UF x MF N = (300 x 40.21) / (1100 x 0.62 x 0.8) N = 22.1081 N = 22 bulbs Maximum spacing between Luminaire (m) Smax = 1.0 x Hm Smax = 1.0 x 1.6 Smax = 1.6 Fitting Layout Fitting required along 7.1m wall, (7.1 / 1.6 )m = 4.437 (5 rows) Number of Lamps in each row, 22lamps / 5 rows = 4.4 (4 lamps per row with 2 lamps on the sixth ) PROJECT 02 INTEGRATION PROJECT Page ! of !17 26
  • 18. BUILDING SCIENCE (BLD 61303) Artificial light Lux Contour Diagram Figure 2.3.2 Artificial light contour of Space A. The contour diagram shown above presents the lighting condition after the artificial lighting is installed and planned according to the analysis and calculation above. The light source is more evenly distributed to the working plane as compared to the light contour diagram in Figure 2.2.1. Bulb colour of cool white is chosen to create a more formal ambience for the working space. Pendant light is used to reduce the amount of light needed as it is in relation of the figure of Utilisation factor, UF, where it is indirectly proportional to the number of light fittings needed. Section analysis Diagram Figure 2.3.3 Section of Space A after application of artificial lighting. The inner portion of the e-learning space has no direct opening due to the location of restrooms that blocks the exposed area of back facade. Thus, the deeper part of space are mainly brighten up by the installation of artificial lighting to introduce balance distribution of light. PROJECT 02 INTEGRATION PROJECT Page ! of !18 26
  • 19. BUILDING SCIENCE (BLD 61303) CHAPTER 03 SPACE B . CASUAL READING SPACE 3.1 Introduction Figure 3.1.1 First floor floor plan with indication of location of Space B. The chosen space is a semi open area located on the first floor. Facade with installation of sun shading system is positioned on one end of the space to avoid direct light penetrating in to the space, causing discomfort like glares and thermal discomfort. Natural light received by the space through the light well exceeds the the requirements as stated in MS 1525. Therefore, design strategies are needed to be applied to prevent regrade of spatial experiences and working ambience. PROJECT 02 INTEGRATION PROJECT Page ! of !19 26 1
  • 20. BUILDING SCIENCE (BLD 61303) 3.2 Daylight Analysis Average Daylight Factor Where, W = Area of windows (m²) A = Total area of internal surfaces (m²) T = Glass transmittance corrected for dirt θ = Visible sky angle in degrees from the centre of the window R = Average reflectance of area A Figure 3.2.1 Diagram showing method of achieving figure for visible sky degree, θ. Floor Area, A (m²) A = (8.915 x 6.8) + (6.915 x 6.8) + (9.345 x 4.0 x 2) A = 182.204m² Area of Facade exposed to Sunlight, W (m²) W = [(1.95 x 3.245) + (3.25 x 1.0) + (0.85 x 1.15 x 4)] + (3.0 x 3.06) W = 22.67m² Average Transmittance, T T = (0.3 + 0.35 + 0.7) T = 0.35 Average Reflectance of surface area, R R = (0.7 + 0.5 + 0.2) / 3 R = 0,467 Daylight Factor, DF DF = W x Tθ A (1-R) DF = 22.67 / 182.204 x (0.35 x 74) / (1 - 0.467) DF = 6.1% PROJECT 02 INTEGRATION PROJECT Page ! of !20 26 DF = W x Tθ A (1 - R) from centre point of exposed facade opposite building
  • 21. BUILDING SCIENCE (BLD 61303) Based on the daylight factors and distribution table stated by the Department of standards Malaysia, 2007, the space is brightly lit by the natural daylight. As stated in the calculation above, daylight received has slightly exceeds requirement of illuminance level as stated in MS 1525. Daylight Lux Contour Diagram Figure 3.2.2 Daylight contour diagram of Space B. Zone DF (%) Distribution Very Bright > 6 Large (including thermal and glare problem) Bright 3 - 6 Good Average 1 - 3 Fair Dark 0 -1 Poor Standard room Illumination recommendation by MS 1525 for reading rooms: 300 lux - 500 lux External Illumination (Shade illuminated by the entire clear blue sky) 20000 lux DF = Ei (indoor illuminance) x 100% Eo (outdoor illuminance) 6.1 = Ei x 100% 20000 Ei = 1220 lux PROJECT 02 INTEGRATION PROJECT Page ! of !21 26
  • 22. BUILDING SCIENCE (BLD 61303) The light contour diagram shows that the space lit up by daylight from the expose facade area on one end and from the light well on the other. It is presented that the illuminance level decreases as it reaches the centre of space, forming unbalance light distribution throughout the space. Section analysis Diagram Figure 3.2.3 Section of Space B with shadow casting. The casual reading space achieved daylight factor of 6.1% and natural illuminance level of 1220 lux. Based on the standards stated in MS 1525, the space is bright lit by daylight as both figure exceeds the required figure. For instance, the bright daylight factor range from 3% - 6% and the suggested light level for reading space is 300 lux - 500 lux. Therefore, design strategies are require to reduce sun exposure to prevent issues of discomfort like glares and thermal discomfort. 3.3 Artificial light Analysis Types of Fixture Recessed Downlight Image of Fixture Product Dimension (mm) 160mm x 160mm Type of Luminous Neutral White PROJECT 02 INTEGRATION PROJECT Page ! of !22 26
  • 23. BUILDING SCIENCE (BLD 61303) Artificial light Lux Contour Diagram Figure 3.3.1 Artificial light contour diagram of Space B. The lux contour diagram presents that the light fittings installed are able to illuminate the casual reading space when daylight is not available as well as to provide an even distribution of light throughout the working plane. However, corners of the room are relatively dark as compared to the front and centre area of the space. Luminous flux (lumen) 1000 lumen Power (Watt) 14.2W Color Temperature (Kelvin) 3500 Color Rendering Index (CRI) 80 Average life rate (hours) 50000 Type of Light Fixture J-Box LED Luminous flux of Lighting, F (lumen) 1100 PROJECT 02 INTEGRATION PROJECT Page ! of !23 26
  • 24. BUILDING SCIENCE (BLD 61303) 3.4 PSALI Scheme Figure 3.4.1 Lighting layout arranged to incorporate with daylight utilisation. Figure 3.4.2 Section showing the lighting layout of artificial lighting system. PROJECT 02 INTEGRATION PROJECT Page ! of !24 26
  • 25. BUILDING SCIENCE (BLD 61303) The artificial lighting introduced to enhance the illumination of chosen space when natural lighting is not sufficient to cater with requirement as per listed in MS 1525. The total of 20 light fittings are controlled by a one-way-two-gang switch, and two single switches. During the brightest portion of the day, daylight factor at its highest, only row B needs to be switched on. The series of row C can be turned on in place of row B to increase the illuminance level of space. Row A and D all only be switch on when daylight factor is at its lowest, at night or during the dark days. Design Strategies Figure 3.4.3 Front facade of building with indication of material used. To reduce possibility of issues like thermal discomfort and glares, louvers and double glazing low-E glass panels have been applied to the front facade exposed to daylight. The floor platforms have been set back by 1000mm to form a buffer some to allow natural ventilation to eliminate heat gain by building facade. Double skin facade fired was also able to improve the comfort ambience of space as well as reduce consumption of energy. PROJECT 02 INTEGRATION PROJECT Page ! of !25 26
  • 26. BUILDING SCIENCE (BLD 61303) CHAPTER 4.0 REFERENCES 1. Philips SlimSurface Dimmable 14.2W 3000K 6" LED Downlight | S6S830K10. (n.d.). Retrieved July 16, 2017, from http://www.bulbs.com/product/S6S830K10 2. F., H., P., S., S., P., . . . F. (2017, May 16). Globe Electric 1-Light Vintage Edison Matte Black Mini Pendant-64906. Retrieved July 16, 2017, from http://www.homedepot.com/p/Globe- Electric-1-Light-Vintage-Edison-Matte-Black-Mini-Pendant-64906/205320312 3. Maxlite Dimmable 11W 4000K A19 LED Bulb, GU24 Base | 11A19GUDLED40/G4. (n.d.). Retrieved July 16, 2017, from http://www.bulbs.com/product/11A19GUDLED40-G4 4. Passionate About Sound - Healthcare. (n.d.). Retrieved July 16, 2017, from https:// www.armstrongceilings.com/commercial/en-us/commercial-ceilings-walls/woodworks- concealed-ceiling-tiles.html 5. Ceiling Wall System . (n.d.). Retrieved July 17, 2017, from http://www.armstrong.com/assets/ global/commclgeu/files/Literature/1709.PDF PROJECT 02 INTEGRATION PROJECT Page ! of !26 26