Question No. 1 2 3 4
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
: 30
MMUP Review Exam - Answer Key
Name: ID.No:
Question No. A B C D
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
: 30
MMUP Review Exam - Answer Sheet
Name: EMP.No:
Cost Control Department
:
MMUP Review Exam
Name: EMP No.
Project:
Date:
Page 1 of 5
Cost Control Department
1 The Performance of a specific task in CPM is known as:
a. Dummy
b. Event
c. Activity
d. Contract
2 Completion of an activity on CPM network diagram is generally known as:
a. Event
b. Node
c. Connector
d. All Of The Above.
3 Pick up the incorrect statement from the following:
a. The Activity Is The Time Consuming Part Of A Project.
b. The Beginning And The End Of A Job Are Called Events.
c. The Activity Which Consumes Maximum Time Is Called Anode.
d. Logically And Sequentially Connected Activities And Events From A Network
4 The time by which activity completion time can be delayed without affecting the start of succeeding
activities is known as:
a. Duration
b. Total Float
c. Free Float
d. Interfering Float
5 The difference between the time available to do a job and the time required to do the job is known as:
a. Event
b. Float
c. Duration
d. Constrain
6 For completion of a project, the critical path of the network represents
a. Minimum Time
b. Maximum Time
c. Maximum Cost
d. Minimum Cost
7 The three time estimates for the activities fo the network shown in the given figure are shown above their
arrows: The earliest expected time for the even 4 is:
3 - 4 - 5 5 - 7 - 9 6 - 8 - 10
a. 19
b. 14
c. 24
d. None Of Those
1 2 3 4
Page 2 of 5
Cost Control Department
8 A subcontractor has the task of erecting 8,400 sq2 of metal scaffolds. The contractor can use several
crews with various cost. It is expected that the production will vary with the crew size as given below:
Consider the following rates:
Labor = $ 96/day; Carpenter = $ 128/day; Foreman = $ 144/day; Scaffolder = $60/day
a. $ 76.22 /Day
b. $ 33.252 /Day
c. $ 70.00 /Day
d. None Of The Above.
9 Assume you can lease an item you need for project for $ 800/day. To purchase the item the cost is $
12,000 plus daily operational cost of $ 400/day. If you need the item for more than 30 days, it is more
economical to:
a. To Lease It
b. To Purchase It
10
Reinforcing steel bars of T10 mm at 10 cm spacing to be replaced by T12 mm. Calculate the new
required spacing
a. 14.4 mm
b. 6.9 mm
c. 12 mm
d. 8.3 mm
11
If a concrete beam is supported as continuous beam, the section at the support must be designated as:
a. T-Beam
b. Rectangular Beam
c. Simply Supported Beam
d. Flange Beam
12 Under normal conditions using an ordinary cement, the period of removal of the form work is:
a. 7 Days For Beam Soffits
b. 14 Days For Bottom Slabs Of Spans 4.6 M And More
c. 21 Days For Bottom Beams Over 6 M Spans
d. All Of The Above.
13 Permissible compressive strength of M 300 concrete grade is
a. 100 Kg/ Cm2
b. 150 Kg/ Cm2
c. 200 Kg/ Cm2
d. 300 Kg/ Cm2
14 Mass concrete is defined as the concrete where: (QCS)
a. The Dimension Is Equal To 1.5 M
b. Where The Large Dimension Exceeds 1.5 M
c. The Least Dimension Exceeds 1.5 M
d. None Of The Above.
Page 3 of 5
Cost Control Department
15 Temperature of fresh concrete should be:
a. Not Exceeds 42 Degrees
b. Equal To 40 Degrees
c. Not Exceeds 32 Degrees
d. None Of The Above.
16 Construction joint should be provided within:
a. The Middle Third Of Spans
b. At 1/3 To 1/4 Of Span In Slabs And Beams
c. Where Bm And S.F. Are Small
d. All Of The Above.
17 Curing:
a. Reduces The Shrinkage Of Concrete
b. Preserves The Properties Of Concrete
c. Prevents The Loss Of Water By Evaporation
d. All Of The Above.
18 The increased cohesiveness of concrete makes it:
a. Less Liable To Segregation
b. More Liable To Segregation
c. More Liable To Bleeding
d. More Liable For Surface Scaling In Frosty Weather
19 Workability improved by adding:
a. Air-Entraining Agent
b. Foaming Agent
c. Oily-Agent
d. All Of The Above.
20 Workability of concrete is measured by:
a. Vicat Apparatus Test
b. Slump Test
c. Minimum Void Method
d. Talbot Richart Test
21 According to the recommendation of IS 456-1978, the expansion joints:
a. Are Provided Where Plane Changes Abruptly
b. Are Provided To Ensure Minimum Resistance.
c. Are Supported On Separate Columns
d. All Of The Above.
22 Shrinkage in concrete can be reduced by using:
a. Low Water Cement Ratio.
b. Less Cement In The Concrete.
c. Proper Concrete Mix.
d. Pre-Saturated Aggregates
23 You are asked to construct a massive dam. The type of cement you will use is:
a. Ordinary Portland Cement
b. Rapid Hardening Cement
c. Low Heat Cement
d. Blast Furnace Slag Cement
Page 4 of 5
Cost Control Department
24 Specified compressive strength of concrete is obtained from cube tests at the end of:
a. 3 Days
b. 7 Days
c. 14 Days
d. 28 Days
25 The grade of concrete M150 means tha compressive strength of a 15 cube after 28 days is
a. 100 Kg/Cm²
b. 150 Kg/Cm²
c. 200 Kg/Cm²
d. 250 Kg/Cm²
26 The main object of compaction of concete is
a. To Elimate Air Holes
b. To Achieve Maximum Density
c. To Provide Intimate Contact Between The Concrete And Embedded Materials
d. All Of The Above
27 Strength of concrete with passage of time
a. Increases
b. Decreases
c. Fluctuates
d. Remains Constant
28
Consider the following statements in relation to the given sketch
1. Soil is partially saturated at degree of saturation = 60%
2. Void Ratio = 40%
3. Water Content = 30%
4. Saturated unit weight = 1.5 glcc
a. 1,2 And 3 Are Correct
b. 1,3 And 4 Are Correct
c. 2,3 And 4 Are Correct
d. 1,2 And 4 Are Correct
29 The structure shown in the given figure is stable if
a. X = 2Y
b. 2X = Y
c. √2
d. X = √2 Y
30
Active earth pressure per meter length on the retaining wall with a smooth vertical back as shown in the
given figure will be
a. 81+
b. 2+
c. 27+
d. 1+
Page 5 of 5

More Related Content

PDF
Mmup questionnaire 1
PDF
Mmup questionnaire 6
PDF
Mmup questionnaire 2
PDF
Mmup questionnaire 4
PDF
Mmup questionnaire 3
PDF
Mmup questionnaire 10
PDF
Mmup questionnaire 7
PDF
Mmup questionnaire 9
Mmup questionnaire 1
Mmup questionnaire 6
Mmup questionnaire 2
Mmup questionnaire 4
Mmup questionnaire 3
Mmup questionnaire 10
Mmup questionnaire 7
Mmup questionnaire 9

Similar to Mmup questionnaire 5 (20)

PDF
Mmup questionnaire 8
PDF
2.concrete technology
DOCX
1. Which section of a contract contains guidelines that ensure f.docx
PDF
Important Points of Structural Engineering ✅.pdf
PDF
ME REVIEWER
PDF
Concrete design mix (ss)
PPTX
Retrofitting of RC members and repair works.pptx
PPT
Concrete mix design
DOCX
1.Which section of a contract contains guidelines that ensure .docx
PDF
Aci mix design very good
PDF
Ssc junior-engineer-question-papers-for-civil-7
PPTX
Concrete technology-questions
PPTX
CONCRETE Design mix
PPTX
Properities Of Plain & Slag Concrete
PDF
MMUP exam quastions (provided by people who took the exam)
PPTX
Abhishek khandelwal
DOCX
@ETCONp Construction Exam 8 .DOCX
PDF
2008 - NOV.pdf
PPTX
Mmup questionnaire 8
2.concrete technology
1. Which section of a contract contains guidelines that ensure f.docx
Important Points of Structural Engineering ✅.pdf
ME REVIEWER
Concrete design mix (ss)
Retrofitting of RC members and repair works.pptx
Concrete mix design
1.Which section of a contract contains guidelines that ensure .docx
Aci mix design very good
Ssc junior-engineer-question-papers-for-civil-7
Concrete technology-questions
CONCRETE Design mix
Properities Of Plain & Slag Concrete
MMUP exam quastions (provided by people who took the exam)
Abhishek khandelwal
@ETCONp Construction Exam 8 .DOCX
2008 - NOV.pdf
Ad

More from Omar Selim (20)

PDF
Omar Salim Biography Omar Salim Biography
PDF
OMAR SELIM portfolio OMAR SELIM portfolio
PDF
BIM_Director_OMAR_SELIM_CV BIM_Director_OMAR_SELIM_CV
PDF
إعادة الإعمار .pdf
PDF
_الذكاء الاصطناعي .pdf
PDF
SmartHome.pdf
PDF
_الذكاء الاصطناعي .pdf
DOCX
Ch-3.docx
DOCX
ch-12.docx
DOCX
Ch-4.docx
DOCX
ch8.docx
DOCX
ch10.docx
DOCX
ch-11.docx
DOCX
ch9.docx
DOCX
ch-13.docx
DOCX
Ch-5.docx
DOCX
Ch-2.docx
DOCX
ch-6.docx
DOCX
Ch-1.docx
DOCX
all.docx
Omar Salim Biography Omar Salim Biography
OMAR SELIM portfolio OMAR SELIM portfolio
BIM_Director_OMAR_SELIM_CV BIM_Director_OMAR_SELIM_CV
إعادة الإعمار .pdf
_الذكاء الاصطناعي .pdf
SmartHome.pdf
_الذكاء الاصطناعي .pdf
Ch-3.docx
ch-12.docx
Ch-4.docx
ch8.docx
ch10.docx
ch-11.docx
ch9.docx
ch-13.docx
Ch-5.docx
Ch-2.docx
ch-6.docx
Ch-1.docx
all.docx
Ad

Recently uploaded (20)

PPTX
Unit 4 Computer Architecture Multicore Processor.pptx
PDF
LIFE & LIVING TRILOGY - PART - (2) THE PURPOSE OF LIFE.pdf
PPTX
What’s under the hood: Parsing standardized learning content for AI
PPTX
Computer Architecture Input Output Memory.pptx
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
PDF
advance database management system book.pdf
PDF
English Textual Question & Ans (12th Class).pdf
PDF
AI-driven educational solutions for real-life interventions in the Philippine...
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
PPTX
Core Concepts of Personalized Learning and Virtual Learning Environments
PDF
HVAC Specification 2024 according to central public works department
PDF
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
PDF
LIFE & LIVING TRILOGY - PART (3) REALITY & MYSTERY.pdf
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 2).pdf
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PDF
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
PDF
What if we spent less time fighting change, and more time building what’s rig...
PPTX
Education and Perspectives of Education.pptx
PDF
Journal of Dental Science - UDMY (2021).pdf
Unit 4 Computer Architecture Multicore Processor.pptx
LIFE & LIVING TRILOGY - PART - (2) THE PURPOSE OF LIFE.pdf
What’s under the hood: Parsing standardized learning content for AI
Computer Architecture Input Output Memory.pptx
A powerpoint presentation on the Revised K-10 Science Shaping Paper
advance database management system book.pdf
English Textual Question & Ans (12th Class).pdf
AI-driven educational solutions for real-life interventions in the Philippine...
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
Core Concepts of Personalized Learning and Virtual Learning Environments
HVAC Specification 2024 according to central public works department
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
LIFE & LIVING TRILOGY - PART (3) REALITY & MYSTERY.pdf
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 2).pdf
FORM 1 BIOLOGY MIND MAPS and their schemes
B.Sc. DS Unit 2 Software Engineering.pptx
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
What if we spent less time fighting change, and more time building what’s rig...
Education and Perspectives of Education.pptx
Journal of Dental Science - UDMY (2021).pdf

Mmup questionnaire 5

  • 1. Question No. 1 2 3 4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 : 30 MMUP Review Exam - Answer Key Name: ID.No:
  • 2. Question No. A B C D 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 : 30 MMUP Review Exam - Answer Sheet Name: EMP.No:
  • 3. Cost Control Department : MMUP Review Exam Name: EMP No. Project: Date: Page 1 of 5
  • 4. Cost Control Department 1 The Performance of a specific task in CPM is known as: a. Dummy b. Event c. Activity d. Contract 2 Completion of an activity on CPM network diagram is generally known as: a. Event b. Node c. Connector d. All Of The Above. 3 Pick up the incorrect statement from the following: a. The Activity Is The Time Consuming Part Of A Project. b. The Beginning And The End Of A Job Are Called Events. c. The Activity Which Consumes Maximum Time Is Called Anode. d. Logically And Sequentially Connected Activities And Events From A Network 4 The time by which activity completion time can be delayed without affecting the start of succeeding activities is known as: a. Duration b. Total Float c. Free Float d. Interfering Float 5 The difference between the time available to do a job and the time required to do the job is known as: a. Event b. Float c. Duration d. Constrain 6 For completion of a project, the critical path of the network represents a. Minimum Time b. Maximum Time c. Maximum Cost d. Minimum Cost 7 The three time estimates for the activities fo the network shown in the given figure are shown above their arrows: The earliest expected time for the even 4 is: 3 - 4 - 5 5 - 7 - 9 6 - 8 - 10 a. 19 b. 14 c. 24 d. None Of Those 1 2 3 4 Page 2 of 5
  • 5. Cost Control Department 8 A subcontractor has the task of erecting 8,400 sq2 of metal scaffolds. The contractor can use several crews with various cost. It is expected that the production will vary with the crew size as given below: Consider the following rates: Labor = $ 96/day; Carpenter = $ 128/day; Foreman = $ 144/day; Scaffolder = $60/day a. $ 76.22 /Day b. $ 33.252 /Day c. $ 70.00 /Day d. None Of The Above. 9 Assume you can lease an item you need for project for $ 800/day. To purchase the item the cost is $ 12,000 plus daily operational cost of $ 400/day. If you need the item for more than 30 days, it is more economical to: a. To Lease It b. To Purchase It 10 Reinforcing steel bars of T10 mm at 10 cm spacing to be replaced by T12 mm. Calculate the new required spacing a. 14.4 mm b. 6.9 mm c. 12 mm d. 8.3 mm 11 If a concrete beam is supported as continuous beam, the section at the support must be designated as: a. T-Beam b. Rectangular Beam c. Simply Supported Beam d. Flange Beam 12 Under normal conditions using an ordinary cement, the period of removal of the form work is: a. 7 Days For Beam Soffits b. 14 Days For Bottom Slabs Of Spans 4.6 M And More c. 21 Days For Bottom Beams Over 6 M Spans d. All Of The Above. 13 Permissible compressive strength of M 300 concrete grade is a. 100 Kg/ Cm2 b. 150 Kg/ Cm2 c. 200 Kg/ Cm2 d. 300 Kg/ Cm2 14 Mass concrete is defined as the concrete where: (QCS) a. The Dimension Is Equal To 1.5 M b. Where The Large Dimension Exceeds 1.5 M c. The Least Dimension Exceeds 1.5 M d. None Of The Above. Page 3 of 5
  • 6. Cost Control Department 15 Temperature of fresh concrete should be: a. Not Exceeds 42 Degrees b. Equal To 40 Degrees c. Not Exceeds 32 Degrees d. None Of The Above. 16 Construction joint should be provided within: a. The Middle Third Of Spans b. At 1/3 To 1/4 Of Span In Slabs And Beams c. Where Bm And S.F. Are Small d. All Of The Above. 17 Curing: a. Reduces The Shrinkage Of Concrete b. Preserves The Properties Of Concrete c. Prevents The Loss Of Water By Evaporation d. All Of The Above. 18 The increased cohesiveness of concrete makes it: a. Less Liable To Segregation b. More Liable To Segregation c. More Liable To Bleeding d. More Liable For Surface Scaling In Frosty Weather 19 Workability improved by adding: a. Air-Entraining Agent b. Foaming Agent c. Oily-Agent d. All Of The Above. 20 Workability of concrete is measured by: a. Vicat Apparatus Test b. Slump Test c. Minimum Void Method d. Talbot Richart Test 21 According to the recommendation of IS 456-1978, the expansion joints: a. Are Provided Where Plane Changes Abruptly b. Are Provided To Ensure Minimum Resistance. c. Are Supported On Separate Columns d. All Of The Above. 22 Shrinkage in concrete can be reduced by using: a. Low Water Cement Ratio. b. Less Cement In The Concrete. c. Proper Concrete Mix. d. Pre-Saturated Aggregates 23 You are asked to construct a massive dam. The type of cement you will use is: a. Ordinary Portland Cement b. Rapid Hardening Cement c. Low Heat Cement d. Blast Furnace Slag Cement Page 4 of 5
  • 7. Cost Control Department 24 Specified compressive strength of concrete is obtained from cube tests at the end of: a. 3 Days b. 7 Days c. 14 Days d. 28 Days 25 The grade of concrete M150 means tha compressive strength of a 15 cube after 28 days is a. 100 Kg/Cm² b. 150 Kg/Cm² c. 200 Kg/Cm² d. 250 Kg/Cm² 26 The main object of compaction of concete is a. To Elimate Air Holes b. To Achieve Maximum Density c. To Provide Intimate Contact Between The Concrete And Embedded Materials d. All Of The Above 27 Strength of concrete with passage of time a. Increases b. Decreases c. Fluctuates d. Remains Constant 28 Consider the following statements in relation to the given sketch 1. Soil is partially saturated at degree of saturation = 60% 2. Void Ratio = 40% 3. Water Content = 30% 4. Saturated unit weight = 1.5 glcc a. 1,2 And 3 Are Correct b. 1,3 And 4 Are Correct c. 2,3 And 4 Are Correct d. 1,2 And 4 Are Correct 29 The structure shown in the given figure is stable if a. X = 2Y b. 2X = Y c. √2 d. X = √2 Y 30 Active earth pressure per meter length on the retaining wall with a smooth vertical back as shown in the given figure will be a. 81+ b. 2+ c. 27+ d. 1+ Page 5 of 5