Managing in the Presence of Uncertainty requires
making decision with Models of that Uncertainty
Monte Carlo Simulation and some related approaches can be the basis of making informed decisions
in the presence of Uncertainty
MONTE CARLO
SIMULATION AND
ESTIMATING
TRADITIONAL AND
AGILE DEVELOPMENT
V1.0 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
+ The Motivation for Monte Carlo
Simulation
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
2
A rough translation of the planning algorithm
from Aristotle’s De Moti Animalium, c. 400 BC
But how does it happen that thinking is
sometimes accompanied by action and
sometimes not, sometimes by motion, and
sometimes not?
It looks as if almost the same thing happens as
in the case of reasoning and making inferences
about unchanging objects.
But in that case the end is a speculative
proposition ... whereas here the conclusion
which results from the two premises is an
action. ... I need covering; a cloak is a
covering. I need a cloak. What I need, I have to
make; I need a cloak. I have to make a cloak.
And the conclusion, the “I have to make a
cloak,” is an action.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 3
Uncertainties are
things we can not be
certain about.
Uncertainty is created
by our incomplete
knowledge ‒ not by
our ignorance
And
By the naturally
occurring variances
in the underlying
processes of nature
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 4
“Am I to understand that my estimate
is greeted by some skepticism?”
+ Some Words about Uncertainty
n When we say uncertainty, we speak about a future state of an system
that is not fixed or determined.
n Uncertainty is related to three aspects in our program management
domain:
n The external world – the activities of the program
n Our knowledge of this world – the planned and actual behaviors of the
program
n Our perception of this world – the data and information we receive about
these behaviors
n Managing in the presence of uncertainty is part of each success factor
n What does Done Look Like?
n What’s the Plan to reach Done
n What resources do we need to reach Done?
n What are the Impediments to reaching Done?
n How are we measuring progress to plan toward Done?
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
5
+ Taxonomy of Uncertainty
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
6
Uncertainty
Irreducible
(Aleatory)
Reducible
(Epistemic)
Natural Variability
Ambiguity
Ontological
Uncertainty
Probabilistic Events
Probabilistic
Impacts
Periods of Exposure
+ Aleatory & Epistemic Uncertainty
n Aleatory Pertaining to stochastic (non-deterministic) events, the
outcome of which is described using probability.
n From the Latin alea
n For example in a game of chance stochastic variability's are the natural
randomness of the process and are characterized by a probability density
function (PDF) for their range and frequency
n Since these variability's are natural they are therefore irreducible.
n Epistemic (subjective or probabilistic) uncertainties are event based
probabilities, are knowledge-based, and are reducible by further
gathering of knowledge.
n Pertaining to the degree of knowledge about models and their parameters.
n From the Greek episteme (knowledge).
Separating these classes helps in design of assessment calculations and
in presentation of results for the integrated program risk assessment.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
7
+ 3 Conditions of Aleatory
Uncertainty
n An aleatory model contains a single unknown parameter.
n Duration
n Cost
n The prior information for this parameter is homogeneous and is
known with certainty.
n Reference Classes
n Past Performance
n The observed data are homogeneous and are known with certainty.
n A set of information that is made up of similar constituents.
n A homogeneous population is one in which each item is of the same type.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
8
+ Measurement Uncertainty
n Precision – how small is the variance of the estimates
n Accuracy – how close is the estimate to the actual values
n Bias – what impacts on precision and accuracy come from the
human judgments (or misjudgments)
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
9
­ Accuracy
­ Precision
­ Accuracy
¯ Precision
¯ Accuracy
­ Precision
¯ Accuracy
¯ Precision
+ Precision and Accuracy
n Credible estimates of program variables require both Accuracy and
Precision
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
10
+ Cost Probability Distributions
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
11
$
Cost Driver (Weight)
Cost = a + bXc
Cost
Estimate
Historical data point
Cost estimating relationship
Standard percent error boundsTechnical Uncertainty
Combined Cost
Modeling and
Technical Uncertainty
Cost Modeling
Uncertainty
† NRO Cost Group Risk Process,Tim Anderson,The Aerospace Corporation, 2003
+
Monte Carlo
Simulation in the
Presence of
Uncertainty
George Louis Leclerc, Comte
de Buffon, asked what was
the probability that the
needle would fall across one
of the lines, marked here in
green.That outcome will
occur only if
𝐴 < 𝑙 sin 𝜃
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
12
+ Monte Carlo Simulation Provides one
Solution the Estimating Problem
n Yes, Monte Carlo is named after the
country full of casinos located on the
French Rivera
n Advantages of Monte Carlo
n Examines all possible states of a
variable, not just the Mean and Variance
n Provides an accurate (true) estimate of
completion
n Overall duration distribution
n Confidence interval (accuracy range)
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
13
n Sensitivity analysis of interacting tasks
n Varied activity distribution types
n Dependency logic can include both probabilistic and conditional
n When resource loaded plans are used – provides integrated cost and
schedule probabilistic model
+ The Monte Carol Methods Starts in
WWII History
n Any method which solves a
problem by generating suitable
random numbers and observing
that fraction of the numbers
obeying some property.
n The Monte Carlo method provides
approximate solutions to a variety
of mathematical problems by
performing statistical sampling
experiments on a computer.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
14
n The method applies to problems with no probabilistic content as well as
to those with inherent probabilistic structure.
n The method is named after the city of Monte Carlo in the principality of
Monaco, because of a roulette, a simple random number generator.The
name and the systematic development of Monte Carlo methods dates
from about 1944 and the Manhattan project.
+ Monte Carlo Simulation Tools
n @Risk – we use this on our programs
n http://www.palisade.com/risk/
n Risk Amp – an embedded Excel MCS simulator, used for cost modeling
n https://www.riskamp.com/
n Risky Project ‒ a MCS for cost and schedule using MSFT Project on our
programs
n http://intaver.com/
n MonteCarlito – haven’t used
n http://www.montecarlito.com/
n SimTools – haven’t used
n http://home.uchicago.edu/~rmyerson/addins.htm
n Monte Carlo Simulation Tutorial
n http://excelmontecarlo.com/
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
15
+ Monte Carlo Simulation Tools
n SimulAr – haven’t used
n http://www.simularsoft.com.ar/SimulAr1e.htm
n Barnecana – popular in our domain
n https://www.barbecana.com/
n Monte Carlo Simulation tool for JIRA – interesting plug in
n https://agilemontecarlo.com/
n Guesstimate – used for quick assessment of cost model
n https://www.getguesstimate.com/
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
16
+ References
n Cost Risk Analysis Made Simple
n https://www.aceit.com/docs/default-source/white-papers/cost-risk-
analysis-made-simple-(aiaa-sep-2004).pdf
n An Implementation of the Lurie-Goldberg Algorithm in Schedule Risk Analysis
n http://www.slideserve.com/Olivia/an-implementation-of-the-lurie-
goldberg-algorithm-in-schedule-risk-analysis
n The Beginning of the Monte Carlo Method
n http://library.lanl.gov/cgi-bin/getfile?00326866.pdf
n The Basics of Monte Carlo Simulation
n http://www.risksig.com/members/present/2001/21023.pdf
n “The Mother of All Guesses: A User Friendly Guide to Statistical
Estimation,” Francois Melese and David Rose, Armed Forces Comptroller,
1998
n http://www.nps.navy.mil/drmi/graphics/StatGuide–web.pdf
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
17
+ References
n Anchoring and Adjustment in Software Estimation
n http://www.cs.toronto.edu/~sme/papers/2005/ESEC-FSE-05-Aranda.pdf
n Managing in the Presence of Uncertainty
n https://www.slideshare.net/galleman/managing-in-the-presence-of-
uncertainty
n How to reduce Agile Risk with Monte Carlo Simulation
n https://blog.versionone.com/how-to-reduce-agile-risk-with-monte-carlo-
simulation/
n Agile project forecasting using Monte Carlo Simulation
n http://scrumage.com/blog/2015/09/agile-project-forecasting-the-monte-
carlo-method/
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
18
+ References
n Effort Estimation in Agile Software Software Development: A Systematic
Literature Review
n https://www.diva-portal.org/smash/get/diva2:881296/FULLTEXT01.pdf
n Monte Carlo Basics
n https://arxiv.org/pdf/cond-mat/0104215.pdf
n Focused Objectives has many papers and a book
n http://focusedobjective.com/forecast_agile_project_spreadsheet/
n Monte Carlo Simulation in Agile Project Estimation
n https://www.academia.edu/8939341/Monte-
Carlo_Simulation_in_Agile_Project_Estimation_Forecasting_Schedule_an
d_Required_Velocity (log in may be required)
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
19

More Related Content

PDF
Kanban Basics for Beginners
PDF
QRQC - Quick Response Quality Control
PDF
Modern Agile - Joshua Kerievsky
PDF
User Story Sizing using Agile Relative Estimation
PDF
PMI-ACP Lesson 9 Agile Risk Management
PDF
Agile Basics / Fundamentals
PDF
Checklist for the Agile Manager
PPTX
story points v2
Kanban Basics for Beginners
QRQC - Quick Response Quality Control
Modern Agile - Joshua Kerievsky
User Story Sizing using Agile Relative Estimation
PMI-ACP Lesson 9 Agile Risk Management
Agile Basics / Fundamentals
Checklist for the Agile Manager
story points v2

What's hot (20)

PDF
Kaizen Event Guide
PPT
Green Belt Training
PDF
Practical estimation techniques
PPTX
Agile Patterns and Anti-Patterns
PPTX
Workshop Cost of Delay In Action
PDF
How to Use VSM Correctly
PPTX
How to estimate in scrum
PDF
Estimating Story Points in Agile - MAGIC Approach
PPTX
Agile Business Value
PDF
Hoshin Kanri: Creating a Strategy Deployment Plan That Gets Results
PPTX
Top 25 lean tools
PDF
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-ii
PDF
Lean Leadership: Helping Leaders Understand Their Role In The Improvement Pro...
PPTX
Monte Carlo and Schedule Risk Analysis
PDF
瓶頸處理九大原則 (精簡版)
PDF
Value Stream Mapping in the Office
PDF
Metrics-Based Process Mapping: Part 1 of 3
PPTX
Agile estimation
PDF
Story Points Estimation And Planning Poker
PPTX
Value stream mapping study with example
Kaizen Event Guide
Green Belt Training
Practical estimation techniques
Agile Patterns and Anti-Patterns
Workshop Cost of Delay In Action
How to Use VSM Correctly
How to estimate in scrum
Estimating Story Points in Agile - MAGIC Approach
Agile Business Value
Hoshin Kanri: Creating a Strategy Deployment Plan That Gets Results
Top 25 lean tools
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-ii
Lean Leadership: Helping Leaders Understand Their Role In The Improvement Pro...
Monte Carlo and Schedule Risk Analysis
瓶頸處理九大原則 (精簡版)
Value Stream Mapping in the Office
Metrics-Based Process Mapping: Part 1 of 3
Agile estimation
Story Points Estimation And Planning Poker
Value stream mapping study with example
Ad

Similar to Monte Carlo Simulation for Agile Development (20)

PPTX
Managing in the Presence of Uncertanty
PPTX
Risk adjusted engineering management
PPTX
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
PDF
12.0 risk management agile+evm (v10.2)
PDF
Managing in the presence of uncertainty
PPTX
Risk Event Modeling and Event Chains
PDF
Risk management of the performance measurement baseline
PDF
Introduction to monte-carlo analysis for software development - Troy Magennis...
PPTX
Injecting Certainty Into An Uncertain Process
PPTX
Using Risk Analysis and Simulation in Project Management
PPT
Project Risk Analysis with Risk Event and Event Chain
PDF
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
PPTX
3. 2. decision making
DOCX
httphome.ubalt.eduntsbarshbusiness-statoprepartIX.htmTool.docx
PPTX
@RISK Unchained Webinar
PDF
Integrating cost, schedule, and technical performance
PPTX
Risk Adjusted Estimating Techniques
PPT
2011 02-04 - d sallier - prévision probabiliste
PPTX
Integrating risk with earned value
PPTX
Showing how to Increase the Probability of Project Success by applying the ...
Managing in the Presence of Uncertanty
Risk adjusted engineering management
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
12.0 risk management agile+evm (v10.2)
Managing in the presence of uncertainty
Risk Event Modeling and Event Chains
Risk management of the performance measurement baseline
Introduction to monte-carlo analysis for software development - Troy Magennis...
Injecting Certainty Into An Uncertain Process
Using Risk Analysis and Simulation in Project Management
Project Risk Analysis with Risk Event and Event Chain
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
3. 2. decision making
httphome.ubalt.eduntsbarshbusiness-statoprepartIX.htmTool.docx
@RISK Unchained Webinar
Integrating cost, schedule, and technical performance
Risk Adjusted Estimating Techniques
2011 02-04 - d sallier - prévision probabiliste
Integrating risk with earned value
Showing how to Increase the Probability of Project Success by applying the ...
Ad

More from Glen Alleman (20)

PDF
Managing risk with deliverables planning
PDF
A Gentle Introduction to the IMP/IMS
PDF
Increasing the Probability of Project Success
PDF
Process Flow and Narrative for Agile+PPM
PDF
Practices of risk management
PDF
Principles of Risk Management
PDF
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
PDF
From Principles to Strategies for Systems Engineering
PDF
NAVAIR Integrated Master Schedule Guide guide
PDF
Building a Credible Performance Measurement Baseline
PDF
Integrated master plan methodology (v2)
PDF
IMP / IMS Step by Step
PDF
DHS - Using functions points to estimate agile development programs (v2)
PDF
Making the impossible possible
PDF
Heliotropic Abundance
PDF
Capabilities based planning
PDF
Process Flow and Narrative for Agile
PDF
Building the Performance Measurement Baseline
PPTX
Program Management Office Lean Software Development and Six Sigma
PDF
Policy and Procedure Rollout
Managing risk with deliverables planning
A Gentle Introduction to the IMP/IMS
Increasing the Probability of Project Success
Process Flow and Narrative for Agile+PPM
Practices of risk management
Principles of Risk Management
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
From Principles to Strategies for Systems Engineering
NAVAIR Integrated Master Schedule Guide guide
Building a Credible Performance Measurement Baseline
Integrated master plan methodology (v2)
IMP / IMS Step by Step
DHS - Using functions points to estimate agile development programs (v2)
Making the impossible possible
Heliotropic Abundance
Capabilities based planning
Process Flow and Narrative for Agile
Building the Performance Measurement Baseline
Program Management Office Lean Software Development and Six Sigma
Policy and Procedure Rollout

Recently uploaded (20)

PPTX
sap open course for s4hana steps from ECC to s4
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
DOCX
The AUB Centre for AI in Media Proposal.docx
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PPTX
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
PDF
gpt5_lecture_notes_comprehensive_20250812015547.pdf
PDF
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PPTX
MYSQL Presentation for SQL database connectivity
PDF
Dropbox Q2 2025 Financial Results & Investor Presentation
PDF
Encapsulation_ Review paper, used for researhc scholars
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
PPTX
A Presentation on Artificial Intelligence
PDF
Advanced methodologies resolving dimensionality complications for autism neur...
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PDF
Machine learning based COVID-19 study performance prediction
PPT
Teaching material agriculture food technology
PDF
Empathic Computing: Creating Shared Understanding
sap open course for s4hana steps from ECC to s4
Digital-Transformation-Roadmap-for-Companies.pptx
The AUB Centre for AI in Media Proposal.docx
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
gpt5_lecture_notes_comprehensive_20250812015547.pdf
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
Per capita expenditure prediction using model stacking based on satellite ima...
MYSQL Presentation for SQL database connectivity
Dropbox Q2 2025 Financial Results & Investor Presentation
Encapsulation_ Review paper, used for researhc scholars
“AI and Expert System Decision Support & Business Intelligence Systems”
A Presentation on Artificial Intelligence
Advanced methodologies resolving dimensionality complications for autism neur...
Building Integrated photovoltaic BIPV_UPV.pdf
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
Agricultural_Statistics_at_a_Glance_2022_0.pdf
Machine learning based COVID-19 study performance prediction
Teaching material agriculture food technology
Empathic Computing: Creating Shared Understanding

Monte Carlo Simulation for Agile Development

  • 1. + Managing in the Presence of Uncertainty requires making decision with Models of that Uncertainty Monte Carlo Simulation and some related approaches can be the basis of making informed decisions in the presence of Uncertainty MONTE CARLO SIMULATION AND ESTIMATING TRADITIONAL AND AGILE DEVELOPMENT V1.0 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017
  • 2. + The Motivation for Monte Carlo Simulation Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 2 A rough translation of the planning algorithm from Aristotle’s De Moti Animalium, c. 400 BC But how does it happen that thinking is sometimes accompanied by action and sometimes not, sometimes by motion, and sometimes not? It looks as if almost the same thing happens as in the case of reasoning and making inferences about unchanging objects. But in that case the end is a speculative proposition ... whereas here the conclusion which results from the two premises is an action. ... I need covering; a cloak is a covering. I need a cloak. What I need, I have to make; I need a cloak. I have to make a cloak. And the conclusion, the “I have to make a cloak,” is an action.
  • 3. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 3 Uncertainties are things we can not be certain about. Uncertainty is created by our incomplete knowledge ‒ not by our ignorance And By the naturally occurring variances in the underlying processes of nature
  • 4. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 4 “Am I to understand that my estimate is greeted by some skepticism?”
  • 5. + Some Words about Uncertainty n When we say uncertainty, we speak about a future state of an system that is not fixed or determined. n Uncertainty is related to three aspects in our program management domain: n The external world – the activities of the program n Our knowledge of this world – the planned and actual behaviors of the program n Our perception of this world – the data and information we receive about these behaviors n Managing in the presence of uncertainty is part of each success factor n What does Done Look Like? n What’s the Plan to reach Done n What resources do we need to reach Done? n What are the Impediments to reaching Done? n How are we measuring progress to plan toward Done? Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 5
  • 6. + Taxonomy of Uncertainty Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 6 Uncertainty Irreducible (Aleatory) Reducible (Epistemic) Natural Variability Ambiguity Ontological Uncertainty Probabilistic Events Probabilistic Impacts Periods of Exposure
  • 7. + Aleatory & Epistemic Uncertainty n Aleatory Pertaining to stochastic (non-deterministic) events, the outcome of which is described using probability. n From the Latin alea n For example in a game of chance stochastic variability's are the natural randomness of the process and are characterized by a probability density function (PDF) for their range and frequency n Since these variability's are natural they are therefore irreducible. n Epistemic (subjective or probabilistic) uncertainties are event based probabilities, are knowledge-based, and are reducible by further gathering of knowledge. n Pertaining to the degree of knowledge about models and their parameters. n From the Greek episteme (knowledge). Separating these classes helps in design of assessment calculations and in presentation of results for the integrated program risk assessment. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 7
  • 8. + 3 Conditions of Aleatory Uncertainty n An aleatory model contains a single unknown parameter. n Duration n Cost n The prior information for this parameter is homogeneous and is known with certainty. n Reference Classes n Past Performance n The observed data are homogeneous and are known with certainty. n A set of information that is made up of similar constituents. n A homogeneous population is one in which each item is of the same type. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 8
  • 9. + Measurement Uncertainty n Precision – how small is the variance of the estimates n Accuracy – how close is the estimate to the actual values n Bias – what impacts on precision and accuracy come from the human judgments (or misjudgments) Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 9 ­ Accuracy ­ Precision ­ Accuracy ¯ Precision ¯ Accuracy ­ Precision ¯ Accuracy ¯ Precision
  • 10. + Precision and Accuracy n Credible estimates of program variables require both Accuracy and Precision Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 10
  • 11. + Cost Probability Distributions Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 11 $ Cost Driver (Weight) Cost = a + bXc Cost Estimate Historical data point Cost estimating relationship Standard percent error boundsTechnical Uncertainty Combined Cost Modeling and Technical Uncertainty Cost Modeling Uncertainty † NRO Cost Group Risk Process,Tim Anderson,The Aerospace Corporation, 2003
  • 12. + Monte Carlo Simulation in the Presence of Uncertainty George Louis Leclerc, Comte de Buffon, asked what was the probability that the needle would fall across one of the lines, marked here in green.That outcome will occur only if 𝐴 < 𝑙 sin 𝜃 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 12
  • 13. + Monte Carlo Simulation Provides one Solution the Estimating Problem n Yes, Monte Carlo is named after the country full of casinos located on the French Rivera n Advantages of Monte Carlo n Examines all possible states of a variable, not just the Mean and Variance n Provides an accurate (true) estimate of completion n Overall duration distribution n Confidence interval (accuracy range) Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 13 n Sensitivity analysis of interacting tasks n Varied activity distribution types n Dependency logic can include both probabilistic and conditional n When resource loaded plans are used – provides integrated cost and schedule probabilistic model
  • 14. + The Monte Carol Methods Starts in WWII History n Any method which solves a problem by generating suitable random numbers and observing that fraction of the numbers obeying some property. n The Monte Carlo method provides approximate solutions to a variety of mathematical problems by performing statistical sampling experiments on a computer. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 14 n The method applies to problems with no probabilistic content as well as to those with inherent probabilistic structure. n The method is named after the city of Monte Carlo in the principality of Monaco, because of a roulette, a simple random number generator.The name and the systematic development of Monte Carlo methods dates from about 1944 and the Manhattan project.
  • 15. + Monte Carlo Simulation Tools n @Risk – we use this on our programs n http://www.palisade.com/risk/ n Risk Amp – an embedded Excel MCS simulator, used for cost modeling n https://www.riskamp.com/ n Risky Project ‒ a MCS for cost and schedule using MSFT Project on our programs n http://intaver.com/ n MonteCarlito – haven’t used n http://www.montecarlito.com/ n SimTools – haven’t used n http://home.uchicago.edu/~rmyerson/addins.htm n Monte Carlo Simulation Tutorial n http://excelmontecarlo.com/ Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 15
  • 16. + Monte Carlo Simulation Tools n SimulAr – haven’t used n http://www.simularsoft.com.ar/SimulAr1e.htm n Barnecana – popular in our domain n https://www.barbecana.com/ n Monte Carlo Simulation tool for JIRA – interesting plug in n https://agilemontecarlo.com/ n Guesstimate – used for quick assessment of cost model n https://www.getguesstimate.com/ Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 16
  • 17. + References n Cost Risk Analysis Made Simple n https://www.aceit.com/docs/default-source/white-papers/cost-risk- analysis-made-simple-(aiaa-sep-2004).pdf n An Implementation of the Lurie-Goldberg Algorithm in Schedule Risk Analysis n http://www.slideserve.com/Olivia/an-implementation-of-the-lurie- goldberg-algorithm-in-schedule-risk-analysis n The Beginning of the Monte Carlo Method n http://library.lanl.gov/cgi-bin/getfile?00326866.pdf n The Basics of Monte Carlo Simulation n http://www.risksig.com/members/present/2001/21023.pdf n “The Mother of All Guesses: A User Friendly Guide to Statistical Estimation,” Francois Melese and David Rose, Armed Forces Comptroller, 1998 n http://www.nps.navy.mil/drmi/graphics/StatGuide–web.pdf Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 17
  • 18. + References n Anchoring and Adjustment in Software Estimation n http://www.cs.toronto.edu/~sme/papers/2005/ESEC-FSE-05-Aranda.pdf n Managing in the Presence of Uncertainty n https://www.slideshare.net/galleman/managing-in-the-presence-of- uncertainty n How to reduce Agile Risk with Monte Carlo Simulation n https://blog.versionone.com/how-to-reduce-agile-risk-with-monte-carlo- simulation/ n Agile project forecasting using Monte Carlo Simulation n http://scrumage.com/blog/2015/09/agile-project-forecasting-the-monte- carlo-method/ Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 18
  • 19. + References n Effort Estimation in Agile Software Software Development: A Systematic Literature Review n https://www.diva-portal.org/smash/get/diva2:881296/FULLTEXT01.pdf n Monte Carlo Basics n https://arxiv.org/pdf/cond-mat/0104215.pdf n Focused Objectives has many papers and a book n http://focusedobjective.com/forecast_agile_project_spreadsheet/ n Monte Carlo Simulation in Agile Project Estimation n https://www.academia.edu/8939341/Monte- Carlo_Simulation_in_Agile_Project_Estimation_Forecasting_Schedule_an d_Required_Velocity (log in may be required) Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2017 19