Module 5: Develop a project plan for a simple project Project Management 3 Future Managers
Module 5: Develop a project plan for a simple project After completing this module, you will be able to: Develop a project plan for a simple project Demonstrate an understanding of the use of project management and tools Participate in the costing & budgeting of a small project Provide project templates to team members Use a paper based and/or electronic filing system for a project. Project Management 3 Future Managers
1. Develop a project plan for a simple project After completing this outcome, you will be able to: Assess components of a given project plan Collect and organise information relating to the individual project/sub-project Develop a project plan for a simple project Project Management 3 Future Managers
1. Develop a project plan for a simple project Why do we plan? A project plan is a roadmap for the project, it help to guide the work from start to finish It serves as a tool for communication with both stakeholders and the project team  We need to plan in terms of resources required Planning, not only establishes what is to be done but also “smoothes the way to make it happen” Planning encourages participation, from all the role players involved in the project Planning leads to prompt action Planning solves problems before they can influence the project and its outcome Planning formulates decisions based on consensus Planning avoids costly changes Project Management 3 Future Managers
1.1 Assessment of the components of a project plan Developing a solid project plan Record assumptions made during project planning Direct project execution and control Provide instructions for documenting what decisions were made and why they were made Specify dates for management reviews Define standards against which project and team members’ performance are measured Project Management 3 Future Managers
1.2 Information on the planning of a project Network planning Time analysis   Resource analysis   Cost analysis Multiple schedules   Progress reports   Key events   Deadlines and activity logic Project Management 3 Future Managers
1.3 Development of a project plan What should be included in a project plan? Documents used during project planning, such as the scope statement, work breakdown structure, and cost estimates The project charter Scope, risk, communication, procurement, and schedule management plan Responsibility assignments Schedule dates and milestones Major risks, constraints, and assumptions and how each will be handled Pending issues and decisions Design and other specifications. Project Management 3 Future Managers
1.3 Development of a project plan A good project plan: Directs how, when, and by whom all project activities should be completed Instructs ways to document what decisions are made and why they are made Specifies dates for management reviews Defines standards against which the project and team members’ performance is measured Project Management 3 Future Managers
1.3 Development of a project plan Additional actions that must be performed Define the project’s quality standards and develop a quality management plan Assign roles and responsibilities, which include developing a staff management plan and acquiring staff for the project team Develop a communication system, which includes creating a communications management plan that will make sure information is distributed to the right people at the right times in an appropriate format Project Management 3 Future Managers
1.3 Development of a project plan Additional actions that must be performed Identify and evaluate the seriousness of potential project risks Develop responses to the potential risks, which include compiling a risk management plan Decide which resources must be produced from outside the project’s parent organisation and which includes developing a procurement management plan Determine and define resource requirements, such as what level of quality is expected from contracted work Project Management 3 Future Managers
Project Management 3 Future Managers
The project plan Project Management 3 Future Managers Skills by task Resources by task Time per task Task relationships costs & constraints statement of work (SOW) WBS network diagram schedule & timeline budget budget
The project plan (large project) Summary of the project (or project overview)   Project objectives Project charter Project assumptions and risks Project milestones Work breakdown structure (WBS) Network diagram Resource details Human resources Equipment Materials and supplies Budget details Project organisation Operating procedures Assessment and review standards Contact points and information sources Project approval Project Management 3 Future Managers
The project plan (large project) Summary of the project (or project overview)   Project objectives Project charter Project assumptions and risks Project milestones Work breakdown structure (WBS) Network diagram Project Management 3 Future Managers
The project plan (large project) Resource details Human resources Equipment Materials and supplies Budget details Project organisation Operating procedures Assessment and review standards Contact points and information sources Project approval Project Management 3 Future Managers
Project plan What is the right level of planning? What are the consequences of not having your project reviewed by qualified individuals? It is more difficult to identify errors in the logic of a network diagram or WBS You might identify missing activities or incomplete activities You might not have all the information you need to create an accurate schedule or budget It is often difficult to see your plan objectively when you do it yourself.  When other people review it, they should be able to understand what you are doing, when you are doing it and what it will cost People might feel left out and you’ve missed a great opportunity to build support for the project with others Project Management 3 Future Managers
Practical 6 This sixth practical of our project will focus on the project plan.  We will do the project plan in table form (page 120) – the elements of the plan will be typed in, and your task is to give a description next to the plan-element explaining what is to happen there. Project Management 3 Future Managers
Project plan: building of house Project Management 3 Future Managers Project plan element Description of what will happen 1. Summary of the project 2. Project objectives 3. Project charter 4. Project assumptions and risks 5. Project milestones 6. Work Breakdown Structure 7. Network diagram 8. Resource details 9. Budget details 10. Project organisation 11. Operating procedures 12. Assessment and review 13. Contact points and information  sources 14. Project approval
Project plan: building of house Project Management 3 Future Managers Project plan element Description of what will happen 1. Summary of the project What the project is about and what it is what we want to achieve 2. Project objectives What is the goal/objective of the project 3. Project charter Authorize a project, formally recognize a project is in progress 4. Project assumptions and risks Assumptions is conditions that must fall in place as planned; it can influence cost, time – a degree of risk involved 5. Project milestones An achievement during the project, e.g. complete stage 1 on time and within the budget – serve as a motivator
Project plan: building of house Project Management 3 Future Managers 6. Work Breakdown Structure Break the project into pieces (deliverables); activities and sub-activities – cover every little part of the project 7. Network diagram Illustrate activity relationship; sequence of activities; interrelationship of activities and activities taken place simultaneously 8. Resource details Resources required to make a success of the project:  labour; material; equipment 9. Budget details Budget available to project – had to complete project within the budget 10. Project organisation A purely project organization structure shows who report to whom and levels of authority
Project plan: building of house Project Management 3 Future Managers 11. Operating procedures Process to be followed; work according to network diagram and Gantt chart  12. Assessment and review Measure project progress and conduct regular assessments – after completion of a project stage 13. Contact points and information  sources If information required – sources available, normally responsibility of project office – support role 14. Project approval Project complete; quality audit been done and project ready to hand-over to client or customer
2.  Demonstrate an understanding of the use of project management tools and techniques After completing this outcome, you will be able to: Apply a range of tools and techniques of project management to support documentation of the project plan Identify corrective steps where tools and techniques usage may occur in the project Apply corrective measures to tools and techniques used for the project Project Management 3 Future Managers
2.1  Apply a range of tools and techniques of project management to support documentation of the project plan Project planning methodology S takeholder skills and knowledge On a construction project On a project where staffing   is defined in advance Project management information systems (PM IS )  Earned value management (EVM) Project Management 3 Future Managers
2.2  Tools and techniques as the foundation of project planning A written scope statement A work breakdown structure Clearly defined activities Activity duration estimates A developed schedule Activity assignments Determined resource needs An estimated project cost A developed budget Project Management 3 Future Managers
3. The costing and budgeting of a small project After completing this outcome, you will be able to: Prepare a work element and cost budget for the project Balance budget figures in accordance with standard accounting practices Project Management 3 Future Managers
Activity 1 – Project plan tools Now that you have completed a project plan, make a list of project tools (Module 2 may help you) which you can use successfully when you start implementing the plan. Project Management 3 Future Managers
3.1 Prepare work element and  cost budget for the project Project Management 3 Future Managers Project: Electrical Re-wiring and Renovation of house Project Manager: Simon Shaw Items Quantity Price per unit Cost 1. Electrical wire 25m 5.00 p/m R125 00 2. Plugs 10 R120.00 1200 00 3. Symphony bath 1 R1 500.00 1500 00 4. Toilet set 1 R850.00 850 00 5. Shower mixer tab 1 R265.00 265 00 6. Bath and basin taps 3 R135.00 405 00 Total 17 4345 00
Project Management 3 Future Managers Project: Electrical re-wiring and renovation of house Project manager: Simon Shaw Items Costs Direct costs: Salaries for project manager; project planner; project engineers Expenses – Sub contractors fee 2. Indirect costs – marketing, training, insurance, depreciation 3. Time related costs Rent per day Running costs Overtime work Contract labour 4. Labour costs 5. Material & Equipment costs 6. Transport costs 7. Project team costs Total budget
Practical 7 The seventh practical on our project is to do:   A budget for the entire project – it will be a combination of the information of practical 5 and activity 4.5 of module 4 In this practical, you and your facilitator can work as a team to do the budget  Project Management 3 Future Managers
Project Management 3 Future Managers
4. Provide project templates to team members After completing this outcome, you will be able to:  Contribute to the monitoring and controlling of cost budget performance of the project by maintaining records and communication Identify deviations from budget, record and communicate Identify and communicate corrective actions for deviations to budget Prepare templates to be used for administration work Project Management 3 Future Managers
4.1 Template for administration work Project Management 3 Future Managers Project:  Electrical re-wiring and renovation of house Project manager:  Simon Shaw Attention:  All the relevant stakeholders Report on budget changes The cost of labour (at a rate of R60.00 per day) has increased by 10%, because of a change in labour legislation made by Government. According to our original budget, we budgeted for labour costs to the amount of R5 000.00 and the change means that labour costs will escalate by R 500.00. The labour costs will now total the amount of R 5 500.00 and we request the parent organisation to add an additional R 500.00 to the budget to assure that the project team can complete the project. Signed:  Project Manager Date:
5. Use a paper and / or electronic filing system for a project After completing this outcome, you will be able to: Use a paper based and / or electronic filing system for a project Project Management 3 Future Managers
5.  Use a paper and/or electronic filing system for a project The filing of the project forms part of the close out phase of the project Close out occurs when we hand over the completed project and the customer accepts it After all payments are made, the project manager can write the final report and send it to all stakeholders Once the close-out report has been completed, the project can be filed Project Management 3 Future Managers

More Related Content

PPT
NCV 3 Project Management Hands-On Support Slide Show - Module 3
PPT
NCV 3 Project Management Hands-On Support Slide Show - Module 1
PPT
NCV 3 Project Management Hands-On Support Slide Show - Module 2
PPT
NCV 3 Project Management Hands-On Support Slide Show - Module 4
PPT
5 project management project planning
PDF
Sample On Project Management By Instant Essay Writing
PPT
Project management planning
PPSX
Planning and Resourcing a Project
NCV 3 Project Management Hands-On Support Slide Show - Module 3
NCV 3 Project Management Hands-On Support Slide Show - Module 1
NCV 3 Project Management Hands-On Support Slide Show - Module 2
NCV 3 Project Management Hands-On Support Slide Show - Module 4
5 project management project planning
Sample On Project Management By Instant Essay Writing
Project management planning
Planning and Resourcing a Project

What's hot (20)

DOCX
Assignment 2 : People in Projects
PPT
Project Planning Scheduling
PPT
Project time management
PDF
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
PDF
Project Management Notes 3
PPTX
Building a-project-schedule
PPTX
project management
PDF
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
PDF
Construction Planing & Schedule
PPT
06 project time management
PPT
Project planning and Scheduling
PDF
Basics of Project Planning
PDF
06 project time management m
PPT
Project management
PPT
Microsoft_Project_101_How_to_Build_a_Project_Plan.
PPTX
project time management
PPT
Project Time Management
PPT
4 steps to perfect project planning
PDF
Construction Project management
PPTX
Ch23-Software Engineering 9
Assignment 2 : People in Projects
Project Planning Scheduling
Project time management
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Management Notes 3
Building a-project-schedule
project management
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
Construction Planing & Schedule
06 project time management
Project planning and Scheduling
Basics of Project Planning
06 project time management m
Project management
Microsoft_Project_101_How_to_Build_a_Project_Plan.
project time management
Project Time Management
4 steps to perfect project planning
Construction Project management
Ch23-Software Engineering 9
Ad

Viewers also liked (8)

PPTX
PPTX
Filipino^module 5 seal the deal
PDF
Drools5 Community Training Module 5 Drools BLIP Architectural Overview + Demos
DOCX
Arrow Consulting PMP
PPTX
PRICING in Service Marketing Module 5
PPTX
Module 5: PROTECTION - Arabic
PPTX
Module 5
DOC
project on construction of house report.
Filipino^module 5 seal the deal
Drools5 Community Training Module 5 Drools BLIP Architectural Overview + Demos
Arrow Consulting PMP
PRICING in Service Marketing Module 5
Module 5: PROTECTION - Arabic
Module 5
project on construction of house report.
Ad

Similar to NCV 3 Project Management Hands-On Support Slide Show - Module 5 (20)

PPT
NCV 4 Project Management Hands-On Support Slide Show - Module 2
PPTX
Welcome to My Presentation Project Planning Phase.pptx
PPTX
system analysis and design Class 3
PPTX
2. PAE AcFn621 Ch-2 Principle ppt.pptx
PDF
Definition of requirements for each project phases.pdf
PDF
Advanced project management mod 3
PDF
Learning unit 1 lectures
PPTX
4 how to plan project for health universities
PPTX
Project management professional
PPSX
Projectmanagement 130721095616-phpapp01
PPSX
Projectmanagement 130721095616-phpapp01
PPTX
Chapter 1 Overview project mângement.ppt
PDF
Project Management Topic.pdf
PPSX
Project management
PPTX
Project Mangement
PPTX
Project Management
PPT
Project management
PDF
Project management
PPTX
Role of project management in construction industry by Engineer Muhammad Kama...
PPTX
ChapterPM_1.pptx for the course project management
NCV 4 Project Management Hands-On Support Slide Show - Module 2
Welcome to My Presentation Project Planning Phase.pptx
system analysis and design Class 3
2. PAE AcFn621 Ch-2 Principle ppt.pptx
Definition of requirements for each project phases.pdf
Advanced project management mod 3
Learning unit 1 lectures
4 how to plan project for health universities
Project management professional
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
Chapter 1 Overview project mângement.ppt
Project Management Topic.pdf
Project management
Project Mangement
Project Management
Project management
Project management
Role of project management in construction industry by Engineer Muhammad Kama...
ChapterPM_1.pptx for the course project management

More from Future Managers (20)

PPTX
N4 tourism communication answer to module 5 activity 5.9
PPTX
Hospitality- desserts - gelatine
PPS
How numerals 0 - 9 got their shape
PPTX
N4 Communication & Management Communication - Module 7 precis
PPTX
N4 Communication & Management Communication - Module 7 passive & active
PPTX
N4 Communication & Management Communication - Modules 3 and 5 true false ques...
PPTX
N4 Communication & Management Communication - Module 6 Explain the difference
PPTX
CModule 6 explain the difference
PPTX
N4 Communication & Management Communication - Module 1 case study
PPT
NCV 4 Personal Assistance Hands-On Support - Module 4
PPTX
NCV 4 Personal Assistance Hands-On Support - Module 3
PPTX
NCV 4 Personal Assistance Hands-On Support - Module 7
PPT
NCV 4 Personal Assistance Hands-On Support - Module 1
PPT
NCV 4 Personal Assistance Hands-On Support - Module 2
PPT
NCV 4 Personal Assistance Hands-On Support - Module 6
PPT
Mechanical Technology Grade 10 Chapter 10 Systems And Control
PPT
Mechanical Technology Grade 10 Chapter 9 Maintenance
PPT
Mechanical Technology Grade 10 Chapter 8 forces
PPT
Mechanical Technology Grade 12 Chapter 6 Terminology Of Machines
PPT
Mechanical Technology Grade 12 Chapter 5 Materials
N4 tourism communication answer to module 5 activity 5.9
Hospitality- desserts - gelatine
How numerals 0 - 9 got their shape
N4 Communication & Management Communication - Module 7 precis
N4 Communication & Management Communication - Module 7 passive & active
N4 Communication & Management Communication - Modules 3 and 5 true false ques...
N4 Communication & Management Communication - Module 6 Explain the difference
CModule 6 explain the difference
N4 Communication & Management Communication - Module 1 case study
NCV 4 Personal Assistance Hands-On Support - Module 4
NCV 4 Personal Assistance Hands-On Support - Module 3
NCV 4 Personal Assistance Hands-On Support - Module 7
NCV 4 Personal Assistance Hands-On Support - Module 1
NCV 4 Personal Assistance Hands-On Support - Module 2
NCV 4 Personal Assistance Hands-On Support - Module 6
Mechanical Technology Grade 10 Chapter 10 Systems And Control
Mechanical Technology Grade 10 Chapter 9 Maintenance
Mechanical Technology Grade 10 Chapter 8 forces
Mechanical Technology Grade 12 Chapter 6 Terminology Of Machines
Mechanical Technology Grade 12 Chapter 5 Materials

Recently uploaded (20)

PPTX
master seminar digital applications in india
PDF
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PPTX
Pharma ospi slides which help in ospi learning
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
Insiders guide to clinical Medicine.pdf
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PDF
Basic Mud Logging Guide for educational purpose
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PDF
Pre independence Education in Inndia.pdf
PPTX
Lesson notes of climatology university.
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PPTX
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PPTX
Institutional Correction lecture only . . .
master seminar digital applications in india
FourierSeries-QuestionsWithAnswers(Part-A).pdf
Microbial diseases, their pathogenesis and prophylaxis
Pharma ospi slides which help in ospi learning
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Insiders guide to clinical Medicine.pdf
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Basic Mud Logging Guide for educational purpose
Final Presentation General Medicine 03-08-2024.pptx
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
Pre independence Education in Inndia.pdf
Lesson notes of climatology university.
Module 4: Burden of Disease Tutorial Slides S2 2025
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
STATICS OF THE RIGID BODIES Hibbelers.pdf
Institutional Correction lecture only . . .

NCV 3 Project Management Hands-On Support Slide Show - Module 5

  • 1. Project Management 3 Project Management 3 Future Managers
  • 2. Module 5: Develop a project plan for a simple project Project Management 3 Future Managers
  • 3. Module 5: Develop a project plan for a simple project After completing this module, you will be able to: Develop a project plan for a simple project Demonstrate an understanding of the use of project management and tools Participate in the costing & budgeting of a small project Provide project templates to team members Use a paper based and/or electronic filing system for a project. Project Management 3 Future Managers
  • 4. 1. Develop a project plan for a simple project After completing this outcome, you will be able to: Assess components of a given project plan Collect and organise information relating to the individual project/sub-project Develop a project plan for a simple project Project Management 3 Future Managers
  • 5. 1. Develop a project plan for a simple project Why do we plan? A project plan is a roadmap for the project, it help to guide the work from start to finish It serves as a tool for communication with both stakeholders and the project team We need to plan in terms of resources required Planning, not only establishes what is to be done but also “smoothes the way to make it happen” Planning encourages participation, from all the role players involved in the project Planning leads to prompt action Planning solves problems before they can influence the project and its outcome Planning formulates decisions based on consensus Planning avoids costly changes Project Management 3 Future Managers
  • 6. 1.1 Assessment of the components of a project plan Developing a solid project plan Record assumptions made during project planning Direct project execution and control Provide instructions for documenting what decisions were made and why they were made Specify dates for management reviews Define standards against which project and team members’ performance are measured Project Management 3 Future Managers
  • 7. 1.2 Information on the planning of a project Network planning Time analysis Resource analysis Cost analysis Multiple schedules Progress reports Key events Deadlines and activity logic Project Management 3 Future Managers
  • 8. 1.3 Development of a project plan What should be included in a project plan? Documents used during project planning, such as the scope statement, work breakdown structure, and cost estimates The project charter Scope, risk, communication, procurement, and schedule management plan Responsibility assignments Schedule dates and milestones Major risks, constraints, and assumptions and how each will be handled Pending issues and decisions Design and other specifications. Project Management 3 Future Managers
  • 9. 1.3 Development of a project plan A good project plan: Directs how, when, and by whom all project activities should be completed Instructs ways to document what decisions are made and why they are made Specifies dates for management reviews Defines standards against which the project and team members’ performance is measured Project Management 3 Future Managers
  • 10. 1.3 Development of a project plan Additional actions that must be performed Define the project’s quality standards and develop a quality management plan Assign roles and responsibilities, which include developing a staff management plan and acquiring staff for the project team Develop a communication system, which includes creating a communications management plan that will make sure information is distributed to the right people at the right times in an appropriate format Project Management 3 Future Managers
  • 11. 1.3 Development of a project plan Additional actions that must be performed Identify and evaluate the seriousness of potential project risks Develop responses to the potential risks, which include compiling a risk management plan Decide which resources must be produced from outside the project’s parent organisation and which includes developing a procurement management plan Determine and define resource requirements, such as what level of quality is expected from contracted work Project Management 3 Future Managers
  • 12. Project Management 3 Future Managers
  • 13. The project plan Project Management 3 Future Managers Skills by task Resources by task Time per task Task relationships costs & constraints statement of work (SOW) WBS network diagram schedule & timeline budget budget
  • 14. The project plan (large project) Summary of the project (or project overview) Project objectives Project charter Project assumptions and risks Project milestones Work breakdown structure (WBS) Network diagram Resource details Human resources Equipment Materials and supplies Budget details Project organisation Operating procedures Assessment and review standards Contact points and information sources Project approval Project Management 3 Future Managers
  • 15. The project plan (large project) Summary of the project (or project overview) Project objectives Project charter Project assumptions and risks Project milestones Work breakdown structure (WBS) Network diagram Project Management 3 Future Managers
  • 16. The project plan (large project) Resource details Human resources Equipment Materials and supplies Budget details Project organisation Operating procedures Assessment and review standards Contact points and information sources Project approval Project Management 3 Future Managers
  • 17. Project plan What is the right level of planning? What are the consequences of not having your project reviewed by qualified individuals? It is more difficult to identify errors in the logic of a network diagram or WBS You might identify missing activities or incomplete activities You might not have all the information you need to create an accurate schedule or budget It is often difficult to see your plan objectively when you do it yourself. When other people review it, they should be able to understand what you are doing, when you are doing it and what it will cost People might feel left out and you’ve missed a great opportunity to build support for the project with others Project Management 3 Future Managers
  • 18. Practical 6 This sixth practical of our project will focus on the project plan.  We will do the project plan in table form (page 120) – the elements of the plan will be typed in, and your task is to give a description next to the plan-element explaining what is to happen there. Project Management 3 Future Managers
  • 19. Project plan: building of house Project Management 3 Future Managers Project plan element Description of what will happen 1. Summary of the project 2. Project objectives 3. Project charter 4. Project assumptions and risks 5. Project milestones 6. Work Breakdown Structure 7. Network diagram 8. Resource details 9. Budget details 10. Project organisation 11. Operating procedures 12. Assessment and review 13. Contact points and information sources 14. Project approval
  • 20. Project plan: building of house Project Management 3 Future Managers Project plan element Description of what will happen 1. Summary of the project What the project is about and what it is what we want to achieve 2. Project objectives What is the goal/objective of the project 3. Project charter Authorize a project, formally recognize a project is in progress 4. Project assumptions and risks Assumptions is conditions that must fall in place as planned; it can influence cost, time – a degree of risk involved 5. Project milestones An achievement during the project, e.g. complete stage 1 on time and within the budget – serve as a motivator
  • 21. Project plan: building of house Project Management 3 Future Managers 6. Work Breakdown Structure Break the project into pieces (deliverables); activities and sub-activities – cover every little part of the project 7. Network diagram Illustrate activity relationship; sequence of activities; interrelationship of activities and activities taken place simultaneously 8. Resource details Resources required to make a success of the project: labour; material; equipment 9. Budget details Budget available to project – had to complete project within the budget 10. Project organisation A purely project organization structure shows who report to whom and levels of authority
  • 22. Project plan: building of house Project Management 3 Future Managers 11. Operating procedures Process to be followed; work according to network diagram and Gantt chart 12. Assessment and review Measure project progress and conduct regular assessments – after completion of a project stage 13. Contact points and information sources If information required – sources available, normally responsibility of project office – support role 14. Project approval Project complete; quality audit been done and project ready to hand-over to client or customer
  • 23. 2. Demonstrate an understanding of the use of project management tools and techniques After completing this outcome, you will be able to: Apply a range of tools and techniques of project management to support documentation of the project plan Identify corrective steps where tools and techniques usage may occur in the project Apply corrective measures to tools and techniques used for the project Project Management 3 Future Managers
  • 24. 2.1 Apply a range of tools and techniques of project management to support documentation of the project plan Project planning methodology S takeholder skills and knowledge On a construction project On a project where staffing is defined in advance Project management information systems (PM IS ) Earned value management (EVM) Project Management 3 Future Managers
  • 25. 2.2 Tools and techniques as the foundation of project planning A written scope statement A work breakdown structure Clearly defined activities Activity duration estimates A developed schedule Activity assignments Determined resource needs An estimated project cost A developed budget Project Management 3 Future Managers
  • 26. 3. The costing and budgeting of a small project After completing this outcome, you will be able to: Prepare a work element and cost budget for the project Balance budget figures in accordance with standard accounting practices Project Management 3 Future Managers
  • 27. Activity 1 – Project plan tools Now that you have completed a project plan, make a list of project tools (Module 2 may help you) which you can use successfully when you start implementing the plan. Project Management 3 Future Managers
  • 28. 3.1 Prepare work element and cost budget for the project Project Management 3 Future Managers Project: Electrical Re-wiring and Renovation of house Project Manager: Simon Shaw Items Quantity Price per unit Cost 1. Electrical wire 25m 5.00 p/m R125 00 2. Plugs 10 R120.00 1200 00 3. Symphony bath 1 R1 500.00 1500 00 4. Toilet set 1 R850.00 850 00 5. Shower mixer tab 1 R265.00 265 00 6. Bath and basin taps 3 R135.00 405 00 Total 17 4345 00
  • 29. Project Management 3 Future Managers Project: Electrical re-wiring and renovation of house Project manager: Simon Shaw Items Costs Direct costs: Salaries for project manager; project planner; project engineers Expenses – Sub contractors fee 2. Indirect costs – marketing, training, insurance, depreciation 3. Time related costs Rent per day Running costs Overtime work Contract labour 4. Labour costs 5. Material & Equipment costs 6. Transport costs 7. Project team costs Total budget
  • 30. Practical 7 The seventh practical on our project is to do:   A budget for the entire project – it will be a combination of the information of practical 5 and activity 4.5 of module 4 In this practical, you and your facilitator can work as a team to do the budget  Project Management 3 Future Managers
  • 31. Project Management 3 Future Managers
  • 32. 4. Provide project templates to team members After completing this outcome, you will be able to: Contribute to the monitoring and controlling of cost budget performance of the project by maintaining records and communication Identify deviations from budget, record and communicate Identify and communicate corrective actions for deviations to budget Prepare templates to be used for administration work Project Management 3 Future Managers
  • 33. 4.1 Template for administration work Project Management 3 Future Managers Project: Electrical re-wiring and renovation of house Project manager: Simon Shaw Attention: All the relevant stakeholders Report on budget changes The cost of labour (at a rate of R60.00 per day) has increased by 10%, because of a change in labour legislation made by Government. According to our original budget, we budgeted for labour costs to the amount of R5 000.00 and the change means that labour costs will escalate by R 500.00. The labour costs will now total the amount of R 5 500.00 and we request the parent organisation to add an additional R 500.00 to the budget to assure that the project team can complete the project. Signed: Project Manager Date:
  • 34. 5. Use a paper and / or electronic filing system for a project After completing this outcome, you will be able to: Use a paper based and / or electronic filing system for a project Project Management 3 Future Managers
  • 35. 5. Use a paper and/or electronic filing system for a project The filing of the project forms part of the close out phase of the project Close out occurs when we hand over the completed project and the customer accepts it After all payments are made, the project manager can write the final report and send it to all stakeholders Once the close-out report has been completed, the project can be filed Project Management 3 Future Managers