Operation Engine II
Session IV
Operations Scheduling
Fatima Aliza
Assistant Professor
IILMAHL
Process Focused Manufacturing
 These types of factories are called Job-
Shops.
 A job shop in an organization in which the
work centers or departments are organized
around similar types of functions or
departmental specialties , such as forging,
milling, turning, heat treating, drilling and
assembly.
 Jobs are usually processed in batches, with
the batch size based either on the customer
order size or some economical quantity.
Master production
schedule(MPS)
Material
requirements
plan(MRP)
Capacity
requirements
plan(CRP)
Planned order
releases report
Work center
loading and
overtime plan
Engineering the
product designs &
processing plans
Order
processing or
routing plans
Assignment of
orders to work
centers
Shop Floor Planning and Control
 Assigning a priority to each order.
 Issuing dispatching lists to each work centers.
 Keeping the WIP inventory updated.
 Providing input- output control on all work
centers.
 Measuring the efficiency , utilization and
productivity of workers and machines at each
work center.
Input- Output Control
 This is a key activity that allows operations managers
to identify such problems as insufficient capacity,
excessive capacity and production difficulties among
a group of connected workstations.
 From such reports operations managers can
determine if the amount of work flowing to a work
center is the planned amount and if the capacity of
the work center is according to plan.
Gantt Charts
 Gantt Charts can be used to visually display the workloads in each
work center in a department.
 It is used to compare the weekly schedule for five work centers in a
model shop.
 The jobs scheduled to be worked on during the week are displayed
with their code names or numbers ( A,B,C, etc.) , beginning times ,
and ending times, which are represented by an open bar. As work
progresses on a job, a solid bar shows how the work center is
performing to the schedule.
 Machine changeovers , maintenance and other planned
nonproduction work are indicated by an X. Blank spaces indicate
planned idle time at the work center.
 Gantt charts are very useful for coordinating a diversity of
schedules of work teams, work centers and activities of projects.
Finite & Infinite Loading
 Infinite approach is used when jobs are assigned to work centers
without considering the capacities of the work centers. This
approach abandons CRP & its loading schedules. Unless a company
has excessive production capacity, unacceptable queues of waiting
jobs occur at work centers.
 Finite approach is used when the capacities of work centers are
allocated among a list of jobs. By using a computer simulation
model or other means each work center’s capacity is allocated to
jobs hour by hour by varying the start and completion times of the
jobs. The end result of this approach is scheduled to a work center
during any hour than the capacity of the work center. This approach
is integral to CRP and is used by many companies today.
Forward & Backward Scheduling
 There are two ways to determine to which time slots jobs are
assigned within work centers.
 In forward scheduling , jobs are assigned to the earliest
unassigned time slots in work centers. This approach assumes
that customers want their jobs delivered as soon as possible.
Although simple to use , excessive in process inventories
usually result because jobs tend to sit and wait for their next
work center assignments.
Order Sequencing Problems
 In order sequencing problems we want to
determine the sequence in which we will
produce a group of waiting orders at a
work center. We analyze these problems
by discussing the various sequencing
rules , the criteria for evaluating the
sequencing rules, a comparison of
sequencing rules , the control of
changeover costs , and the minimization
of production costs.
Sequencing rules
 First come first serve (FCFS): The next job to be produced is
the one that arrived first among the waiting jobs.
 Shortest Processing time(SPT): The next job to be produced
is the one with the shortest processing time among the waiting
jobs.
 Earliest Due Date(EDD): the next job to be produced is the one
with the earliest due date among the waiting jobs.
 Least slack(LS): The next job to be produced is the one with
the least slack ( time to due date minus total remaining
production time) among the waiting jobs.
 Critical Ratio(CR): The next job to be produced is the one with
the least critical ratio ( time to due date divided by total
remaining production time) among the waiting jobs.
 Least changeover cost(LCC): Since some jobs logically follow
each other because of ease of changeovers, the sequence of
waiting jobs is determined by analyzing the total cost of making
all of the machine changeovers between jobs.
Criteria for evaluating sequencing
rules
 Average flow time: the average amount of
time jobs spend in the shop.
 Average number of jobs in the system:
The average number of jobs in the shop.
 Average job lateness: The average amount
of time that a job’s completion date exceeds
its promised delivery date.
 Changeover cost: The total cost of making
all the machine changeovers in a group of
jobs.
Controlling changeover costs
 Changeover costs are the costs of
changing a processing step in a
production system over from one job to
another. They include costs for such
things as changing machine settings,
getting job instructions, and changing
materials and tools. Usually , jobs should
be produced in the sequence that
minimizes the cost of these changeovers.
Scheduling product – focused
manufacturing
 There are two general types of product focused production
: Batch & Continuous
 Batch production is often called a Flow shop because
products follow along direct linear routes. Large batches of
several standardized products are produced in the same
production products are produced in batches , the
production system must be changed over when a different
product is to be produced.
 In Continuous production, a few highly standardized
products are produced continuously in very large volumes
and changeovers are rare. The products may be discrete
such as plastic molded products , or they may be
continuous , such as gasoline.
Batch Scheduling
 In product focused systems that produce
products in batches, a key issue is the
size of batches. Two approaches to this
issue will be discussed here:
 EOQ for production lots
 Run out method
EOQ for production lots
 The production lot size problem is solved
using the following formula:
 EOQ=√ (2DS/C) (p/(p-d)
Run – Out method
 Various deficiencies of the EOQ in
planning production lot sizes have led to
the development of the run–out method.
 This method attempts to use the total
production capacity available in each time
period to produce just enough of each
product so that if all production stops, the
finished goods inventory for each product
runs out at the same time.
Delivery schedules : Line of
Balance method
 Some production systems often commit to
delivery schedules for their products that
stipulate how many products must be
delivered to customers in each future week.
If it is important that actual product
deliveries match with the planned delivery
schedule, a system must be devised to
schedule and control all the production steps.
To avoid any delays and corrective actions
line of balance (LOB) has been used to
schedule and control upstream production
steps.
Operation engine  ii session iv  operations scheduling

More Related Content

PDF
Presentation on operation scheduling
PPT
Operations Scheduling
PPT
Operations Scheduling
DOCX
What is forward and backward scheduling
PPT
PPT
Ch17 scheduling
PPT
Operation scheduling
PPTX
Scheduling
Presentation on operation scheduling
Operations Scheduling
Operations Scheduling
What is forward and backward scheduling
Ch17 scheduling
Operation scheduling
Scheduling

What's hot (19)

PPT
Scheduling
PPTX
Work Center Scheduling
PPTX
Scheduling production
PPTX
Types of loading, production & operations management
PPTX
Production scheduling(draft agenda)
PPT
C8 scheduling
PPTX
Loading jobs and methods definitivo
PPT
Scheduling and sequencing
PPT
Ppc unit-4-production scheduling
PPTX
Operations scheduling
PPT
PDF
Forward scheduling vs. backward scheduling in production planning
PPT
Ppc unit-2-work study
PPT
Master production schedule
PDF
PPT
Chap017 Scheduling Edit
PPTX
Mpc sequencing
PPT
Capacity Requirement Planning
PPT
Production Management and Scheduling
Scheduling
Work Center Scheduling
Scheduling production
Types of loading, production & operations management
Production scheduling(draft agenda)
C8 scheduling
Loading jobs and methods definitivo
Scheduling and sequencing
Ppc unit-4-production scheduling
Operations scheduling
Forward scheduling vs. backward scheduling in production planning
Ppc unit-2-work study
Master production schedule
Chap017 Scheduling Edit
Mpc sequencing
Capacity Requirement Planning
Production Management and Scheduling
Ad

Viewers also liked (16)

PPTX
1. c or c++ programming course out line
PPT
Chapter 1 - An Introduction to Programming
PPT
2 the visible pc
PPT
Data com chapter 1 introduction
PPT
ICTCoreCh11
PPTX
Learning C++ - Introduction to c++ programming 1
PPT
11. Computer Systems Hardware 1
PPS
a+ ptc
PPT
data communication
PPSX
C++ Programming Language
DOCX
Data communications Class notes
PPTX
Powerpoint for data communication
PPTX
Presentation on data communication
PPT
Lect 1. introduction to programming languages
PPTX
Data communication and network Chapter -1
PPT
Chapter 1: Introduction to Data Communication and Networks
1. c or c++ programming course out line
Chapter 1 - An Introduction to Programming
2 the visible pc
Data com chapter 1 introduction
ICTCoreCh11
Learning C++ - Introduction to c++ programming 1
11. Computer Systems Hardware 1
a+ ptc
data communication
C++ Programming Language
Data communications Class notes
Powerpoint for data communication
Presentation on data communication
Lect 1. introduction to programming languages
Data communication and network Chapter -1
Chapter 1: Introduction to Data Communication and Networks
Ad

Similar to Operation engine ii session iv operations scheduling (20)

PPTX
SCHEDULING RULES DONE.pptx
DOCX
Scheduling
PDF
Programación de operaciones (GTO) Ingeniería civil industrial
PPT
PPTX
OPERATIONS-SCHEDULING-AND-SEQUENCING.pptx
PPT
Scheduling
PPT
Scheduling
PPT
Scheduling
PPTX
Unit 7 production scheduling
PPT
schedulingandsequencing-140424065526-phpapp02__1_.ppt
DOCX
PPT
Mba ii pmom_unit-1.4 process design, analysis & selection a
PPT
production scheduling
PPT
Topic 5 Production Sequencing and Scheduling.ppt
PPT
Scheduling(production and operations management systems).ppt
PPT
Ch 6 Scheduling.ppt
PPT
Ch 6 Scheduling.ppt
PPT
scheduling_1.ppt
PPT
scheduling.ppt course not for industrial engineering students
PPTX
Ch 6 Schedhhhhhhhhgjbfhgffihgguiihhhuling.pptx
SCHEDULING RULES DONE.pptx
Scheduling
Programación de operaciones (GTO) Ingeniería civil industrial
OPERATIONS-SCHEDULING-AND-SEQUENCING.pptx
Scheduling
Scheduling
Scheduling
Unit 7 production scheduling
schedulingandsequencing-140424065526-phpapp02__1_.ppt
Mba ii pmom_unit-1.4 process design, analysis & selection a
production scheduling
Topic 5 Production Sequencing and Scheduling.ppt
Scheduling(production and operations management systems).ppt
Ch 6 Scheduling.ppt
Ch 6 Scheduling.ppt
scheduling_1.ppt
scheduling.ppt course not for industrial engineering students
Ch 6 Schedhhhhhhhhgjbfhgffihgguiihhhuling.pptx

Recently uploaded (20)

PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
RMMM.pdf make it easy to upload and study
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
O7-L3 Supply Chain Operations - ICLT Program
PDF
102 student loan defaulters named and shamed – Is someone you know on the list?
PDF
TR - Agricultural Crops Production NC III.pdf
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PPTX
PPH.pptx obstetrics and gynecology in nursing
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PDF
01-Introduction-to-Information-Management.pdf
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
Pharma ospi slides which help in ospi learning
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
RMMM.pdf make it easy to upload and study
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
Anesthesia in Laparoscopic Surgery in India
O7-L3 Supply Chain Operations - ICLT Program
102 student loan defaulters named and shamed – Is someone you know on the list?
TR - Agricultural Crops Production NC III.pdf
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PPH.pptx obstetrics and gynecology in nursing
Microbial diseases, their pathogenesis and prophylaxis
01-Introduction-to-Information-Management.pdf
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Pharma ospi slides which help in ospi learning
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
Final Presentation General Medicine 03-08-2024.pptx
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
O5-L3 Freight Transport Ops (International) V1.pdf
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
Abdominal Access Techniques with Prof. Dr. R K Mishra

Operation engine ii session iv operations scheduling

  • 1. Operation Engine II Session IV Operations Scheduling Fatima Aliza Assistant Professor IILMAHL
  • 2. Process Focused Manufacturing  These types of factories are called Job- Shops.  A job shop in an organization in which the work centers or departments are organized around similar types of functions or departmental specialties , such as forging, milling, turning, heat treating, drilling and assembly.  Jobs are usually processed in batches, with the batch size based either on the customer order size or some economical quantity.
  • 3. Master production schedule(MPS) Material requirements plan(MRP) Capacity requirements plan(CRP) Planned order releases report Work center loading and overtime plan Engineering the product designs & processing plans Order processing or routing plans Assignment of orders to work centers
  • 4. Shop Floor Planning and Control  Assigning a priority to each order.  Issuing dispatching lists to each work centers.  Keeping the WIP inventory updated.  Providing input- output control on all work centers.  Measuring the efficiency , utilization and productivity of workers and machines at each work center.
  • 5. Input- Output Control  This is a key activity that allows operations managers to identify such problems as insufficient capacity, excessive capacity and production difficulties among a group of connected workstations.  From such reports operations managers can determine if the amount of work flowing to a work center is the planned amount and if the capacity of the work center is according to plan.
  • 6. Gantt Charts  Gantt Charts can be used to visually display the workloads in each work center in a department.  It is used to compare the weekly schedule for five work centers in a model shop.  The jobs scheduled to be worked on during the week are displayed with their code names or numbers ( A,B,C, etc.) , beginning times , and ending times, which are represented by an open bar. As work progresses on a job, a solid bar shows how the work center is performing to the schedule.  Machine changeovers , maintenance and other planned nonproduction work are indicated by an X. Blank spaces indicate planned idle time at the work center.  Gantt charts are very useful for coordinating a diversity of schedules of work teams, work centers and activities of projects.
  • 7. Finite & Infinite Loading  Infinite approach is used when jobs are assigned to work centers without considering the capacities of the work centers. This approach abandons CRP & its loading schedules. Unless a company has excessive production capacity, unacceptable queues of waiting jobs occur at work centers.  Finite approach is used when the capacities of work centers are allocated among a list of jobs. By using a computer simulation model or other means each work center’s capacity is allocated to jobs hour by hour by varying the start and completion times of the jobs. The end result of this approach is scheduled to a work center during any hour than the capacity of the work center. This approach is integral to CRP and is used by many companies today.
  • 8. Forward & Backward Scheduling  There are two ways to determine to which time slots jobs are assigned within work centers.  In forward scheduling , jobs are assigned to the earliest unassigned time slots in work centers. This approach assumes that customers want their jobs delivered as soon as possible. Although simple to use , excessive in process inventories usually result because jobs tend to sit and wait for their next work center assignments.
  • 9. Order Sequencing Problems  In order sequencing problems we want to determine the sequence in which we will produce a group of waiting orders at a work center. We analyze these problems by discussing the various sequencing rules , the criteria for evaluating the sequencing rules, a comparison of sequencing rules , the control of changeover costs , and the minimization of production costs.
  • 10. Sequencing rules  First come first serve (FCFS): The next job to be produced is the one that arrived first among the waiting jobs.  Shortest Processing time(SPT): The next job to be produced is the one with the shortest processing time among the waiting jobs.  Earliest Due Date(EDD): the next job to be produced is the one with the earliest due date among the waiting jobs.  Least slack(LS): The next job to be produced is the one with the least slack ( time to due date minus total remaining production time) among the waiting jobs.  Critical Ratio(CR): The next job to be produced is the one with the least critical ratio ( time to due date divided by total remaining production time) among the waiting jobs.  Least changeover cost(LCC): Since some jobs logically follow each other because of ease of changeovers, the sequence of waiting jobs is determined by analyzing the total cost of making all of the machine changeovers between jobs.
  • 11. Criteria for evaluating sequencing rules  Average flow time: the average amount of time jobs spend in the shop.  Average number of jobs in the system: The average number of jobs in the shop.  Average job lateness: The average amount of time that a job’s completion date exceeds its promised delivery date.  Changeover cost: The total cost of making all the machine changeovers in a group of jobs.
  • 12. Controlling changeover costs  Changeover costs are the costs of changing a processing step in a production system over from one job to another. They include costs for such things as changing machine settings, getting job instructions, and changing materials and tools. Usually , jobs should be produced in the sequence that minimizes the cost of these changeovers.
  • 13. Scheduling product – focused manufacturing  There are two general types of product focused production : Batch & Continuous  Batch production is often called a Flow shop because products follow along direct linear routes. Large batches of several standardized products are produced in the same production products are produced in batches , the production system must be changed over when a different product is to be produced.  In Continuous production, a few highly standardized products are produced continuously in very large volumes and changeovers are rare. The products may be discrete such as plastic molded products , or they may be continuous , such as gasoline.
  • 14. Batch Scheduling  In product focused systems that produce products in batches, a key issue is the size of batches. Two approaches to this issue will be discussed here:  EOQ for production lots  Run out method
  • 15. EOQ for production lots  The production lot size problem is solved using the following formula:  EOQ=√ (2DS/C) (p/(p-d)
  • 16. Run – Out method  Various deficiencies of the EOQ in planning production lot sizes have led to the development of the run–out method.  This method attempts to use the total production capacity available in each time period to produce just enough of each product so that if all production stops, the finished goods inventory for each product runs out at the same time.
  • 17. Delivery schedules : Line of Balance method  Some production systems often commit to delivery schedules for their products that stipulate how many products must be delivered to customers in each future week. If it is important that actual product deliveries match with the planned delivery schedule, a system must be devised to schedule and control all the production steps. To avoid any delays and corrective actions line of balance (LOB) has been used to schedule and control upstream production steps.