Trimble Advanced Route Optimization
Technology - QUANTM
Content
 Background
 Advanced route planning tool: Quantm
 Conventional planning vs Quantm
 Case studies
 Conclusions
Between vision and viability there are important decisions to make
 Around 80% of civil infrastructure projects are delivered over
budget, over time…
 The greatest opportunities to contain overall costs and minimise
environmental and social impact are at the planning stage
 Conventional planning methods heavily rely on professional
experience and judgment using manual methods
 An intelligent route planning tool has been specifically developed
to address the complex planning process
Background
Planning
Feasibility
Design
Engineering
Estimating
Bidding
Construction
Operation
Maintenance
Planning
Feasibility
Design
Engineering
Trimble Quantm Technology
 Quantm is a revolutionary planning tool for road/rail alignment
selection with combined international expertise
– Scoping study
– Feasibility study
– Value engineering
 It automatically generates multiple cost effective and viable
alignments that meet the defined constraints
• Consider all feasible alternatives to help make the best
decisions
• Dramatically reduce planning time and project costs
 Quantm technology has been used globally for planning over
40,000km of road and railway projects
• Australia, New Zealand, America, Europe, Russia, Middle East,
Africa, South East Asia, China
Trimble Quantm Technology
…new technologies are transforming the way the world works
Trimble Quantm Technology
 Digital Terrain Model (DTM) based optimisation engine
 Input data: End points, design parameters, cost data, constraints
 Comprehensive corridor/alignment search within the study area
 Simultaneous 3D optimization with multiple alternatives
Trimble Quantm Technology
Cross sections
Profile view
Alignment
comparison
Alignment
summary
Plan view
Conventional Planning vs Quantm
7
Items Conventional Quantm
Project data
Topographical maps, or
DTM limited in size
Digital Terrain Model
200+ millions points
Planning method
Planning time
Manual, 2D
Months, years
Intelligent, 3D interactive
Weeks, productivity up 50%
Construction cost Often over budget
Cost control
saving 5~30%
Alignment quality
Heavily rely on
experienced engineers
Better fit into terrain
Balanced earthworks
Major structures/
Control points
Potential misjudgment,
missing viable corridors
Never miss viable
corridors/alignments
3D Visualization
Limited in length or rely
on third party software
Real time rendering
Sensitivity analyses
‘What if’ scenarios
Time consuming
Slow, labor intensive
Fast
quick response
Case Studies: Beijing to Shenyang HSR
 660km, 350km/h
 3 Corridors, 10 local options
 Comprehensive analysis
 3 weeks
Example of a large mining rail project – 500km
Corridor Analysis
Comparison of 50 Alternatives – alignments blocked by cost
Increasing costs
In this example it allows
the operator to review 50
Alignments x 500km a
total of 25,000km with
earthwork volumes
calculated @ 100m
intervals
TGV High Speed Rail with RAVE:
 Lisbon – Madrid 200km, 2005-2007
 Lisbon – Porto 300km, 2010
 Aveiro – Salamanca 220km, 2009
 Porto – Braga 45km, 2008-2010
 Braga – Vigo 45km, 2008-2010
Quantm Benefits:
 Planning time reduction
 Cost reduction by 10%, or over €300millions
 Better decision-making by integrating
environmental, community, cultural and
engineering into a single analysis
Case Studies: Portugal TGV Projects
Case Studies: Kyrgyzstan 250km Rail
12
 Connect Uzbekistan - Kyrgyzstan to
Kashgar, Xinjiang, China
 1:50K ASTER GDEM
 4 corridors/alignments, 2 weeks
 Real time earthwork and cost
estimation, significant cost reduction
Traditional Method
 Topographic maps
 Manual estimates on volumes
and costs
 6 months study
 AECOM, 1748km
 Phase I: 16 corridors
 Phase II: 7 sections
 Explore ‘what if’
scenarios
 A$114B (US$91B)
 Phase II in 3 months!
 8% tunnels -- 29% cost
Case Studies: Australia HSR Project
13Source: AECOM (2013): High Speed Rail Study Phase 2: Key Findings and Executive Summary
Quantm Summary - Iterative
User
Interface
Data
Optimisation
DTM
Engine
Scoping Feasibility Design1:50000 1:10000 1:2000
DTM
Geometrics
Constraints
Cost
Fast /Efficient
Quick Response
Solve Problems
Control Risk
Environmental
Reduce Cost
3D Visualisation
Conclusions
Trimble Quantm assists planners to plan a new
road/rail project more rapidly with lower
construction costs. Quantm makes it easier to:
 Consider all feasible alternatives to
help make the best decisions
 Plan for sustainability with better
environmental and public outcomes
 Invest in a better future by reducing
capital and operating costs
Trimble Advanced Route Optimization  Technology - QUANTM
Quantm Video Summary
Trimble Alignment Planning System
Thank You for your kind attention
Bill_lazaris@trimble.com
Your Free Demo Download
http://www.trimble.com/alignment/request-free-
demo.aspx

More Related Content

PPTX
Axle load for Rail way - linkedin
PPTX
Field compaction methods
PPTX
Bridge introduction
PPTX
1.railway intro and rails
PPTX
Soil Mechanics
PPTX
Rail fastenings and joints
PDF
Canal regulation works. m4pptx
PPT
Rigid Pavements Design Part - I
Axle load for Rail way - linkedin
Field compaction methods
Bridge introduction
1.railway intro and rails
Soil Mechanics
Rail fastenings and joints
Canal regulation works. m4pptx
Rigid Pavements Design Part - I

What's hot (20)

PDF
Water cycle and water budget
PPT
Pavement design
PPT
Lecture01 140412064456-phpapp02
PPTX
Basic concepts on structural dynamics
PPTX
Earthen Dams
PDF
Permeability of Soils & Seepage Analysis
PPT
Diversionheadworks
PPT
Prestressed composite beams
PPTX
1. railway track gauge
PPTX
Canal outlets and modules
PPTX
SHEAR DESIGN OF PRESTRESSED CONCRETE
PDF
Report on Pile Foundation
PPTX
Rigid Pavement Design Part II
PPTX
earth dam.pptx
PPT
Advantages of continous members
PDF
Effect of expansive soils on buildings and its prevention
PPTX
Sub grade
PDF
Panam Project Presentation
PPTX
Design of gravity dams
PDF
Vertical Stresses Below Applied Load.pdf
Water cycle and water budget
Pavement design
Lecture01 140412064456-phpapp02
Basic concepts on structural dynamics
Earthen Dams
Permeability of Soils & Seepage Analysis
Diversionheadworks
Prestressed composite beams
1. railway track gauge
Canal outlets and modules
SHEAR DESIGN OF PRESTRESSED CONCRETE
Report on Pile Foundation
Rigid Pavement Design Part II
earth dam.pptx
Advantages of continous members
Effect of expansive soils on buildings and its prevention
Sub grade
Panam Project Presentation
Design of gravity dams
Vertical Stresses Below Applied Load.pdf
Ad

Viewers also liked (20)

PDF
Innovation Showcase – Bentley’s AssetWise Optram
PDF
Hajj Step by Step Presentation and Guide by Think Tarteeb
PDF
MENA Rail Pioneer Innovative Showcase
PDF
Light & support industries yanbu
PDF
Video analytics for public safety solutions - Hitachi
PPTX
Presentation Islam
PPSX
Hotec me 2013 seminar g wilkinson viability dist
PPT
Mosques
PDF
Metro & Light Rail Projects in Saudi Arabia
PPTX
Aged parents presentation
PDF
MedaLogistics16 | Hussein Balaghi
PDF
Pioneer Innovation Showcase - EY
PPTX
Khutbah keagungan kota makkah
PPT
Makkaj ppt final
PDF
Jeddah Master Transportation Plan
PDF
Addressing the challenges of delivering Mega Projects
PPTX
Companions of Holy Prophet (pbuh)
PDF
Jeddah metro full presentation - Briefing Day March, 30th
Innovation Showcase – Bentley’s AssetWise Optram
Hajj Step by Step Presentation and Guide by Think Tarteeb
MENA Rail Pioneer Innovative Showcase
Light & support industries yanbu
Video analytics for public safety solutions - Hitachi
Presentation Islam
Hotec me 2013 seminar g wilkinson viability dist
Mosques
Metro & Light Rail Projects in Saudi Arabia
Aged parents presentation
MedaLogistics16 | Hussein Balaghi
Pioneer Innovation Showcase - EY
Khutbah keagungan kota makkah
Makkaj ppt final
Jeddah Master Transportation Plan
Addressing the challenges of delivering Mega Projects
Companions of Holy Prophet (pbuh)
Jeddah metro full presentation - Briefing Day March, 30th
Ad

Similar to Trimble Advanced Route Optimization Technology - QUANTM (20)

PDF
Quantm Overview
PDF
Quantm enterprise english
PDF
Quantm professional english
PPTX
Dinamikler 2017 - Alan Sharp Sunum
PDF
Trimble Civil Engineering Construction
PDF
Alignment brochure web
PPTX
Bim its applications
PPTX
Mandated BIM! Are you ready?
PPTX
big-ideas-in-bim ..............work.pptx
PPTX
Masters thesis presentation
PDF
Trimble, TILOS & The Future
PDF
Building Information Modelling (BIM) Lessons at University of Hull's Student ...
PDF
DR15_0331_Managing the Information Labyrinth Final
PPTX
Bim cafm presentation 23 june2014
PDF
Integrating BIM & GIS - Closing the Data Loop, September 2019
PDF
Digital Quality Management in Construction 1st Edition Paul Marsden
PPTX
Corridor Selection in USA and UAE with GIS
PDF
Rtcaus13 abcd
PPTX
Designing to Enhance Construction Planning & Monitoring
PDF
Reducing Risk and Liability in Infrastructure Projects
Quantm Overview
Quantm enterprise english
Quantm professional english
Dinamikler 2017 - Alan Sharp Sunum
Trimble Civil Engineering Construction
Alignment brochure web
Bim its applications
Mandated BIM! Are you ready?
big-ideas-in-bim ..............work.pptx
Masters thesis presentation
Trimble, TILOS & The Future
Building Information Modelling (BIM) Lessons at University of Hull's Student ...
DR15_0331_Managing the Information Labyrinth Final
Bim cafm presentation 23 june2014
Integrating BIM & GIS - Closing the Data Loop, September 2019
Digital Quality Management in Construction 1st Edition Paul Marsden
Corridor Selection in USA and UAE with GIS
Rtcaus13 abcd
Designing to Enhance Construction Planning & Monitoring
Reducing Risk and Liability in Infrastructure Projects

More from Ibrahim Al-Hudhaif (20)

PDF
Total contract control for rail projects mounir boemond
PDF
Understanding the digital commuter etienne chevreau
PDF
Performance based contracts in railways ibraheem sheerah
PDF
Saudi arabia construction report feb. 2016
PDF
Business Case for Green Buildings
PDF
Energy Efficient Buildings Codes
PDF
Excellence through collaboration – the delivery of sustainability in mega pr...
PDF
Saudi Arabia’s Sustainable Construction Limitations: The Experts’ Views
PDF
Energy Efficiency and its Transformative Power
PDF
Current and future Mega Projects in Jubail and Ras Al-Khair Industrial Cities
PDF
Saudi Talent in Mega Projects
PDF
Oman Rail - in-country value strategic approach
PDF
Regional Integrated Supply Chain Strategy for Rail
PDF
Kuwait PPP Transport Projects
PDF
Makkah Metro - Makkah Mass Rail Project (MMRP)
PDF
meed projects - gcc mainline network projects
PDF
cit- cross-border passenger and freight traffic legal interoperability - Cesa...
PDF
URBAN TRANSPORT, SUSTAINABILITY AND THE ECONOMY
PDF
Hitachi Rail - Alistair Dormer
PDF
Jordan Hejaz Rail - Abdullah malkawi
Total contract control for rail projects mounir boemond
Understanding the digital commuter etienne chevreau
Performance based contracts in railways ibraheem sheerah
Saudi arabia construction report feb. 2016
Business Case for Green Buildings
Energy Efficient Buildings Codes
Excellence through collaboration – the delivery of sustainability in mega pr...
Saudi Arabia’s Sustainable Construction Limitations: The Experts’ Views
Energy Efficiency and its Transformative Power
Current and future Mega Projects in Jubail and Ras Al-Khair Industrial Cities
Saudi Talent in Mega Projects
Oman Rail - in-country value strategic approach
Regional Integrated Supply Chain Strategy for Rail
Kuwait PPP Transport Projects
Makkah Metro - Makkah Mass Rail Project (MMRP)
meed projects - gcc mainline network projects
cit- cross-border passenger and freight traffic legal interoperability - Cesa...
URBAN TRANSPORT, SUSTAINABILITY AND THE ECONOMY
Hitachi Rail - Alistair Dormer
Jordan Hejaz Rail - Abdullah malkawi

Recently uploaded (20)

PPTX
MYSQL Presentation for SQL database connectivity
PDF
Advanced methodologies resolving dimensionality complications for autism neur...
PDF
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
PDF
Review of recent advances in non-invasive hemoglobin estimation
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
PDF
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
PPTX
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
PDF
Dropbox Q2 2025 Financial Results & Investor Presentation
PPTX
sap open course for s4hana steps from ECC to s4
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PPTX
20250228 LYD VKU AI Blended-Learning.pptx
PDF
cuic standard and advanced reporting.pdf
PPTX
Big Data Technologies - Introduction.pptx
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Electronic commerce courselecture one. Pdf
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PPTX
Understanding_Digital_Forensics_Presentation.pptx
PDF
The Rise and Fall of 3GPP – Time for a Sabbatical?
MYSQL Presentation for SQL database connectivity
Advanced methodologies resolving dimensionality complications for autism neur...
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
Review of recent advances in non-invasive hemoglobin estimation
“AI and Expert System Decision Support & Business Intelligence Systems”
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
Dropbox Q2 2025 Financial Results & Investor Presentation
sap open course for s4hana steps from ECC to s4
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
20250228 LYD VKU AI Blended-Learning.pptx
cuic standard and advanced reporting.pdf
Big Data Technologies - Introduction.pptx
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Electronic commerce courselecture one. Pdf
Mobile App Security Testing_ A Comprehensive Guide.pdf
Digital-Transformation-Roadmap-for-Companies.pptx
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
Understanding_Digital_Forensics_Presentation.pptx
The Rise and Fall of 3GPP – Time for a Sabbatical?

Trimble Advanced Route Optimization Technology - QUANTM

  • 1. Trimble Advanced Route Optimization Technology - QUANTM
  • 2. Content  Background  Advanced route planning tool: Quantm  Conventional planning vs Quantm  Case studies  Conclusions Between vision and viability there are important decisions to make
  • 3.  Around 80% of civil infrastructure projects are delivered over budget, over time…  The greatest opportunities to contain overall costs and minimise environmental and social impact are at the planning stage  Conventional planning methods heavily rely on professional experience and judgment using manual methods  An intelligent route planning tool has been specifically developed to address the complex planning process Background Planning Feasibility Design Engineering Estimating Bidding Construction Operation Maintenance Planning Feasibility Design Engineering Trimble Quantm Technology
  • 4.  Quantm is a revolutionary planning tool for road/rail alignment selection with combined international expertise – Scoping study – Feasibility study – Value engineering  It automatically generates multiple cost effective and viable alignments that meet the defined constraints • Consider all feasible alternatives to help make the best decisions • Dramatically reduce planning time and project costs  Quantm technology has been used globally for planning over 40,000km of road and railway projects • Australia, New Zealand, America, Europe, Russia, Middle East, Africa, South East Asia, China Trimble Quantm Technology
  • 5. …new technologies are transforming the way the world works Trimble Quantm Technology  Digital Terrain Model (DTM) based optimisation engine  Input data: End points, design parameters, cost data, constraints  Comprehensive corridor/alignment search within the study area  Simultaneous 3D optimization with multiple alternatives
  • 6. Trimble Quantm Technology Cross sections Profile view Alignment comparison Alignment summary Plan view
  • 7. Conventional Planning vs Quantm 7 Items Conventional Quantm Project data Topographical maps, or DTM limited in size Digital Terrain Model 200+ millions points Planning method Planning time Manual, 2D Months, years Intelligent, 3D interactive Weeks, productivity up 50% Construction cost Often over budget Cost control saving 5~30% Alignment quality Heavily rely on experienced engineers Better fit into terrain Balanced earthworks Major structures/ Control points Potential misjudgment, missing viable corridors Never miss viable corridors/alignments 3D Visualization Limited in length or rely on third party software Real time rendering Sensitivity analyses ‘What if’ scenarios Time consuming Slow, labor intensive Fast quick response
  • 8. Case Studies: Beijing to Shenyang HSR  660km, 350km/h  3 Corridors, 10 local options  Comprehensive analysis  3 weeks
  • 9. Example of a large mining rail project – 500km
  • 10. Corridor Analysis Comparison of 50 Alternatives – alignments blocked by cost Increasing costs In this example it allows the operator to review 50 Alignments x 500km a total of 25,000km with earthwork volumes calculated @ 100m intervals
  • 11. TGV High Speed Rail with RAVE:  Lisbon – Madrid 200km, 2005-2007  Lisbon – Porto 300km, 2010  Aveiro – Salamanca 220km, 2009  Porto – Braga 45km, 2008-2010  Braga – Vigo 45km, 2008-2010 Quantm Benefits:  Planning time reduction  Cost reduction by 10%, or over €300millions  Better decision-making by integrating environmental, community, cultural and engineering into a single analysis Case Studies: Portugal TGV Projects
  • 12. Case Studies: Kyrgyzstan 250km Rail 12  Connect Uzbekistan - Kyrgyzstan to Kashgar, Xinjiang, China  1:50K ASTER GDEM  4 corridors/alignments, 2 weeks  Real time earthwork and cost estimation, significant cost reduction Traditional Method  Topographic maps  Manual estimates on volumes and costs  6 months study
  • 13.  AECOM, 1748km  Phase I: 16 corridors  Phase II: 7 sections  Explore ‘what if’ scenarios  A$114B (US$91B)  Phase II in 3 months!  8% tunnels -- 29% cost Case Studies: Australia HSR Project 13Source: AECOM (2013): High Speed Rail Study Phase 2: Key Findings and Executive Summary
  • 14. Quantm Summary - Iterative User Interface Data Optimisation DTM Engine Scoping Feasibility Design1:50000 1:10000 1:2000 DTM Geometrics Constraints Cost Fast /Efficient Quick Response Solve Problems Control Risk Environmental Reduce Cost 3D Visualisation
  • 15. Conclusions Trimble Quantm assists planners to plan a new road/rail project more rapidly with lower construction costs. Quantm makes it easier to:  Consider all feasible alternatives to help make the best decisions  Plan for sustainability with better environmental and public outcomes  Invest in a better future by reducing capital and operating costs
  • 18. Trimble Alignment Planning System Thank You for your kind attention Bill_lazaris@trimble.com Your Free Demo Download http://www.trimble.com/alignment/request-free- demo.aspx