SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
BACHELOR OF QUANTITY SURVEYING (HONOURS)
MARCH 2016 INTAKE
SITE SURVEYING [QSB 60103]
FIELDWORK 1 REPORT
LEVELLING
GROUP MEMBERS:
NAME STUDENT ID
PANG KAI YUN 0319802
SAM WEI YIN 0320364
TRACE GEW YEE 0320269
YEO KAI WEN 0319844
LECTURER: MR. CHAI VOON CHIET
1
CONTENT
No. Content Page Number
1. Objectives 2
2. Introduction 3
3. Fieldwork 9
4. Raw Data 10
5. Adjusted Data 12
6. Discussion 14
7. References 15
2
OBJECTIVES
 To enable to have a basic knowledge on how to set up the instruments such as
Automatic level (Auto- level), tripod stand, levelling rod rather than learning from the
books.
 To apply the theories that had been taught in class.
 To have an experience using Auto-level while setting up, collaborating, levelling and
recording the data that have been collected.
 To learn how to analyse the data.
 To identify the reduced level of each station and spot of relative height.
 To determine the difference in height of the points.
 To experience the life being as a quantity surveyor and expose the actual working
environment such as working under the hot weather in site.
 To determine the error of the mis-closure in order whether is it acceptable or not on
the levelling calculations.
 To know the precautions while using the Auto-level.
 To boost the ability of teamwork while doing on fieldwork.
3
INTRODUCTION TO LEVELLING
What is levelling?
Levelling is the measurement of geodetic height which using an optical levelling
instrument and a level staff or rod that have a numbered scale. Common levelling
instruments include spirit level, dumpy level, digital level and laser level. Levelling is defined
as ‘an art of determining the relative height of different points on, above or below the surface’.
The principle of levelling is to obtain the horizontal line to which vertical distances of the
points. By using this instrument of the levelling, it can be used for design the highways,
sewers, railways and others. It can used to calculate the volume of earthwork and used as
site layout for new foundation, contouring drainage and estimate the fall of the pipe.
When do we level?
 To determine the difference in height between two or more points.
 To determine the height of discrete points.
 To provide spot heights or contours on plan.
 To provide the data for road cross-sections or volume of the earthworks.
 To provide a level or inclined plane in the setting out of construction works.
4
Definition of Term Used in Levelling
Level surface
 The surface that parallel to the mean spheroidal surface of the earth
Vertical line
 Any line that lying vertically on the level surface.
Horizontal line
 Any line that lying on horizontal plane which is straight line tangential to level line.
Vertical plane
 A plane that containing a vertical line
Horizontal plane
 A plane tangential to level surface at a point which is perpendicular to the direction of
gravity.
Datum
 Any surface or line from which vertical distances are measured. There are two types
of Datum which is Ordnance Datum (O.D.) and Assume Datum (A.D.).
Bench-mark (B.M.)
 A diced reference point of known elevation.
Temporary Bench- mark (T.B.M.)
 Which is set up by the surveyor for is own task temporary
Reduce Level
 A vertical distance of a point above or below the datum. The elevation of a point is
either plus or minus according to the point.
5
Line of Collimation (HI)
 The line intersects with the cross hairs of the optical center of the object.
Backsight (BS)
 The first reading of the instrument set up at the first point.
Intermediate Sight (IS)
 The reading between the backsight and foresight.
Foresight (FS)
 The final reading of the instrument.
Change point (C.P.)
 A transfer point of the levelling. A new point which the previous point of the backsight
and foresight are taken.
Levelling Method
1. Height of Collimation Method
6
2. Rise and Fall Method
Apparatus UsedFor Levelling
Automatic level (Auto- level)
It is a professional levelling tool which is used by contractors, builders, land surveyors and
engineers who demand accurate the levelling survey. It is a self- levelling optical instrument
that measure horizontal planes and angles at distances no matter long distance or short
distance. This instrument is easy to set up. Before we use this instrument, we have to make
sure that the spirit bubble is in center of the black circle.
7
Adjustable Leg Tripod
This instrument is easy to set up due to each leg can be adjusted to the required height. The
function of this instrument is to ensure a stable instrument setup for reliable measurements.
If the instrument is moved, it must be set up again by loosen the screw and adjust it to make
sure that the levelling tripod is placed horizontally.
Optical Plummet
Is a device that used to center the instrument and used in place of a plumb bob to center
transits and the theodolites over a given point. It is preferred for its steadiness in strong
winds. It also protects the instrument from the accident like falling down. The device has a
lock below to lock the instruments that used in the fieldwork.
8
Horizontal Bubble Level
A tool for determine whether the surface is horizontal. The function of the horizontal bubble
level is same as the spirit level which has to ensure that the bubble is at the center of the
black circle. It is to check the accuracy of a level. The reading indicates to the surface which
is parallel to the horizontal plane.
Bar-Coded Level Rod
An instrument that used to determine the relative heights of the different points above the
datum area with the use of automatic level. It is a graduated wooden or aluminium rod.
9
FIELD WORK
10
RAW DATA
Height of Collimation Method
Back Sight
(BS)
Fore Sight (FS) Height of Collimation
Reduced
Level
Bench Mark
(BM)
0.805 100.805 100.000 BM 101
1.380 3.090 99.095 97.715 BM 1
1.360 1.385 99.070 97.710 BM 2
1.365 1.440 98.995 97.630 BM 3
1.485 1.435 99.045 97.560 BM 4
1.225 1.195 99.075 97.850 BM 5
1.305 1.275 99.105 97.800 BM 6
1.400 1.545 98.960 97.560 BM 7
1.205 1.155 99.010 97.805 BM 8
2.615 1.300 100.325 97.710 BM 9
1.370 0.355 101.340 99.970 BM 10
1.365 99.975 BM 101
- 15.515
- 15.540
15.540
- 100.000
- 99.975
- 0.025 - 0.025
11
Rise and Fall Method
Back Sight
(BS)
Fore Sight
(FS)
Height of
Collimation
Reduced
Level
Bench Mark
(BM)
Back Sight
(BS)
0.805 100.000 BM 101
1.380 3.090 2.285 97.715 BM 1
1.360 1.385 0.005 97.710 BM 2
1.365 1.440 0.080 97.630 BM 3
1.485 1.435 0.070 97.560 BM 4
1.225 1.195 0.290 97.850 BM 5
1.305 1.275 0.050 97.800 BM 6
1.400 1.545 0.240 97.560 BM 7
1.205 1.155 0.245 97.805 BM 8
2.615 1.300 0.095 97.710 BM 9
1.370 0.355 2.260 99.970 BM 10
1.365 0.005 99.975 BM 101
- 15.515
- 15.540
15.540
- 2.800
- 2.825
2.825
- - 99.975
- 100.000
- 0.025 - 0.025 - 0.025
Mis-closure = 99.975 m - 100.000 m
= - 0.025 m
Maximum allowable error of closure = ± 12 √ 𝑘
= ± 12 √ 𝑛𝑜.𝑜𝑓 𝑠𝑒𝑡𝑢𝑝
= ± 12 √11
= ± 39.799mm ( ± 0.0398m )
 Therefore, the levelling is acceptable.
12
ADJUSTED DATA
Height of Collimation Method
Back Sight
(BS)
Fore Sight
(FS)
Height of
Collimation
Reduced
Level
Correction
Adjusted
Reduced
Level
Bench
Mark (BM)
0.805 100.805 100.000 0 100.00000 BM 101
1.380 3.090 99.095 97.715 + 0.00227 97.71727 BM 1
1.360 1.385 99.070 97.710 + 0.00454 97.71454 BM 2
1.365 1.440 98.995 97.630 + 0.00681 97.63681 BM 3
1.485 1.435 99.045 97.560 + 0.00908 97.56908 BM 4
1.225 1.195 99.075 97.850 + 0.01135 97.86135 BM 5
1.305 1.275 99.105 97.800 + 0.01362 97.81362 BM 6
1.400 1.545 98.960 97.560 + 0.01589 97.57589 BM 7
1.205 1.155 99.010 97.805 + 0.01816 97.82316 BM 8
2.615 1.300 100.325 97.710 + 0.02043 97.73043 BM 9
1.370 0.355 101.340 99.970 + 0.02270 99.99270 BM 10
1.365 99.975 + 0.02497 99.99997 BM 101
- 15.515
- 15.540
15.540
- 100.000
- 99.975
- 100.000
- 100.000
- 0.025 - 0.025 0.000
13
Rise and Fall Method
Back
Sight
(BS)
Fore
Sight
(FS)
Rise Fall
Reduced
Level Correction
Adjusted
Reduced
Level
Bench
Mark
(BM)
0.805 100.000 0 100.00000 BM 101
1.380 3.090 2.285 97.715 + 0.00227 97.71727 BM 1
1.360 1.385 0.005 97.710 + 0.00454 97.71454 BM 2
1.365 1.440 0.080 97.630 + 0.00681 97.63681 BM 3
1.485 1.435 0.070 97.560 + 0.00908 97.56908 BM 4
1.225 1.195 0.290 97.850 + 0.01135 97.86135 BM 5
1.305 1.275 0.050 97.800 + 0.01362 97.81362 BM 6
1.400 1.545 0.240 97.560 + 0.01589 97.57589 BM 7
1.205 1.155 0.245 97.805 + 0.01816 97.82316 BM 8
2.615 1.300 0.095 97.710 + 0.02043 97.73043 BM 9
1.370 0.355 2.260 99.970 + 0.02270 99.99270 BM 10
1.365 0.005 99.975 + 0.02497 99.99997 BM 101
- 15.515
- 15.540
15.540
- 2.800
- 2.825
2.825
- 100.000
- 99.975
- 100.000
- 100.000
- 0.025 - 0.025 - 0.025 0.000
Correction per set-up = Error of mis-closure ÷ Number of set-up
= (100.0000 - 99.975) ÷ 11
= + 0.00227 m
14
DISCUSSION
In this field work, we are required to measure the reduced level (RL) of 10 points
around the staff parking at Taylor’s University Lakeside Campus. The levelling process
begins with obtaining the backsight (BS) of BM101 and the foresight (FS) of BM 1. The
reduce level of BM101 is given which is 100.000m. Then, the auto level is shifted to another
point by following the checkpoint set on the plan of the carpark. After shifting 11 point, we
will get back to BM101. All the reading is collected and recorded down.
The reduced level of each staff station is being calculated through the two methods,
which are Height of Collimation Method and Rise and Fall Method. There is a mis-closure
error in the levelling process. The error of mis-closure we calculated is - 0.025m which is
within the ± 39.799mm acceptable range of mis-closure. Thus, the levelling is acceptable.
The error of mis-closure can be caused by the staff is not held vertically. If the staff is not
held vertical, the staff reading obtained is greater than the correct reading. The error also
can be caused by sun. Due to bright sunshine on the objective, staff reading cannot be
taken properly.
The reduced level is adjusted by using the loop mis-closure method. The correction
per set-up is calculated to distribute the error. The correction per set-up is + 0.00227 m. All
the reduced level are adjusted and the final reduce level is equivalent to the original given
benchmark level.
In conclusion, this fieldwork helps us to understand better on the concept of levelling.
We get to learn how to conduct a fieldwork and how to use the levelling apparatus. We really
enjoy the process of doing this fieldwork. This is a very great experience and it will definitely
help us in our future.
15
REFERENCES
Levelling Equipment in Surveying. (n.d.). Retrieved July 5, 2016, from
http://www.aboutcivil.org/levelling-equipment.html
Levelling Tutorials. (n.d.). Retrieved July 11, 2016, from http://www.levelling.uhi.ac.uk/
Surveying Equipment. (n.d.). Retrieved July 11, 2016, from
http://www.engineersupply.com/surveying-equipment.aspx
Welcome to Agriinfo.in. (n.d.). Retrieved June 11, 2016, from
http://www.agriinfo.in/?page=topic
What is levelling? - Surveying & Levelling. (2015). Retrieved June 11, 2016, from
http://www.civileblog.com/levelling/

More Related Content

PDF
Levelling
PDF
Leveling final-report
DOCX
Project 1- Levelling
PDF
Site Surveying Leveling
PDF
Levelling report-1
DOCX
Site surveying report1
PPT
DOCX
Assignment 2 - Traverse
Levelling
Leveling final-report
Project 1- Levelling
Site Surveying Leveling
Levelling report-1
Site surveying report1
Assignment 2 - Traverse

What's hot (20)

DOCX
Levelling report
DOCX
engineering survey 1 report levelling
DOCX
Fieldwork 1 (leveling)
DOCX
Two Peg Test - Report
DOCX
Theodolite report
DOCX
SITE SURVEYING: Transversing
DOCX
Profile and Cross-Section - Report
PDF
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
DOCX
Contouring Report
PDF
Traversing final-report
DOCX
Levelling final
DOCX
Sand replacement
PDF
Ss report 1
PPTX
Setting out work
DOCX
Closed Traverse Surveying - Report
PPTX
levelling and contouring
PDF
Site Surveying Traversing
DOCX
Site surveying report i
PDF
Setting out 12042018
PPT
Topic 2 area & volume
Levelling report
engineering survey 1 report levelling
Fieldwork 1 (leveling)
Two Peg Test - Report
Theodolite report
SITE SURVEYING: Transversing
Profile and Cross-Section - Report
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
Contouring Report
Traversing final-report
Levelling final
Sand replacement
Ss report 1
Setting out work
Closed Traverse Surveying - Report
levelling and contouring
Site Surveying Traversing
Site surveying report i
Setting out 12042018
Topic 2 area & volume
Ad

Similar to Assignment 1 - Levelling (20)

DOCX
Site survey report 1
DOCX
Site survey Fieldwork1 (levelling)
PDF
Site Surveying Levelling
PDF
Site surveying-almost-1
DOCX
Site surveying report 1
PDF
Site surveying 1 - done
PDF
Site surveying 1 - done
DOCX
1 st report
PDF
Ss report 1
DOC
Ss report 1
DOCX
SITE SURVEYING LEVELING
PDF
Ss report 1
DOC
Site Surveying Report 1 (Levelling)
DOCX
Site Surveying Report - Traversing
DOCX
Site surveying-report-leveling
PPTX
Lecture 6- Levellinggggggggggggggggg.pptx
DOCX
Fieldwork 1
DOCX
Fieldwork 1
PPTX
Definition types and uses of leveling.pptx
PPTX
LEVELLING METHODS AND INSTRUMENTS IN SURVEYING
Site survey report 1
Site survey Fieldwork1 (levelling)
Site Surveying Levelling
Site surveying-almost-1
Site surveying report 1
Site surveying 1 - done
Site surveying 1 - done
1 st report
Ss report 1
Ss report 1
SITE SURVEYING LEVELING
Ss report 1
Site Surveying Report 1 (Levelling)
Site Surveying Report - Traversing
Site surveying-report-leveling
Lecture 6- Levellinggggggggggggggggg.pptx
Fieldwork 1
Fieldwork 1
Definition types and uses of leveling.pptx
LEVELLING METHODS AND INSTRUMENTS IN SURVEYING
Ad

More from Kai Yun Pang (20)

PDF
Assignment 2 - Resort Proposal at Pulau Langkawi
PDF
Assignment 2 - Report
PDF
Assignment 1 - Water Pump Station
PDF
Assignment 1 - Microsoft Project
PDF
Assignment - Financial Appraisal
PDF
Assignment - Financial Appraisal
PDF
Assignment - FIDIC Contract
PDF
Assignment - Report
PDF
Seminar - CIPAA 2012
PDF
Assignment - S Hotel (Presentation Slide)
PDF
Assignment - S Hotel
PDF
Assignment - Case Study Report
PDF
Assignment - Journal
PPTX
Assignment - Community Service
PDF
Assignment - Final Account
PDF
Assignment - Report
PDF
Seminar - Partial Possession by Employer
PDF
Seminar - Question
PDF
Assignment - MK Land
DOCX
Assignment - Financial Analysis
Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Report
Assignment 1 - Water Pump Station
Assignment 1 - Microsoft Project
Assignment - Financial Appraisal
Assignment - Financial Appraisal
Assignment - FIDIC Contract
Assignment - Report
Seminar - CIPAA 2012
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel
Assignment - Case Study Report
Assignment - Journal
Assignment - Community Service
Assignment - Final Account
Assignment - Report
Seminar - Partial Possession by Employer
Seminar - Question
Assignment - MK Land
Assignment - Financial Analysis

Recently uploaded (20)

PPTX
Cell Structure & Organelles in detailed.
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PPTX
Cell Types and Its function , kingdom of life
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
Computing-Curriculum for Schools in Ghana
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
Basic Mud Logging Guide for educational purpose
PDF
Insiders guide to clinical Medicine.pdf
PPTX
PPH.pptx obstetrics and gynecology in nursing
PDF
TR - Agricultural Crops Production NC III.pdf
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PPTX
Pharma ospi slides which help in ospi learning
PDF
Pre independence Education in Inndia.pdf
PDF
Classroom Observation Tools for Teachers
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
01-Introduction-to-Information-Management.pdf
Cell Structure & Organelles in detailed.
O5-L3 Freight Transport Ops (International) V1.pdf
Pharmacology of Heart Failure /Pharmacotherapy of CHF
Anesthesia in Laparoscopic Surgery in India
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
Abdominal Access Techniques with Prof. Dr. R K Mishra
Cell Types and Its function , kingdom of life
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
Computing-Curriculum for Schools in Ghana
Microbial disease of the cardiovascular and lymphatic systems
Basic Mud Logging Guide for educational purpose
Insiders guide to clinical Medicine.pdf
PPH.pptx obstetrics and gynecology in nursing
TR - Agricultural Crops Production NC III.pdf
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
Pharma ospi slides which help in ospi learning
Pre independence Education in Inndia.pdf
Classroom Observation Tools for Teachers
Final Presentation General Medicine 03-08-2024.pptx
01-Introduction-to-Information-Management.pdf

Assignment 1 - Levelling

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) MARCH 2016 INTAKE SITE SURVEYING [QSB 60103] FIELDWORK 1 REPORT LEVELLING GROUP MEMBERS: NAME STUDENT ID PANG KAI YUN 0319802 SAM WEI YIN 0320364 TRACE GEW YEE 0320269 YEO KAI WEN 0319844 LECTURER: MR. CHAI VOON CHIET
  • 2. 1 CONTENT No. Content Page Number 1. Objectives 2 2. Introduction 3 3. Fieldwork 9 4. Raw Data 10 5. Adjusted Data 12 6. Discussion 14 7. References 15
  • 3. 2 OBJECTIVES  To enable to have a basic knowledge on how to set up the instruments such as Automatic level (Auto- level), tripod stand, levelling rod rather than learning from the books.  To apply the theories that had been taught in class.  To have an experience using Auto-level while setting up, collaborating, levelling and recording the data that have been collected.  To learn how to analyse the data.  To identify the reduced level of each station and spot of relative height.  To determine the difference in height of the points.  To experience the life being as a quantity surveyor and expose the actual working environment such as working under the hot weather in site.  To determine the error of the mis-closure in order whether is it acceptable or not on the levelling calculations.  To know the precautions while using the Auto-level.  To boost the ability of teamwork while doing on fieldwork.
  • 4. 3 INTRODUCTION TO LEVELLING What is levelling? Levelling is the measurement of geodetic height which using an optical levelling instrument and a level staff or rod that have a numbered scale. Common levelling instruments include spirit level, dumpy level, digital level and laser level. Levelling is defined as ‘an art of determining the relative height of different points on, above or below the surface’. The principle of levelling is to obtain the horizontal line to which vertical distances of the points. By using this instrument of the levelling, it can be used for design the highways, sewers, railways and others. It can used to calculate the volume of earthwork and used as site layout for new foundation, contouring drainage and estimate the fall of the pipe. When do we level?  To determine the difference in height between two or more points.  To determine the height of discrete points.  To provide spot heights or contours on plan.  To provide the data for road cross-sections or volume of the earthworks.  To provide a level or inclined plane in the setting out of construction works.
  • 5. 4 Definition of Term Used in Levelling Level surface  The surface that parallel to the mean spheroidal surface of the earth Vertical line  Any line that lying vertically on the level surface. Horizontal line  Any line that lying on horizontal plane which is straight line tangential to level line. Vertical plane  A plane that containing a vertical line Horizontal plane  A plane tangential to level surface at a point which is perpendicular to the direction of gravity. Datum  Any surface or line from which vertical distances are measured. There are two types of Datum which is Ordnance Datum (O.D.) and Assume Datum (A.D.). Bench-mark (B.M.)  A diced reference point of known elevation. Temporary Bench- mark (T.B.M.)  Which is set up by the surveyor for is own task temporary Reduce Level  A vertical distance of a point above or below the datum. The elevation of a point is either plus or minus according to the point.
  • 6. 5 Line of Collimation (HI)  The line intersects with the cross hairs of the optical center of the object. Backsight (BS)  The first reading of the instrument set up at the first point. Intermediate Sight (IS)  The reading between the backsight and foresight. Foresight (FS)  The final reading of the instrument. Change point (C.P.)  A transfer point of the levelling. A new point which the previous point of the backsight and foresight are taken. Levelling Method 1. Height of Collimation Method
  • 7. 6 2. Rise and Fall Method Apparatus UsedFor Levelling Automatic level (Auto- level) It is a professional levelling tool which is used by contractors, builders, land surveyors and engineers who demand accurate the levelling survey. It is a self- levelling optical instrument that measure horizontal planes and angles at distances no matter long distance or short distance. This instrument is easy to set up. Before we use this instrument, we have to make sure that the spirit bubble is in center of the black circle.
  • 8. 7 Adjustable Leg Tripod This instrument is easy to set up due to each leg can be adjusted to the required height. The function of this instrument is to ensure a stable instrument setup for reliable measurements. If the instrument is moved, it must be set up again by loosen the screw and adjust it to make sure that the levelling tripod is placed horizontally. Optical Plummet Is a device that used to center the instrument and used in place of a plumb bob to center transits and the theodolites over a given point. It is preferred for its steadiness in strong winds. It also protects the instrument from the accident like falling down. The device has a lock below to lock the instruments that used in the fieldwork.
  • 9. 8 Horizontal Bubble Level A tool for determine whether the surface is horizontal. The function of the horizontal bubble level is same as the spirit level which has to ensure that the bubble is at the center of the black circle. It is to check the accuracy of a level. The reading indicates to the surface which is parallel to the horizontal plane. Bar-Coded Level Rod An instrument that used to determine the relative heights of the different points above the datum area with the use of automatic level. It is a graduated wooden or aluminium rod.
  • 11. 10 RAW DATA Height of Collimation Method Back Sight (BS) Fore Sight (FS) Height of Collimation Reduced Level Bench Mark (BM) 0.805 100.805 100.000 BM 101 1.380 3.090 99.095 97.715 BM 1 1.360 1.385 99.070 97.710 BM 2 1.365 1.440 98.995 97.630 BM 3 1.485 1.435 99.045 97.560 BM 4 1.225 1.195 99.075 97.850 BM 5 1.305 1.275 99.105 97.800 BM 6 1.400 1.545 98.960 97.560 BM 7 1.205 1.155 99.010 97.805 BM 8 2.615 1.300 100.325 97.710 BM 9 1.370 0.355 101.340 99.970 BM 10 1.365 99.975 BM 101 - 15.515 - 15.540 15.540 - 100.000 - 99.975 - 0.025 - 0.025
  • 12. 11 Rise and Fall Method Back Sight (BS) Fore Sight (FS) Height of Collimation Reduced Level Bench Mark (BM) Back Sight (BS) 0.805 100.000 BM 101 1.380 3.090 2.285 97.715 BM 1 1.360 1.385 0.005 97.710 BM 2 1.365 1.440 0.080 97.630 BM 3 1.485 1.435 0.070 97.560 BM 4 1.225 1.195 0.290 97.850 BM 5 1.305 1.275 0.050 97.800 BM 6 1.400 1.545 0.240 97.560 BM 7 1.205 1.155 0.245 97.805 BM 8 2.615 1.300 0.095 97.710 BM 9 1.370 0.355 2.260 99.970 BM 10 1.365 0.005 99.975 BM 101 - 15.515 - 15.540 15.540 - 2.800 - 2.825 2.825 - - 99.975 - 100.000 - 0.025 - 0.025 - 0.025 Mis-closure = 99.975 m - 100.000 m = - 0.025 m Maximum allowable error of closure = ± 12 √ 𝑘 = ± 12 √ 𝑛𝑜.𝑜𝑓 𝑠𝑒𝑡𝑢𝑝 = ± 12 √11 = ± 39.799mm ( ± 0.0398m )  Therefore, the levelling is acceptable.
  • 13. 12 ADJUSTED DATA Height of Collimation Method Back Sight (BS) Fore Sight (FS) Height of Collimation Reduced Level Correction Adjusted Reduced Level Bench Mark (BM) 0.805 100.805 100.000 0 100.00000 BM 101 1.380 3.090 99.095 97.715 + 0.00227 97.71727 BM 1 1.360 1.385 99.070 97.710 + 0.00454 97.71454 BM 2 1.365 1.440 98.995 97.630 + 0.00681 97.63681 BM 3 1.485 1.435 99.045 97.560 + 0.00908 97.56908 BM 4 1.225 1.195 99.075 97.850 + 0.01135 97.86135 BM 5 1.305 1.275 99.105 97.800 + 0.01362 97.81362 BM 6 1.400 1.545 98.960 97.560 + 0.01589 97.57589 BM 7 1.205 1.155 99.010 97.805 + 0.01816 97.82316 BM 8 2.615 1.300 100.325 97.710 + 0.02043 97.73043 BM 9 1.370 0.355 101.340 99.970 + 0.02270 99.99270 BM 10 1.365 99.975 + 0.02497 99.99997 BM 101 - 15.515 - 15.540 15.540 - 100.000 - 99.975 - 100.000 - 100.000 - 0.025 - 0.025 0.000
  • 14. 13 Rise and Fall Method Back Sight (BS) Fore Sight (FS) Rise Fall Reduced Level Correction Adjusted Reduced Level Bench Mark (BM) 0.805 100.000 0 100.00000 BM 101 1.380 3.090 2.285 97.715 + 0.00227 97.71727 BM 1 1.360 1.385 0.005 97.710 + 0.00454 97.71454 BM 2 1.365 1.440 0.080 97.630 + 0.00681 97.63681 BM 3 1.485 1.435 0.070 97.560 + 0.00908 97.56908 BM 4 1.225 1.195 0.290 97.850 + 0.01135 97.86135 BM 5 1.305 1.275 0.050 97.800 + 0.01362 97.81362 BM 6 1.400 1.545 0.240 97.560 + 0.01589 97.57589 BM 7 1.205 1.155 0.245 97.805 + 0.01816 97.82316 BM 8 2.615 1.300 0.095 97.710 + 0.02043 97.73043 BM 9 1.370 0.355 2.260 99.970 + 0.02270 99.99270 BM 10 1.365 0.005 99.975 + 0.02497 99.99997 BM 101 - 15.515 - 15.540 15.540 - 2.800 - 2.825 2.825 - 100.000 - 99.975 - 100.000 - 100.000 - 0.025 - 0.025 - 0.025 0.000 Correction per set-up = Error of mis-closure ÷ Number of set-up = (100.0000 - 99.975) ÷ 11 = + 0.00227 m
  • 15. 14 DISCUSSION In this field work, we are required to measure the reduced level (RL) of 10 points around the staff parking at Taylor’s University Lakeside Campus. The levelling process begins with obtaining the backsight (BS) of BM101 and the foresight (FS) of BM 1. The reduce level of BM101 is given which is 100.000m. Then, the auto level is shifted to another point by following the checkpoint set on the plan of the carpark. After shifting 11 point, we will get back to BM101. All the reading is collected and recorded down. The reduced level of each staff station is being calculated through the two methods, which are Height of Collimation Method and Rise and Fall Method. There is a mis-closure error in the levelling process. The error of mis-closure we calculated is - 0.025m which is within the ± 39.799mm acceptable range of mis-closure. Thus, the levelling is acceptable. The error of mis-closure can be caused by the staff is not held vertically. If the staff is not held vertical, the staff reading obtained is greater than the correct reading. The error also can be caused by sun. Due to bright sunshine on the objective, staff reading cannot be taken properly. The reduced level is adjusted by using the loop mis-closure method. The correction per set-up is calculated to distribute the error. The correction per set-up is + 0.00227 m. All the reduced level are adjusted and the final reduce level is equivalent to the original given benchmark level. In conclusion, this fieldwork helps us to understand better on the concept of levelling. We get to learn how to conduct a fieldwork and how to use the levelling apparatus. We really enjoy the process of doing this fieldwork. This is a very great experience and it will definitely help us in our future.
  • 16. 15 REFERENCES Levelling Equipment in Surveying. (n.d.). Retrieved July 5, 2016, from http://www.aboutcivil.org/levelling-equipment.html Levelling Tutorials. (n.d.). Retrieved July 11, 2016, from http://www.levelling.uhi.ac.uk/ Surveying Equipment. (n.d.). Retrieved July 11, 2016, from http://www.engineersupply.com/surveying-equipment.aspx Welcome to Agriinfo.in. (n.d.). Retrieved June 11, 2016, from http://www.agriinfo.in/?page=topic What is levelling? - Surveying & Levelling. (2015). Retrieved June 11, 2016, from http://www.civileblog.com/levelling/