SlideShare a Scribd company logo
Lessons from the project
front line
www.pwc.co.uk
APM Event
November 2015
PwC
Agenda
1. Some war stories
2. Key theme to project success
3. Theory to reality
4. Project assurance
5. Summary
6. Q&A
Lessons from the project front line
PwC 2
November 2015
Jenny Tuohy
PwC | Programme/Project Manager
M: 07808 799447
E: jenny.f.tuohy@uk.pwc.com
PwC
Lessons from the project front line
3
November 2015
PwC
Some war
stories
PwC
War Story No.1
Transformation programme
Lessons from the project front line
4
November 2015
Background
• PwC’s own transformation programme for
the financial statements audit practice
• Objective was to update the auditing tools
and approach to reflect new methodologies,
IT capabilities, and our clients current
business models
• The days of using IT as a filing cabinet
where over!
• Tight window of opportunity to deploy the
new software due to the annual audit cycle
• Performance was business
(reputational) critical
Time Cost
Performance
PwC
War Story No.1
Transformation programme
Lessons from the project front line
5
November 2015
Scope
• Using agile development, design and deploy a bespoke IT solution for the global audit practice to
document their work
• The UK firm worked in collaboration with the US and Australian firms to lead the global programme
• Matrix team combining IT, audit and compliance SMEs
• Training of the UK practice (circa. 8,000 people) on the software, but also to embed and deliver key
behavioral changes
Outcome Success
• Global launch and now
80,000 people are using the
new software
• Yes but...
Lessons learnt
• Agile IT development really
does need a homogenous,
small and simple user base
• Change is about culture and
mind-sets, not the tools
• Governance, governance,
governance
PwC
War Story No.2
ERP IT implementation programme
Lessons from the project front line
6
November 2015
Background
• A utility company were implementing a new
ERP billing system
• Corporate board was not confident in the
programmes direction and the progress of the
programme to date
• Highly regulated market, and the regulator had
imposed a tight timeline
• Performance was business
(reputational) critical
Time Cost
Performance
PwC
War Story No.2
ERP IT implementation programme
Lessons from the project front line
7
November 2015
Scope
• Complete an independent review on the status of the programme
• Determine if perceived risks/issues were real
• Provide recommendations to rebuild trust between the programme and the business
Outcome Success
• Trust restored between the
programme team and the
corporate board
• Yes but...
Lessons learnt
• Consistent and effective
reporting is vital
• Know your numbers (have a
Dragons Den mind set)
• Governance, governance,
governance!
PwC
War Story No.3
Business acquisition
Lessons from the project front line
8
November 2015
Time Cost
Performance
CMA
Competition & Markets Authority
Background
• Secondment to a privately owned
manufacturing company
• Project managed an acquisition they were
making as a result of an investigation by the
Competitions and Market Authority (CAM)
into one of their competitors
• Underlying IT to support the acquisition did
not already exist within the company
• End to end business processes for the new
business were not defined or mapped
• 8 week timeframe
• Performance (customer service on-boarding
experience) was paramount
PwC
War Story No.3
Business acquisition
Lessons from the project front line
9
November 2015
Scope
• Design and map the end to end business processes for the new acquisition
• Implement and tests a new IT systems to ensure the business was operation on day 1
• Existing IT was provided by a mixture of in-house and third party software providers
• De-coupling of IT from competitors, however, hardware (BT line etc.) restrictions applied
• Training of new staff members on the company and it’s processes
Outcome Success
• New business was fully
operational on Day
• Yes but...
Lessons learnt
• Tailor your methodology –
an agile and document light
approach was key
• Team work and
communications is key
• Governance, governance,
governance!
PwC
War Story No.4
Internal audit project reviews
Lessons from the project front line
10
November 2015
Background
• Project Assurance function provided via the
Internal Audit team
• Range of public sector clients, including
the MOD
• Projects for review are identified annually as
part of the Internal Audit’s risk based profiling
• Time, cost and performance requirements
considered for all audits
Time Cost
Performance
PwC
War Story No.4
Internal audit project reviews
Lessons from the project front line
11
November 2015
Scope
• Scope varied on a project by project basis, but always asked to consider if the project was/is going to
be successful
• But what does success mean? And who is asking?
• Balance of providing independent review of project versus future recommendations and gateway
review points
• Need to decouple with other audits to prevent ‘over auditing’ e.g. the MPA
Outcome Success
• In flight status report to
enable real time
improvements/resolutions
• Can we really decide?!
Lessons learnt
• Paper, paper everywhere
• Responsibility and
succession planning is key
• Governance, governance,
governance!!
PwC
Lessons from the project front line
12
November 2015
PwC
Key theme to project
success
PwC
Good governance is really
another way of saying
good people
(management)
Governance – It’s all about people!
Lessons from the project front line
13
November 2015
Don’t get lost in the detail
– its not all just about
deliverables and products
PwC
Key lessons learnt – Governance
Lessons from the project front line
14
November 2015
Governance
Project
Board
Project
Manager
Project
Team
• Project Board roles
(Executive, Senior User,
Senior Supplier) are key
• The board must be
empowered and engaged
• Roles clearly understood
(not just documented)
• If appropriate, succession
plans are in place
• Effective reporting is
essential
• Don’t hide bad news
• Lead from the front
• Get to know your team
and their strengths and
weaknesses
• Don’t be afraid to deal
with development points
• Ensure you act as the
link between the board
and the team
• Know your methodologies,
but don’t solely rely
on them
• Be flexible in approach
and your role e.g. get
involved in UAT
• Have the project info
at your fingertips
• Be consistent and honest
PwC
Lessons from the project front line
15
November 2015
PwC
Theory to reality
PwC
Theory to reality – Embedded assurance
Lessons from the project front line
16
November 2015
The theme of governance is nothing new,
but how do you ensure it happens?
Embedded assurance
What does this mean to you and how does it help?
Exercise – Over to you!
PwC
Theory to reality – Embedded assurance
Lessons from the project front line
17
November 2015
But if you where going
to audit yourself, what
would you honestly say?
Embedded assurance
The Project Board is responsible, via its Project Assurance role,
for monitoring all aspects of the project’s performance and
products independently of the Project Manager.
Project Assurance has to be independent of the Project Manager;
therefore the Project Board cannot delegate any of its assurance
activities to the Project Manager.
– PRINCE2 (2009)
“
”
PwC
Theory to reality – Embedded assurance
Lessons from the project front line
18
November 2015
• Self assessment – Act as your own conscience
- Is your governance structure clear?
- How could you demonstrate good governance in action?
- How is your documentation looking – Too much or too little? Would you really like to
cold review it?!
• Project team internal reviews – Builds up team members knowledge and engagement
- How would the team rate themselves?
- P3M3 maturity assessment? Others?
• Independent external reviews – Obtain recommendations for improvement
- Powerful stakeholder tool
- Aligned to project stages
- Effective intermediary when third parties/multiple suppliers are involved
Approaches you
could consider
Planning needs to include plans for project assurance, both in terms of timelines and budgets
PwC
Lessons from the project front line
19
November 2015
PwC
Project assurance
PwC
Project assurance
Lessons from the project front line
20
November 2015
PwC believe so much in the power of assurance for enabling good
governance, that there is an entire team dedicated to providing
project assurance for our clients
The role of assurance is to provide information to those that sponsor,
govern and manage a project to help them make better informed
decisions which reduce the causes of project failure, promote the
conditions for success and deliver improved outcomes.
– PwC (2015)
“
”There are a few PwC team tools which I consistently use to think about if I was to audit myself, what
would I consider, and how does this help with governance…
PwC
Project assurance – PwC tools
Delivery models
Lessons from the project front line
21
November 2015
Deep
dives
Continuous
assurance
Gate
reviews
Programme
assessments
Highly detailed reviews evaluating
specific programme area(s)
• Ability to identify root causes of any
issues and how can they be addressed
• Evaluating whether recommended
actions have been carried out
• A focus on whether individual
programme elements meets
specific objectives
Focused deep dives
Acting as a ‘critical friend’;
also known as a ‘Watch and
Challenge’ brief
• Regular contact with the programme
team helps in-depth understanding of
all aspects of the programme
• Able to provide real time observations
and challenge over changes to
programme scope, benefits case or
forward planning
Continuous assurance approach
High level of detail to assess the
quality of programme governance
also known as a ‘health-check’.
• Ensures the programme is
set up for success
• Identifies potential control design
weaknesses and improvement
opportunities
• Provides observations over key
decisions which affect outcomes.
• Identifies risks and issues
threatening the successful delivery
of the programme
Programme assessments
Medium level of detail to assess
programme governance and
alignment with objectives
• Point in time assessment of
programme performance,
status and outlook
• Assesses programme readiness
for subsequent phases.
• Identifies lessons learnt for
future phases
Staged ‘gate reviews’
PwC
Project assurance – PwC tools
‘The 12 elements’
Lessons from the project front line
22
November 2015
12 elements
of delivery
excellenceEngaged
stakeholders
Clear
scope
Managed
risks and
opportunities
Delivery-
enabling
plans
Focussed
benefits
management
High-
performing
teams
Smart
financing
Integrated
suppliers
Agile
change
control
Embedded
life-cycle
assurance
and
learningActive
quality
management
Governance-
enabling
decision-making
Governance and
management
Assesses how the programme,
as a whole, is being managed
– by looking at the
governance and decision-
making arrangements;
stakeholder and talent
management, and how
lessons are being learned
Programme delivery
This area examines how the
programme is being
delivered, looking at the plans
and schedules, dependency
logs, risk registers, change
control processes, and how
the business requirements are
being met. It also assesses
how well the overall benefits
are being specified and
measured
Commercial and finance
Reviews how the programme
is being managed from a
commercial and cost point of
view. It assesses the capability
to manage contractual
arrangements with higher
risks and how effective the
reporting and the supply of
financial information are
PwC
Lessons from the project front line
23
November 2015
PwC
Summary
PwC
Lessons from the project front line
Lessons from the project front line
24
November 2015
Project and
programmes
really are unique
but transferable
Don’t get lost in
the detail – It’s not
all just about the
deliverables and
products
Good governance
is really another
way of saying
good people
(management)
Project success is
consistently linked
to good
governance
By having a project
assurance mind-
set you
can plan to deliver
good governance
and so ultimately
project success
What will now you do differently?
PwC
Thank you and please get in touch
Lessons from the project front line
25
November 2015
Jenny Tuohy
PwC | Programme/Project Manager
M: 07808 799447
E: jenny.f.tuohy@uk.pwc.com
This publication has been prepared for general guidance on matters of interest only, and does not constitute professional advice. You should not act upon the
information contained in this publication without obtaining specific professional advice. No representation or warranty (express or implied) is given as to the
accuracy or completeness of the information contained in this publication, and, to the extent permitted by law, PwC does not accept or assume any liability,
responsibility or duty of care for any consequences of you or anyone else acting, or refraining to act, in reliance on the information contained in this publication
or for any decision based on it.
© 2015 PwC. All rights reserved. PwC refers to the PwC network and/or one or more of its member firms, each of which is a separate legal entity. Please see
www.pwc.com/structure for further details.
151021-160021-JT-OS

More Related Content

PDF
A green belt practitioners guide for quality champions publication v2021
PPTX
CMMI & PMBOK & OPM3
PDF
Programme Management in the transport sector - a TfL case study webinar, 19th...
PPT
PDF
Doc publishing -LeanSixSigma Project
PDF
The new PMP, what it is and how to get prepared for it
PPTX
Enhancing business value in organizations using OPM3
PPT
Project Mng Basics Belarusian State University Final
A green belt practitioners guide for quality champions publication v2021
CMMI & PMBOK & OPM3
Programme Management in the transport sector - a TfL case study webinar, 19th...
Doc publishing -LeanSixSigma Project
The new PMP, what it is and how to get prepared for it
Enhancing business value in organizations using OPM3
Project Mng Basics Belarusian State University Final

What's hot (20)

PPTX
PMI-ACP Agile free sample from EVOLVE
PDF
New Techniques to Elevate QA to Program Assurance
PDF
Use of lean metrics apm 170216 slides to share
PPTX
CAPM Exam Prep Course Preview
PDF
Introduce the processes of project management pmbok6 by mm rahman stm-skill ...
PDF
PMI-ACP Introduction (1PDU)
PPTX
Pmp(project management professional ) presentation
PPTX
Iso27001leadauditor2020
PDF
Prince2 & PMBOK Comparison Demystified
PDF
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PPT
Agile project management framework
PPTX
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
PDF
Organizational project maturity model (opm3)
PPT
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
PPTX
Pmi dec 13
PPTX
PMP Exam Preparation Workshop
PPTX
1 project management framework - Fifth edition
PPTX
PMBOK® Guide Sixth Edition Update
PDF
ICEBERG: a different look at Software Project Management
PPTX
Maintaining PMP Credential
PMI-ACP Agile free sample from EVOLVE
New Techniques to Elevate QA to Program Assurance
Use of lean metrics apm 170216 slides to share
CAPM Exam Prep Course Preview
Introduce the processes of project management pmbok6 by mm rahman stm-skill ...
PMI-ACP Introduction (1PDU)
Pmp(project management professional ) presentation
Iso27001leadauditor2020
Prince2 & PMBOK Comparison Demystified
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
Agile project management framework
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Organizational project maturity model (opm3)
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
Pmi dec 13
PMP Exam Preparation Workshop
1 project management framework - Fifth edition
PMBOK® Guide Sixth Edition Update
ICEBERG: a different look at Software Project Management
Maintaining PMP Credential
Ad

Viewers also liked (20)

PPT
Pwc systems-implementation-lessons-learned
PDF
Uni fi controller_ug
PPTX
Collecting statistics from the unifi wireless controller
PDF
unifi ap datasheet
PPTX
MSCS : Windows Server 2016 Quoi de neuf pour votre datacenter
PPTX
SQL Server 2016: Just a Few of Our DBA's Favorite Things
PDF
MCSA: Windows Server 2016
PPTX
SQL server 2016 New Features
PDF
4 Qualities Every Student Leader Should Have
PPTX
Visual management - Leadership Support for the Front Line
PDF
(Mikrotik)MTCNA presentation Material-IDN
PPTX
MikroTik MTCNA
PDF
A-Z Web Development Concept
PDF
10 Steps to Becoming a Better Leader
PPSX
C++ Programming Language
ODP
Linux Introduction (Commands)
PDF
CBSE XII Communication And Network Concepts
PDF
How To Be A Better Leader At Work – Manager Skills
PDF
HTML CSS Basics
PPT
Linux command ppt
Pwc systems-implementation-lessons-learned
Uni fi controller_ug
Collecting statistics from the unifi wireless controller
unifi ap datasheet
MSCS : Windows Server 2016 Quoi de neuf pour votre datacenter
SQL Server 2016: Just a Few of Our DBA's Favorite Things
MCSA: Windows Server 2016
SQL server 2016 New Features
4 Qualities Every Student Leader Should Have
Visual management - Leadership Support for the Front Line
(Mikrotik)MTCNA presentation Material-IDN
MikroTik MTCNA
A-Z Web Development Concept
10 Steps to Becoming a Better Leader
C++ Programming Language
Linux Introduction (Commands)
CBSE XII Communication And Network Concepts
How To Be A Better Leader At Work – Manager Skills
HTML CSS Basics
Linux command ppt
Ad

Similar to Lessons From The Project Front Line - 4th November 2015 (20)

PPTX
You have a project manager yay
PPT
South Florida Pmi Presentation 2011 Short
PPTX
Kick off_Flintec_05052014 v3
PPTX
Project Management - Foundation
PPT
Project management skills
PPT
Project Manangement Introduction
PDF
Your project selected_for_audit_sip18_project_auditors
PPTX
Project management framework 01
PPT
Project Management For Nonprofits
PPT
Pmbok framework helping material
PPTX
Project Management power point presentation.pptx
DOCX
1PJM6000 Week 1Project Management PracticesProfess.docx
DOCX
1PJM6000 Week 1Project Management PracticesProfess.docx
PPTX
Project Management Professional (PMP) Certification Trainer Materials Free Sa...
PDF
Getting your project started in fp7
PPTX
Project Management Introduction General PM lifecycles
PPSX
What's the colour of your project?
PPTX
PM & PM LC.pptx
PDF
Project Management for Public Works Professionals - Santa Fe Branch 2017
PDF
02/23/2013 Meeting - Investigate! (Mock Computer Aided Investigation Workshop)
You have a project manager yay
South Florida Pmi Presentation 2011 Short
Kick off_Flintec_05052014 v3
Project Management - Foundation
Project management skills
Project Manangement Introduction
Your project selected_for_audit_sip18_project_auditors
Project management framework 01
Project Management For Nonprofits
Pmbok framework helping material
Project Management power point presentation.pptx
1PJM6000 Week 1Project Management PracticesProfess.docx
1PJM6000 Week 1Project Management PracticesProfess.docx
Project Management Professional (PMP) Certification Trainer Materials Free Sa...
Getting your project started in fp7
Project Management Introduction General PM lifecycles
What's the colour of your project?
PM & PM LC.pptx
Project Management for Public Works Professionals - Santa Fe Branch 2017
02/23/2013 Meeting - Investigate! (Mock Computer Aided Investigation Workshop)

More from Association for Project Management (20)

PDF
How using AI in construction planning boosts efficiency and production
PDF
APM North East Network: Micro P3 Express – A framework for all small projects
PDF
Leveraging Projects and PMOs to drive Sustainability, 2 July 2025
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PDF
Transforming Tomorrow Managing Change in the Public Sector.pdf
PPTX
1155 Teri Okoro.pptx APM People Interest Network Presents: A People-Centric A...
PPTX
1100 Kate Howes.pptx The Value of Education and Training: Developing a Learni...
PPTX
0815 Matt Gitsham APM Conf 2025-Professor of Sustainable Development and Acad...
PPTX
1510 Rami Deen Turning Fools Gold to Sustainable Gold v0.9.pptx
PPTX
1100 Suzanne Maxted & Ellie Cady APM Sustainability Interest Network presents...
PPTX
1510 day 2 Hall 5 Arun Khuttan Building a project business case using the UN ...
PPTX
1155 Helen Clayton_Tasha Clark - ESG Slides - Final - APM Conference 25.pptx
PPTX
1100 Mark & Andrew APM Enabling Change IN Slides.pptx
PPTX
0945 APM presentation from Gabrielle Walker.pptx
PDF
How you can use behavioural insights on your projects and pitfalls to be awar...
PPTX
Sadie B Okiji - Head of projects, NHS Sussex
PPTX
Cyara Buchuck-Wilsenach.pptx Embedding DEI into Sustainable Project Managemen...
PPTX
APM 2025 Tayyab Jamil Slide Deck_Rethinking Technology Projects For Sustaina...
PPTX
1155 Robbie Warwick - Chaos to Clarity V1.0.pptx
PPTX
Daniel O’Neill Director of Project Delivery, Tevalis and Felicity Peart Count...
How using AI in construction planning boosts efficiency and production
APM North East Network: Micro P3 Express – A framework for all small projects
Leveraging Projects and PMOs to drive Sustainability, 2 July 2025
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
Transforming Tomorrow Managing Change in the Public Sector.pdf
1155 Teri Okoro.pptx APM People Interest Network Presents: A People-Centric A...
1100 Kate Howes.pptx The Value of Education and Training: Developing a Learni...
0815 Matt Gitsham APM Conf 2025-Professor of Sustainable Development and Acad...
1510 Rami Deen Turning Fools Gold to Sustainable Gold v0.9.pptx
1100 Suzanne Maxted & Ellie Cady APM Sustainability Interest Network presents...
1510 day 2 Hall 5 Arun Khuttan Building a project business case using the UN ...
1155 Helen Clayton_Tasha Clark - ESG Slides - Final - APM Conference 25.pptx
1100 Mark & Andrew APM Enabling Change IN Slides.pptx
0945 APM presentation from Gabrielle Walker.pptx
How you can use behavioural insights on your projects and pitfalls to be awar...
Sadie B Okiji - Head of projects, NHS Sussex
Cyara Buchuck-Wilsenach.pptx Embedding DEI into Sustainable Project Managemen...
APM 2025 Tayyab Jamil Slide Deck_Rethinking Technology Projects For Sustaina...
1155 Robbie Warwick - Chaos to Clarity V1.0.pptx
Daniel O’Neill Director of Project Delivery, Tevalis and Felicity Peart Count...

Recently uploaded (20)

PPTX
5 Stages of group development guide.pptx
PDF
Nidhal Samdaie CV - International Business Consultant
PDF
How to Get Funding for Your Trucking Business
PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
PDF
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
PPTX
Amazon (Business Studies) management studies
PDF
Unit 1 Cost Accounting - Cost sheet
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
DOCX
Business Management - unit 1 and 2
PPTX
Principles of Marketing, Industrial, Consumers,
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
PDF
IFRS Notes in your pocket for study all the time
PPT
Chapter four Project-Preparation material
PPTX
HR Introduction Slide (1).pptx on hr intro
PDF
MSPs in 10 Words - Created by US MSP Network
PDF
Tata consultancy services case study shri Sharda college, basrur
5 Stages of group development guide.pptx
Nidhal Samdaie CV - International Business Consultant
How to Get Funding for Your Trucking Business
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
Amazon (Business Studies) management studies
Unit 1 Cost Accounting - Cost sheet
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
Business Management - unit 1 and 2
Principles of Marketing, Industrial, Consumers,
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
unit 1 COST ACCOUNTING AND COST SHEET
Power and position in leadershipDOC-20250808-WA0011..pdf
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
New Microsoft PowerPoint Presentation - Copy.pptx
IFRS Notes in your pocket for study all the time
Chapter four Project-Preparation material
HR Introduction Slide (1).pptx on hr intro
MSPs in 10 Words - Created by US MSP Network
Tata consultancy services case study shri Sharda college, basrur

Lessons From The Project Front Line - 4th November 2015

  • 1. Lessons from the project front line www.pwc.co.uk APM Event November 2015
  • 2. PwC Agenda 1. Some war stories 2. Key theme to project success 3. Theory to reality 4. Project assurance 5. Summary 6. Q&A Lessons from the project front line PwC 2 November 2015 Jenny Tuohy PwC | Programme/Project Manager M: 07808 799447 E: jenny.f.tuohy@uk.pwc.com
  • 3. PwC Lessons from the project front line 3 November 2015 PwC Some war stories
  • 4. PwC War Story No.1 Transformation programme Lessons from the project front line 4 November 2015 Background • PwC’s own transformation programme for the financial statements audit practice • Objective was to update the auditing tools and approach to reflect new methodologies, IT capabilities, and our clients current business models • The days of using IT as a filing cabinet where over! • Tight window of opportunity to deploy the new software due to the annual audit cycle • Performance was business (reputational) critical Time Cost Performance
  • 5. PwC War Story No.1 Transformation programme Lessons from the project front line 5 November 2015 Scope • Using agile development, design and deploy a bespoke IT solution for the global audit practice to document their work • The UK firm worked in collaboration with the US and Australian firms to lead the global programme • Matrix team combining IT, audit and compliance SMEs • Training of the UK practice (circa. 8,000 people) on the software, but also to embed and deliver key behavioral changes Outcome Success • Global launch and now 80,000 people are using the new software • Yes but... Lessons learnt • Agile IT development really does need a homogenous, small and simple user base • Change is about culture and mind-sets, not the tools • Governance, governance, governance
  • 6. PwC War Story No.2 ERP IT implementation programme Lessons from the project front line 6 November 2015 Background • A utility company were implementing a new ERP billing system • Corporate board was not confident in the programmes direction and the progress of the programme to date • Highly regulated market, and the regulator had imposed a tight timeline • Performance was business (reputational) critical Time Cost Performance
  • 7. PwC War Story No.2 ERP IT implementation programme Lessons from the project front line 7 November 2015 Scope • Complete an independent review on the status of the programme • Determine if perceived risks/issues were real • Provide recommendations to rebuild trust between the programme and the business Outcome Success • Trust restored between the programme team and the corporate board • Yes but... Lessons learnt • Consistent and effective reporting is vital • Know your numbers (have a Dragons Den mind set) • Governance, governance, governance!
  • 8. PwC War Story No.3 Business acquisition Lessons from the project front line 8 November 2015 Time Cost Performance CMA Competition & Markets Authority Background • Secondment to a privately owned manufacturing company • Project managed an acquisition they were making as a result of an investigation by the Competitions and Market Authority (CAM) into one of their competitors • Underlying IT to support the acquisition did not already exist within the company • End to end business processes for the new business were not defined or mapped • 8 week timeframe • Performance (customer service on-boarding experience) was paramount
  • 9. PwC War Story No.3 Business acquisition Lessons from the project front line 9 November 2015 Scope • Design and map the end to end business processes for the new acquisition • Implement and tests a new IT systems to ensure the business was operation on day 1 • Existing IT was provided by a mixture of in-house and third party software providers • De-coupling of IT from competitors, however, hardware (BT line etc.) restrictions applied • Training of new staff members on the company and it’s processes Outcome Success • New business was fully operational on Day • Yes but... Lessons learnt • Tailor your methodology – an agile and document light approach was key • Team work and communications is key • Governance, governance, governance!
  • 10. PwC War Story No.4 Internal audit project reviews Lessons from the project front line 10 November 2015 Background • Project Assurance function provided via the Internal Audit team • Range of public sector clients, including the MOD • Projects for review are identified annually as part of the Internal Audit’s risk based profiling • Time, cost and performance requirements considered for all audits Time Cost Performance
  • 11. PwC War Story No.4 Internal audit project reviews Lessons from the project front line 11 November 2015 Scope • Scope varied on a project by project basis, but always asked to consider if the project was/is going to be successful • But what does success mean? And who is asking? • Balance of providing independent review of project versus future recommendations and gateway review points • Need to decouple with other audits to prevent ‘over auditing’ e.g. the MPA Outcome Success • In flight status report to enable real time improvements/resolutions • Can we really decide?! Lessons learnt • Paper, paper everywhere • Responsibility and succession planning is key • Governance, governance, governance!!
  • 12. PwC Lessons from the project front line 12 November 2015 PwC Key theme to project success
  • 13. PwC Good governance is really another way of saying good people (management) Governance – It’s all about people! Lessons from the project front line 13 November 2015 Don’t get lost in the detail – its not all just about deliverables and products
  • 14. PwC Key lessons learnt – Governance Lessons from the project front line 14 November 2015 Governance Project Board Project Manager Project Team • Project Board roles (Executive, Senior User, Senior Supplier) are key • The board must be empowered and engaged • Roles clearly understood (not just documented) • If appropriate, succession plans are in place • Effective reporting is essential • Don’t hide bad news • Lead from the front • Get to know your team and their strengths and weaknesses • Don’t be afraid to deal with development points • Ensure you act as the link between the board and the team • Know your methodologies, but don’t solely rely on them • Be flexible in approach and your role e.g. get involved in UAT • Have the project info at your fingertips • Be consistent and honest
  • 15. PwC Lessons from the project front line 15 November 2015 PwC Theory to reality
  • 16. PwC Theory to reality – Embedded assurance Lessons from the project front line 16 November 2015 The theme of governance is nothing new, but how do you ensure it happens? Embedded assurance What does this mean to you and how does it help? Exercise – Over to you!
  • 17. PwC Theory to reality – Embedded assurance Lessons from the project front line 17 November 2015 But if you where going to audit yourself, what would you honestly say? Embedded assurance The Project Board is responsible, via its Project Assurance role, for monitoring all aspects of the project’s performance and products independently of the Project Manager. Project Assurance has to be independent of the Project Manager; therefore the Project Board cannot delegate any of its assurance activities to the Project Manager. – PRINCE2 (2009) “ ”
  • 18. PwC Theory to reality – Embedded assurance Lessons from the project front line 18 November 2015 • Self assessment – Act as your own conscience - Is your governance structure clear? - How could you demonstrate good governance in action? - How is your documentation looking – Too much or too little? Would you really like to cold review it?! • Project team internal reviews – Builds up team members knowledge and engagement - How would the team rate themselves? - P3M3 maturity assessment? Others? • Independent external reviews – Obtain recommendations for improvement - Powerful stakeholder tool - Aligned to project stages - Effective intermediary when third parties/multiple suppliers are involved Approaches you could consider Planning needs to include plans for project assurance, both in terms of timelines and budgets
  • 19. PwC Lessons from the project front line 19 November 2015 PwC Project assurance
  • 20. PwC Project assurance Lessons from the project front line 20 November 2015 PwC believe so much in the power of assurance for enabling good governance, that there is an entire team dedicated to providing project assurance for our clients The role of assurance is to provide information to those that sponsor, govern and manage a project to help them make better informed decisions which reduce the causes of project failure, promote the conditions for success and deliver improved outcomes. – PwC (2015) “ ”There are a few PwC team tools which I consistently use to think about if I was to audit myself, what would I consider, and how does this help with governance…
  • 21. PwC Project assurance – PwC tools Delivery models Lessons from the project front line 21 November 2015 Deep dives Continuous assurance Gate reviews Programme assessments Highly detailed reviews evaluating specific programme area(s) • Ability to identify root causes of any issues and how can they be addressed • Evaluating whether recommended actions have been carried out • A focus on whether individual programme elements meets specific objectives Focused deep dives Acting as a ‘critical friend’; also known as a ‘Watch and Challenge’ brief • Regular contact with the programme team helps in-depth understanding of all aspects of the programme • Able to provide real time observations and challenge over changes to programme scope, benefits case or forward planning Continuous assurance approach High level of detail to assess the quality of programme governance also known as a ‘health-check’. • Ensures the programme is set up for success • Identifies potential control design weaknesses and improvement opportunities • Provides observations over key decisions which affect outcomes. • Identifies risks and issues threatening the successful delivery of the programme Programme assessments Medium level of detail to assess programme governance and alignment with objectives • Point in time assessment of programme performance, status and outlook • Assesses programme readiness for subsequent phases. • Identifies lessons learnt for future phases Staged ‘gate reviews’
  • 22. PwC Project assurance – PwC tools ‘The 12 elements’ Lessons from the project front line 22 November 2015 12 elements of delivery excellenceEngaged stakeholders Clear scope Managed risks and opportunities Delivery- enabling plans Focussed benefits management High- performing teams Smart financing Integrated suppliers Agile change control Embedded life-cycle assurance and learningActive quality management Governance- enabling decision-making Governance and management Assesses how the programme, as a whole, is being managed – by looking at the governance and decision- making arrangements; stakeholder and talent management, and how lessons are being learned Programme delivery This area examines how the programme is being delivered, looking at the plans and schedules, dependency logs, risk registers, change control processes, and how the business requirements are being met. It also assesses how well the overall benefits are being specified and measured Commercial and finance Reviews how the programme is being managed from a commercial and cost point of view. It assesses the capability to manage contractual arrangements with higher risks and how effective the reporting and the supply of financial information are
  • 23. PwC Lessons from the project front line 23 November 2015 PwC Summary
  • 24. PwC Lessons from the project front line Lessons from the project front line 24 November 2015 Project and programmes really are unique but transferable Don’t get lost in the detail – It’s not all just about the deliverables and products Good governance is really another way of saying good people (management) Project success is consistently linked to good governance By having a project assurance mind- set you can plan to deliver good governance and so ultimately project success What will now you do differently?
  • 25. PwC Thank you and please get in touch Lessons from the project front line 25 November 2015 Jenny Tuohy PwC | Programme/Project Manager M: 07808 799447 E: jenny.f.tuohy@uk.pwc.com
  • 26. This publication has been prepared for general guidance on matters of interest only, and does not constitute professional advice. You should not act upon the information contained in this publication without obtaining specific professional advice. No representation or warranty (express or implied) is given as to the accuracy or completeness of the information contained in this publication, and, to the extent permitted by law, PwC does not accept or assume any liability, responsibility or duty of care for any consequences of you or anyone else acting, or refraining to act, in reliance on the information contained in this publication or for any decision based on it. © 2015 PwC. All rights reserved. PwC refers to the PwC network and/or one or more of its member firms, each of which is a separate legal entity. Please see www.pwc.com/structure for further details. 151021-160021-JT-OS