Project Integration
Management
PMP Preparation Course
March – April 2015
Session 3
by Andrey Mikityuk
Head of Project Management Team
Credit Suisse Moscow
Overview
Initiating Planning Executing Monitoring
and
Controlling
Closing
Develop
Project
Charter
Develop
Project
Management
Plan
Direct and
Manage
Project Work
Monitor and
Control
Project Work
Perform
Integrated
Change
Control
Close Project
or Phase
Integration Management – balancing all knowledge areas with each
other
Develop Project Charter
Develop
Project
Charter
Inputs
1. Project Statement
of Work
2. Business Case
3. Agreements
4. Enterprise
Environmental
Factors
5. Organizational
Process Assets
Outputs
1. Project Charter
Tools and
Techniques
1. Expert Judgment
2. Facilitation
Techniques
• Business need
• Product Scope
Description
• Strategic Plan
• Business
need
• Cost/Benefit
Analysis
Contracts,
memorandums,
letters of intent,
verbal, email, etc.
• Government
standards
• Organizational
culture
• Marketplace
conditions
• Standards, policies,
procedures
• Templates
• Historical
information and
lessons learned
• Brainstorming
• Conflict resolution
• Problem solving
• Meeting
management
Business Case
Fundamentals
 every project should have a business case
 project is selected only based on sound business case (no “management discretionary”
projects)
 project manger should be assigned as early as feasible (prior to start of planning), and
understands the business case and reason for project selection
Business case is important – it affects decision-making
Project can be initiated as a result of:
 Market demand
 Organizational need (e.g., reduce costs)
 Customer request
 Technological advance
 Legal requirement
 Ecological impacts
 Social need
Project Charter
 Project Name and Description
 Project Sponsor(s)
 Business Case, Objectives and Success Criteria
 Project manager and his authority
 Pre-assigned resources
 High-level requirements
 Summary milestone schedule
 High-level budget
 High-level risks
 Assumptions and constraints
 Known stakeholders
 Project approval requirements (who approves what)
Project charter
defines
project
boundaries
Project Selection
Benefit measurement models
(comparative approach)
• Murder board
• Peer review
• Scoring model
• Economic models
• Present Value (PV)
• Net Present Value (NPV)
• Internal Rate of Return
(IRR)
• Payback period
• Cost-Benefit ratio
• Economic Value Added
(EVA)
Constrained optimization
methods (mathematical approach)
• Linear programming
• Integer programming
• Dynamic programming
• Multi-objective programming
Methods
Image from John E. A. Bertram’s article “Constrained optimization in human walking: cost minimization and gait plasticity”
http://jeb.biologists.org/content/208/6/979.figures-only
IRR formal definition: rate at which
NPV = 0
Simple: rate which your project
returns if you treat it as investment
Economic Models
You may be asked to calculate PV and cost/benefit; for others just
understand the idea
Payback period – number of
periods (years / months) to
return invested money (also:
break-even point)
Cost-Benefit ratio =
Benefit (Revenue) / Cost
Remember: revenue, not profit
Economic Value Added (EVA)
= Net Operating Profit After
Taxes – Cost of Capital
Return of Investment =
(revenue – cost) / cost (simple)
Total Cost of Ownership (TCO) –
cost including non-project costs
(operational)
Few More Economic
Concepts
 Opportunity Cost
 Sunk Costs
 Law of Diminishing Returns
 Working Capital
 Depreciation
◦ Straight-line depreciation
◦ Accelerated depreciation
Develop Project Management
Plan
Develop
Project
Management
Plan
Inputs
1. Project Charter
2. Outputs from other
processes
3. Enterprise
Environmental
Factors
4. Organizational
Process Assets
Outputs
1. Project
Management Plan
Tools and
Techniques
1. Expert Judgment
2. Facilitation
Techniques
• Governmental or
industry
standards
• PM practices for
the industry (e.g.
construction or
software
development)
• PMIS
• Organizational
structure, culture,
management
practices
• Infrastructure
(existing facilities
and capital
equipment)
• Staff
management
practices
(hiring/firing,
performance
reviews, etc)
• Standardized guidelines
• Project Management plan template
• Guideline for tailoring
• Project closure guidelines (validation and
acceptance criteria)
• Change control procedures
• Project files from previous projects
• Historical information and lessons learned
• Configuration management knowledge base (versions
and baselines of all standards and policies)
• Tailor the process
• Develop technical details
• Determine resources and skills
needed
• Define level of configuration
management
• Determine which projects will be
subject for change control
• Set priorities
Project Management Plan
Management Plans
 Change MP
 Configuration MP
 Scope MP
 Requirements MP
 Schedule MP
 Cost MP
 Quality MP
 Process Improvement plan
 Human Resource MP
 Communications MP
 Risk MP
 Procurement MP
 Stakeholder MP
Baselines
 Scope
 Schedule
 Cost
Other
 Life Cycle of the project
 Details of tailoring decisions
 How integrity of project
baselines will be maintained
Knowledge Area
Integration
Scope
Schedule
Cost
Quality
Human Resource
Communications
Risk
Procurement
Stakeholder
performance
measurement
baseline
Good project plan is…
 Iterative and non-contradictory
 Consistent with PMO guidelines
 Validated with program/portfolio managers
 Impact from/to other projects incorporated
 Has inputs from all internal stakeholders, including:
◦ Team members
◦ Resource managers
◦ Sponsor
 Has buy-in (approved)
 Realistic (everybody believe it can be met)
Don’t forget kick-off meeting which finalizes planning process!
Direct and Manage Project
Work
Direct and
Manage
Project Work
Inputs
1. Project
Management Plan
2. Approved Change
Requests
3. Enterprise
Environmental
Factors
4. Organizational
Process Assets
Outputs
1. Deliverables
2. Work performance
data
3. Change requests
4. Project
management plan
updates
5. Project documents
updatesTools and
Techniques
1. Expert Judgment
2. Project
Management
Information
System (PMIS)
3. Meetings
• Organizational,
company or
customer culture
• Infrastructure
(existing
facilities and
capital
equipment)
• Staff
administration
• Stakeholder risk
tolerances
• PMIS
• Standardized guidelines and work
instructions
• Communication requirements (allowed
communication media, record retention and
security requirements)
• Issue and defect management procedures
• Process measurement database
• Project files from previous project
• Issue and defect management databases
• Corrective actions
• Preventive
actions
• Defect repairs
• Information exchange
• Brainstorming, options
evaluation or design
• Decision making
Examples: requirements,
project logs, risk register,
stakeholder register
Monitor and Control Project
Work
Monitor and
Control
Project Work
Inputs
1. Project Management
Plan
2. Schedule forecasts
3. Cost forecasts
4. Validated changes
5. Work performance
information
6. Enterprise
Environmental Factors
7. Organizational
Process Assets
Outputs
1. Change requests
2. Work performance
reports
3. Project
management plan
updates
4. Project documents
updates
Tools and
Techniques
1. Expert judgment
2. Analytical
techniques
3. Project
management
information system
4. Meetings
• SV (schedule
variance),
• SPI (schedule
performance
index)
• Regression analysis
• Grouping methods
• Causal analysis
• Root cause analysis
• Forecasting methods
• Failure mode and effect analysis
(FMEA)
• Fault tree analysis (FTA)
• Reserve analysis
• Trend analysis
• Earned value management
• Variance analysis
Status reports, memos,
justifications, information
notes, recommendations
and updates
• CV (cost
variance),
• CPI (cost
performance
index)
• Governmental
or industry
standards
• Work
authorization
system
• Stakeholder
risk tolerance
• PMIS • Organizational communication
requirements
• Financial control procedures (time
reporting, expenditure reviews, etc.)
• Issue and defect management
procedures
• Change control procedures
• Risk control procedures
• Process measurement database
• Lessons learned database
• Corrective actions
• Preventive
actions
• Defect repairs
Actions in Monitor and Control
project Work
 Compare actual performance against the project
management plan
 Assess performance to determine if any
corrective or preventive actions are needed
 Identify new risks and track existing
 Maintain an accurate, timely information base
concerning the project’s products
 Provide information to support status reporting
 Provide forecasts to update current
cost/schedule information
 Monitor implementation of approved changes
 Provide appropriate reporting of project status to
program management
Change requests
Preventive actions
(prevent anticipated
problem)
Corrective actions
(problem already
occurred)
Defect Repairs
(defect in deliverable)
All changes should pass change control process before implementation.
Good project manager:
• Has realistic and up-to-date plans and baselines
• Creates metrics which cover all aspects of the project
• Continuously tracks project performance against baselines
• Systematic, not randomly focused on different areas
• Proactively looks out for problems
• Looks for a root cause of a problem before proposing action
• Evaluates effectiveness of proposed actions
Perform Integrated Change
Control
Perform
Integrated
Change
Control
Inputs
1. Project
Management Plan
2. Work performance
Reports
3. Change requests
4. Enterprise
Environmental
Factors
5. Organizational
Process Assets
Outputs
1. Approved change
requests
2. Change log
3. Project
management plan
updates
4. Project documents
updates
Tools and
Techniques
1. Expert Judgment
2. Meetings
3. Change control
tools
• PMIS
• Change control procedures
• Process measurement documents
• Project documents
• Configuration management knowledge base
• Change
management plan
• Baselines (scope,
schedule, cost)
Change control meetings
• Resource
availability
• Schedule and
cost data
• EVM reports
• Burnup or
burndown
charts
Change life cycle
Direct and
Manage
Project
Work
Monitor and
Control
Project Work
Perform
Integrated
Change
Control
New
Status of the
change
Created
Create formal
change
request
Approved
Rejected
Update the
change log
Update the
change log
Update PM plan
and project
documents
1. Assess the change
• against Project Charter (is it part of the project at
all?)
• against Risk log (check if it change is a result of
materialized risk, and has reserves for it already)
2. Assess impact
• within knowledge area
• on all other project constraints
3. Identify options
4. Approve/Reject the change (as defined in
Change MP)
• Project manager
• Change Control Board (CCB)
• Customer (if needed)
As part of Integrated Change Control you also should:
• Prevent the root cause of changes
• Manage stakeholders’ expectations by communicating statuses of changes
Configuration management
Configuration Management (CM) is another part of Perform
Integrated Change Control process
What is that all about?
• Problem occurred
because “wrong
version of something”
have been used
• Team members don’t
know where to look
for actual versions of
documents
• Lack of control for
changes
Step 1. Configuration identification
Which deliverables needs to be versioned /
controlled?
Step 2. Configuration status accounting
What are the current versions of all
deliverables?
What are the open change requests?
Step 3. Configuration verification and
audit
Independent review to establish compliance
Close Project or Phase
Close
Project or
Phase
Inputs
1. Project
Management Plan
2. Accepted
deliverables
3. Organizational
Process Assets
Outputs
1. Final product,
service or result
transition
2. Organizational
process assets
updates
Tools and
Techniques
1. Expert Judgment
2. Analytical
techniques
3. Meetings
• Closure
guidelines or
requirements
• Historical
information and
lessons learned
• Regression analysis
• Trend analysis
Can include partial
or interim
deliverables for
phased or
cancelled projects
• Project files
• Project or phase
closure documents
• Historical information
Actions during project closure
Confirm work is done to requirements
Complete procurements closure (another knowledge area!)
Gain final acceptance of the product
Complete financial closure
Hand off completed product
Solicit feedback from the customer about the project
Complete final performance reporting
Index and archive records
Gather final lessons learned and update knowledge base

More Related Content

PDF
Fundamentals of project management
PPT
project management concepts
PPTX
Project Cost Management - PMBOK6
PPTX
Project management process and Project Management Knowledge areas
PDF
Project Management Concepts
PPTX
Project integration management
PPTX
Smart project management - Best Practices to Manage Project effectively
PPT
2.project lifecycle
Fundamentals of project management
project management concepts
Project Cost Management - PMBOK6
Project management process and Project Management Knowledge areas
Project Management Concepts
Project integration management
Smart project management - Best Practices to Manage Project effectively
2.project lifecycle

What's hot (20)

PPT
Project Time Management
PPTX
Project management
PPT
WBS presentation
PDF
PMP Chap 5 - Project Scope Management - Part1
PDF
Chap 4.0 Project integration management Overview
PPT
Project Management
PPTX
Project management
PDF
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PPTX
2. project initiation
PDF
Project quality management
PPT
06. Project Management Process Groups
PDF
PMP_Project Cost Management
PPT
05 project scope management
PPTX
PMP-Cost Management area
PDF
Project cost management
PPTX
Project Management Steps
PPT
Project Management PPT
PDF
PMP PMBOK 6th
PDF
PMP ITTOs Quick Review
PDF
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
Project Time Management
Project management
WBS presentation
PMP Chap 5 - Project Scope Management - Part1
Chap 4.0 Project integration management Overview
Project Management
Project management
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
2. project initiation
Project quality management
06. Project Management Process Groups
PMP_Project Cost Management
05 project scope management
PMP-Cost Management area
Project cost management
Project Management Steps
Project Management PPT
PMP PMBOK 6th
PMP ITTOs Quick Review
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
Ad

Viewers also liked (20)

PPTX
PMP Preparation 2 - Processes
PPTX
PMP Preparation 1 - Framework
PPTX
Pmp inititating process group
PDF
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
PPT
PMP Flash Card
PDF
Dr. Hector Upegui, Is there a new momentum for disability management? A refle...
PDF
We Trained You Why Didnt You Learn A Case Study In Change Management
PPT
PMI-PBA 商業分析讀書會 20150725
PDF
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
PPTX
10 me667 chap2 project management
PDF
Pmbok 5cartulinas
PPSX
Pmp pmbok 5 updates vs pmbok 4
PPTX
Pm training 1 18
PPT
Chap04 project integration management
PPT
Rohit demo sap ps_module_training
PDF
PMBOOK 5
PPTX
Project management
PPT
PMI Long Island Chapter
PPSX
Project Closing Process
PMP Preparation 2 - Processes
PMP Preparation 1 - Framework
Pmp inititating process group
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
PMP Flash Card
Dr. Hector Upegui, Is there a new momentum for disability management? A refle...
We Trained You Why Didnt You Learn A Case Study In Change Management
PMI-PBA 商業分析讀書會 20150725
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
10 me667 chap2 project management
Pmbok 5cartulinas
Pmp pmbok 5 updates vs pmbok 4
Pm training 1 18
Chap04 project integration management
Rohit demo sap ps_module_training
PMBOOK 5
Project management
PMI Long Island Chapter
Project Closing Process
Ad

Similar to PMP Prep 3 - Project Integration Management (20)

PPTX
04 projectintegrationmanagement
PDF
04.integration management updated
PDF
L1-Project Integration Management.pdf
PPTX
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
PDF
PMP integration review
PDF
PMI Project Management fundamentos basicos
PPTX
PMP Training - 04 project integration management
PPTX
PPT1-PROJECT-_-Project-Management.pptx
PPTX
1. Introduction to Project Management and the Project Management Framework
PPTX
PMI Project Management Principles
PPTX
B-PMP Preparation Course, April09 - Ch 04 - Integration&Professional-v3.pptx
PPTX
CAPM Exam preparation - series 1
PPTX
Introduction to Project Management (workshop) - v.1
PPTX
Lecture 27 Projects (03-11-20).pptx
PPTX
theorycccccccccccccccccccccccccccccccccccccccccccc
PPT
PmiprojectmanagementprinciplesAmit Payal
PPTX
Session 21 4th edition PMP
PPTX
An Introduction to Project Management
PPTX
A-PMP Preparation Course, 0905 - Ch 1,2,3 - Framework-v2.pptx
PPT
6396901
04 projectintegrationmanagement
04.integration management updated
L1-Project Integration Management.pdf
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
PMP integration review
PMI Project Management fundamentos basicos
PMP Training - 04 project integration management
PPT1-PROJECT-_-Project-Management.pptx
1. Introduction to Project Management and the Project Management Framework
PMI Project Management Principles
B-PMP Preparation Course, April09 - Ch 04 - Integration&Professional-v3.pptx
CAPM Exam preparation - series 1
Introduction to Project Management (workshop) - v.1
Lecture 27 Projects (03-11-20).pptx
theorycccccccccccccccccccccccccccccccccccccccccccc
PmiprojectmanagementprinciplesAmit Payal
Session 21 4th edition PMP
An Introduction to Project Management
A-PMP Preparation Course, 0905 - Ch 1,2,3 - Framework-v2.pptx
6396901

Recently uploaded (20)

PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PPTX
Lecture (1)-Introduction.pptx business communication
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PDF
WRN_Investor_Presentation_August 2025.pdf
PDF
Roadmap Map-digital Banking feature MB,IB,AB
PDF
Laughter Yoga Basic Learning Workshop Manual
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PDF
Unit 1 Cost Accounting - Cost sheet
PPT
Data mining for business intelligence ch04 sharda
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PDF
COST SHEET- Tender and Quotation unit 2.pdf
DOCX
Business Management - unit 1 and 2
PDF
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
PPTX
HR Introduction Slide (1).pptx on hr intro
PDF
Business model innovation report 2022.pdf
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PDF
Deliverable file - Regulatory guideline analysis.pdf
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
ICG2025_ICG 6th steering committee 30-8-24.pptx
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
Lecture (1)-Introduction.pptx business communication
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
WRN_Investor_Presentation_August 2025.pdf
Roadmap Map-digital Banking feature MB,IB,AB
Laughter Yoga Basic Learning Workshop Manual
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
Unit 1 Cost Accounting - Cost sheet
Data mining for business intelligence ch04 sharda
340036916-American-Literature-Literary-Period-Overview.ppt
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
COST SHEET- Tender and Quotation unit 2.pdf
Business Management - unit 1 and 2
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
HR Introduction Slide (1).pptx on hr intro
Business model innovation report 2022.pdf
Power and position in leadershipDOC-20250808-WA0011..pdf
Deliverable file - Regulatory guideline analysis.pdf
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise

PMP Prep 3 - Project Integration Management

  • 1. Project Integration Management PMP Preparation Course March – April 2015 Session 3 by Andrey Mikityuk Head of Project Management Team Credit Suisse Moscow
  • 2. Overview Initiating Planning Executing Monitoring and Controlling Closing Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase Integration Management – balancing all knowledge areas with each other
  • 3. Develop Project Charter Develop Project Charter Inputs 1. Project Statement of Work 2. Business Case 3. Agreements 4. Enterprise Environmental Factors 5. Organizational Process Assets Outputs 1. Project Charter Tools and Techniques 1. Expert Judgment 2. Facilitation Techniques • Business need • Product Scope Description • Strategic Plan • Business need • Cost/Benefit Analysis Contracts, memorandums, letters of intent, verbal, email, etc. • Government standards • Organizational culture • Marketplace conditions • Standards, policies, procedures • Templates • Historical information and lessons learned • Brainstorming • Conflict resolution • Problem solving • Meeting management
  • 4. Business Case Fundamentals  every project should have a business case  project is selected only based on sound business case (no “management discretionary” projects)  project manger should be assigned as early as feasible (prior to start of planning), and understands the business case and reason for project selection Business case is important – it affects decision-making Project can be initiated as a result of:  Market demand  Organizational need (e.g., reduce costs)  Customer request  Technological advance  Legal requirement  Ecological impacts  Social need
  • 5. Project Charter  Project Name and Description  Project Sponsor(s)  Business Case, Objectives and Success Criteria  Project manager and his authority  Pre-assigned resources  High-level requirements  Summary milestone schedule  High-level budget  High-level risks  Assumptions and constraints  Known stakeholders  Project approval requirements (who approves what) Project charter defines project boundaries
  • 6. Project Selection Benefit measurement models (comparative approach) • Murder board • Peer review • Scoring model • Economic models • Present Value (PV) • Net Present Value (NPV) • Internal Rate of Return (IRR) • Payback period • Cost-Benefit ratio • Economic Value Added (EVA) Constrained optimization methods (mathematical approach) • Linear programming • Integer programming • Dynamic programming • Multi-objective programming Methods Image from John E. A. Bertram’s article “Constrained optimization in human walking: cost minimization and gait plasticity” http://jeb.biologists.org/content/208/6/979.figures-only
  • 7. IRR formal definition: rate at which NPV = 0 Simple: rate which your project returns if you treat it as investment Economic Models You may be asked to calculate PV and cost/benefit; for others just understand the idea Payback period – number of periods (years / months) to return invested money (also: break-even point) Cost-Benefit ratio = Benefit (Revenue) / Cost Remember: revenue, not profit Economic Value Added (EVA) = Net Operating Profit After Taxes – Cost of Capital Return of Investment = (revenue – cost) / cost (simple) Total Cost of Ownership (TCO) – cost including non-project costs (operational)
  • 8. Few More Economic Concepts  Opportunity Cost  Sunk Costs  Law of Diminishing Returns  Working Capital  Depreciation ◦ Straight-line depreciation ◦ Accelerated depreciation
  • 9. Develop Project Management Plan Develop Project Management Plan Inputs 1. Project Charter 2. Outputs from other processes 3. Enterprise Environmental Factors 4. Organizational Process Assets Outputs 1. Project Management Plan Tools and Techniques 1. Expert Judgment 2. Facilitation Techniques • Governmental or industry standards • PM practices for the industry (e.g. construction or software development) • PMIS • Organizational structure, culture, management practices • Infrastructure (existing facilities and capital equipment) • Staff management practices (hiring/firing, performance reviews, etc) • Standardized guidelines • Project Management plan template • Guideline for tailoring • Project closure guidelines (validation and acceptance criteria) • Change control procedures • Project files from previous projects • Historical information and lessons learned • Configuration management knowledge base (versions and baselines of all standards and policies) • Tailor the process • Develop technical details • Determine resources and skills needed • Define level of configuration management • Determine which projects will be subject for change control • Set priorities
  • 10. Project Management Plan Management Plans  Change MP  Configuration MP  Scope MP  Requirements MP  Schedule MP  Cost MP  Quality MP  Process Improvement plan  Human Resource MP  Communications MP  Risk MP  Procurement MP  Stakeholder MP Baselines  Scope  Schedule  Cost Other  Life Cycle of the project  Details of tailoring decisions  How integrity of project baselines will be maintained Knowledge Area Integration Scope Schedule Cost Quality Human Resource Communications Risk Procurement Stakeholder performance measurement baseline
  • 11. Good project plan is…  Iterative and non-contradictory  Consistent with PMO guidelines  Validated with program/portfolio managers  Impact from/to other projects incorporated  Has inputs from all internal stakeholders, including: ◦ Team members ◦ Resource managers ◦ Sponsor  Has buy-in (approved)  Realistic (everybody believe it can be met) Don’t forget kick-off meeting which finalizes planning process!
  • 12. Direct and Manage Project Work Direct and Manage Project Work Inputs 1. Project Management Plan 2. Approved Change Requests 3. Enterprise Environmental Factors 4. Organizational Process Assets Outputs 1. Deliverables 2. Work performance data 3. Change requests 4. Project management plan updates 5. Project documents updatesTools and Techniques 1. Expert Judgment 2. Project Management Information System (PMIS) 3. Meetings • Organizational, company or customer culture • Infrastructure (existing facilities and capital equipment) • Staff administration • Stakeholder risk tolerances • PMIS • Standardized guidelines and work instructions • Communication requirements (allowed communication media, record retention and security requirements) • Issue and defect management procedures • Process measurement database • Project files from previous project • Issue and defect management databases • Corrective actions • Preventive actions • Defect repairs • Information exchange • Brainstorming, options evaluation or design • Decision making Examples: requirements, project logs, risk register, stakeholder register
  • 13. Monitor and Control Project Work Monitor and Control Project Work Inputs 1. Project Management Plan 2. Schedule forecasts 3. Cost forecasts 4. Validated changes 5. Work performance information 6. Enterprise Environmental Factors 7. Organizational Process Assets Outputs 1. Change requests 2. Work performance reports 3. Project management plan updates 4. Project documents updates Tools and Techniques 1. Expert judgment 2. Analytical techniques 3. Project management information system 4. Meetings • SV (schedule variance), • SPI (schedule performance index) • Regression analysis • Grouping methods • Causal analysis • Root cause analysis • Forecasting methods • Failure mode and effect analysis (FMEA) • Fault tree analysis (FTA) • Reserve analysis • Trend analysis • Earned value management • Variance analysis Status reports, memos, justifications, information notes, recommendations and updates • CV (cost variance), • CPI (cost performance index) • Governmental or industry standards • Work authorization system • Stakeholder risk tolerance • PMIS • Organizational communication requirements • Financial control procedures (time reporting, expenditure reviews, etc.) • Issue and defect management procedures • Change control procedures • Risk control procedures • Process measurement database • Lessons learned database • Corrective actions • Preventive actions • Defect repairs
  • 14. Actions in Monitor and Control project Work  Compare actual performance against the project management plan  Assess performance to determine if any corrective or preventive actions are needed  Identify new risks and track existing  Maintain an accurate, timely information base concerning the project’s products  Provide information to support status reporting  Provide forecasts to update current cost/schedule information  Monitor implementation of approved changes  Provide appropriate reporting of project status to program management
  • 15. Change requests Preventive actions (prevent anticipated problem) Corrective actions (problem already occurred) Defect Repairs (defect in deliverable) All changes should pass change control process before implementation. Good project manager: • Has realistic and up-to-date plans and baselines • Creates metrics which cover all aspects of the project • Continuously tracks project performance against baselines • Systematic, not randomly focused on different areas • Proactively looks out for problems • Looks for a root cause of a problem before proposing action • Evaluates effectiveness of proposed actions
  • 16. Perform Integrated Change Control Perform Integrated Change Control Inputs 1. Project Management Plan 2. Work performance Reports 3. Change requests 4. Enterprise Environmental Factors 5. Organizational Process Assets Outputs 1. Approved change requests 2. Change log 3. Project management plan updates 4. Project documents updates Tools and Techniques 1. Expert Judgment 2. Meetings 3. Change control tools • PMIS • Change control procedures • Process measurement documents • Project documents • Configuration management knowledge base • Change management plan • Baselines (scope, schedule, cost) Change control meetings • Resource availability • Schedule and cost data • EVM reports • Burnup or burndown charts
  • 17. Change life cycle Direct and Manage Project Work Monitor and Control Project Work Perform Integrated Change Control New Status of the change Created Create formal change request Approved Rejected Update the change log Update the change log Update PM plan and project documents 1. Assess the change • against Project Charter (is it part of the project at all?) • against Risk log (check if it change is a result of materialized risk, and has reserves for it already) 2. Assess impact • within knowledge area • on all other project constraints 3. Identify options 4. Approve/Reject the change (as defined in Change MP) • Project manager • Change Control Board (CCB) • Customer (if needed) As part of Integrated Change Control you also should: • Prevent the root cause of changes • Manage stakeholders’ expectations by communicating statuses of changes
  • 18. Configuration management Configuration Management (CM) is another part of Perform Integrated Change Control process What is that all about? • Problem occurred because “wrong version of something” have been used • Team members don’t know where to look for actual versions of documents • Lack of control for changes Step 1. Configuration identification Which deliverables needs to be versioned / controlled? Step 2. Configuration status accounting What are the current versions of all deliverables? What are the open change requests? Step 3. Configuration verification and audit Independent review to establish compliance
  • 19. Close Project or Phase Close Project or Phase Inputs 1. Project Management Plan 2. Accepted deliverables 3. Organizational Process Assets Outputs 1. Final product, service or result transition 2. Organizational process assets updates Tools and Techniques 1. Expert Judgment 2. Analytical techniques 3. Meetings • Closure guidelines or requirements • Historical information and lessons learned • Regression analysis • Trend analysis Can include partial or interim deliverables for phased or cancelled projects • Project files • Project or phase closure documents • Historical information
  • 20. Actions during project closure Confirm work is done to requirements Complete procurements closure (another knowledge area!) Gain final acceptance of the product Complete financial closure Hand off completed product Solicit feedback from the customer about the project Complete final performance reporting Index and archive records Gather final lessons learned and update knowledge base