Total System Value
Time Away


When analysing the major equipment in a mining sequence, time
away from an area is just as important as time spent on the task.
This time away allows for all other processes to occur that are
needed for pit turn around - eg:
 Coal mining current strip
 Parting mining current strip
 Drilling preparation next strip
 Drilling next strip
 Blasting next strip
 Etc




These processes usually cannot take place until the major
mining task is out of the area
As production increases in at a mine site by adding more
equipment that cannot work together in the same area, time
away is reduced at a greater rate then the increase in the
production rate
Time Away Example

Days
Pit A
Pit B
Pit C
Pit D

Lets look at a single dragline working in 4 pits:
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1

 Here the dragline spends 30 days in each pit
 So the dragline spends 90 days away from a pit for all other activities to

occur

Days
Pit A
Pit B
Pit C
Pit D

What happens if we double the rate of production out of
these four pits by adding another dragline:
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 2
Dragline 2
Dragline 2
Dragline 2
Dragline 2
Dragline 2
Dragline 2
Dragline 2

 The two draglines spend 30 days in a pit each, and only 30 days away
 The production out of the pit has doubled, but the time for other

processes to take place is only one third of what is was before – 30 days
Time Away Example Continued



Days
Pit A
Pit B
Pit C
Pit D

So what affect does this have on the processes that need to
occur while the dragline is away?
Lets say there are 3 processes that need to occur while the
dragline is away: Process X, Y, and Z
5 5 5 5 5
Dragline 1
Z Z Z Z Z
Y Y Y Y Y
X X X X X

5 5
X
Z
Y Z
X Y

5 5 5 5
X X X X
Dragline 1
Z Z Z Z
Y Y Y Y

5 5 5 5 5 5
X Y Y Y Y Y
X X X X X
Z
Dragline 1
Y Z Z Z Z Z

5 5 5 5 5 5
Y Z Z Z Z Z
X Y Y Y Y Y
X X X X X
Z
Dragline 1

5 5 5 5 5 5
Z
Dragline 1
Y Z Z Z Z Z
X Y Y Y Y Y
X X X X X

5 5
X
Z
Y Z
X Y

5 5 5 5
X X X X
Dragline 1
Z Z Z Z
Y Y Y Y

5 5 5 5 5 5
X Y Y Y Y Y
X X X X X
Z
Dragline 1
Y Z Z Z Z Z

Park up time

 Here processes X, Y and Z all have 30 days to complete their tasks and

there is no park up required

5 5 5 5 5 5
Y Z Z Z Z Z
X Y Y Y Y Y
X X X X X
Z
Dragline 1

5
Z
Y
X
Time Away Example Continued




From the previous Gantt Chart we can see that the time is
sufficient to allow the tasks to complete their required
activities
Here the task size dictates the process size requirement:
Time Away Example - Doubling
Production


Now with the second dragline included and one third of the
time, how do the additional processes look:

BEST CASE DRAGLINE SEQUENCE SCEANRIO:
Days
Pit A
Pit B
Pit C
Pit D

5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Dragline 1
X X Y Y Z Z
Dragline 1
X X Y Y Z Z
Dragline 1
X X Y Y Z Z
Dragline 1
X X Y Y Z Z
X X Y Y Z Z
Dragline 1
X X Y Y Z Z
Dragline 1
X X Y Y Z Z
Dragline 1
X X Y Y Z Z
Dragline 1
Y Z Z
Dragline 2
X X Y Y Z Z
Dragline 2
X X Y Y Z Z
Dragline 2
X X Y Y Z Z
Dragline 2
X X Y
X X Y Y Z Z
Dragline 2
X X Y Y Z Z
Dragline 2
X X Y Y Z Z
Dragline 2
X X Y Y Z Z

Park up time

Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X

 As Processes X, Y and Z require to complete the tasks in 1/3rd of the

time, they need 3 times the capacity. Their work load has only doubled,
but it is the time they have to complete their tasks that is determining the
rate they require
 The difference between the required rate and the new workload ends up
becoming park up time, here it is 1/3rd of the time
Time Away Example - Doubling
Production




The process requirements are now being dictated by the
time to complete the task rather then the size of the task
This leads to peak demands and park up time requirements
Time Away Example - Doubling
Production


With the additional dragline in the system, the timing
between the draglines also influences the demand on
processes X, Y and Z:

WORST CASE DRAGLINE SEQUENCE SCEANRIO:
Days
Pit A
Pit B
Pit C
Pit D

5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Dragline 1
X X Y Z
Dragline 1
X X Y Z
Dragline 1
X X Y Z
Dragline 1
X X Y Z
X X Y Z
Dragline 1
X X Y Z
Dragline 1
X X Y Z
Dragline 1
X X Y Z
Dragline 1
Dragline 2
X X Y Z
Dragline 2
X X Y Z
Dragline 2
X X Y Z
Dragline 2
X X Y Z
X X Y Z
Dragline 2
X X Y Z
Dragline 2
X X Y Z
Dragline 2
X X Y Z
Dragline 2

PARKED UP
PARKED UP
PARKED UP

X X
X X
X X
X X
X X
X X
X X
X X
Y Y
Y
Y Y Y
Y
Y Y Y
Y
Y Y Y
Y
Y Y Y
Y
Y Y Y
Y
Y Y Y
Y
Y Y Y
Y
Y
Z Z Z
Z
Z Z Z
Z
Z Z Z
Z
Z Z Z
Z
Z Z Z
Z
Z Z Z
Z
Z Z Z
Z
Z Z Z
Z

 In the worst case dragline sequence scenario, the peak demands and

park up times of process X, Y and Z have become more intense
 Process X has been kept at a requirement of 3 times the original, but
processes Y and Z now need to operate at 6 times the original
requirement, and are parked up 2/3rds of the time
Time Away Example - Doubling
Production


Here the time demand is being amplified due to the timing of
the dragline activities
Time Away





Days
Pit A
Pit B
Pit C
Pit D

From the previous example it can be seen that time away is heavily
affected when adding more processes into a system when trying to
increase production
Time away however will be the inverse of the increase in production if
the increase in production is done with the same number, but larger
processes:
One dragline in 4 pits:
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1
Dragline 1

 As before the time on task for the dragline is 30 days, and time away is 90 days


Days
Pit A
Pit B
Pit C
Pit D

One dragline in 4 pits with double the rate:
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Dragline 1

Dragline 1
Dragline 1

Dragline 1
Dragline 1

Dragline 1

Dragline 1
Dragline 1

Dragline 1
Dragline 1

Dragline 1
Dragline 1

Dragline 1

Dragline 1
Dragline 1

 Here the time on task for the dragline is 15 days, and the time away is 45 days
 The production has doubled and the time away has halved

Dragline 1
Time Away






The previous examples were done for a dragline, but the
principal is the same for any major operating equipment in
the system that cannot work together in the same area
If production doubles at a mine site, and if the equipment
doesn’t double in size and remain the same number or work
together in the same area, then the time away will end up
being affected, which will affect the other processes that
need to occur
What is happening here is that the other processes
requirement is not relying on the size of the task, but the time
it has to do it
Always customised – no two sites are
the same

Thank you

Total
System
Value

More Related Content

PDF
Tc&Tt
PDF
GDB tutorial
PPT
TuringSlashPython - Undergraduate Final Year Project
PPTX
Real-time Fluid Simulation in Shadow of the Tomb Raider
PPTX
TSV Mining: Variation outside of planning, contingency, inventory and intensity
DOCX
CV Faizan 17.12.16
PPTX
TSV Mining: Variation Analysis in Mining Part 1 - Precision and Accuracy
DOCX
Mining Cost Cutting Cycle and the ways to Avoid the Traps
Tc&Tt
GDB tutorial
TuringSlashPython - Undergraduate Final Year Project
Real-time Fluid Simulation in Shadow of the Tomb Raider
TSV Mining: Variation outside of planning, contingency, inventory and intensity
CV Faizan 17.12.16
TSV Mining: Variation Analysis in Mining Part 1 - Precision and Accuracy
Mining Cost Cutting Cycle and the ways to Avoid the Traps

Viewers also liked (16)

PDF
Cara daftar Forex di FBS.com
PDF
A fully packaged geek is all you need to be truly agile!
PDF
Tutorial fbs meta trader4
PPTX
The Future of Technology in 2023 A.D.
PPTX
Escuelas y precursores
PDF
Swimming pool equipments
PPTX
Grupo m.01 andreu,bori,sedes el ray
PPTX
TSV Mining: Overburden fleet analysis, overstating benefits and statistical i...
PPTX
Marketing and social media campaigns. (Old Spice)
PPTX
TSV Mining: Critical density in mining and changes to sustainable low cost pr...
PPTX
Green technology
PPTX
Industrial visit to samsonite, Nashik
PPT
Whirlpool
PPTX
Handwritten character recognition using artificial neural network
PDF
SIRIUSの教科書サンプル
PDF
Momotarou
Cara daftar Forex di FBS.com
A fully packaged geek is all you need to be truly agile!
Tutorial fbs meta trader4
The Future of Technology in 2023 A.D.
Escuelas y precursores
Swimming pool equipments
Grupo m.01 andreu,bori,sedes el ray
TSV Mining: Overburden fleet analysis, overstating benefits and statistical i...
Marketing and social media campaigns. (Old Spice)
TSV Mining: Critical density in mining and changes to sustainable low cost pr...
Green technology
Industrial visit to samsonite, Nashik
Whirlpool
Handwritten character recognition using artificial neural network
SIRIUSの教科書サンプル
Momotarou
Ad

Similar to Equipment 'Time Away Theory' in the opencut coal mining industry (20)

PPTX
Pert and mbo
PPT
Process Selection and Facility layout.ppt
DOCX
Chapters 15 & 16Short Term Scheduling & KanbanThe 3-18 m.docx
PPT
Tn6 facility+layout
PPT
Tn6 facility layout
PPT
Program Evaluation and Review Technique
PPT
Mba ii pmom_unit-1.4 process design, analysis & selection a
PDF
Process dsign and facility layout
PPTX
Operation engine ii session iv operations scheduling
PPTX
Scheduling
PDF
Pre-Post Analysis on Multi-Skill Development using Flow Line Data at Expressw...
PPTX
Process selection and Facility Layout Session 3 (1).pptx
PPT
Ch5 process analysis
PPT
Ch5 process+analysis
PPT
Production And Operation Materials
PPT
Production And Operation Materials
PDF
ITFT - PROJECT MANAGEMENT
PPTX
Assembly line balancing
PPT
S pert cpm
PPT
MA1.ppt
Pert and mbo
Process Selection and Facility layout.ppt
Chapters 15 & 16Short Term Scheduling & KanbanThe 3-18 m.docx
Tn6 facility+layout
Tn6 facility layout
Program Evaluation and Review Technique
Mba ii pmom_unit-1.4 process design, analysis & selection a
Process dsign and facility layout
Operation engine ii session iv operations scheduling
Scheduling
Pre-Post Analysis on Multi-Skill Development using Flow Line Data at Expressw...
Process selection and Facility Layout Session 3 (1).pptx
Ch5 process analysis
Ch5 process+analysis
Production And Operation Materials
Production And Operation Materials
ITFT - PROJECT MANAGEMENT
Assembly line balancing
S pert cpm
MA1.ppt
Ad

Recently uploaded (20)

PPT
Data mining for business intelligence ch04 sharda
PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
DOCX
Business Management - unit 1 and 2
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PDF
How to Get Business Funding for Small Business Fast
PPT
Chapter four Project-Preparation material
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PPTX
Amazon (Business Studies) management studies
PDF
Business model innovation report 2022.pdf
PDF
Chapter 5_Foreign Exchange Market in .pdf
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PPTX
Probability Distribution, binomial distribution, poisson distribution
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
PDF
Roadmap Map-digital Banking feature MB,IB,AB
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PDF
A Brief Introduction About Julia Allison
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
How to Get Funding for Your Trucking Business
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PPTX
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
Data mining for business intelligence ch04 sharda
New Microsoft PowerPoint Presentation - Copy.pptx
Business Management - unit 1 and 2
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
How to Get Business Funding for Small Business Fast
Chapter four Project-Preparation material
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
Amazon (Business Studies) management studies
Business model innovation report 2022.pdf
Chapter 5_Foreign Exchange Market in .pdf
Power and position in leadershipDOC-20250808-WA0011..pdf
Probability Distribution, binomial distribution, poisson distribution
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
Roadmap Map-digital Banking feature MB,IB,AB
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
A Brief Introduction About Julia Allison
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
How to Get Funding for Your Trucking Business
COST SHEET- Tender and Quotation unit 2.pdf
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...

Equipment 'Time Away Theory' in the opencut coal mining industry

  • 1. Presented by: Christopher Braund Director TSV Mining Pty Ltd M: +61 438 886 473 cbraund@tsvmining.com.au www.tsvmining.com.au Total System Value
  • 2. Time Away  When analysing the major equipment in a mining sequence, time away from an area is just as important as time spent on the task. This time away allows for all other processes to occur that are needed for pit turn around - eg:  Coal mining current strip  Parting mining current strip  Drilling preparation next strip  Drilling next strip  Blasting next strip  Etc   These processes usually cannot take place until the major mining task is out of the area As production increases in at a mine site by adding more equipment that cannot work together in the same area, time away is reduced at a greater rate then the increase in the production rate
  • 3. Time Away Example  Days Pit A Pit B Pit C Pit D Lets look at a single dragline working in 4 pits: 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1  Here the dragline spends 30 days in each pit  So the dragline spends 90 days away from a pit for all other activities to occur  Days Pit A Pit B Pit C Pit D What happens if we double the rate of production out of these four pits by adding another dragline: 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 2 Dragline 2 Dragline 2 Dragline 2 Dragline 2 Dragline 2 Dragline 2 Dragline 2  The two draglines spend 30 days in a pit each, and only 30 days away  The production out of the pit has doubled, but the time for other processes to take place is only one third of what is was before – 30 days
  • 4. Time Away Example Continued   Days Pit A Pit B Pit C Pit D So what affect does this have on the processes that need to occur while the dragline is away? Lets say there are 3 processes that need to occur while the dragline is away: Process X, Y, and Z 5 5 5 5 5 Dragline 1 Z Z Z Z Z Y Y Y Y Y X X X X X 5 5 X Z Y Z X Y 5 5 5 5 X X X X Dragline 1 Z Z Z Z Y Y Y Y 5 5 5 5 5 5 X Y Y Y Y Y X X X X X Z Dragline 1 Y Z Z Z Z Z 5 5 5 5 5 5 Y Z Z Z Z Z X Y Y Y Y Y X X X X X Z Dragline 1 5 5 5 5 5 5 Z Dragline 1 Y Z Z Z Z Z X Y Y Y Y Y X X X X X 5 5 X Z Y Z X Y 5 5 5 5 X X X X Dragline 1 Z Z Z Z Y Y Y Y 5 5 5 5 5 5 X Y Y Y Y Y X X X X X Z Dragline 1 Y Z Z Z Z Z Park up time  Here processes X, Y and Z all have 30 days to complete their tasks and there is no park up required 5 5 5 5 5 5 Y Z Z Z Z Z X Y Y Y Y Y X X X X X Z Dragline 1 5 Z Y X
  • 5. Time Away Example Continued   From the previous Gantt Chart we can see that the time is sufficient to allow the tasks to complete their required activities Here the task size dictates the process size requirement:
  • 6. Time Away Example - Doubling Production  Now with the second dragline included and one third of the time, how do the additional processes look: BEST CASE DRAGLINE SEQUENCE SCEANRIO: Days Pit A Pit B Pit C Pit D 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 Dragline 1 X X Y Y Z Z Dragline 1 X X Y Y Z Z Dragline 1 X X Y Y Z Z Dragline 1 X X Y Y Z Z X X Y Y Z Z Dragline 1 X X Y Y Z Z Dragline 1 X X Y Y Z Z Dragline 1 X X Y Y Z Z Dragline 1 Y Z Z Dragline 2 X X Y Y Z Z Dragline 2 X X Y Y Z Z Dragline 2 X X Y Y Z Z Dragline 2 X X Y X X Y Y Z Z Dragline 2 X X Y Y Z Z Dragline 2 X X Y Y Z Z Dragline 2 X X Y Y Z Z Park up time Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X Z Y X  As Processes X, Y and Z require to complete the tasks in 1/3rd of the time, they need 3 times the capacity. Their work load has only doubled, but it is the time they have to complete their tasks that is determining the rate they require  The difference between the required rate and the new workload ends up becoming park up time, here it is 1/3rd of the time
  • 7. Time Away Example - Doubling Production   The process requirements are now being dictated by the time to complete the task rather then the size of the task This leads to peak demands and park up time requirements
  • 8. Time Away Example - Doubling Production  With the additional dragline in the system, the timing between the draglines also influences the demand on processes X, Y and Z: WORST CASE DRAGLINE SEQUENCE SCEANRIO: Days Pit A Pit B Pit C Pit D 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 Dragline 1 X X Y Z Dragline 1 X X Y Z Dragline 1 X X Y Z Dragline 1 X X Y Z X X Y Z Dragline 1 X X Y Z Dragline 1 X X Y Z Dragline 1 X X Y Z Dragline 1 Dragline 2 X X Y Z Dragline 2 X X Y Z Dragline 2 X X Y Z Dragline 2 X X Y Z X X Y Z Dragline 2 X X Y Z Dragline 2 X X Y Z Dragline 2 X X Y Z Dragline 2 PARKED UP PARKED UP PARKED UP X X X X X X X X X X X X X X X X Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z  In the worst case dragline sequence scenario, the peak demands and park up times of process X, Y and Z have become more intense  Process X has been kept at a requirement of 3 times the original, but processes Y and Z now need to operate at 6 times the original requirement, and are parked up 2/3rds of the time
  • 9. Time Away Example - Doubling Production  Here the time demand is being amplified due to the timing of the dragline activities
  • 10. Time Away    Days Pit A Pit B Pit C Pit D From the previous example it can be seen that time away is heavily affected when adding more processes into a system when trying to increase production Time away however will be the inverse of the increase in production if the increase in production is done with the same number, but larger processes: One dragline in 4 pits: 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1  As before the time on task for the dragline is 30 days, and time away is 90 days  Days Pit A Pit B Pit C Pit D One dragline in 4 pits with double the rate: 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1 Dragline 1  Here the time on task for the dragline is 15 days, and the time away is 45 days  The production has doubled and the time away has halved Dragline 1
  • 11. Time Away    The previous examples were done for a dragline, but the principal is the same for any major operating equipment in the system that cannot work together in the same area If production doubles at a mine site, and if the equipment doesn’t double in size and remain the same number or work together in the same area, then the time away will end up being affected, which will affect the other processes that need to occur What is happening here is that the other processes requirement is not relying on the size of the task, but the time it has to do it
  • 12. Always customised – no two sites are the same Thank you Total System Value