SlideShare a Scribd company logo
3
Most read
6
Most read
8
Most read
Prolongation cost calculation
RRGS BANDARA
Once a Contractor has secured an
extension of time and relief from liquidated
damages, thoughts will quickly turn to
recovery of the costs incurred due to the
delayed completion date – i.e.
“Prolongation Costs”.
If you ask an Employer’s QS how such
costs should be determined the answer is
often an unequivocal statement that the
rates and prices from the Preliminaries
BOQ shall be divided by the original
contract duration and the derived daily rate
for preliminaries shall then be applied to
the extended duration.
The sharp witted Employer’s QS may even refine this
logic with the caveat that the BOQ rates and prices
should first be adjusted to remove fixed costs,
mobilization and demobilization costs, overheads and
profit.
Whilst both answers are quite wrong, these
approaches are often used in order to achieve result,
despite the inaccurate answer. The problem is that
neither approach attempts to address the underlying
question of what costs / losses were actually incurred
by the Contractor as a consequence of the delaying
events for which the Employer was responsible.
The answer to this question cannot be found
in the BOQ, but can (and should) be found in
a detailed analysis of the Contractor’s cost
records The express wording of the contract
will dictate which heads of claim are
admissible, but in general terms an accurate
understanding of Prolongation Cost
entitlement can be derived by application of
the following basic principles:
-Identify the events that gave rise to the
extension of time – as it is the cost / loss
arising from these events that the Contractor
is entitled to recover;
-Identify the point in time that the delay
occurred – a common mistake is to
identify the costs that were incurred over
the extended duration at the end of the
contract period. This is incorrect. The delay
may have occurred prior to full mobilization
and thus the actual costs incurred at that
time may be lower;
-Identify the direct costs that follow
from the compensable delay events –
the Contractor is not entitled to costs
arising from delay events for which it is
responsible. Separation of the two can
defeat arguments that the claim is global
and includes elements of the Contractor’s
own culpability;
-Assess only time related costs and not
one off capital costs – time related costs
are those which necessarily arise as a
consequence of additional time spent on
the project and would typically include
staff salaries; insurance, rents, utilities,
bonds, accommodation, office services,
car leases & running costs, etc. but
would not include purchase costs of
offices, photocopiers, vehicles etc.
-Exclude task related costs – a
common mistake is to include task
related costs (e.g. labour, plant hire or
scaffolding costs) that would have
been incurred in any event. These
costs may only have been incurred at a
later point in time and are therefore not
additional. Such costs would need to
be separately recovered through a
properly formulated disruption cost
claim;
-Exclude profit – the purpose of the claim
is to put the Contractor back into the
position it would have been, but for the
delay. ‘Profit’ is not ‘cost’ and thus any
claim for profit can only be by way of a
‘loss of opportunity’ claim – which may be
expressly precluded by the wording of the
contract and would in any case have to
be proved, i.e. that opportunities did in
fact present themselves and were
refused because key resources could not
be released from the delayed project;
-Allow for off-site costs – costs incurred in the Contractor’s head
office (and elsewhere) may be as a direct result of the project
delay. The fact that these costs were incurred off site does not
mean that the Contractor is not entitled to receive them;
-If possible, avoid formulae for determining overheads (e.g.
Hudson’s, Emden’s etc.) – unless you are a Contractor and you
fully understand the basis of your ‘loss of opportunity’ claim and
how to present it! By indentifying actual incurred overhead costs
rather than rely on theory based formulae that commonly produce
high assessments;
-Interest / Finance Charges – remember that charging interest on
a debt may be prohibited in your jurisdiction or by your contract.
Most interest or finance claims suffer from a lack of facts and are
commonly: unsupported, theoretical assessments of loss.
However, a skilled claimant can often find ways to lend credibility
to this type of claim.
Calculation of Costs. Once the contractor is granted an extension
of time with costs, the computation of the recoverable items
must also be substantiated with properly maintained records and
invoices. Normally, the contractor should prove actual loss from
records. Only where this is not possible, and as an exception
rather than the rule, will calculation be allowed by reference to
formulae such as the Eichleay formula, and the Hudson or Emden
formulae. The formula is applied to assess loss where certain
things have been established proving that the contractor did
actually suffer loss. The contractor must show that it would have
secured work on another contractor and would have been
recovering overheads from this other project, and that there was
profit capable of being earned elsewhere and there was no
change in the market thereafter affecting profitability of the
work.
It must also be established that the
contractor was unable to deploy
resources elsewhere and had no
possibility of recovering the overheads
from other sources, e.g., from an
increased volume of work. Thus such
formulae are likely only to be relevant
and of value if the event causing the
delay has the characteristic of a breach
of contract.

More Related Content

PPTX
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
PDF
Prolongation and HOOH Costs
PDF
Extension of Time (EoT) in Construction Project presentation
PDF
5. international standard contract for construction
PPTX
Tenders contract -arti
PDF
Quality control IN CONSTRUCTION
PPTX
Ppt on nationalism in india...
PPTX
Insepction and quality control
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Prolongation and HOOH Costs
Extension of Time (EoT) in Construction Project presentation
5. international standard contract for construction
Tenders contract -arti
Quality control IN CONSTRUCTION
Ppt on nationalism in india...
Insepction and quality control

What's hot (20)

PDF
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
PDF
Training fidic moustafa ismail 2017 _ lec 4
PPTX
Liquidated damages contracts
PDF
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
PPTX
Triple constraint
PDF
Fidic contracts 2017 - Notable Changes
 
PDF
Time Impact Analysis
PDF
Claims
PDF
Bim arabia red fidic
PPT
Construction Law Presentation
PPTX
Extension of time Analysis
PPTX
VERTEX Construction Delays and Forensic Schedule Analyses
PDF
Fidic contracts management introduction
PDF
EOT Related Cost Compensation Determination
PPSX
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
PPTX
Eot claims hr__may2012
PPTX
Time management in fidic red book 2017(prmg080 project)
PPT
Chapter 3- Construction Law
PDF
Delay analysis ... wise after the event.
PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Training fidic moustafa ismail 2017 _ lec 4
Liquidated damages contracts
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Triple constraint
Fidic contracts 2017 - Notable Changes
 
Time Impact Analysis
Claims
Bim arabia red fidic
Construction Law Presentation
Extension of time Analysis
VERTEX Construction Delays and Forensic Schedule Analyses
Fidic contracts management introduction
EOT Related Cost Compensation Determination
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
Eot claims hr__may2012
Time management in fidic red book 2017(prmg080 project)
Chapter 3- Construction Law
Delay analysis ... wise after the event.
Extension of time (E.O.T) By Ahmed Ibarhim
Ad

Similar to Prolongation cost calculation (20)

DOCX
Reasonableness of Construction Completion Costs
PPTX
Quantify Construction Damages related to Delay, disruption, and inefficiencies
DOCX
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
PPTX
Construction claims, disputes and project closure
PDF
ms construction Group 7-Claims-Part 9- Cost.pdf
PPTX
Cost value reconciliation (cvr)
PDF
CLAIMS AND GROUP 7 MS CONSTRUCTIONcombinepdf.pdf
PPTX
Prolongation, specific Procedures and key
PDF
Commercial and Legal Aspects of Liquidated Damages and Penalties
PDF
Design & Build contracts - key points for a main contractor with technology a...
PDF
Management Reserve
PPT
Liquidated damages
PDF
Handbook-for-Value-Based-Billing-Engagements
PPT
Contingencies and provisioning[1]
PDF
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
PDF
Construction Contract Issues for Owners of Residences
PPTX
Quick Costs - how to avoid challenges to success fees.
PDF
What Was the FASB Thinking?
PDF
10 Essentials For An Effective Construction Contract
PDF
descripe th different types of delay.pdf
Reasonableness of Construction Completion Costs
Quantify Construction Damages related to Delay, disruption, and inefficiencies
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
Construction claims, disputes and project closure
ms construction Group 7-Claims-Part 9- Cost.pdf
Cost value reconciliation (cvr)
CLAIMS AND GROUP 7 MS CONSTRUCTIONcombinepdf.pdf
Prolongation, specific Procedures and key
Commercial and Legal Aspects of Liquidated Damages and Penalties
Design & Build contracts - key points for a main contractor with technology a...
Management Reserve
Liquidated damages
Handbook-for-Value-Based-Billing-Engagements
Contingencies and provisioning[1]
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
Construction Contract Issues for Owners of Residences
Quick Costs - how to avoid challenges to success fees.
What Was the FASB Thinking?
10 Essentials For An Effective Construction Contract
descripe th different types of delay.pdf
Ad

More from R.R.G.S Bandara (6)

PPTX
Preparation of boq
DOCX
Legal system of sri lanaka
DOCX
General notes to BSR BUILDING SCHEDULE OF RATES
PDF
Automo lesson3
DOCX
පිලිකා cancer protection
PPTX
00 eng tech note1
Preparation of boq
Legal system of sri lanaka
General notes to BSR BUILDING SCHEDULE OF RATES
Automo lesson3
පිලිකා cancer protection
00 eng tech note1

Recently uploaded (20)

PDF
737-MAX_SRG.pdf student reference guides
PPTX
introduction to high performance computing
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PDF
PPT on Performance Review to get promotions
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PPTX
UNIT - 3 Total quality Management .pptx
PPT
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPTX
Information Storage and Retrieval Techniques Unit III
PPT
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
PDF
Visual Aids for Exploratory Data Analysis.pdf
PPTX
Safety Seminar civil to be ensured for safe working.
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PDF
COURSE DESCRIPTOR OF SURVEYING R24 SYLLABUS
737-MAX_SRG.pdf student reference guides
introduction to high performance computing
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
Fundamentals of safety and accident prevention -final (1).pptx
PPT on Performance Review to get promotions
R24 SURVEYING LAB MANUAL for civil enggi
UNIT - 3 Total quality Management .pptx
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
III.4.1.2_The_Space_Environment.p pdffdf
Automation-in-Manufacturing-Chapter-Introduction.pdf
Information Storage and Retrieval Techniques Unit III
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
Visual Aids for Exploratory Data Analysis.pdf
Safety Seminar civil to be ensured for safe working.
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
COURSE DESCRIPTOR OF SURVEYING R24 SYLLABUS

Prolongation cost calculation

  • 2. Once a Contractor has secured an extension of time and relief from liquidated damages, thoughts will quickly turn to recovery of the costs incurred due to the delayed completion date – i.e. “Prolongation Costs”.
  • 3. If you ask an Employer’s QS how such costs should be determined the answer is often an unequivocal statement that the rates and prices from the Preliminaries BOQ shall be divided by the original contract duration and the derived daily rate for preliminaries shall then be applied to the extended duration.
  • 4. The sharp witted Employer’s QS may even refine this logic with the caveat that the BOQ rates and prices should first be adjusted to remove fixed costs, mobilization and demobilization costs, overheads and profit. Whilst both answers are quite wrong, these approaches are often used in order to achieve result, despite the inaccurate answer. The problem is that neither approach attempts to address the underlying question of what costs / losses were actually incurred by the Contractor as a consequence of the delaying events for which the Employer was responsible.
  • 5. The answer to this question cannot be found in the BOQ, but can (and should) be found in a detailed analysis of the Contractor’s cost records The express wording of the contract will dictate which heads of claim are admissible, but in general terms an accurate understanding of Prolongation Cost entitlement can be derived by application of the following basic principles: -Identify the events that gave rise to the extension of time – as it is the cost / loss arising from these events that the Contractor is entitled to recover;
  • 6. -Identify the point in time that the delay occurred – a common mistake is to identify the costs that were incurred over the extended duration at the end of the contract period. This is incorrect. The delay may have occurred prior to full mobilization and thus the actual costs incurred at that time may be lower; -Identify the direct costs that follow from the compensable delay events – the Contractor is not entitled to costs arising from delay events for which it is responsible. Separation of the two can defeat arguments that the claim is global and includes elements of the Contractor’s own culpability;
  • 7. -Assess only time related costs and not one off capital costs – time related costs are those which necessarily arise as a consequence of additional time spent on the project and would typically include staff salaries; insurance, rents, utilities, bonds, accommodation, office services, car leases & running costs, etc. but would not include purchase costs of offices, photocopiers, vehicles etc.
  • 8. -Exclude task related costs – a common mistake is to include task related costs (e.g. labour, plant hire or scaffolding costs) that would have been incurred in any event. These costs may only have been incurred at a later point in time and are therefore not additional. Such costs would need to be separately recovered through a properly formulated disruption cost claim;
  • 9. -Exclude profit – the purpose of the claim is to put the Contractor back into the position it would have been, but for the delay. ‘Profit’ is not ‘cost’ and thus any claim for profit can only be by way of a ‘loss of opportunity’ claim – which may be expressly precluded by the wording of the contract and would in any case have to be proved, i.e. that opportunities did in fact present themselves and were refused because key resources could not be released from the delayed project;
  • 10. -Allow for off-site costs – costs incurred in the Contractor’s head office (and elsewhere) may be as a direct result of the project delay. The fact that these costs were incurred off site does not mean that the Contractor is not entitled to receive them; -If possible, avoid formulae for determining overheads (e.g. Hudson’s, Emden’s etc.) – unless you are a Contractor and you fully understand the basis of your ‘loss of opportunity’ claim and how to present it! By indentifying actual incurred overhead costs rather than rely on theory based formulae that commonly produce high assessments; -Interest / Finance Charges – remember that charging interest on a debt may be prohibited in your jurisdiction or by your contract. Most interest or finance claims suffer from a lack of facts and are commonly: unsupported, theoretical assessments of loss. However, a skilled claimant can often find ways to lend credibility to this type of claim.
  • 11. Calculation of Costs. Once the contractor is granted an extension of time with costs, the computation of the recoverable items must also be substantiated with properly maintained records and invoices. Normally, the contractor should prove actual loss from records. Only where this is not possible, and as an exception rather than the rule, will calculation be allowed by reference to formulae such as the Eichleay formula, and the Hudson or Emden formulae. The formula is applied to assess loss where certain things have been established proving that the contractor did actually suffer loss. The contractor must show that it would have secured work on another contractor and would have been recovering overheads from this other project, and that there was profit capable of being earned elsewhere and there was no change in the market thereafter affecting profitability of the work.
  • 12. It must also be established that the contractor was unable to deploy resources elsewhere and had no possibility of recovering the overheads from other sources, e.g., from an increased volume of work. Thus such formulae are likely only to be relevant and of value if the event causing the delay has the characteristic of a breach of contract.